Fabrication Grand Schedule of Air Heater Unit 3 & 4

PLTU Bukit Asam PT PLN (Persero) KIT SUMBAGSEL

ID Task Name Duration Start Finish ay '17 Jun '17 Jul '17 Aug '17 Sep '17 Oct '17 Nov '17 Dec '17 Jan '18 Feb '18 Mar '18 Apr '18 May '18 Jun '18 Jul '18 Aug '18 Sep '18 Oct '18 Nov '18 Dec '18 Jan '19
8 152229 5 121926 3 10172431 7 142128 4 111825 2 9 162330 6 132027 4 111825 1 8 152229 5 121926 5 121926 2 9 162330 7 142128 4 111825 2 9 162330 6 132027 3 101724 1 8 152229 5 121926 3 10172431 7 1421
1 AIR HEATER 588 days Mon May 22, '17 Mon Dec 31, '18
2 Kesepakatan Kick Off Meeting 1 day Mon May 22, '17 Tue May 23, '17
3 PEKERJAAN DI WORKSHOP 250 days Mon Jun 19, '17 Sat Feb 24, '18
4 SURVEY & PERSIAPAN PROYEK 4 days Mon Jun 19, '17 Fri Jun 23, '17
5 Contract sign 1 day Mon Jun 19, '17 Tue Jun 20, '17
6 Kick of meeting (internal) 1 day Tue Jun 20, '17 Wed Jun 21, '17
7 Pre-Production Meeting 2 days Wed Jun 21, '17 Fri Jun 23, '17
8 ENGINEERING & APPROVAL DRAWING 60 days Mon Jun 19, '17 Fri Aug 18, '17
9 Spesifikasi Teknis 14 days Mon Jun 19, '17 Mon Jul 3, '17
10 GA Drawing Unit 3 & Unit 4 60 days Mon Jun 19, '17 Fri Aug 18, '17
14 Detail Drawing Unit 3 & Unit 4 30 days Mon Jun 19, '17 Wed Jul 19, '17
21 Other Document 30 days Mon Jun 19, '17 Wed Jul 19, '17
24 PROCUREMENT 199 days Mon Jun 19, '17 Thu Jan 4, '18
25 Usulan Pengadaan Barang Lokal 19 days Mon Jun 19, '17 Sat Jul 8, '17
26 Usulan Pengadaan Barang Import 10 days Mon Jun 19, '17 Thu Jun 29, '17
27 Pengiriman PO Tube Sheet 3 days Mon Jun 19, '17 Thu Jun 22, '17
28 Import Material PT Kalorindo 104 days Thu Jun 22, '17 Wed Oct 4, '17
30 Import Material oleh PT Midigio 185 days Mon Jun 19, '17 Thu Dec 21, '17
34 Local Material 60 days Sat Jul 8, '17 Wed Sep 6, '17
38 Consumable Material 30 days Wed Sep 6, '17 Fri Oct 6, '17
42 Inspeksi Material Lokal 3 days Mon Sep 18, '17 Thu Sep 21, '17 9/18 9/21
43 Inspeksi Material Tube Sheet 3 days Mon Sep 18, '17 Thu Sep 21, '17 9/18 9/21
44 Inspeksi Material Tube 3,33m 2 days Wed Sep 27, '17 Fri Sep 29, '17
45 Inspeksi Material Tube 9,885m dan Expansion Joint 7 days Thu Dec 28, '17 Thu Jan 4, '18 12/28 1/4
46 PABRIKASI 131 days Thu Sep 21, '17 Tue Jan 30, '18
47 Baffle 48 days Thu Sep 21, '17 Wed Nov 8, '17
57 Part Support 70 days Mon Oct 2, '17 Mon Dec 11, '17
78 Assembling 83 days Wed Nov 8, '17 Tue Jan 30, '18
83 PACKAGING 10 days Sun Jan 21, '18 Wed Jan 31, '18
89 PENGIRIMAN 72 days Thu Dec 14, '17 Sat Feb 24, '18
90 Pengurusan Perijinan untuk di PLTU Bukit Asam & Dokumen 14 days Thu Dec 14, '17 Thu Dec 28, '17
Lainnya
95 Seleksi Ekspedisi 14 days Thu Dec 14, '17 Thu Dec 28, '17
96 Pengurusan Perijinan Proses Transportasi 14 days Thu Dec 14, '17 Thu Dec 28, '17
99 Finalisasi Ekspedisi 7 days Thu Dec 28, '17 Thu Jan 4, '18
100 Alat Berat Siap Operasi Di PLTU 5 days Thu Jan 4, '18 Tue Jan 9, '18
