Pekerjaan Pembangunan

Prasarana Kereta Api Ringan


Light Rail Transit (LRT) Lintas
Pelayanan Taman Mini - Cibubur
Date Figure (Data Gambar):
19 July 2017 at 19:58

Location (Lokasi) :
KM 9+100 Jagorawi CSCB 007

Obyek Figure (Obyek Gambar):


Trial Chipping Joint Construction Using Retarder
(Admixture Type D)

Annotation Figure (Keterangan Gambar):


Preparation Formwork For Pouring Concrete

Date Figure (Data Gambar):


19 July 2017 at 20:27

Location (Lokasi) :
KM 9+100 Jagorawi CSCB 007

Obyek Figure (Obyek Gambar):


Trial Chipping Joint Construction Using Retarder
(Admixture Type D)

Annotation Figure (Keterangan Gambar):


Pouring Concrete fc 50 Mpa into casting area

Date Figure (Data Gambar):


19 July 2017 at 20:28

Location (Lokasi) :
KM 9+100 Jagorawi CSCB 007

Obyek Figure (Obyek Gambar):


Trial Chipping Joint Construction Using Retarder
(Admixture Type D)

Annotation Figure (Keterangan Gambar):


Pouring Concrete fc 50 Mpa into casting area

Date Figure (Data Gambar):


19 July 2017 at 20:30

Location (Lokasi) :
KM 9+100 Jagorawi CSCB 007

Obyek Figure (Obyek Gambar):


Trial Chipping Joint Construction Using Retarder
(Admixture Type D)

Annotation Figure (Keterangan Gambar):


After Pouring Concrete fc 50 Mpa
Pekerjaan Pembangunan
Prasarana Kereta Api Ringan Light
Rail Transit (LRT) Lintas
Pelayanan Taman Mini - Cibubur
Date Figure (Data Gambar):
19 July 2017 at 20:30

Location (Lokasi) :
KM 9+100 Jagorawi CSCB 007

Obyek Figure (Obyek Gambar):


Trial Chipping Joint Construction Using Retarder
(Admixture Type D)

Annotation Figure (Keterangan Gambar):


Four samples for casting retarder 1 hour, 2
hours, 3 & 4 hours

Date Figure (Data Gambar):


19 July 2017 at 21:30

Location (Lokasi) :
KM 9+100 Jagorawi CSCB 007

Obyek Figure (Obyek Gambar):


Trial Chipping Joint Construction Using Retarder
(Admixture Type D)

Annotation Figure (Keterangan Gambar):


Casting retarder 1 hour after pouring concrete
box number 1

Date Figure (Data Gambar):


19 July 2017 at 21:30

Location (Lokasi) :
KM 9+100 Jagorawi CSCB 007

Obyek Figure (Obyek Gambar):


Trial Chipping Joint Construction Using Retarder
(Admixture Type D)

Annotation Figure (Keterangan Gambar):


Visual condition after retarder poured Box
Number 1

Date Figure (Data Gambar):


19 July 2017 at 22:30

Location (Lokasi) :
KM 9+100 Jagorawi CSCB 007

Obyek Figure (Obyek Gambar):


Trial Chipping Joint Construction Using Retarder
(Admixture Type D)

Annotation Figure (Keterangan Gambar):


Casting retarder 2 hours after pouring concrete
Box Number 2
Pekerjaan Pembangunan
Prasarana Kereta Api Ringan Light
Rail Transit (LRT) Lintas
Pelayanan Taman Mini - Cibubur
Date Figure (Data Gambar):
19 July 2017 at 20:30

Location (Lokasi) :
KM 9+100 Jagorawi CSCB 007

Obyek Figure (Obyek Gambar):


Trial Chipping Joint Construction Using Retarder
(Admixture Type D)

Annotation Figure (Keterangan Gambar):


Visual condition after retarder poured, Box
Number 2

Date Figure (Data Gambar):


19 July 2017 at 23:30

Location (Lokasi) :
KM 9+100 Jagorawi CSCB 007

Obyek Figure (Obyek Gambar):


Trial Chipping Joint Construction Using Retarder
(Admixture Type D)

