You are on page 1of 12

International Journal of Project Management 20 (2002) 107118

www.elsevier.com/locate/ijproman

Evaluating the risks of public private partnerships for


infrastructure projects
Darrin Grimsey a, Mervyn K. Lewis b,*
a
PricewaterhouseCoopers, Spring Street, GPO Box 1331L, Melbourne, Victoria, Australia
b
School of International Business, University of South Australia, North Terrace, GPO Box 2471, Adelaide, Australia

Received 14 October 1999; received in revised form 16 May 2000; accepted 9 July 2000

Abstract
In many countries, limitations upon the public funds available for infrastructure have led governments to invite private sector
entities to enter into long-term contractual agreements for the nancing, construction and/or operation of capital intensive projects.
For the public procurer, there is an obvious need to ensure that value-for-money has been achieved. To the project sponsors, such
ventures are characterised by low equity in the project vehicle and a reliance on direct revenues to cover operating and capital costs,
and service debt nance provided by banks and other nanciers. Risk evaluation is complex, requiring the analysis of risk from the
dierent perspectives of the public and private sector entities. This paper analyses the principles involved, drawing on practical
experience of evaluating such projects to present a framework for assessing the risks, and using as illustration a case study of a
waste water treatment facility in Scotland which is typical of most PPP projects. # 2001 Elsevier Science Ltd. All rights reserved.
Keywords: Public private partnerships; Infrastructure; Project nance; Risk analysis

1. Introduction arrangement has even earlier origins. According to


Monod [3], the rst ``concession'' was granted in 1782 to
For most of the post-war period, government has Perrier in France and concerned water distribution, which
been the principal provider of infrastructure (at least in the context of this paper seems entirely appropriate.
outside of the United States). Over the last decade, that In Australia, public/private sector infrastructure
position has begun to change. Faced with pressure to arrangements date back to the bicentennial year 1988. In
reduce public sector debt and, at the same time, expand the UK, the Private Finance Initiative (PFI) was intro-
and improve public facilities, governments have looked duced by the Conservative Government in November
to private sector nance, and have invited private sector 1992, widening its privatisation and contracting out
entities to enter into long-term contractual agreements policies to incorporate the provision of infrastructure
which may take the form of construction or manage- and public services by a hybrid approach of combined
ment of public sector infrastructure facilities by the pri- public and private sector funding [4]. Procurement was
vate sector entity, or the provision of services (using subsequently redened as the provision of services
infrastructure facilities) by the private sector entity to rather than the ownership of assets, with partnerships
the community on behalf of a public sector body. sought on a range of projects and PFI promoted as a
These arrangements often take the form of a build- preferred procurement method a position which did
operate-transfer (BOT) arrangement [1]. The acronym not change with the incoming Labour administration
BOT was rst used in the early eighties by Turkey's which in 1997 built on the initiative with Public Private
Prime Minister Targut Ozal [2]. However, the concept Partnerships [5]. The European Commission, through
itself can be traced back to Hong Kong in the late fties its grant mechanism, is encouraging PPPs with projects
when a privatised vehicle tunnel was rst talked about, so far in Portugal, Italy, Netherlands, Greece and Ire-
and if regarded as a form of concession or franchise land [6]. The techniques have been adapted to promote
investment both in local authority services and in infra-
* Corresponding author. Tel.: +61-8-8302-0536; fax: +61-8-8302-
structure projects more generally elsewhere [7,8].
0512. This paper analyzes the risks of PPP arrangements from
E-mail address: mervyn.lewis@unisa.edu.au (M.K. Lewis). the perspectives of the various parties. The character of
0263-7863/01/$22.00 # 2001 Elsevier Science Ltd. All rights reserved.
PII: S0263-7863(00)00040-5
108 D. Grimsey, M.K. Lewis / International Journal of Project Management 20 (2002) 107118

