JADWAL WAKTU PELAKSANAAN

(TIME SCHEDULE BENTUK KURVA "S")


KEGIATAN : PELAKSANAAN PEKERJAAN PAGAR GEDUNG CELEBES CONVENTION CENTRE
PEKERJAAN : PEMBANGUNAN SITE DEVELOPMENT TAHAP II
KOTA : MAKASSAR
TAHUN ANGGARAN : 2007

BOBOT WAKTU PELAKSANAAN ( BULAN )


NO URAIAN PEKERJAAN RENCANA BULAN I BULAN II BULAN III BULAN IV ket
% 20-26 27-2/9 3-9 10-16 17-23 24-30 1-7/10 8-14 15-21 22-28 29-4 5-11 12-18 19-25 26-2/12 3-10
I PEKERJAAN PERSIAPAN 0.80 0.050 0.050 0.050 0.050 0.050 0.050 0.050 0.050 0.050 0.050 0.050 0.050 0.050 0.050 0.050 0.050 100%
II PEK. TERALIS PENGAMAN PANTAI 48.97 4.081 4.081 4.081 4.081 4.081 4.081 4.081 4.081 4.081 4.081 4.081 4.081 75%
III PEKERJAAN PAGAR DEPAN 45.69 3.807 3.807 3.807 3.807 3.807 3.807 3.807 3.807 3.807 3.807 3.807 3.807 50%
IV PEK. PAGAR PENGAMAN CHILLER 4.32 0.360 0.360 0.360 0.360 0.360 0.360 0.360 0.360 0.360 0.360 0.360 0.360 25%
V PEKERJAAN PEMBERSIHAN 0.22 0.024 0.024 0.024 0.024 0.024 0.024 0.024 0.024 0.024 0%
JUMLAH 100.00 0.050 4.131 7.938 8.298 8.298 8.298 8.298 8.323 8.323 8.323 8.323 8.323 8.323 4.242 0.435 0.074
RENCANA REALISASI KOMULATIF (%) 0.05 4.18 12.12 20.42 28.72 37.01 45.31 53.64 61.96 70.28 78.60 86.93 95.25 99.49 99.93 100.00
REALISASI KOMULATIF (%) 0.06 0.87 1.57 2.63 4.38 7.00 10.00 12.19 12.19 17.75 23.87 30.75 35.012 36.86
DEVIASI YANG TERJADI +/- 0.01 3.32 10.55 17.79 24.34 30.01 35.31 41.44 49.77 52.53 54.74 56.17 60.24 62.63

Makassar, 11 Nopemberr 2007


Di ketahui oleh Di setujui Di buat oleh
Pejabat Pelaksana Teknis Kegiatan konsultan pengawas Kontraktor Pelaksana
Dinas koperasi dan UKM Prov.SUL-SEL CV. MALLOMO ENGINEERING PT.SINAR MULIA PRATAMA

Drs.H. ANWAR LATIF,Msi Ir. ISMAIL ALFIAN SUKARNO NOOR JAYA


Nip. 580 009 128 Site Engineering Direktur