You are on page 1of 203

No.

URAIAN SATUAN VOLUME HARGA SATUAN


(Rp)
1 M' Pagar Sementara Dari Kayu Tinggi 2
A-01 m

Dolken Kayu
- 8-10 / 400 cm Btg 1.25 28,000.00

Semen
- Portland Kg 2.5 1,406.00

- Pasir beton M3 0.005 255,400.00

- Koral Beton 2/3 M3 0.009 211,100.00

Kayu balok
- terentang M3 0.072 2,640,000.00

Paku Biasa 2" -


- 5" Kg 0.06 23,400.00
- Residu Kg 0.4 8,100.00
- Pekerja Oh 0.4 42,000.00

- Tukang Kayu Oh 0.2 65,000.00

- Kepala Tukang Oh 0.02 75,000.00


- Mandor Oh 0.02 80,000.00
Jumlah
Dibulatkan

A-02 1 M' Pagar Sementara Seng Gelombang Tinggi 2 m

Dolken Kayu
- 8-10 / 400 cm Btg 1.25 28,000.00

Semen
- Portland Kg 2.5 1,406.00
Seng
Gelombang
- BJLS-30 Lbr 1.2 62,900.00

- Pasir beton M3 0.005 255,400.00

- Koral Beton 2/3 M3 0.009 211,100.00

Kayu balok
- terentang M3 0.072 2,640,000.00

Paku Biasa 2" -


- 5" Kg 0.06 23,400.00

- Meni Besi Kg 0.45 30,400.00


- Pekerja Oh 0.4 42,000.00

- Tukang Kayu Oh 0.2 65,000.00

- Kepala Tukang Oh 0.02 75,000.00


- Mandor Oh 0.02 80,000.00
Jumlah
Dibulatkan

1 M' Pagar
SementaraKawat Duri
A-03 Tinggi 1,80 m

Dolken Kayu
- 8-10 / 400 cm Btg 1 28,000.00

Semen
- Portland Kg 2 1,406.00

- Kawat Duri Kg 2.5 63,500.00

- Pasir beton M3 0.005 255,400.00


- Koral Beton 2/3 M3 0.009 211,100.00

Paku Biasa 2" -


- 5" Kg 0.06 23,400.00
- Pekerja Oh 0.3 42,000.00

- Tukang Kayu Oh 0.2 65,000.00

- Kepala Tukang Oh 0.02 75,000.00


- Mandor Oh 0.02 80,000.00
Jumlah
Dibulatkan

1 M2 Pengukuran Dan
A-04 Pasang Bouwplank

- Kayu kaso 5/7 M3 0.012 1,870,500.00

Paku Biasa 2" -


- 5" Kg 0.02 23,400.00

Kayu papan
- albasia M3 0.007 2,071,700.00
- Pekerja Oh 0.1 42,000.00

- Tukang Kayu Oh 0.1 65,000.00

- Kepala Tukang Oh 0.01 75,000.00


- Mandor Oh 0.005 80,000.00
Jumlah
Dibulatkan

1 M2 Pembuatan Kantor
Sementara dgn Lantai
A-05 Diplester

Dolken Kayu
- 8-10 / 400 cm Btg 1.25 28,000.00
Kayu Balok
- terentang M3 0.18 2,640,000.00

- Paku Biasa Kg 0.85 23,400.00

- Besi Strip Kg 1.1 26,800.00

Semen
- Portland Kg 35 1,406.00

- Pasir Pasang M3 0.15 233,400.00

- Pasir beton M3 0.1 255,400.00

- Koral Beton2/3 M3 0.15 211,100.00

- Bata Merah Bh 30 775

- Seng Plat m' 0.25 15,815.00

Kawat
- harmonika M2 2 35,900.00

Kaca Polos
- 3mm M2 0.08 87,400.00

- Kunci Tanam Bh 0.15 94,500.00

Plywood 120 x
- 240 x 0,4 cm Lbr 0.06 140,000.00
- Pekerja Oh 2 42,000.00

- Tukang Kayu Oh 2 65,000.00

- Tukang Batu Oh 1 65,000.00

- Kepala Tukang Oh 0.3 75,000.00


- Mandor Oh 0.05 80,000.00
Jumlah
Dibulatkan
1 M2 Pembuatan Gudang
A-06 Semen dan Alat-alat

Dolken Kayu
- 8-10 / 400 cm Btg 1.7 28,000.00

Kayu balok
- terentang M3 0.21 2,640,000.00

- Paku Biasa Kg 0.3 23,400.00

Semen
- Portland Kg 10.5 1,406.00

- Pasir Beton M3 0.03 255,400.00

- Koral Beton 2/3 M3 0.05 211,100.00

Seng
Gelombang
- BJLS 30 Lbr 1.5 62,900.00
- Pekerja Oh 1 42,000.00

- Tukang Kayu Oh 2 65,000.00

- Kepala Tukang Oh 0.2 75,000.00


- Mandor Oh 0.05 80,000.00
Jumlah
Dibulatkan
1 M2 Pembuatan Bedeng
A-07 Buruh

Dolken Kayu
- 8-10 / 400 cm Btg 1.25 28,000.00

Kayu balok
- terentang M3 0.186 2,640,000.00
- Paku Biasa Kg 0.3 23,400.00

Semen
- Portland Kg 18 1,406.00

- Pasir Beton M3 0.03 255,400.00

- Koral Beton 2/3 M3 0.05 211,100.00

Seng
Gelombang
- BJLS 30 Lbr 1.5 62,900.00
- Pekerja Oh 1 42,000.00

- Tukang Kayu Oh 2 65,000.00

- Kepala Tukang Oh 0.2 75,000.00


- Mandor Oh 0.05 80,000.00
Jumlah
Dibulatkan
1 M2 Membersihkan Lapangan dan
A-08 Perataan
- Pekerja Oh 0.1 42,000.00
- Mandor Oh 0.05 80,000.00
Jumlah
Dibulatkan
1M2 Pembuatan Jalan
A-09 Sementara