101 Pengiriman Hopper Atas (1 kontainer) 8 days Sun Jan 28, '18 Mon Feb 5, '18
102 Pengiriman Directing (1 kontainer) 8 days Sun Jan 28, '18 Mon Feb 5, '18
103 Pengiriman Deflecting (1 kontainer) 8 days Mon Feb 5, '18 Tue Feb 13, '18
104 Pengiriman Casing Luar (1 kontainer) 8 days Mon Feb 5, '18 Tue Feb 13, '18
105 Pengiriman Rockwool + Consumable (2 kontainer) 8 days Tue Feb 13, '18 Wed Feb 21, '18
106 Pengiriman Struktur (1 trailer) 8 days Tue Feb 13, '18 Wed Feb 21, '18
107 Pengiriman Lower Bundle Tahap 1 (3 Bundle) 8 days Tue Feb 13, '18 Wed Feb 21, '18
108 Pengiriman Lower Bundle Tahap 2 (3 Bundle) 8 days Tue Feb 13, '18 Wed Feb 21, '18
109 Pengiriman Lower Bundle Tahap 3 (2 Bundle) 8 days Tue Feb 13, '18 Wed Feb 21, '18
110 Pengecekan Barang Datang Dengan Surat Jalan 3 days Wed Feb 21, '18 Sat Feb 24, '18
111 Serah Terima Barang Dengan PT Midigio 1 day Fri Feb 23, '18 Sat Feb 24, '18
112 PEKERJAAN DI SITE (direncanakan pemasangan secara seri) 305 days Thu Mar 1, '18 Mon Dec 31, '18
113 UNIT 4 63 days Thu Mar 1, '18 Thu May 3, '18
114 Pembongkaran Air Heater existing 11 days Thu Mar 1, '18 Mon Mar 12, '18
115 PEMASANGAN AIR HEATER UNIT 4 49 days Sun Mar 4, '18 Sun Apr 22, '18
116 Tools, Consumable Parts, Safety Equipment siap dikirim 7 days Sun Mar 4, '18 Sun Mar 11, '18
117 Persiapan 7 days Sun Mar 4, '18 Sun Mar 11, '18
122 Pemasangan Lower Bundle 4 days Sun Mar 11, '18 Thu Mar 15, '18
123 Pemasangan Hopper Bagian Bawah 3 days Thu Mar 15, '18 Sun Mar 18, '18
124 Pemasangan Upper Bundle 19 days Sun Mar 18, '18 Fri Apr 6, '18
125 Pemasangan Deflecting 3 days Fri Apr 6, '18 Mon Apr 9, '18
126 Pemasangan Expantion Joint 2 days Mon Apr 9, '18 Wed Apr 11, '18
127 Pemasangan Structure Plate Cover Bawah 2 days Wed Apr 11, '18 Fri Apr 13, '18
128 Pemasangan Structure Plate Cover Atas 3 days Wed Apr 11, '18 Sat Apr 14, '18
129 Pemasangan Rockwool (Termasuk Cover Rockwool) 2 days Fri Apr 13, '18 Sun Apr 15, '18
Fabrication Grand Schedule of Air Heater Unit 3 & 4
PLTU Bukit Asam PT PLN (Persero) KIT SUMBAGSEL

ID Task Name Duration Start Finish ay '17 Jun '17 Jul '17 Aug '17 Sep '17 Oct '17 Nov '17 Dec '17 Jan '18 Feb '18 Mar '18 Apr '18 May '18 Jun '18 Jul '18 Aug '18 Sep '18 Oct '18 Nov '18 Dec '18 Jan '19
8 152229 5 121926 3 10172431 7 142128 4 111825 2 9 162330 6 132027 4 111825 1 8 152229 5 121926 5 121926 2 9 162330 7 142128 4 111825 2 9 162330 6 132027 3 101724 1 8 152229 5 121926 3 10172431 7 1421
130 Pemasangan Casing (Seluruh Sisi Air Heater) 3 days Sat Apr 14, '18 Tue Apr 17, '18
131 Pemasangan Manhole Plate 3 days Sat Apr 14, '18 Tue Apr 17, '18
132 Pemasangan Ducting 2 days Sun Apr 15, '18 Tue Apr 17, '18
133 Pemasangan Hopper Bagian Atas 2 days Sun Apr 15, '18 Tue Apr 17, '18
134 Pemasangan Atap 2 days Tue Apr 17, '18 Thu Apr 19, '18
135 Pemasangan Conveyor dan Blower 2 days Tue Apr 17, '18 Thu Apr 19, '18
136 Pengujian Struktur Bangunan 2 days Thu Apr 19, '18 Sat Apr 21, '18