infrastructure investments and the nature of PPPs shape . Externalities, whereby benets and costs are con-
the riskiness of any individual project. Thus we begin by ferred upon those not a party to the transaction (e.g.
examining the nature of infrastructure and how PPPs spillovers);
are structured. . Natural monopolies, for which scale economies
make it ecient to have only one provider (for
example, of an electricity grid).
2. What is infrastructure?
The trend away from public to private provision of
Infrastructure is easier to recognize than dene. infrastructure has been underpinned by a marked
Investment in infrastructure is thought to provide ``basic change in thinking and practice on these matters. There
services to industry and households'' [9], ``key inputs into has been the perception, for example, that a move from
the economy'' [10], and ``a crucial input to economic `taxpayer pays' to `user pays' (i.e. from ability-to-pay to
activity and growth'' [7], although what is ``basic'', ``key'' the benet principle) in the provision of infrastructure
and ``crucial'' varies from country to country and from services (water, power) is likely to be associated with a
one time to another (steel production was once regarded better economic use of the services. Many industries
as essential infrastructure). Recently, the activities considered to be natural monopolies, e.g. electricity
regarded as infrastructure investment include: generation and telecommunications, have been broken
up geographically into dierent regional rms or, with
. Energy (power generation and supply);
deregulation, separated into competitive (or potentially
. Transport (toll roads, light rail systems, bridges
competitive) sectors vis-a-vis those sectors that remain
and tunnels);
natural monopolies (the distinction between power sup-
. Water (sewerage, waste water treatment and water
ply and high-voltage transmission, and between railway
supply);
operation and rail track services). In those activities
. Telecommunications (telephones);
which have natural monopoly characteristics, substitu-
. Social infrastructure (hospitals, prisons, courts,
tion of price-cap regulation for rate-of-return regulation
museums, schools and Government accommoda-
(i.e. xing of maximum prices rather than the mark up
tion).
over costs) has created strong incentives to reduce costs,
These share with other types of xed investment (such while third party access to certain facilities that are not
as property development, oce construction [11]) a economic to duplicate has widened competition in the
number of common characteristics: upstream and downstream markets served by the facil-
ities. All of this has laid the groundwork for PPP
. Duration (infrastructure is long-lived, and has a
arrangements.
long gestation process);
. Illiquid (the lumpiness and indivisibility of infra-
structure projects makes for a limited secondary
3. PPP arrangements
market);
. Capital intensive (projects are large scale and
Confusion sometimes exists between `infrastructure
highly geared);
nancing' and `infrastructure investment'. The former
. Valuation (projects are dicult to value because of
can arise from the privatisation of existing facilities,
taxation and pricing rules and embedded options
whereas infrastructure investment involves the develop-
[12,13] and guarantees).
ment, operation and ownership either by the private
The result is that evaluation of the projects is a complex sector alone or in a joint venture between government
and specialised activity. and the private sector entity. The distinction is analo-
The litmus test used to be that infrastructure had to gous to buying an existing oce block, already fully let,
be provided by government-owned enterprises (the pre- as opposed to developing a new site the attendant
dominant approach in Europe) or by privately owned risks are obviously quite dierent in the two cases.
utilities subject to rate of return regulation (the Accordingly, PPPs can be dened as agreements
approach in much of the United States). This conviction where public sector bodies enter into long-term con-
derived from a number of inherent features, such as the tractual agreements with private sector entities for the
existence of: construction or management of public sector infra-
structure facilities by the private sector entity, or the
. Network services, providing integrative activities provision of services (using infrastructure facilities) by
which bind economic activity together; the private sector entity to the community on behalf of
. Public goods, from which it is dicult (and per- a public sector entity. They can take many forms and
haps not desirable) to exclude non-payers (the may incorporate some or all of the following features
non-excludability principle); [14]:
D. Grimsey, M.K. Lewis / International Journal of Project Management 20 (2002) 107118 109

. The public sector entity transfers facilities con- between ESW (the public procurer) and Stirling Water.
trolled by it to the private sector entity (with or There is also a separate operating agreement between
without payment in return) usually for the term of Stirling Water and Thames Water, the private sector
the arrangement; operator of the works. The project reached nancial
. The private sector entity builds, extends or reno- close in March 1999 and the gure sets out the links and
vates a facility; key contractual arrangements between the parties
. The public sector entity species the operating involved.
features of the facility; From the viewpoint of the public procurer, there is an
. Services are provided by the private sector entity obvious need to ensure that money has been spent eco-
using the facility for a dened period of time (usually nomically, eciently and eectively. At its simplest, the
with restrictions on operations and pricing); and Government seeks to utilise private sector nance in the
. The private sector entity agrees to transfer the provision of public sector infrastructure and services
facility to the public sector (with or without pay- and thereby achieve value-for-money. Value-for-money,
ment) at the end of the arrangement. dened as the eective use of public funds on a capital
project, can come from private sector innovation and
A classic example of a BOT arrangement is the third skills in asset design, construction techniques and
Dartford Crossing of the River Thames linking two operational practices, and also from transferring key
stretches of the M25 motorway circling London, to be risks in design, construction delays, cost overruns and
operated (with virtually guaranteed toll income) by the nance and insurance to private sector entities for them
vehicle company for up to 20 years, following which the to manage. However, in some cases, the emphasis on
facility will revert to the UK government. In Australia, risk transfer can be misleading as value-for-money
projects such as the Sydney Harbour Tunnel and the requires equitable allocation of risk between the public
City Link (linked motorways) project in Melbourne are and private sector partners, and there may be an inher-
also BOT arrangements. ent conict between the public sector's need to demon-
With a BOO (build-own-operate) project, the private strate the value-for-money versus the private sector's
sector entity nances, builds, owns and operates an infra- need for robust revenue streams to support the nan-
structure facility eectively in perpetuity. An example cing arrangements [15].
comes from the water treatment plants serving parts of From the perspective of the project sponsors, PPP
South Australia. These facilities are nanced, designed, (and PFI) is essentially project nancing, characterised
built and operated by a private sector rm to process by the formation of a highly-geared special purpose
raw water, provided by the public sector entity, into l- company for the project vehicle and consequently a
tered water which is then returned to the public sector reliance on direct revenues to pay for operating costs
utility for delivery to consumers. and cover debt nancing while giving the desired return
Although governments have been motivated into on risk capital. Although there are exceptional cases
entering into PPP arrangements by the desire to reduce such as the Hong Kong Harbour Tunnel which started
debt (and contain taxation), another consideration has making a prot four years after opening, these arrange-
been the benets of sharing nancial risks and rewards ments typically last for long periods and take a long
between public and private sector bodies. We now time to generate a prot. It is therefore important to
examine these risks. have a clear understanding of the principles of limited-
recourse nancing. PPP projects are viable only if a
reliable, long-term revenue stream can be established.
4. Risks The risk that the predicted revenues do not materialise
is the greatest risk to the commercial viability of a
Much of the risk of a PPP project comes from the project.
complexity of the arrangement itself in terms of doc- This risk is borne by those providing nance or
umentation, nancing, taxation, technical details, sub- nancial guarantees. Straight equity participation is
agreements etc involved in a major infrastructure ven- generally low, only 5% of the total funding (4.95 mil-
ture, while the nature of the risk alters over the duration lion out of funding of 99 million) in the case of the
of the project. For example, the construction phase of AV&S project. This situation is more starkly illustrated
the project will give rise to dierent risks from those by the designconstructmanagenance (DCMF) of a
during the operating phase. PFI private prison currently operating in Bridgend,
Some idea of the complexity is given in Fig. 1. The South Wales which was funded with only 250,000 of
project concerned is the Almond Valley and Seaeld equity constituting 0.3% of the total funding of 83.5
(AV&S) project involving the construction and opera- million. Subordinated debt is often regarded as the
tion of a water treatment facility for East of Scotland equivalent of equity, but this comprises only a further
Water (ESW), with a services contract over 30 years 14% of funds invested in the AV& S project.
110 D. Grimsey, M.K. Lewis / International Journal of Project Management 20 (2002) 107118

