ERP Implementation
Methodology
How to succeed with your ERP implementation
Since 1997, John has consulted on over 27 ERP engagements for some of the nations leading
companies. Founder of Columbia Technical Consulting, Inc., and JDE Resources Services,
John has provided ERP solution services, consulting, project management, supply chain
consulting, operational assessments, and process and systems alignment and optimization
services to organizations throughout the nation.
.
Johns expertise in ERP systems, supply chain consulting, and project management have been
requested by, and provided to, national consulting firms as; Accenture, Ernst and Young, Cap
Gemini, Delta Cubed, Panex Consulting, Premier Consulting, AMX International, Foothills
Consulting, Rapidigm Consulting, The Hunter Group, Jagwire Group, PCM Solutions,
Systems Management Inc., Versa Tech, PCI, Jibe Consulting, and many more
Knowledge Transfer
Continuous
Setup Piloting Integration Cutover Post Support Improvement
Action Teams:
Analyze issues, activities and processes
Functional Develop and test creative ideas and solutions
Teams Take ownership of ideas and solutions
Develop specific action steps and commit to action
plans
Perform day-to-day project tasks
Assume accountability for design changes
Own project
Columbia Technical Consulting Services, Inc.
All Rights Reserved
Project Management
A process that continues throughout the project, ensuring that the project is completed on time, within
budget and within scope, making the best use of the resources available
Project Manager as
Coach/Facilitator/
Coordinator
Effective, Synergistic Team
Team building
Workplan Appropriate skill sets
Individuals given responsibility/accountability Well understood objectives
Set milestones Change management
Time boxed Buy in
Columbia Technical Consulting Services, Inc.
All Rights Reserved
Detail Project Startup
Identify and deploy project team clarify and
assign project roles and responsibilities
Identify risks and mitigation plan
Detailed project plans prepared
Establish project team workspace
Establish project team ground rules
Establish project infrastructure:
Milestones
Meeting schedules and process
Identify project deliverables
Establish document templates, repository and
version control
Columbia Technical Consulting Services, Inc.
All Rights Reserved
Project Plan
TASKS
Detail Project Planning
PARTICIPANTS
Project manager, process owners,
team leads, IT
Project
Planning
DELIVERABLES
Training Plan
Issues database
Installed software
Project tracking and reporting
methods
Documentation standards
Initial end user training strategy
TASK
Review all sales cycle
documentation.
Schedule and attend design
meetings
Develop design review
presentation document,
including scope, phases, major
issues/gaps
Signoff Project Design
Complete initial setup
Application Analysis
Documentation
and Design
Signoff setup documentation
Incorporate any changes to
scope into the project plan,
budgets etc.
Columbia Technical Consulting Services, Inc.
All Rights Reserved
Stage 1 Set-Up
Application Analysis and Design (cont.)
PARTICIPANTS
CTCI consultants, client
functional leads, XXX
Consulting Services PM, Client
PM
TASK
Plan for prototype environment
installation
System Install Software
Install
PARTICIPANTS
Install consultants, IT
DELIVERABLES
Plan to prepare for the facility,
hardware, software and
resources.
An environment to utilize during
prototype
Columbia Technical Consulting Services, Inc.
All Rights Reserved
Summary
System Install
Network tuning
Server Acquisition
PC Client Acquisition
Software Installation
Deployment server
installation
Installation Planner
Installation Workbench
Server installation
Workstation installation
TASK
Create an empty Pilot environment
(1st pass)
Enter ERP software application
setups
Application
Validate setup in pilot
setup Update setup documentation to
reflect actual setup
PARTICIPANTS
Client MIS personnel
CTCI consultants (Client will assist
to increase clients familiarity with
setup steps)
DELIVERABLES
Completed setup documentation
TASK
Project Team
Training Identify training requirements
for client implementation project
team
Obtain / develop ERP
functional/technical training
schedule and schedule the
classes documenting the dates
on the project schedule
RESPONSIBILITY
Client project manager, CTCI
project manager
DELIVERABLES
Project team training plan
Project team Columbia
training
All
Technical Consulting Services, Inc.
Rights Reserved
Stage 2 - Piloting
WHAT
Testing discrete transactions,
Procedures
and Documentation inquiries, reports within each
module
GOAL
Functional Testing
90% of the business
requirements configured,
detailed processes defined
Data
Migration DELIVER
Pilot test plan
Customization Design Desktop procedures
and Development
Conversion, interface plan
Application gap analysis
Report development matrix
Detailed design
Proof of concept
Knowledge transfer to client
Columbia Technical Consulting Services, Inc.