Batu Belah
- 15/20 M3 0.15 205,500.00

- Batu Pecah 5/7 M3 0.09 196,000.00

- Pasir Pasang M3 0.01 233,400.00


- Pekerja Oh 1 42,000.00
- Mandor Oh 0.05 80,000.00
Jumlah
Dibulatkan
1 M3 Bongkaran Beton
A-10 Bertulang
- Pekerja Oh 6.667 42,000.00
- Mandor Oh 0.333 80,000.00
Jumlah
Dibulatka
n

A-11 1 M3 Bongkaran Dinding Tembok Bata Merah


- Pekerja Oh 6.667 42,000.00
- Mandor Oh 0.033 80,000.00
Jumlah
Dibulatkan

1 M Pagar beton Pracetak ( 5 x 50 x 213 )


A-12 cm

Panel Beton
- Pracetak Lbr 0.986 199,200.00

Kolom Beton
- Pracetak Btg 0.525 264,000.00

- Pasir Beton M3 0.074 255,400.00

- Koral 2/3 M3 0.146 211,100.00

Semen abu -
- abu Kg 45 1,406.00
- Pekerja Oh 0.375 42,000.00

- Tukang Batu Oh 0.125 65,000.00

- Kepala Tukang Oh 0.012 75,000.00


- Mandor Oh 0.019 80,000.00
Jumlah
Dibulatkan

A-13 1 M Pagar kawat ayam tiang besi L50.50.5, tinggi 1 m'

Kawat ram
- ayam Lbr 0.434 14,900.00
Besi siku L
- 50.50.5 Kg 6.786 18,300.00

Besi pelat (1,2


- x 3) mm Kg 0.0424 18,300.00
- Baut bh 4 600

Semen
- Portland Kg 2.5 1,406.00

- Pasir beton M3 0.005 255,400.00

- Koral Beton 2/3 M3 0.009 211,100.00


- Pekerja Oh 0.375 42,000.00

- Tukang Batu Oh 0.125 65,000.00

- Kepala Tukang Oh 0.012 75,000.00


- Mandor Oh 0.019 80,000.00
Jumlah
Dibulatkan

A-14 1 M2 Pagar BRC lengkap dengan tiang

BRC lengkap
- dengan tiang Lbr 0.434 171,300.00

Semen
- Portland Kg 2 1,406.00

- Kawat Duri Kg 2.5 63,500.00

- Pasir beton M3 0.005 255,400.00

- Koral Beton 2/3 M3 0.009 211,100.00


- Pekerja Oh 0.375 42,000.00

- Tukang Batu Oh 0.125 65,000.00


- Kepala Tukang Oh 0.012 75,000.00
- Mandor Oh 0.019 80,000.00
Jumlah
Dibulatkan

A-15 1 M2 Steiger Werk / perancah dari Bambu

Bambu 6 - 10
- (600) cm btng 1 25,000.00
- Tali ijuk kg 0.25 23,400.00
- Pekerja org 0.25 42,000.00

- Tukang kayu org 0.017 65,000.00

- Kepala tukang org 0.002 75,000.00


- Mandor org 0.013 80,000.00
Jumlah
Dibulatkan

A-16 1 M' Cerucuk Bambu

Bambu 7 -10
- (400) cm btng 1.25 25,000.00
- Pekerja org 0.5 42,000.00
- Mandor org 0.025 80,000.00
Jumlah
Dibulatkan
HARGA
(Rp)