Fig. 1. Contractual arrangements in a PFI/PPP project.


D. Grimsey, M.K. Lewis / International Journal of Project Management 20 (2002) 107118 111

Typically, the providers of nance look to the cashow however, there is clearly the risk of losses arising from a
of the project as the source of funds for repayments. changing political climate toward the provision of pub-
Financial security against the project company itself is lic services by the private sector, while the prices
not sought because the company usually has minimal charged for many public sector services are politically
assets and because the nancing is without recourse to sensitive and may be price-capped in some way.
the sponsor companies. However, performance guaran- Nevertheless, in principle, the risks of PPP projects
tees are often made available by the sponsor companies seem little dierent from those of other project nan-
in favour of the lenders. Thus the key principle for large cing activities, and can be evaluated using much the
PPP projects is to achieve a nancial structure with as same basic techniques. The critical question, as always,
little recourse as possible to the sponsors whilst at the is whether revenue streams can cover operating costs,
same time providing sucient credit support so that the service debt nance and provide returns to risk capital.
lenders are satised with the credit risks. Consider the case of infrastructure in the form of a
What are the risks? At least nine risks face any infra- power plant. Sponsors of the power project borrow
structure project [1619]: money to build a generation plant. The sponsors con-
tract to supply power to utilities, projecting that the
. Technical risk, due to engineering and design fail-
contract revenues will suce to pay debt service and
ures;
generate prots. But risks abound. Will the plant actu-
. Construction risk, because of faulty construction
ally be built on time? Will the plant work? And will the
techniques and cost escalation and delays in con-
market value of the contracts enable participants to
struction;
avoid an income shortfall? Can rates be raised to levels
. Operating risk, due to higher operating costs and
that more or less equal the utility's costs for providing
maintenance costs;
electricity, an activity that has historically been regu-
. Revenue risk, e.g. due to trac shortfall or failure
lated by government? None of these questions can sen-
to extract resources, the volatility of prices and
sibly be dodged or ignored in project evaluation.
demand for products and services sold (e.g.
Ultimately, the `bottom line' (i.e. project default risk)
minerals, oce space etc.) leading to revenue de-
is borne by the nanciers, and when considering this
ciency;
scenario the uncertainties concerning future cash ows
. Financial risks arising from inadequate hedging of
can be thought of as falling into two categories:
revenue streams and nancing costs;
. Force majeure risk, involving war and other cala- 1. Moderate (and perhaps not so moderate) devia-
mities and acts of God. tions from estimated cash ow projections, due to
. Regulatory/political risks, due to legal changes uctuating prices, costs, timing delays, minor
and unsupportive government policies; technical problems, etc.
. Environmental risks, because of adverse environ- 2. Disasters to a project, due to a major cost over-
mental impacts and hazards; run, downturn in the economy, change in legal
. Project default, due to failure of the project from a rulings, alteration to the political climate, envir-
combination of any of the above. onmental disaster etc, which could lead to project
failure and bankruptcy.
Successful project design requires expert analysis of
all of them and the design of contractual arrangements The dierence here is not simply one of scale. Rather,
prior to competitive tendering that allocate risk burdens the distinction we have in mind recalls that made by
appropriately. For this purpose the risks can be broadly Frank Knight in his classic 1921 treatise [21]. Knight
categorized as global or elemental [20]. Global risks are distinguished sharply between one type of situation,
those risks that are normally allocated through the which he called ``risk,'' and another situation altogether,
project agreement and typically include political, legal, which he named ``uncertainty.'' In both cases, the actual
commercial and environmental risks. Elemental risks future outcome is not predictable with certainty. But in
are considered as those associated with the construction, the case of risk, the probabilities of the various future
operation, nance and revenue generation components outcomes are known (either exactly mathematically, or
of the project. from past experience of similar situations). In the case
Most of these risks are common to any project nancing of uncertainty, the probabilities of the various future
activity, and apply with more or less force depending on outcomes are merely ``wild guesses'' because
the project concerned. With some PPP agreements, rev-
enue risk and market risk might be low, indeed negligible. the `instance' in question is so entirely unique that
For example, the revenue from a toll bridge might be there are no others or not a sucient number to
more assured than that of an oileld, while a private make it possible to tabulate enough like it to form a
prison is likely to operate with a higher occupancy rate basis for any inference of value about any real
(e.g. 100%) than a luxury hotel! At the same time, probability in the case we are interested in. (p. 226).
112 D. Grimsey, M.K. Lewis / International Journal of Project Management 20 (2002) 107118

