You are on page 1of 5

Transformers and substations

Surviving a
short-circuit
Short-circuit withstand capability of power transformers
Thomas Fogelberg

The power transformer is a vital component in the transmission of electric power.


Thanks to the many years of accumulated knowledge, experience and sophisticat-
ed development in production and testing processes, the transformer is now a
highly efficient piece of apparatus with an outstanding reliability.

Transformers, however, are not the only components to have experienced changes.
The rapidly evolving electricity market is causing networks to be operated closer to
their limits. At the same time, the booming demand for new transformers combined
with high material prices is putting pressure on manufacturers and their suppliers.
All these aspects combine to make assuring the robustness of transformers more
important than ever before.

ABB draws on its vast experience in power transformer


manufacturing in delivering equipment that
displays a truly outstanding
short-circuit performance.

24 ABB Review 1/2008


Surviving a short-circuit

Transformers and substations

A s power ratings and


transmission voltages
have increased, the thermal
1 The choice of materials involves a trade-off between material losses
and price
Furthermore, the increasing
demand for transformers is
pushing manufacturing facil-
and mechanical aspects of ities and their material sup-
Qualitative discussion of materials utilization
transformers have become pliers to the limits of their
more pronounced, both in capacity, leading to extend-
Optimum material utilization with normal
terms of local over-heating loss evaluation and high material prices
ed delivery times.
control and in the need for
Technical limits of
withstanding electrodynamic 100 % flux density Meanwhile, growth in grid
forces originated by fault Hig
current density, utilization is outstripping
Material utilization

hm acoustic emissions,
events occurring in electrical ate mechanical stresses new investment, leading
ria
lp
systems. ABBs transformers Lo ric
e
to individual components
w
are today handling 800 kV, ma
ter being operated closer to
ial
the highest commercial trans- Optimum material utilization pri
ce their limits.
with normal loss evaluation
mission voltages presently in and material prices
use. They are also handling Testing
three-phase ratings of 1500 The testing of new trans-
to 2000 MVA in system intertie Low Normal High formers is the utmost dem-
applications and up to Loss evaluation onstration of their quality.
1200 MVA in generator step- Todays designs, marked by
up applications. high material prices and
often low loss evaluations, are seeing
2 Failures caused by short-circuits are still a
Background materials being pushed closer to their
major cause of transformer outages
The demand of transformers is now limits and exposed to greater stresses
booming in a way similar to after the than ever before 1 .
Second World War. At that time, Euro-
pean and American markets were The acceptance testing concerning
served by domestic suppliers who dielectric aspects is well covered by
invested to full capacity to meet the the international standards that have
needs of state-controlled utilities and been developed over the years. The
IShort-circuit
power companies. Installations of proving of thermal and mechanical
400 kV to 800 kV AC were implement- integrity of new large GSU (generator
ed. It was also a time when numerous step-up) and intertie transformers is
IEC and ANSI international standards still, however, a field where design
were laid down. tion. As a result, many former govern- and production weaknesses can pass
mental bodies have been transformed without being detected.
The first signals of a shift in demand to profit-making companies. Produc-
appeared in the early 1980s. By the tion, transmission and distribution This article mainly addresses how
end of this decade, the electrical were broken up into separate entities, ABBs design, production, supply
system industry has gone through with the role of transmission becoming chain and testing philosophy verifies
its biggest change since the inventions weaker and less clear as a result. It mechanical aspects of reliable large
of Edison and Westinghouse. has especially become more difficult power transformers in other words,
to obtain a collective responsibility. their ability to pass a short-circuit
The last 25 years have been character- Fluctuations in prices are considered test.
ized by a huge global consolidation the concern of end-customers and
on both the supply and user side of long-term commitment in infrastruc- Reliability
electrical equipment. A fully domestic ture has shifted to a shorter-term Modern power systems are complex
business has been transformed to a horizon. arrangements with a high number
fully global one, with consequences of individual pieces of apparatus.
in both commercial and procurement For the transformer market in par- To ensure reliable operation, it is of
matters. The procurement side has ticular, the most significant changes utmost importance that key elements
additionally had to deal with the of recent years are caused by the such as large power transformer have
markets for raw materials, many of huge demand for electrical energy a high degree of availability, thus
which are no longer in their traditional in regions such as Asia, the Middle minimizing the outages of individual
balance. East and South America. Additionally, components or whole blocks of
the so-called old world has needed power generation.
Changes to the grids were motivated to re-invest, as the age of its trans-
by rational reasons for opening up former fleet reaches 40 to 50 years. The ability to withstand a short circuit
markets to enable trading and regional These developments are additionally is recognized as an essential charac-
interconnections. Political stakeholders boosted by environmental concerns. teristic of power transformers. IEC
wished to enable increased competi- and IEEE Standards, as well as other