All Rights Reserved
Stage 2 Piloting
Procedures and Documentation
TASK
Deliver Top Ten template
procedures
Complete desktop procedures
Procedures
and Documentation
RESPONSIBILITIES
CTCI consultants
Client Functional Leads
DELIVERABLES
Desktop procedures
Quick Reference Cards
TASK
Create scripts for each function
Collect non-converted business data
Configure & test
Create versions, menus, etc.
Functional Testing
Conduct preliminary test to validate
system setup
RESPONSIBILITIES
Consultants
Client Functional Leads
DELIVERABLES
Pilot Plan
Test scripts
TASK
Create migration plan
transfer business data, control
tables, central objects
Create selected master tables
Run conversions
Run integrities and reconciliation
RESPONSIBILITY
Data
Migration Client MIS personnel
CTCI consultants
Client functional leads
DELIVERABLES
Migration Plan
Conversion plan
DELIVERABLES
Functional specifications
Program specifications
Completed customization
Columbia Technical Consulting Services, Inc.
All Rights Reserved
Stage 3 - Integration
WHAT
Integration / Conversion
Testing
Building on base design
Validating integrated business
processes
Stress testing
Conference Room
Pilot
GOAL
Verify that the processes and system
Stress Testing
will support the business across
interfaces
Task
Develop acceptance criteria at Project
Integration / Conversion Kickoff
Testing
Final validation of application setup
Validate converted data
Review pilot Functional
Review pilot Integration
Signoff pilot
Responsibilities
Client project manager
CTCI Project Manager
Client functional leads
CTCI consultants
Client project team
Deliverables
Acceptance Criteria
Client acceptance of the system
Completed integrated pilot
Task
Deliver pilot plan templates and pilot
concepts to client functional leads
Approve pilot plan
Conference Room
Pilot Run functional pilot scripts
Modify desktop procedures as needed
Responsibilities
CTCI consultants
Client functional leads
Deliverables
Approved pilot plan
Task
Hardware response time
Database throughput
Network traffic and performance
Application response time
Deliverables
Completed stress tests
TASK
Confirm migration plan
Final test to transfer business
data, control tables, central objects
Create selected master tables
Run conversions
Run integrities and reconciliation
RESPONSIBILITY
Data Client MIS personnel
Migration
CTCI consultants
Client functional leads
DELIVERABLES
Migration Plan
Conversion plan
Preliminary Production DB
Final Gap Analysis
TASK
Review stress test results
Analyze breaking points
Re-test
RESPONSIBILITIES
Client MIS
CTCI Consultants
System Performance
DELIVERABLES
and Assessment System analysis report
System design
WHAT
End User Full business simulation
Training
Training
System
Go
Cutover GOAL
Live
To fine-tune cutover procedures
User and verify potential impacts
Acceptance
DELIVER
User system acceptance
End user training
Validate cutover/fall back plan
Process optimization
TASK
End User Develop Go Live plan
Training
Identify end user training
needs
Go Setup client site training
Live facilities
Develop and publish schedule
Complete training prior to
going live
RESPONSIBILITY
Client project manager, Client
functional leads
Deliverables
End user training plan
End user training
Columbia Technical Consulting Services, Inc.
All Rights Reserved
Stage 4 Cutover
User Acceptance
TASK
Final validation of application
Validate converted data
Review pilot functional
Review pilot Integration desktop
procedures, end user training,
Go integration testing
Live Signoff/User Acceptance Testing
User (UAT)
Acceptance
RESPONSIBILITY
Client functional lead
Client project manager
Client project team
CTCI consultant
DELIVERABLES
Acceptance criteria
Client acceptance of the system
TASK
Develop schedule
Develop a contingency plan
Process final conversions
Cutover
Go
Live
RESPONSIBILITY
Client Project Manager, CTCI
Project Manager
DELIVERABLES
Go Live cutover schedule
TASK
Complete end user menus,
responsibilities
Deliver final setup
Cutover
documentation, issues logs.
Begin live processing
Go
RESPONSIBILITY
Client system administrator,
CTCI consultants
Live DELIVERABLES
Go Live
Final documentation
Define
Monitor Plan
Continuous
Implement Improvement Analyze
Measure Develop
Test
For more information regarding this presentation, methodology, and tools used,
or to schedule this presentation at your organization contact John Paulson;