Knight went on to argue that the main function of the water from the feeding catchments of Almond Valley
`entrepreneur' is to bear the brunt of this uncertainty of and Seaeld and to provide new arrangements as an
the future. The prots of enterprise (`pure prots' over alternative to the disposal of sewage sludge at sea. The
and above interest payments on debt capital and/or main parties to the project and an indication of their
dividend payments to shareholders) is a reward for connecting relationships are shown in Fig. 1, but in
facing this uncertainty. summary:
However, the reality in the nancing of projects is
. ESW is the procuring entity and the authority
often quite dierent to that envisaged by Knight. For
responsible for providing water, collecting and
example, developers who put up blocks of oces or ats
treating waste water and disposing of sewage
for future sale commonly set up a new limited company
sludges within its region;
for each new building. This company borrows money
. Stirling Water is the special purpose company set
and/or sells equity shares. If the building fails to make a
up for the purpose of nancing, constructing and
prot, this particular company goes bankrupt. But the
operating the AV&S project;
sponsor may survive. The successful entrepreneur is
. Thames Water, MJ Gleeson and Montgomery
often one who knows how to shift the burden of uncer-
Watson are the project sponsors providing risk
tainty onto others, in particular investors and/or cred-
capital and acting respectively as the operator,
itors, in such a way that he himself will survive, waiting
contractor and designer to Stirling Water; and
for a more propitious time for others to again be per-
. MBIA is providing the credit enhancement insur-
suaded to take chances with their money. As Blatt [22]
ance policy so that the project can attain a credit
puts it, the prudent entrepreneur reacts to true uncer-
rating of AAA. While institutional investors pur-
tainty by attempting to make others bear the con-
chased the bonds, the MBIA policy uncondition-
sequences.
ally and irrevocably guarantees scheduled
Clearly, an analysis of the nature of the risks [23
repayments of principal and interest under the
25] and who bears them is vital, and the evalua-
bonds issued and therefore MBIA eectively
tion of projects requires the use of several risk analysis
assumed the role of senior lender.
techniques tailored to suit the interests of the various
parties to the project. Nevertheless, the Knightian dis- Stirling Water funded the 99 million project from:
tinction remains. At least in theory, risk can be insured
. 79.217 million of 27.5 year AAA rated credit
against, diversied, calculated with dierent prob-
enhanced bonds paying a xed coupon of 5.822%;
abilities, but true uncertainty or disaster scenarios are
. 14.835 million of subordinated debt provided by
something else again. How are risks handled in practice?
Thames Water. The subordinated debt has the same
To answer this question we will look at risk analysis
term as the bonds and a similar interest rate; and
from the dierent perspectives of the parties to the
. 4.95 million of equity split between Thames Water
AV&S project.
(49%), MJ Gleeson (41%) and Montgomery Wat-
son (10%). The internal rate of return on the equity
was projected to be 16.56% nominal and 12.5%
5. Risk analysis in practice
real at nancial close.
The AV&S project constitutes a major initiative being
undertaken by ESW to improve the quality of the water
within the River Almond and the Firth of Forth and to 6. Project risks
implement an alternative to the current practice of dis-
posal of sewage sludge at sea. The project is driven by Stirling Water as the project vehicle has taken on
ESW's requirements to comply with its obligations certain construction and operating risks over the con-
under the Urban Water Treatment (Scotland) Regula- tract period but has allocated away contractually many
tions 1994. The project is just one of around ten PFI of these risks to the construction contractor and the
schemes currently in procurement with the three Scot- operator, as is usual under such arrangements. Stirling
tish water authorities in order to comply with new reg- Water retained the risk that projected maintenance costs
ulatory standards to be in force by the end of December are exceeded, such as those arising from shorter than
2000. ESW alone has indicated that capital investment anticipated asset life spans, increased ination on spe-
over 5 years of 850 million is required to achieve the cic items of plant and machinery or the requirement to
required standard in its region. carry out unexpected repairs.
Following a long procurement process of over 2 years, Once the plants are commissioned Stirling Water
in March 1999 ESW entered into the Services Contract receives payment based on the volume of waste water
with Stirling Water pursuant to which Stirling Water treated. The payment mechanism is the key to the risk
agreed to upgrade and improve the treatment of waste apportionment and is not like a normal PFI deal where
D. Grimsey, M.K. Lewis / International Journal of Project Management 20 (2002) 107118 113