ABB Review 1/2008 25


Surviving a short-circuit

Transformers and substations

national standards hence specify that of more than 60 MVA rating are pro-
3 Electromagnetic forces tend to minimize the
power transformers have to be short- duced every year.
density of magnetic energy
circuit proof and lay out how this
should be verified. Unfortunately, Design considerations
however, there is extensive evidence How will all those changes affect
that the matter is not as simple as the todays design and future reliability
standards would suggest. The failures and availability? In view of rising
caused by short circuits 2 are still a demand, many new suppliers will
major cause of transformer outages be entering the market, with distribu-
though failure rates vary widely in tion-side manufacturers also moving
different countries and systems, into the power transformer sector.
depending on various circumstances, At the same time, the large increase
network characteristics and the equip- in material prices, combined with
ment installed. traditional low loss evaluations, will
drive stresses upwards as margins are
Nowadays fast developing regions, reduced.
with steeply rising demand for electric
power, are adding more and more The mechanical rigidity of a trans-
generating capacity and interconnec- former will become the most vital
Factbox Attributes of power transformers
tions to their systems. In addition to performance factor for the future.
manufactured by ABB
this the western world is characterized There are three reasons for this:
by: Withstand to short circuit stresses
A short-circuit safe transformer is charac- Expanding cross-border electricity Seismic requirements
terized by trade (bringing network operations Transport handling
Mechanical sound design and technology close to their physical limits)
Based on fundamental mechanics Development of wind generation The short-circuit force gives rise to
Verified by many short-circuit tests (which is often integrated into the mechanical forces that can reach hun-
Rigid core clamping structure for short- grid without taking into account dred of tons in milliseconds. The cur-
circuit strength and transport available network capacities) rent peaks and the corresponding forc-
Accurate manufacturing guided by strict Changing load flows es depend on many factors. In high-
tolerances and quality systems Ageing network components voltage systems, the most probable
Rigid winding mandrels Changed network operating condi- type of short circuit is a single-line-to-
Verified drying and pressing procedures tions earth flashover, normally due to envi-
Rigid low-voltage winding design and ronmental conditions such as a light-
clamping These factors lead to old and new ning strike on the line, equipment fail-
transformers being exposed to severe ure at the station, pollution of insula-
Recommendations short-circuit requirements. tion strings, and similar causes. Some-
Which units are worth being considered for times, short-circuit faults will develop
short-circuit testing? ABB has succeeded in building trans- into other more extensive faults, such
formers with an outstanding reliability as single-phase-to-earth faults devel-
Important generator step-up transform- record. This is a result of dedicated oping into a double-phase-to-earth
ers and auxiliary units in power plants development work, long time experi- and eventually three-phase faults. The
Key feeding transformers at power plant ence in building transformers for the relative severity of the different types
sub-stations or huge load centers most demanding service conditions of fault depends on the characteristics
Strategic intertie transformers and meticulous follow-up of incidents of the system. On the other hand there
three-winding system transformers taking place in tests and operation. are factors such as arc resistances and
(tertiary), auto-transformers earth network impedances that have
Transformers with axial split winding Ten years ago, ABB launched the some compensatory effects. The severi-
connections business concept, TrafoStarTM. This ty of a short circuit and the peak cur-
Series of transformers, one to be taken integrates engineering tools, manufac- rent and forces depends to a consider-
out turing accuracy, major suppliers with able extent on the condition of the
Always track feeding transformers common material specifications, test- installation, and in particular on the
Transformers connected to networks ing and quality management system. short-circuit impedance value of the
known for many faults and high fault This concept is now used for large transformer and the short-circuit appar-
currents power transformers in 14 plants in all ent power of the system(s).
global regions. Since the inception of
All power transformers designs/contracts TrafoStarTM, 10,000 power transformers The fault configuration that normally
to be checked by design reviews to have been produced according to this gives the highest through-currents in
IEC 60076 Part 5 (2006-02) concept; of these, 2,000 units are very any winding of the transformer is the
large GSUs and intertie transformers. symmetrical three-phase fault. Hence,
More than 1,500 power transformers it is meaningful to use this fault mode