137 Pembersihan Area Kerja 1 day Sat Apr 21, '18 Sun Apr 22, '18
138 PENGETESAN 4 21 days Thu Apr 12, '18 Thu May 3, '18
139 Persiapan 7 days Fri Apr 13, '18 Fri Apr 20, '18
143 Inspeksi Pembongkaran 5 days Fri Apr 13, '18 Wed Apr 18, '18
144 Inspeksi Pemasangan 10 days Thu Apr 12, '18 Sun Apr 22, '18
145 Pengujian Pneumatic Bundle 2 days Fri Apr 20, '18 Sun Apr 22, '18
146 Pengujian Sambungan Las (NDT) 1 day Sat Apr 21, '18 Sun Apr 22, '18
147 Final Inspection Istallation 1 day Sun Apr 22, '18 Mon Apr 23, '18
148 Preliminary Run (Pengujian Sebelum Commissioning Test) 4 days Mon Apr 23, '18 Fri Apr 27, '18
151 Commissioning Test 6 days Fri Apr 27, '18 Thu May 3, '18
155 UNIT 3 60 days Thu Nov 1, '18 Mon Dec 31, '18
156 Pembongkaran Air Heater existing 11 days Thu Nov 1, '18 Mon Nov 12, '18
157 PEMASANGAN AIR HEATER UNIT 3 49 days Thu Nov 1, '18 Thu Dec 20, '18
158 Tools, Consumable Parts, Safety Equipment siap dikirim 7 days Thu Nov 1, '18 Thu Nov 8, '18
159 Persiapan 7 days Thu Nov 1, '18 Thu Nov 8, '18
164 Pemasangan Lower Bundle 4 days Thu Nov 8, '18 Mon Nov 12, '18
165 Pemasangan Hopper Bagian Bawah 3 days Mon Nov 12, '18 Thu Nov 15, '18
166 Pemasangan Upper Bundle 19 days Thu Nov 15, '18 Tue Dec 4, '18
167 Pemasangan Deflecting 3 days Tue Dec 4, '18 Fri Dec 7, '18
168 Pemasangan Expantion Joint 2 days Fri Dec 7, '18 Sun Dec 9, '18
169 Pemasangan Structure Plate Cover Bawah 2 days Sun Dec 9, '18 Tue Dec 11, '18
170 Pemasangan Structure Plate Cover Atas 3 days Sun Dec 9, '18 Wed Dec 12, '18
171 Pemasangan Rockwool (Termasuk Cover Rockwool) 2 days Tue Dec 11, '18 Thu Dec 13, '18
172 Pemasangan Casing (Seluruh Sisi Air Heater) 3 days Wed Dec 12, '18 Sat Dec 15, '18
173 Pemasangan Manhole Plate 3 days Wed Dec 12, '18 Sat Dec 15, '18
174 Pemasangan Ducting 2 days Thu Dec 13, '18 Sat Dec 15, '18
175 Pemasangan Hopper Bagian Atas 2 days Thu Dec 13, '18 Sat Dec 15, '18
176 Pemasangan Atap 2 days Sat Dec 15, '18 Mon Dec 17, '18
177 Pemasangan Conveyor dan Blower 2 days Sat Dec 15, '18 Mon Dec 17, '18
178 Pengujian Struktur Bangunan 2 days Mon Dec 17, '18 Wed Dec 19, '18
179 Pembersihan Area Kerja 1 day Wed Dec 19, '18 Thu Dec 20, '18
180 PENGETESAN 3 23 days Sat Dec 8, '18 Mon Dec 31, '18
181 Persiapan 7 days Tue Dec 11, '18 Tue Dec 18, '18
185 Inspeksi Pembongkaran 5 days Tue Dec 11, '18 Sun Dec 16, '18
186 Inspeksi Pemasangan 10 days Sat Dec 8, '18 Tue Dec 18, '18
187 Pengujian Pneumatic Bundle 2 days Sun Dec 16, '18 Tue Dec 18, '18
188 Pengujian Sambungan Las (NDT) 1 day Mon Dec 17, '18 Tue Dec 18, '18
189 Final Inspection Istallation 1 day Thu Dec 20, '18 Fri Dec 21, '18
190 Preliminary Run (Pengujian Sebelum Commissioning Test) 4 days Fri Dec 21, '18 Tue Dec 25, '18
193 Commissioning Test 6 days Tue Dec 25, '18 Mon Dec 31, '18
197 AS BUILT DRAWING & REPORTING 7 days Mon Dec 24, '18 Mon Dec 31, '18 12/31