the operator is paid on making the facility available. volume throughput or suering larger than expected
The contract is more akin to the UK's design, build, deductions for poor performance would result in lower
nance and operate (DBFO) programme for roads than forecast revenues, which would impact on the
where shadow tolls are paid within payment bands (ie. equity return and may adversely eect Stirling Water's
dened levels of trac volume), a structure in fact ability to make repayments of subordinated debt and
devised by PricewaterhouseCoopers. The aim of such a even coupons on the bonds.
structure is to allocate a sucient element of volume The proportion of the tari indexed to the retail prices
risk to the service company and also to limit the index (RPI) is 65%, applied to all three revenue-gen-
authority's exposure to an increase in payments arising erating bands. The remaining 35% of the tari is not
from a greater than anticipated volume of waste water subject to indexation but is xed for the contract term.
delivered. The AV&S payment bands are as follows: Proportionally this division approximates to the percen-
tage of the nominal cash ow used to service the bond
. The rst band for waste water treatment is for
nancing. However, it is possible that there will not be a
between 0 and 90,000 cu m pa and pays 13.883 p.
precise match between Stirling Water's revenues and
This band is designed to generate sucient rev-
costs resulting in costs rising faster than revenue arising
enue to cover xed operating and maintenance
under the contract and this risk is borne by Stirling
costs and outstanding amounts due under the
Water and its shareholders.
bond issue;
The risk of any adverse changes in law is an important
. The second band for waste water treatment is for
element and on the AV&S project the risk is shared
between 90,000 cu m pa and 101,000 cu m pa and
between ESW and Stirling Water over the rst ten years
pays 9.2555 p. This band is designed to provide
of the contract. After this time, the risk is borne by ESW.
sucient revenue to meet payments under the
subordinated debt; and
. The third band for waste water treatment is for
7. Risk analysis
between 101,000 cu m pa and 107,000 cu m pa and
pays 4.628 p. This band is designed to meet the
Having sketched the key risks inherent in the project
shareholders' target investment returns.
it is important to look at the nature and quantum of
. The fourth band for waste water treatment is for
risk from the dierent perspectives of the main parties
ows in excess of 107,000 cu m pa and is free of
to the project. As a guide to the methodology employed,
charge. This band is designed to cap the payments
Fig. 2 provides a ow chart of the analytical approach.
to be made by ESW.
For each of the three major groups of entities, it sum-
Payment above the third band eectively is capped marises their risk perspective, the key variables, the major
thereby limiting ESW's exposure to payments under the risks they face, and the risk analysis which is appropriate.
contract, while there is a separate rate for the treatment There are several risk analysis techniques available ran-
and disposal of imported sludge. The contract provides ging in complexity from simple expected cost analysis
for payment to be subject to performance-related adjust- through sensitivity analysis and on to more complex
ments geared to any breaches in environmental discharge probabilistic techniques involving computer-aided sta-
consent standards set by SEPA. A major concern for tistical sampling. The technique that should be used, as
Stirling Water is the impact of the quality of the waste indicated, is largely dependent on the exposure of the
water delivered to the works by ESW upon the opera- party to the risk and the nature of the return expected
tor's ability to treat the waste water to a standard which by the party.
results in the discharged waste water and sludge com-
plying with the required consents. For this reason the 7.1. Procurer
contract contains a list of inuent concentration levels.
In the event that these are exceeded and as a result ESW, as the procurer, was only interested in the
Stirling Water is unable to treat the waste water to the expected costs in the form of the payments they would
required standard, then Stirling Water will nevertheless have to make under the contract. In accordance with
be entitled to payment in full. Government guidelines the projected payments to each
Stirling Water is protected through the contract of the bidders were discounted at 6% real and summed
against circumstances inuenced by ESW that would to derive the net present value (NPV) of each of the
impact on the volume of waste water such as the issuing bids. From ESW's perspective, the risk analysis centred
of trade euent discharge consents, the introduction of on establishing equality of treatment between bidders
water metering or greatly increased capital investment for bid evaluation and to facilitate a comparison with
in the sewerage infrastructure leading to a reduction of the public sector comparator in order to demonstrate
water inltration to the sewers. However, under the value-for-money in NPV terms. The value-for-money
payment mechanism, failure to achieve forecast levels of criterion should establish the best means for achieving
114 D. Grimsey, M.K. Lewis / International Journal of Project Management 20 (2002) 107118

Fig. 2. Flow chart of analytical approach.