35,000.00

3,515.00

1,277.00

1,899.90

190,080.00

1,404.00
3,240.00
16,800.00

13,000.00

1,500.00
1,600.00
269,315.90
269,316.00

35,000.00

3,515.00
75,480.00

1,277.00

1,899.90

190,080.00

1,404.00

13,680.00
16,800.00

13,000.00

1,500.00
1,600.00
355,235.90
355,236.00

28,000.00

2,812.00

158,750.00

1,277.00
1,899.90

1,404.00
12,600.00

13,000.00

1,500.00
1,600.00
222,842.90
222,843.00

22,446.00

468

14,501.90
4,200.00

6,500.00

750
400
49,265.90
49,266.00

35,000.00
475,200.00

19,890.00

29,480.00

49,210.00

35,010.00

25,540.00

31,665.00

23,250.00

3,953.75

71,800.00

6,992.00

14,175.00

8,400.00
84,000.00

130,000.00

65,000.00

22,500.00
4,000.00
1,135,065.75
1,135,066.00
47,600.00

554,400.00

7,020.00

14,763.00

7,662.00

10,555.00

94,350.00
42,000.00

130,000.00

15,000.00
4,000.00
927,350.00
927,350.00

35,000.00

491,040.00
7,020.00

25,308.00

7,662.00

10,555.00

94,350.00
42,000.00

130,000.00

15,000.00
4,000.00
861,935.00
861,935.00

4,200.00
4,000.00
8,200.00
8,200.00

30,825.00

17,640.00

2,334.00
42,000.00
4,000.00
96,799.00
96,799.00
280,014.00
26,640.00
306,654.00

306,654.00

280,014.00
2,640.00
282,654.00
282,654.00

196,411.20

138,600.00

18,899.60

30,820.60

63,270.00
15,750.00

8,125.00

900
1,520.00
474,296.40
474,296.00

6,466.60
124,183.80

775.92
2,400.00

3,515.00

1,277.00

1,899.90
15,750.00

8,125.00

900
1,520.00
166,813.22
166,813.00

74,344.20

2,812.00

158,750.00

1,277.00

1,899.90
15,750.00

8,125.00
900
1,520.00
265,378.10
265,378.00

25,000.00
5,850.00
10,500.00

1,105.00

150
1,040.00
43,645.00
43,645.00

31,250.00
21,000.00
2,000.00
54,250.00
54,250.00
B. ANALISA HARGA SATUAN PEKERJAAN TANAH

No. URAIAN SATUAN VOLUME HARGA SATUAN HARGA


(Rp) (Rp)
1 M3 Galian Tanah
B-01 Biasa sedalam 1 m
- Pekerja Oh 0.4 42,000.00 16,800.00
- Mandor Oh 0.04 80,000.00 3,200.00
Jumlah 20,000.00
Dibulatkan 20,000.00
1 M3 Galian Tanah
B-02 Biasa Sedalam 2 m
- Pekerja Oh 0.526 42,000.00 22,092.00
- Mandor Oh 0.052 80,000.00 4,160.00
Jumlah 26,252.00
Dibulatkan 26,252.00
1 M3 Galian Tanah
B-03 Biasa Sedalam 3 m
- Pekerja Oh 0.735 42,000.00 30,870.00
- Mandor Oh 0.073 80,000.00 5,840.00
Jumlah 36,710.00
Dibulatkan 36,710.00
1 M3 Galian Tanah
B-04 Keras Sedalam 1 m
- Pekerja Oh 0.625 42,000.00 26,250.00
- Mandor Oh 0.062 80,000.00 4,960.00
Jumlah 31,210.00
Dibulatkan 31,210.00
1 M3 Galian Tanah
B-05 Lumpur Sedalam 1 m
- Pekerja Oh 0.823 42,000.00 34,566.00
- Mandor Oh 0.083 80,000.00 6,640.00
Jumlah 41,206.00
Dibulatkan 41,206.00
C. ANALISA HARGA SATUAN PEKERJAAN PONDASI

HARGA
No. URAIAN SATUAN VOLUME SATUAN HARGA
(Rp) (Rp)

1 M3 Pasanag
Pondasi batu
Kali adk 1pc :
C-01 3 ps
- Batu Belah M3 1.1 205,500.00 226,050.00
Semen
- Portland Kg 202 1,406.00 284,012.00

- Pasir Pasang M3 0.485 233,400.00 113,199.00


- Pekerja Oh 1.5 42,000.00 63,000.00

- Tukang Batu Oh 0.6 65,000.00 39,000.00


Kepala
- Tukang Oh 0.06 75,000.00 4,500.00
- Mandor Oh 0.075 80,000.00 6,000.00
Jumlah 735,761.00
Dibulatkan 735,761.00

1 M3 Pasang
Pondasi Batu
kali adk 1pc :
C-02 4ps
- Batu Belah M3 1.1 205,500.00 226,050.00
Semen
- Portland Kg 163 1,406.00 229,178.00

- Pasir Pasang M3 0.52 233,400.00 121,368.00


- Pekerja Oh 1.5 42,000.00 63,000.00

- Tukang Batu Oh 0.6 65,000.00 39,000.00


Kepala
- Tukang Oh 0.06 75,000.00 4,500.00
- Mandor Oh 0.075 80,000.00 6,000.00
Jumlah 689,096.00
Dibulatkan 689,096.00

1 M3 Pasang
Pondasi Batu
kali adk 1pc :
C-03 5ps
- Batu Belah M3 1.1 205,500.00 226,050.00
Semen
- Portland Kg 136 1,406.00 191,216.00

- Pasir Pasang M3 0.544 233,400.00 126,969.60


- Pekerja Oh 1.5 42,000.00 63,000.00

- Tukang Batu Oh 0.6 65,000.00 39,000.00


Kepala
- Tukang Oh 0.06 75,000.00 4,500.00
- Mandor Oh 0.075 80,000.00 6,000.00
Jumlah 656,735.60
Dibulatkan 656,736.00

1 M3 Pasang
Pondasi Batu
Kosong
(aanstamping
C-04 )
- Batu Belah M3 1.2 205,500.00 246,600.00
- Pasir Urug M3 0.3 175,300.00 52,590.00
- Pekerja Oh 0.78 42,000.00 32,760.00

- Tukang Batu Oh 0.39 65,000.00 25,350.00


Kepala
- Tukang Oh 0.039 75,000.00 2,925.00
- Mandor Oh 0.039 80,000.00 3,120.00
Jumlah 363,345.00
Dibulatkan 363,345.00
NO URAIAN SAT VOLUME HRG.SAT
1 M3 Sloof Beton Tulang
15/20 (180 kg besi +
bekisting) 4dia. 12 ring 8-
D-17r2 15
Kayu papan terentang M3 0.27 2,850,000
Paku Biasa 2" - 5" Kg 2 23,400
Besi Beton Kg 180 16,500
Kawat Beton Kg 3 27,700
Semen Portland Kg 323 1,200
Pasir Beton M3 0.52 225,000
Koral Beton 2/3 M3 0.78 200,000
Pekerja Oh 4.85 55,000
Tukang Batu Oh 0.35 70,000
Tukang Kayu Oh 1.56 70,000
Tukang Besi Oh 1.4 70,000
Kepala Tukang Oh 0.331 80,000
Mandor Oh 0.17 85,000
Jumlah
Dibulatkan

1 M3 Kolom Beton Tulang


15/20 (180 kg besi +
bekisting) 4dia.12 8-15
Kayu papan terentang M3 0.4 2,850,000
Paku Biasa 2" - 5" Kg 4 23,400
Minyak Bekisting Ltr 40,500
Besi Beton Kg 180 16,500
Kawat Beton Kg 1.8 27,700
Semen Portland Kg 323 1,200
Pasir Beton M3 0.52 225,000
Koral Beton 2/3 M3 0.78 200,000
Kayu Balok Terentang M3 0.15 2,640,000
Dolken -8-10/4m Btg 20 15,000
Pekerja Oh 7.3 55,000
Tukang Batu Oh 0.35 70,000
Tukang Kayu Oh 3.3 70,000
Tukang Besi Oh 2.1 70,000
Kepala Tukang Oh 0.57 80,000
Mandor Oh 0.25 85,000
Jumlah
Dibulatkan
1 M3 Balok Beton Tulang
15/20 sofi-sofi, ring balk +
balok poratl (180 kg besi +
bekisting) 4dia. 12, 8-15
Kayu papan terentang M3 0.32 2,850,000
Paku Biasa 2" - 5" Kg 3.2 23,400
Besi Beton Kg 180 16,500
Kawat Beton Kg 2.25 27,700
Semen Portland Kg 323 1,200
Pasir Beton M3 0.52 225,000
Koral Beton 2/3 M3 0.78 200,000
Kayu Balok Terentang M3 0.14 2,640,000
Dolken -8-10/4m Btg 16 15,000
Pekerja Oh 5.96 55,000
Tukang Batu Oh 0.35 70,000
Tukang Kayu Oh 2.8 70,000
Tukang Besi Oh 1.4 70,000
Kepala Tukang Oh 0.455 80,000
Mandor Oh 0.208 85,000
Jumlah
Dibulatkan