Annotation Figure (Keterangan Gambar):


Casting retarder 3 hour after pouring concrete
box number 3

Date Figure (Data Gambar):


19 July 2017 at 23:30

Location (Lokasi) :
KM 9+100 Jagorawi CSCB 007

Obyek Figure (Obyek Gambar):


Trial Chipping Joint Construction Using Retarder
(Admixture Type D)

Annotation Figure (Keterangan Gambar):


Visual condition after retarder poured Box
Number 3

Date Figure (Data Gambar):


20 July 2017 at 14:30

Location (Lokasi) :
KM 9+100 Jagorawi CSCB 007

Obyek Figure (Obyek Gambar):


Trial Chipping Joint Construction Using Retarder
(Admixture Type D)

Annotation Figure (Keterangan Gambar):


Spraying cast area using water jet pump
Pekerjaan Pembangunan
Prasarana Kereta Api Ringan Light
Rail Transit (LRT) Lintas
Pelayanan Taman Mini - Cibubur
Date Figure (Data Gambar):
20 July 2017 at 14:30

Location (Lokasi) :
KM 9+100 Jagorawi CSCB 007

Obyek Figure (Obyek Gambar):


Trial Chipping Joint Construction Using Retarder
(Admixture Type D)

Annotation Figure (Keterangan Gambar):


Spraying cast area using water jet pump

Date Figure (Data Gambar):


20 July 2017 at 14:35

Location (Lokasi) :
KM 9+100 Jagorawi CSCB 007

Obyek Figure (Obyek Gambar):


Trial Chipping Joint Construction Using Retarder
(Admixture Type D)

Annotation Figure (Keterangan Gambar):


Visual condition after Spraying using water jet
Pump

Date Figure (Data Gambar):


20 July 2017 at 14:35

Location (Lokasi) :
KM 9+100 Jagorawi CSCB 007

Obyek Figure (Obyek Gambar):


Trial Chipping Joint Construction Using Retarder
(Admixture Type D)

Annotation Figure (Keterangan Gambar):


Visual condition after Spraying using Water jet
pump Box Number 1

Date Figure (Data Gambar):


20 July 2017 at 14:35

Location (Lokasi) :
KM 9+100 Jagorawi CSCB 007

Obyek Figure (Obyek Gambar):


Trial Chipping Joint Construction Using Retarder
(Admixture Type D)

Annotation Figure (Keterangan Gambar):


Visual condition after Spraying using Water jet
pump Box Number 2
Pekerjaan Pembangunan
Prasarana Kereta Api Ringan Light
Rail Transit (LRT) Lintas
Pelayanan Taman Mini - Cibubur
Date Figure (Data Gambar):
20 July 2017 at 14:35

Location (Lokasi) :
KM 9+100 Jagorawi CSCB 007

Obyek Figure (Obyek Gambar):


Trial Chipping Joint Construction Using Retarder
(Admixture Type D)

Annotation Figure (Keterangan Gambar):


Visual condition after Spraying using Water jet
pump Box Number 3

Date Figure (Data Gambar):


20 July 2017 at 14:35

Location (Lokasi) :
KM 9+100 Jagorawi CSCB 007

Obyek Figure (Obyek Gambar):


Trial Chipping Joint Construction Using Retarder
(Admixture Type D)

Annotation Figure (Keterangan Gambar):


Visual condition after Spraying using Water jet
pump Box Number 4

Date Figure (Data Gambar):


20 July 2017 at 14:35

Location (Lokasi) :
KM 9+100 Jagorawi CSCB 007

Obyek Figure (Obyek Gambar):


Trial Chipping Joint Construction Using Retarder
(Admixture Type D)

Annotation Figure (Keterangan Gambar):


Visual condition after Spraying using Water jet
pump Box Number 1

Date Figure (Data Gambar):


20 July 2017 at 14:35

Location (Lokasi) :
KM 9+100 Jagorawi CSCB 007

Obyek Figure (Obyek Gambar):


Trial Chipping Joint Construction Using Retarder
(Admixture Type D)

Annotation Figure (Keterangan Gambar):


Visual condition after Spraying using Water jet
pump Box Number 2