D. Grimsey, M.K. Lewis / International Journal of Project Management 20 (2002) 107118 115

the required project function for the least cost. Part of Table 1
the value-for-money analysis involves a comparison of Procurer: interest rate sensitivity
the project against a traditional public sector procure- Interest rate % increase/decrease in NPV
ment and operation route known as the public sector of expected cost stream from
comparator. The main risks analysed from this per- base case
spective concerned the following issues: Base case 1% 3.3
Base case 0.5% 1.7
. The contract was conditional on obtaining plan- Base case Base case NPV
ning consent and a risk-sharing mechanism was Base case +0.5% +1.8
Base case +1% +3.6
agreed whereby ESW would pay for a proportion
Base case +1.5% +5.4
of the planning change costs through an adjust- Base case +2% +7.5
ment to the taris;
. Stirling Water had qualied their bid in relation to
passing the risk of costs resulting from nds, such
as antiquities, being uncovered during the con- sensitivity techniques were again used. Table 2 shows
struction phase of the project back to ESW; and the variation in the NPVs at ination assumptions ran-
. Bidders were also asked to calculate the impact of ging from 2 to 6%. The NPVs are reduced at higher
delay to the programmed contract signing date in ination rates partly because the debt element of the
terms of the acceleration costs necessary still to nancing being serviced by the revenue stream of the
achieve the commencement date for the main per- project has not been indexed. The eect of discounting
iod for waste water treatment of January 2001. an element of the project's revenue stream xed in
ESW and its advisers made an assessment of the nominal terms at a xed discount rate of 6% real will
likely delay and adjusted the bids accordingly. lower the NPV of the debt element of the revenue
stream at higher ination rates and therefore lower the
The risks were analysed by establishing the expected overall NPVs. The analysis demonstrates that ESW is
cost to ESW of these risks and adjusting the NPV of the well protected against the risk that ination increases in
bid. In the case of Stirling Water this resulted in approxi- the future.
mately a one percent increase in the NPV of the bid. When It is widely acknowledged that sensitivity analysis is
compared with the competitors, this led to the conclusion limited to indicating the potential eects upon an out-
that their bid provided ESW with the most economic- come, in this case the NPV, if a movement in the vari-
ally advantageous proposal relative to the other bidders. able occurs. Critics of this form of analysis argue that
Under the Project Development Agreement, ESW unless some indication of how likely it is that a quanti-
also retained the risk of movements in the underlying ed movement will occur then this form of analysis is
interest rates up to nancial close, a practice common to not of much use. This argument ignores the fact that
such projects. In this case, the specic risk is that any some important economic variables cannot easily be
increase in the level of interest rates, and thus of the quantied in terms of likelihood and extent of change.
nancing costs for the project, prior to nancial close Who in the UK, for example, during the late seventies
will result in a higher tari being levied, while the dis- could have reasonably predicted that ination would be
count rate used in the analysis is xed at 6% real. 3% or less in the late nineties, a period of only 20
Interest rate risk is generally dicult to quantify with years that is, 10 years less than the contract term in
any real precision. To get a feel for the likely impact of this case study? Under such circumstances, sensitivity
this risk, sensitivity analysis was carried out on the analysis provides a useful tool for analysing these risks
nancial model that yielded the results shown in Table in terms of bid evaluation.
1. The sensitivity analysis indicates that ESW were rea-
sonably well protected against movements in the
underlying interest rate with a moderate rate increase of Table 2
1% leading to an increase in the NPV of the cost stream Procurer: ination sensitivity
of the project of 3.6% (the approximate gradient of the RPI assumption (%) % increase/decrease in NPV
interest rate sensitivity relationship). of expected cost stream from
ESW also carry ination rate risk to the extent that base case
RPI deviates from that projected in the nancial model. 2 +4.79
Whilst it is generally accepted that there is a link between 3 +1.47
interest rates and ination the analysis looked at these 3.5 Base Case NPV
independently since ination rates may not be reected 4 1.36
5 3.79
fully in the ination premia built into interest rates [26]. 6 5.90
Like interest rates, ination is dicult to predict and
116 D. Grimsey, M.K. Lewis / International Journal of Project Management 20 (2002) 107118