1 M3 Tangga Beton Tulang


D-29 (90 kg besi + bekisting)
Kayu papan terentang M3 0.25 2,850,000
Paku Biasa 2" - 5" Kg 3 23,400
Minyak Bekisting Ltr 1.2 40,500
Besi Beton Kg 90 16,500
Kawat Beton Kg 3 27,700
Semen Portland Kg 323 1,200
Pasir Beton M3 0.52 225,000
Koral Beton 2/3 M3 0.78 200,000
Kayu Balok Terentang M3 0.105 2,640,000
Dolken -8-10/4m Btg 14 15,000
Pekerja Oh 5.6 55,000
Tukang Batu Oh 0.35 70,000
Tukang Kayu Oh 2.3 70,000
Tukang Besi Oh 1.4 70,000
Kepala Tukang Oh 0.405 80,000
Mandor Oh 0.202 85,000
Jumlah
Dibulatkan
1 M3 Membuat Plat Lantai
Tb. 10 Cm Beton Bertulang
3 ( 90 Kg Besi + Bekisting )
Kayu Terentang M3 0.4 2,850,000
Paku Biasa 2" - 5" Kg 4 23,400
Minyak Bekisting Ltr 2 40,500
Besi Beton Polos Kg 90 16,500
Kawat Beton Kg 3 27,700
Kayu Balok Terentang M3 0.105 151,100
Plywood Tebal 9 mm Lbr 3.5 151,100
Dolken kayu Galam o - 8-
10/4 m Btg 60 15,000
Semen Portland Kg 323 1,200
Pasir Beton M3 0.52 225,000
Koral Beton 2/3 M3 0.78 200,000
Pekerja Oh 5.2 55,000
Tukang Batu Oh 0.35 70,000
Tukang Kayu Oh 3.3 70,000
Kepala Tukang Oh 0.365 80,000
Mandor Oh 1.06 85,000
Jumlah
Dibulatkan
JUMLAH

769,500
46,800
2,970,000
83,100
387,600
117,000
156,000
266,750
24,500
109,200
98,000
26,480
14,450
5,069,380
5,069,380

1,140,000
93,600
-
2,970,000
49,860
387,600
117,000
156,000
396,000
300,000
401,500
24,500
231,000
147,000
45,600
21,250
6.480.910
6.481.000
912,000
74,880
2,970,000
62,325
387,600
117,000
156,000
369,600
240,000
327,800
24,500
196,000
98,000
36,400
17,680
6.412.865
6,413,000

712,500
70,200
48,600
1,485,000
83,100
387,600
117,000
156,000
277,200
210,000
308,000
24,500
161,000
98,000
32,400
17,170
4,188,720
4,189,000
1,140,000
93,600
81,000
1,485,000
83,100
15,866
528,850

900,000
387,600
117,000
156,000
286,000
24,500
231,000
29,200
90,100
5,648,816
5,649,000
E. ANALISA HARGA SATUAN PEKERJAAN DINDING

No. URAIAN SATUAN VOLUME HARGA SATUAN HARGA


(Rp) (Rp)
M2 Pasang Bata Merah Tebal 1 Bata, 1pc :
E-01 1 3ps
- Bata Merah Bh 140 775 108,500.00
- Semen Portland Kg 32.95 1,406.00 46,327.70
- Pasir Pasang M3 0.091 233,400.00 21,239.40
- Pekerja Oh 0.65 42,000.00 27,300.00
- Tukang Batu Oh 0.2 65,000.00 13,000.00
- Kepala Tukang Oh 0.02 75,000.00 1,500.00
- Mandor Oh 0.03 80,000.00 2,400.00
Jumlah 220,267.10
Dibulatkan 220,267.00
M2 Pasang Bata
Merah Tebal 1 Bata,
E-02 1 1pc : 4ps
- Bata Merah Bh 140 775 108,500.00
- Semen Portland Kg 26.55 1,406.00 37,329.30
- Pasir Pasang M3 0.093 233,400.00 21,706.20
- Pekerja Oh 0.65 42,000.00 27,300.00
- Tukang Batu Oh 0.2 65,000.00 13,000.00
- Kepala Tukang Oh 0.02 75,000.00 1,500.00
- Mandor Oh 0.03 80,000.00 2,400.00
Jumlah 211,735.50
Dibulatkan 211,736.00
M2 Pasang Bata
Merah Tebal 1 Bata,
E-03 1 1pc : 5ps
- Bata Merah Bh 140 775 108,500.00
- Semen Portland Kg 22.2 1,406.00 31,213.20
- Pasir Pasang M3 0.102 233,400.00 23,806.80
- Pekerja Oh 0.65 42,000.00 27,300.00
- Tukang Batu Oh 0.2 65,000.00 13,000.00
- Kepala Tukang Oh 0.02 75,000.00 1,500.00
- Mandor Oh 0.03 80,000.00 2,400.00
Jumlah 207,720.00
Dibulatkan 207,720.00
M2 Pasang Bata Merah Tebal 1/2 Bata, 1pc :
E-04 1 3ps
- Bata Merah Bh 70 775 54,250.00
- Semen Portland Kg 14.37 1,406.00 20,204.22
- Pasir Pasang M3 0.04 233,400.00 9,336.00
- Pekerja Oh 0.32 42,000.00 13,440.00
- Tukang Batu Oh 0.1 65,000.00 6,500.00
- Kepala Tukang Oh 0.01 75,000.00 750
- Mandor Oh 0.015 80,000.00 1,200.00
Jumlah 105,680.22
Dibulatkan 105,680.00
M2 Pasang Bata Merah Tebal 1/2 Bata, 1pc :
E-05 1 4ps
- Bata Merah Bh 70 775 54,250.00
- Semen Portland Kg 11.5 1,406.00 16,169.00
- Pasir Pasang M3 0.043 233,400.00 10,036.20
- Pekerja Oh 0.32 42,000.00 13,440.00
- Tukang Batu Oh 0.1 65,000.00 6,500.00
- Kepala Tukang Oh 0.01 75,000.00 750
- Mandor Oh 0.015 80,000.00 1,200.00
Jumlah 102,345.20
Dibulatkan 102,345.00
M2 Pasang Bata Merah Tebal 1/2 Bata, 1pc :
E-06 1 5ps
- Bata Merah Bh 70 775 54,250.00
- Semen Portland Kg 9.68 1,406.00 13,610.08
- Pasir Pasang M3 0.045 233,400.00 10,503.00
- Pekerja Oh 0.32 42,000.00 13,440.00
- Tukang Batu Oh 0.1 65,000.00 6,500.00
- Kepala Tukang Oh 0.01 75,000.00 750
- Mandor Oh 0.015 80,000.00 1,200.00
Jumlah 100,253.08
Dibulatkan 100,253.00
F. ANALISA HARGA SATUAN PEKERJAAN PLESTERAN
HARGA
No. URAIAN SATUAN VOLUME SATUAN HARGA
(Rp) (Rp)

