EMI Erection works Progress status as of 26.09.

2017

Collector well 1:

Pump house:

HOT crane erection completed


Concrete chipping in floor slab of pump house is under progress for base frame erection
VT Pump erection, panel erection and other electrical works are yet to commence
Work men strength of EMI erection agency 04 Persons

Control room:

LT Panel erection completed.


Other electrical works yet to commence.

Thirukampliyur

Pump house:

HOT crane erection completed.


Base frame erected over floor slab for 05 VT Pumps and presently master level aligning
works is under progress. Cement grouting yet to be done.
VT Pump erection works are yet to commence.
Work men strength of EMI erection agency 09 Persons ( 05 Mechanical & 04
Electrical).
Control room:

VCB panel ( Indoor Type) erection completed.


Cable routing ( Cable tray) work is under progress.
Erection of Starter Panels are yet to commence.

Transformer yard:

Two Pole structure work completed


Transformer erection work completed.
Transformer yard civil works except fencing, earth pit, all civil works completed

Kottaikaranpatty

Pump house:

HOT crane erection is under progress.


Base frame fabrication completed for 05 VT Pumps
Concrete chipping in floor slab of pump house is yet to commence for base frame erection
VT Pump erection works are yet to commence.
Work men strength of EMI erection agency Nil

Control room:
EMI Work is yet to commence

Transformer yard:

Two Pole structure work completed


Transformer yard civil works except fencing, earth pit, all civil works completed
Transformer erection is yet to commenced.

Guziliamparai

Pump house:

EMI erection works are yet to commence.

Control room:

EMI Works are yet to commence

Transformer yard:

Six Pole structure work is under progress


Transformer yard civil works except fencing, earth pit, all civil works completed
Transformer erection is yet to be commenced.
Kovilur

Pump house:

EMI erection works are yet to commence.

Control room:

EMI Works are yet to commence

Transformer yard:

Six Pole structure work is under progress


Transformer yard civil works yet to be commenced.
Transformer erection is yet to be commenced.

Vadamadurai

EMI erection works are yet to commence.

Reddiyarchatram

EMI erection works are yet to commence.