7.2. Sponsors all valid combinations of the values of input variables to


simulate all possible outcomes.
From the sponsors' perspective, the risk analysis cen- A summary of the results of the quantitative risk
tres around establishing the potential impact on the analysis on the Stirling Water nancial model is shown
equity return. For the purpose of this exercise, the dis- in Table 3. This analysis suggests that the sponsors are
tinction between subordinated debt and equity is unlikely to achieve the base level rates of return, yet are
ignored because the degree of subordination gives sub- taking a reasonable amount of nancial risk commen-
ordinated debt virtually the same characteristics as surate with risk capital investments in such projects.
equity. Subordinated debt is favoured in the UK Although the relevant risks modelled contained upside
because it enables the sponsors to extract cash from the potential, the analysis also indicates that there is, over-
project vehicle where dividends would be restricted by all, no likely nancial upside for the sponsors. The main
the prot and loss account and also because the interest opportunity for nancial upside comes from increased
is tax deductible. In order to review Stirling Water's waste water volumes, but the payments made by ESW
nancial proposals from the sponsors' perspective an are capped as described earlier. Also, the procurer in
analysis of the impact of the equity risks on the nancial this case was in a strong bargaining position; England
model had to take account of potential upside as well as and France have some of the largest water companies in
downside risk. the world and they were vying for a foothold in the
A simulation exercise was therefore carried out using relatively small Scottish market.
the following methodology. First, a realistic downside
(and upside) case for each risk was dened by ESW's 7.3. Senior lenders
technical adviser Halcrow Crouch to establish a trian-
gular risk distribution for each risk. The relevant risks For senior lenders the nature of non-recourse or lim-
for this analysis were: ited recourse funding clearly carries a rather dierent
risk or credit assessment than a conventional full
. volume risk;
recourse loan where the enforcement of security by the
. the risk of mid-life capital expenditure and asset
lender is additional to its ability to sue the borrower, and
management costs being greater than forecast;
the lender can assess the value of the assets used as col-
. operating cost; and
lateral. With project nancing, the facilities often do not
. operating performance.
have a capital worth, in terms of a wide market, to which
Whilst construction delay is an important project risk lenders would wish to attribute value. Lenders, of course,
it was not included. This was because the risk analysis insist on having the opportunity to step in and rescue a
looked at the risks from the project sponsors' perspec- failing project but they cannot simply sell o the asset to
tive as equity investors in Stirling Water. For them, realise value. In contracts such as AV&S, the assets
delay risk is dealt with contractually through liquidated essentially take the form of the contract with the pro-
damages contained in the construction contract and curing authority. It is therefore understandable that
also business interruption insurance. Eectively, there- senior lenders tend to take a pessimistic view where risk
fore, the risk resides with the construction contractor analysis is concerned. The key dierence between the
and the insurer and not with the project sponsors. senior lenders and the sponsors is that for the senior lender
Second, having delineated the relevant risks for holding debt rather than equity there is never any potential
examination: upside gain in the project, only downside risk that could
reduce the ability of the borrower to make principal and
. a simulation exercise was carried out using the
interest payments under the loan agreement.
@RISK computer software package to determine
the distribution of the relevant risks overall. Then,
third,
. from this analysis an assessment was made of the Table 3
impact on the blended equity/subordinated debt Sponsors: equity/subordinated debt risk analysis
IRR.
Simulation Decrease in blended
The @RISK software package uses a Monte Carlo equity IRR
simulation process to perform a risk analysis. Simula- Minimum simulation result Base case 7.17%
tion in this sense refers to a method whereby the dis- 5% probability of returns being less than: Base case 5.48%
tribution of possible outcomes is generated by letting 25% probability of the returns being less than: Base case 3.9%
the computer recalculate the nancial model over and 50% probability of the returns being less than: Base case 2.52%
over again, each time using dierent randomly selected 75% probability of the returns being less than: Base case 1.47%
95% probability of returns being less than: Base case 0.57%
sets of values for the probability distributions contained Maximum simulation result Base case 0.06%
in the spreadsheet model. In eect, the computer is trying
D. Grimsey, M.K. Lewis / International Journal of Project Management 20 (2002) 107118 117

Senior lenders therefore focus on cover to the income Table 4


stream over the term of the loan and analyse risk to Senior lenders: robustness analysis of cash ows
establish robustness by reference to cover ratios. The Sensitivity Changea ADSCR LLCR
most important of these ratios are the loan life cover (%)
ratio (LLCR) and the annual debt service cover ratio
Base case nancial model 1.26 1.32
(ADSCR). The LLCR provides a snap shot on a given Construction cost +3 1.26 1.32
date of the NPV of the projected cashows from that OPEX +12.5 1.08 1.15
date until retirement of the loan relative to the loan Downside ow 1.07 1.12
outstanding on that particular date. The ADSCR is an Midlife CAPEX +10 1.24 1.29
historic ratio that measures the cashow for the pre- Operational performance 2 1.20 1.26
Combined downside: 1.04 1.10
vious year in relation to the amount of loan principal downside ow plus midlife CAPEX
and interest payable for that period.
a
The sensitivities tested from the lenders' perspective As dened by ESW's technical adviser (see text).
are intended to capture the risks left with the service
company rather than the project as a whole, taking
account of the fact that it will seek to mitigate key risks Overall, the combination of risk analysis techniques
by allocating them away contractually. The main used on the AV&S project demonstrated that:
instruments used for allocating risk will be:
. The project delivers value-for-money to the procur-
ing entity ESW and satises the main government
. The Design and Construction (D&C) Contract criteria for investing in capital projects;
which mitigates the Service Company's exposure . The project has reasonable but not excessive
to design risk and construction cost and time upside potential for the project sponsors and
overrun risk; and downside potential commensurate with the levels
. The Operation and Maintenance (O&M) Contract of return anticipated in the base case; and
which mitigates the Service Company's exposure . The downside sensitivity testing suggests that the
to performance risk and operations and main- project is suciently robust and nancially stable
tenance cost risk. from the viewpoint of lenders.