1 M2 Plesteran adk.
F-01 1pc : 2ps Tebal 15 mm
- Semen Portland Kg 8.52 1,406.00 11,979.12
- Pasir Pasang M3 0.017 233,400.00 3,967.80
- Pekerja Oh 0.2 42,000.00 8,400.00
- Tukang Batu Oh 0.15 65,000.00 9,750.00
- Kepala Tukang Oh 0.015 75,000.00 1,125.00
- Mandor Oh 0.01 80,000.00 800
Jumlah 36,021.92
Dibulatkan 36,022.00

1 M2 Plesteran adk.
F-02 1pc : 3ps Tebal 15 mm
- Semen Portland Kg 6.48 1,406.00 9,110.88
- Pasir Pasang M3 0.019 233,400.00 4,434.60
- Pekerja Oh 0.2 42,000.00 8,400.00
- Tukang Batu Oh 0.15 65,000.00 9,750.00
- Kepala Tukang Oh 0.015 75,000.00 1,125.00
- Mandor Oh 0.01 80,000.00 800
Jumlah 33,620.48
Dibulatkan 33,620.00

1 M2 Plesteran adk.
F-03 1pc : 4ps Tebal 15 mm
- Semen Portland Kg 5.2 1,406.00 7,311.20
- Pasir Pasang M3 0.02 233,400.00 4,668.00
- Pekerja Oh 0.2 42,000.00 8,400.00
- Tukang Batu Oh 0.15 65,000.00 9,750.00
- Kepala Tukang Oh 0.015 75,000.00 1,125.00
- Mandor Oh 0.01 80,000.00 800
Jumlah 32,054.20
Dibulatkan 32,054.00

1 M2 Plesteran adk.
F-04 1pc : 3ps Tebal 20 mm
- Semen Portland Kg 10.8 1,406.00 15,184.80
- Pasir Pasang M3 0.026 233,400.00 6,068.40
- Pekerja Oh 0.25 42,000.00 10,500.00
- Tukang Batu Oh 0.2 65,000.00 13,000.00
- Kepala Tukang Oh 0.02 75,000.00 1,500.00
- Mandor Oh 0.0125 80,000.00 1,000.00
Jumlah 47,253.20
Dibulatkan 47,253.00

1 M2 Plesteran adk.
F-05 1pc : 4ps Tebal 20 mm
- Semen Portland Kg 8.68 1,406.00 12,204.08
- Pasir Pasang M3 0.028 233,400.00 6,535.20
- Pekerja Oh 0.25 42,000.00 10,500.00
- Tukang Batu Oh 0.2 65,000.00 13,000.00
- Kepala Tukang Oh 0.02 75,000.00 1,500.00
- Mandor Oh 0.0125 80,000.00 1,000.00
Jumlah 44,739.28
Dibulatkan 44,739.00
1 M2 Plesteran adk.
F-06 1pc:5ps tebal 20 mm
- Semen Portland Kg 7.29 1,406.00 10,249.74
- Pasir Pasang M3 0.026 233,400.00 6,068.40
- Pekerja Oh 0.25 42,000.00 10,500.00
- Tukang Batu Oh 0.2 65,000.00 13,000.00
- Kepala Tukang Oh 0.02 75,000.00 1,500.00
- Mandor Oh 0.0125 80,000.00 1,000.00
Jumlah 42,318.14
Dibulatkan 42,318.00
F-11 1 M2 Acian Plesteran
- Semen Portland Kg 4 1,406.00 5,624.00
- Pekerja Oh 0.143 42,000.00 6,006.00
- Tukang batu Oh 0.107 65,000.00 6,955.00
- Kepala Tukang Oh 0.0105 75,000.00 787.5
- Mandor Oh 0.0105 80,000.00 840
Jumlah 20,212.50
Dibulatkan 20,213.00
G. ANALISA HARGA SATUAN PEKERJAAN PENUTUP ATAP

No. URAIAN SATUAN VOLUME HARGA SATUAN


(Rp)
M2 Pasang Atap
G-01 1 Genteng Palentong
- Genteng palentong Bh 25 1,900.00
- Pekerja Oh 0.15 42,000.00
- Tukang kayu Oh 0.075 65,000.00
- Kepala tukang Oh 0.008 75,000.00
- Mandor Oh 0.008 80,000.00
Jumlah
Dibulatkan