26 ABB Review 1/2008


Surviving a short-circuit

Transformers and substations

as a basic design criterion for the The failure modes for radial forces often questionable contribution to
transformer. include: stability granted by radial supports
Buckling of inner windings 4a from the core to the windings or from
In dealing with short-circuit events in Stretching of outer windings one winding to another is deliberately
power transformers, the first step is to Spiraling of end turns in helical ignored in any ABB transformer de-
evaluate any very high fault currents windings 4b signs.1) This means that the mechanical
that will affect the windings in con- stability of the winding is determined
nection with the various types of The failure modes for axial forces by the hardness of the copper (yield
faults the unit is likely to experience include: point) and conductor geometry.
in service. Mechanical collapse of yoke insula- Spiraling in helical type windings is
tion, press rings and press plates, avoided by strictly limiting the forces
When determining the magnitude of and core clamps that can occur, or by changing the
the currents, circuit analysis and theory Conductor tilting type of winding. Also the dynamic
of symmetrical components are used. Conductor axial bending between response from the winding is consid-
The calculations are performed by spacers ered.
means of automated programs, since Possible initial dielectric failures
the system and the transformer charac- inside windings, followed by Designing power transformers is an
teristics constitute the input data. mechanical collapse iteration and interaction process that
seeks the optimal solution from the
Force calculations per failure mode The axial forces are calculated with point of view of:
Electromagnetic forces tend to deform programs based on finite element Masses and losses
the windings so as to minimize the method (FEM) that fully take into Sound level
magnetic energy density stored in account axial displacements caused Short-circuit strength
their volume. For a two-winding trans- by workshop tolerances and pitch of Winding temperatures, hot spots
former example, this means that an helical type windings. Windings are and cooling equipment
inner winding will tend to reduce its dimensioned for maximum compres- Dielectric strength between wind-
radius and an outer winding to in- sion forces, where dynamic effects are ings and inside windings
crease its radius. In axial directions, embedded.
the windings get compressed to ABBs designers are supported by the
reduce their height 3 . An important feature of ABBs short worlds most advanced set of design
circuit technology is that inner wind- and verification programs for power
Forces and relating withstand criteria ings subject to radial compression are transformers. These interactive appli-
can be split into two components: designed to be completely self-sup-
Radial forces porting as regards any collapse by Footnote
Axial forces free buckling. For this reason, any 1)
The reliance on radial supports can compromise the
mechanical stability of the windings due to relax-
ation of the supports under load and over time
4 Examples of deformations caused to windings by extreme forces:

a Buckling: Collapse of the cylindrical winding b Spiraling: Tangential shift of the end turns in 5 Transformer manufacturing requires a high
shell helical-type windings degree of accuracy

ABB Review 1/2008 27


Surviving a short-circuit

Transformers and substations

cations are used today in 14 On account of the high in-


7 Rated power (MVA) of SC tested TrafoStarTM transformers
power transformer plants. vestment costs in test equip-
ment, such tests are possible
300
Manufacturing and accuracy in only a handful of locations
Ampere-turn balancing be- 250 in the world. The test re-
tween the windings is a pre- 200 quires power capacities in the
requisite to avoid excessive 150
range of a large power grid
axial forces on the windings. together with sophisticated
100
control and measuring equip-
This is achieved through 50 ment. One such facility is
strict manufacturing toler- 0 KEMA in the Netherlands,
1997 1998 2000 2000 2001 2002 2002 2005 2006 2007
ances for windings 5 . where a number of short
circuit tests were carried out
Since the windings can be on behalf of ABB 7 .
regarded as springs built of about 20 avoid any displacements between the
percent cellulose, the correct compact- coils. The different cellulose-based More than 140 ABB power transform-
ing when exposed to moisture and components are manufactured and ers of different designs have passed
temperatures is important in obtaining treated from raw material entirely in short-circuit tests, including around 30
the exact length and spring constant ABBs own pressboard machines and that were built after 1996 according to
for long-time service. Well defined pro- kit-centers around the world. This se- TrafoStar technology 8 .
cesses in the winding shop and active cures a common method of producing
part assembly are necessary. The final all these key elements with significant In CIGRE and at other technical con-
pressure setting after the vapor-phase influence on the windings dynamic ferences, KEMA reports are showing
process is used to bring the windings strength 6 . test failures in around 30 to 40 per-
under pressure for their life time. cent of the performed SC tests on
power transformers. ABBs own test
The most important criteria are that all
A short-circuit force gives record over the last 11 years has been
windings need a given pressure to rise to mechanical forces three failures out of 28 tests. When
that can reach hundred of the ABB tests are removed from the
overall statistics, other manufacturers
6 ABBs common method of manufacturing tons in milliseconds. are showing much higher short-circuit
secures a common method of producing all
test failure rates. This highlights the
key elements. This has significant influence
Short-circuit strength verification extreme challenge of building fully
on the winding dynamic strength.
The new IEC Standard 60076-5 (2006-2) short-circuit safe transformers in the
provides two options for verifying the world today.
transformers ability to withstand the
dynamic effects of a short-circuit. The new IEC Standard also allows for
These are: a design verification where the manu-
a) A full short-circuit test performed at facturer shows its calculated stresses
a certified lab or and compares it with its own rules
b) A theoretical evaluation of the abili- manifested by several short-circuit
ty to withstand the dynamic effects tests. To comply with this Standard,
of short-circuit events based on the stresses shall not exceed the manufac-
manufacturers design rules and turers maximum allowable stresses or
construction experience, in line 0.8 of the critical stress value identi-
with the new IEC guidelines fied by the manufacturer. The stress
values must furthermore comply with
the corresponding maximum ones
8 Due to the high investments involved, power
given for guidance in the new IEC
transformer short-circuit testing can only be
Standard 60076-5.
performed in few places in the world. This is
KEMA in the Netherlands.

Thomas Fogelberg
ABB Transformers
Ludvika, Sweden
thomas.fogelberg@se.abb.com

28 ABB Review 1/2008

You might also like