It is therefore crucial to the nancial robustness of


bids, given the highly geared nancing structure envi- 8. Conclusion
saged, that these risks should be allocated away from
the service company under strong contracts to suitable Project nance and PPP/PFI arrangements are foun-
counterparties. However, even when risk is transferred ded on the transfer of risk from the public to the private
contractually some residual risk will remain with the sector under circumstances where the private sector is
service company. For instance, if the operating costs best placed to manage the risk. The general principles
turned out to be signicantly greater than originally are common to all public sectors insofar as the projects
forecast it is conceivable that the service company could seek to shift risk from the public sector to the supplier
decide that it was in its best interests to share the pain and oer a prot incentive to the private sector in
with the O&M Contractor by agreeing to a price return. However, the principal aim for the public sector
increase to absorb some of the increased cost, rather is to achieve value-for-money in the services provided
than running the risk of the O&M Contractor aban- while ensuring that the private sector entities meet their
doning the contract. The operating expenditure (OPEX) contractual obligations properly and eciently.
and capital expenditure (CAPEX) sensitivities tested are Value-for-money and risk transfer principles accep-
intended to reect this residual risk. ted, fundamentally PPP projects are viable only if a
Table 4 below displays the results of the robustness robust, long term revenue stream, over the period of the
analysis on Stirling Water's nancial model. The concession, can be established. A framework for inves-
ADSCR and LLCR (see earlier denitions of these tigating and carrying out an analysis of the risks has
cover ratios) only fall below the minimum requirement been outlined in this paper that systematically views
(ADSCR of 1.15 and LLCR of 1.15) under the OPEX, project risk from the perspectives of the procuring
Flow and Combined Scenario. However, in no case do entity, the project sponsors and the senior lenders. For a
the ADSCR or LLCR fall below 1.0, which would project to be successful, the diering (and conicting)
indicate a default under the loan agreement. This ana- needs of these parties must be satised in the risk allo-
lysis indicates to the senior lenders that the Stirling cation process, and this would seem to have been
Water nancing plan is reasonably robust to support achieved in the waste water treatment project used to
the level of funding anticipated. illustrate the application of the framework.
118 D. Grimsey, M.K. Lewis / International Journal of Project Management 20 (2002) 107118

References [12] Dixit AK, Pindyck R. S., Investment under uncertainty. Prince-
ton (NJ): Princeton University Press, 1994.
[13] Adam C. Embedded options in infrastructure projects. Journal of
[1] McCarthy SC, Perry JG. BOT contracts for water supply. In: Applied Finance and Investment 1996;1(1):336.
World water 89. Thos. Telford London: 1989. [14] Peirson G, McBride P. Public/private sector infrastructure
[2] Augenblick M., Scott Custer Jr. B. The build, operate and trans- arrangements. CPA Communique 1996;73:14.
fer (BOT) approach to infrastructure projects in the developing [15] Grimsey D, Graham R. PFI in the NHS. Engineering, Con-
countries. Working papers. World Bank, Washington: August struction and Architectural Management 1997;4(3):21531.
1990. [16] Chapman CB, Ward SC. Project risk management processes,
[3] Monod J. The private sector and the management of public techniques and insights. Chichester: John Wiley and Sons, 1997.
drinking water supply. Washington: World Bank, 1982. [17] Kerzner H. Project management, a systems approach to plan-
[4] Owen G, Merna A. The private nance initiative. Engineering, ning, scheduling and controlling. 3rd ed. New York: Van Nos-
Construction and Architectural Management 1997;4(3):21531. trand Reinhold, 1989.
[5] Mustafa A. Publicprivate partnership: an alternative institu- [18] Smith RC, Walter I. Global nancial services. New York: Harper
tional model for implementing the private nance initiative in the Business, 1990.
provision of transport infrastructure. Journal of Project Finance [19] Thobani M. Private infrastructure, public risk. Finance and
1999;5(2):6479. Development 1998;36(1):503.
[6] Horner R. Public private partnerships, the way forward. Irish [20] Merna A, Smith NJ. Privately nanced concession contract, Vols. 1
Banking Review Summer: 1999; 25-34. and 2. 2nd ed. Hong Kong: Asia Law and Practice, 1996.
[7] East Asia Analytical Unit. Asia's infrastructure in the crisis, har- [21] Knight F. Risk, uncertainty and prot. Boston: Houghton Mif-
nessing private enterprise. Canberra: Department of Foreign in, 1921.
Aairs and Trade, 1998. [22] Blatt JM. Dynamic economic systems. New York: Sharpe, 1983.
[8] International Finance Corporation. Project nance in developing [23] World Bank. Toolkits for private sector participation in water
countries. Washington:: The World Bank, 1999. and sanitation. Washington: World Bank, 1997.
[9] Martini CA, Lee DQ. Diculties in infrastructure nancing. [24] Economic Committee APEC. Infrastructure development
Journal of Applied Finance and Investment 1996;1(1):247. conference summary and case studies. Singapore: APEC Secre-
[10] Threadgold A. Private nancing of infrastructure and other long- tariat, 1996.
term capital projects. Journal of Applied Finance and Investment [25] CEDA. Infrastructure and economic development. CEDA infor-
1996;1(1):712. mation paper no. 60. Committee for Economic Development in
[11] Lewis M.K. Banking on real estate, In: Fair D.E., Raymond R. Australia, Melbourne: 1999.
editors. The competitiveness of nancial institutions and centres [26] Lewis MK, Mizen, PD. Monetary economics. Oxford University
in Europe. Dordrecht: Kluwer, 1994. Press, Oxford, 2000.

You might also like