1 M2 Pasang Genteng Bubung


G-02 Palentong
Genteng bubung
- palentong Bh 5 6,000.00
- Semen Portland Kg 8 1,406.00
- Pasir pasang M3 0.032 233,400.00
- Pekerja Oh 0.4 42,000.00
- Tukang kayu Oh 0.2 65,000.00
- Kepala tukang Oh 0.02 75,000.00
- Mandor Oh 0.002 80,000.00
Jumlah
Dibulatkan
1 M2 Pasang Roof Light Fibreglass ( 180 x
G-03 90 ) cm
- Roof light fibreglass Lbr 0.6 100,000.00
- Paku biasa " - 1" Kg 0.05 23,800.00
- Pekerja Oh 0.14 42,000.00
- Tukang kayu Oh 0.067 65,000.00
- Kepala tukang Oh 0.007 75,000.00
- Mandor Oh 0.007 80,000.00
Jumlah
Dibulatkan

1 M2 Pasang Atap Asbes


Gelombang ( 3,00 x 1,05 m ) x 4
G-04 mm
- Asbes gelombang Lbr 0.35 80,000.00
- Paku seng Kg 0.12 23,800.00
- Pekerja Oh 0.14 42,000.00
- Tukang kayu Oh 0.07 65,000.00
- Kepala tukang Oh 0.007 75,000.00
- Mandor Oh 0.007 80,000.00
Jumlah
Dibulatkan

G-05 1 M2 Pasang Atap Asbes Gelombang ( 2,70 x 1,05 m ) x 4 mm


- Asbes gelombang Lbr 0.42 73,300.00
- Paku seng Kg 0.12 23,800.00
- Pekerja Oh 0.14 42,000.00
- Tukang kayu Oh 0.07 65,000.00
- Kepala tukang Oh 0.007 75,000.00
- Mandor Oh 0.007 80,000.00
Jumlah
Dibulatkan

1 M2 Pasang Atap Asbes


Gelombang ( 2,40 x 1,05 m ) x 4
G-06 mm
- Asbes gelombang Lbr 0.44 65,900.00
- Paku seng Kg 0.12 23,800.00
- Pekerja Oh 0.14 42,000.00
- Tukang kayu Oh 0.067 65,000.00
- Kepala tukang Oh 0.007 75,000.00
- Mandor Oh 0.007 80,000.00
Jumlah
Dibulatkan

M2 Pasang Atap Asbes


Gelombang ( 2,10 x
G-07 1 1,05 m ) x 4 mm
- Asbes gelombang Lbr 0.51 58,500.00
- Paku seng Kg 0.12 23,800.00
- Pekerja Oh 0.14 42,000.00
- Tukang kayu Oh 0.067 65,000.00
- Kepala tukang Oh 0.007 75,000.00
- Mandor Oh 0.007 80,000.00
Jumlah
Dibulatkan

1 M2 Pasang Atap Asbes


Gelombang ( 1,50 x 1,05 m ) x 4
G-08 mm
- Asbes gelombang Lbr 0.8 42,300.00
- Paku seng Kg 0.12 23,800.00
- Pekerja Oh 0.14 42,000.00
- Tukang kayu Oh 0.067 65,000.00
- Kepala tukang Oh 0.007 75,000.00
- Mandor Oh 0.007 80,000.00
Jumlah
Dibulatkan

1 M Pasang Nok Stel Gelombang


G-09 1,05 m
- Nok stel gelombang Lbr 2.1 38,100.00
- Paku sekrup 3,5" Bh 6 800
- Pekerja Oh 0.084 42,000.00
- Tukang kayu Oh 0.125 65,000.00
- Kepala tukang Oh 0.013 75,000.00
- Mandor Oh 0.004 80,000.00
Jumlah
Dibulatkan

G-10 1 M2 Pasang Atap Genteng Beton


- Genteng beton bh 11 8,500.00
- Paku biasa 2" - 5" Kg 0.03 23,400.00
- Pekerja Oh 0.2 42,000.00
- Tukang kayu Oh 0.1 65,000.00
- Kepala tukang Oh 0.01 75,000.00
- Mandor Oh 0.01 80,000.00
Jumlah
Dibulatkan

1 M2 Pasang Atap Genteng


G-11 Murando Natural
Genteng murando
- natural bh 18 2,700.00
- Pekerja Oh 0.15 42,000.00
- Tukang kayu Oh 0.075 65,000.00
- Kepala tukang Oh 0.008 75,000.00
- Mandor Oh 0.008 80,000.00
Jumlah
Dibulatkan

1 M2 Pasang Atap Genteng


G-12 Murando Glazur
Genteng murando
- glazur bh 18 4,000.00
- Pekerja Oh 0.15 42,000.00
- Tukang kayu Oh 0.075 65,000.00
- Kepala tukang Oh 0.008 75,000.00
- Mandor Oh 0.008 80,000.00
Jumlah
Dibulatkan
HARGA
(Rp)

47,500.00
6,300.00
4,875.00
600
640
59,915.00
59,915.00

30,000.00
11,248.00
7,468.80
16,800.00
13,000.00
1,500.00
160
80,176.80
80,177.00

60,000.00
1,190.00
5,880.00
4,355.00
525
560
72,510.00
72,510.00

28,000.00
2,856.00
5,880.00
4,550.00
525
560
42,371.00
42,371.00

30,786.00
2,856.00
5,880.00
4,550.00
525
560
45,157.00
45,157.00

28,996.00
2,856.00
5,880.00
4,355.00
525
560
43,172.00
43,172.00

29,835.00
2,856.00
5,880.00
4,355.00
525
560
44,011.00
44,011.00

33,840.00
2,856.00
5,880.00
4,355.00
525
560
48,016.00
48,016.00

80,010.00
4,800.00
3,528.00
8,125.00
975
320
97,758.00
97,758.00

93,500.00
702
8,400.00
6,500.00
750
800
110,652.00
110,652.00

48,600.00
6,300.00
4,875.00
600
640
61,015.00
61,015.00

72,000.00
6,300.00
4,875.00
600
640
84,415.00
84,415.00
H. ANALISA HARGA SATUAN PEKERJAAN PENUTUP LANGIT-LANGIT

No. URAIAN SATUAN VOLUME HARGA SATUAN


(Rp)
(Rp)

1 M2 Langit-langit Asbes
( 1,00 x 1,00 ) m, tebal 5
H-01 mm

Pelat asbes tebal


- 4 mm m2 1.1 22,500.00

- Paku seng Kg 0.01 23,800.00


- Pekerja Oh 0.03 42,000.00

- Tukang kayu Oh 0.07 65,000.00

- Kepala tukang Oh 0.007 75,000.00


- Mandor Oh 0.0015 80,000.00
Jumlah
Dibulatkan

1 M2 Langit-langit Asbes
( 1,00 x 1,00 ) m, tebal 3,5
H-02 mm

Pelat asbes tebal


- 3,5 mm Lbr 1.1 19,500.00

- Paku seng Kg 0.01 23,800.00


- Pekerja Oh 0.03 42,000.00

- Tukang kayu Oh 0.07 65,000.00

- Kepala tukang Oh 0.007 75,000.00


- Mandor Oh 0.0015 80,000.00
Jumlah
Dibulatkan

H-03 1 M2 Langit-langit Akustik ( 60 x 120 ) cm


Akustik 600 x
- 1200 Lbr 1.5 132,800.00
- Paku Kg 0.05 23,800.00
- Pekerja Oh 0.06 42,000.00

- Tukang kayu Oh 0.1 65,000.00

- Kepala tukang Oh 0.01 75,000.00


- Mandor Oh 0.003 80,000.00
Jumlah
Dibulatkan

H-04 1 M2 Langit-langit Akustik ( 60 x 120 ) cm + Rangka Alluminium

Profil Alluminium
- "T" M 3.6 12,200.00

- Kawat f 4 mm Kg 0.15 28,200.00

- Ramset / dina bolt Bh 1.05 7,200.00

Akustik 600 x
- 1200 Lbr 1.5 132,800.00
- Pekerja Oh 0.15 42,000.00

- Tukang kayu Oh 0.5 65,000.00

- Kepala tukang Oh 0.05 75,000.00


- Mandor Oh 0.0075 80,000.00
Jumlah
Dibulatkan

H-05 1 M2 Langit-langit teakwood (60 x 120) cm, t = 4 mm + rangka kayu borneo super

Kayu Balok
- Borneo Super M3 0.023 2,640,000.00

- Paku biasa 2" - 5" Kg 0.06 23,400.00


Teakwood 120 cm
- x 240 cm x 0,4 cm Lbr 0.39 131,700.00
- Pekerja Oh 0.27 42,000.00

- Tukang kayu Oh 0.4 65,000.00

- Kepala tukang Oh 0.04 75,000.00


- Mandor Oh 0.0135 80,000.00
Jumlah
Dibulatkan

H-06 1 M2 Langit-langit Teakwood 3 mm + Rangka Kayu Borneo Super

Kayu Balok
- Borneo Super M3 0.023 2,640,000.00

- Paku biasa 2" - 5" Kg 0.06 23,400.00

Teakwood (120 x
- 240x 0,3) cm Lbr 0.39 129,100.00
- Pekerja Oh 0.27 42,000.00

- Tukang kayu Oh 0.4 65,000.00

- Kepala tukang Oh 0.04 75,000.00


- Mandor Oh 0.0135 80,000.00
Jumlah
Dibulatkan

H-07 1 M2 Langit-langit Triplek 4 mm + Rangka Kayu Borneo Super

Kayu Balok
- Borneo Super M3 0.023 2,640,000.00

- Paku biasa 2" - 5" Kg 0.06 23,800.00


Triplek 120 cm x
- 240 cm x 0,4 cm Lbr 0.39 64,400.00
- Pekerja Oh 0.27 42,000.00

- Tukang kayu Oh 0.4 65,000.00

- Kepala tukang Oh 0.04 75,000.00


- Mandor Oh 0.0135 80,000.00
Jumlah
Dibulatkan

H-08 1 M2 Langit-langit Gypsum Board, tebal 9 mm + rangka besi hollow

Hollow 4/4
- Zincromate Btg 0.415 29,200.00

Hollow 2/4
- Zincromate Btg 0.15 22,600.00

Gypsum board
( 120 x 240 x 9 )
- mm Lbr 0.364 79,800.00

- Paku gypsum kg 0.11 17,500.00

- Ramset / dina bolt Bh 4 7,200.00

- Cotton plaster Bh 0.072 15,000.00

- Compoun Zak 0.125 75,000.00


- Pekerja Oh 0.1 42,000.00

- Tukang kayu Oh 0.05 65,000.00

- Kepala tukang Oh 0.005 75,000.00


- Mandor Oh 0.005 80,000.00
Jumlah
Dibulatkan
H-09 1 M2 Langit-langit GRC t = 4 mm + rangka besi hollow

Hollow 4/4
- Zincromate Btg 0.415 29,200.00

Hollow 2/4
- Zincromate Btg 0.15 22,600.00

GRC ( 120 x 240 x


- 4 ) mm Lbr 0.364 67,500.00

- Paku GRC kg 0.11 35,000.00

- Ramset / dina bolt Bh 4 7,200.00

- Cotton plaster Bh 0.072 15,000.00

- Compoun Zak 0.125 75,000.00


- Pekerja Oh 0.1 42,000.00

- Tukang kayu Oh 0.05 65,000.00

- Kepala tukang Oh 0.005 75,000.00


- Mandor Oh 0.005 80,000.00
Jumlah
Dibulatkan

H-10 1 M2 Langit-langit gypsum t = 9 mm + Rangka Kayu Borneo Super

Kayu Balok
- Borneo Super M3 0.023 2,640,000.00

- Paku biasa 2" - 5" Kg 0.06 23,800.00

Gypsum board
( 120 x 240 x 9 )
- mm Lbr 0.39 79,800.00

- Paku sekrup kg 0.11 17,500.00


- Pekerja Oh 0.27 42,000.00

- Tukang kayu Oh 0.4 65,000.00

- Kepala tukang Oh 0.04 75,000.00


- Mandor Oh 0.0135 80,000.00
Jumlah
Dibulatkan

H-11 1 M2 Langit-langit GRC t = 4 mm + Rangka Kayu Borneo Super

Kayu Balok
- Borneo Super M3 0.023 2,640,000.00

- Paku biasa 2" - 5" Kg 0.06 23,800.00

GRC ( 120 x 240 x


- 4 ) mm Lbr 0.39 67,500.00

- Paku GRC kg 0.11 35,000.00


- Pekerja Oh 0.27 42,000.00

- Tukang kayu Oh 0.4 65,000.00

- Kepala tukang Oh 0.04 75,000.00


- Mandor Oh 0.0135 80,000.00
Jumlah
Dibulatkan

1 M List Langit-langit Kayu


H-12 Profil 10 cm

- List Kayu profil M 1.05 29,400.00


- Paku Kg 0.01 23,800.00
- Pekerja Oh 0.05 42,000.00

- Tukang kayu Oh 0.05 65,000.00

- Kepala tukang Oh 0.005 75,000.00


- Mandor Oh 0.003 80,000.00
Jumlah
Dibulatkan
1 M List Langit-langit
H-13 Gypsum 10 cm

- List gypsum M 1.05 8,500.00

- Tepung gypsum Kg 0.15 12,500.00


- Pekerja Oh 0.05 42,000.00

- Tukang kayu Oh 0.05 65,000.00

- Kepala tukang Oh 0.005 75,000.00


- Mandor Oh 0.003 80,000.00
Jumlah
Dibulatkan
HARGA
(Rp)
(Rp)

24,750.00

238
1,260.00

4,550.00

525
120
31,443.00
31,443.00

21,450.00

238
1,260.00

4,550.00

525
120
28,143.00
28,143.00
199,200.00
1,190.00
2,520.00

6,500.00

750
240
210,400.00
210,400.00

43,920.00

4,230.00

7,560.00

199,200.00
6,300.00

32,500.00

3,750.00
600
298,060.00
298,060.00

ayu borneo super

60,720.00

1,404.00
51,363.00
11,340.00

26,000.00

3,000.00
1,080.00
154,907.00
154,907.00

60,720.00

1,404.00

50,349.00
11,340.00

26,000.00

3,000.00
1,080.00
153,893.00
153,893.00

60,720.00

1,428.00
25,116.00
11,340.00

26,000.00

3,000.00
1,080.00
128,684.00
128,684.00

12,118.00

3,390.00

29,047.20

1,925.00

28,800.00

1,080.00

9,375.00
4,200.00

3,250.00

375
400
93,960.20
93,960.00
12,118.00

3,390.00

24,570.00

3,850.00

28,800.00

1,080.00

9,375.00
4,200.00

3,250.00

375
400
91,408.00
91,408.00

60,720.00

1,428.00

31,122.00

1,925.00
11,340.00

26,000.00

3,000.00
1,080.00
136,615.00
136,615.00

60,720.00

1,428.00

26,325.00

3,850.00
11,340.00

26,000.00

3,000.00
1,080.00
133,743.00
133,743.00

30,870.00
238
2,100.00

3,250.00

375
240
37,073.00
37,073.00
8,925.00

1,875.00
2,100.00

3,250.00

375
240
16,765.00
16,765.00
No. URAIAN SATUAN VOLUME HARGA SATUAN HARGA
(Rp) (Rp)

1 M2 Lantai Ubin Granito


ukuran 40 x 40 cm Setara
I-01 Essenza

- Granito 40 x 40 cm m2 1.05 345,000.00 362,250.00

- Semen portland Kg 9.8 1,406.00 13,778.80

- Pasir pasang M3 0.0215 233,400.00 5,018.10

- Semen warna Kg 1.3 15,700.00 20,410.00


- Pekerja Oh 0.25 42,000.00 10,500.00

- Tukang batu Oh 0.12 65,000.00 7,800.00

- Kepala tukang Oh 0.012 75,000.00 900


- Mandor Oh 0.0125 80,000.00 1,000.00
Jumlah 421,656.90
Dibulatkan 421,657.00

1 M2 Lantai Ubin Granito


ukuran 30 x 30 cm Setara
I-02 Essenza

- Granito 30 x 30 cm m2 1.05 322,800.00 338,940.00

- Semen portland Kg 10 1,406.00 14,060.00

- Pasir pasang M3 0.0215 233,400.00 5,018.10

- Semen warna Kg 1.5 15,700.00 23,550.00


- Pekerja Oh 0.26 42,000.00 10,920.00

- Tukang batu Oh 0.125 65,000.00 8,125.00

- Kepala tukang Oh 0.0125 75,000.00 937.5


- Mandor Oh 0.013 80,000.00 1,040.00
Jumlah 402,590.60
Dibulatkan 402,591.00
1 M Plint Ubin Granito ukuran
I-03 10 x 40 cm Setara Essenza

Plint granito 10 x 40
- cm Bh 2.65 27,600.00 73,140.00

- Semen portland Kg 1.2 1,406.00 1,687.20

- Pasir pasang M3 0.003 233,400.00 700.2

- Semen warna Kg 0.1 15,700.00 1,570.00


- Pekerja Oh 0.06 42,000.00 2,520.00

- Tukang batu Oh 0.03 65,000.00 1,950.00

- Kepala tukang Oh 0.003 75,000.00 225


- Mandor Oh 0.003 80,000.00 240
Jumlah 82,032.40
Dibulatkan 82,032.00

1 M Plint Ubin Granito ukuran


I-04 10 x 30 cm Setara Essenza

Plint granito 10 x 30
- cm Bh 3.33 25,900.00 86,247.00

- Semen portland Kg 1.65 1,406.00 2,319.90

- Pasir pasang M3 0.0032 233,400.00 746.88

- Semen warna Kg 0.1 15,700.00 1,570.00


- Pekerja Oh 0.09 42,000.00 3,780.00

- Tukang batu Oh 0.09 65,000.00 5,850.00

- Kepala tukang Oh 0.009 75,000.00 675


- Mandor Oh 0.0045 80,000.00 360
Jumlah 101,548.78
Dibulatkan 101,549.00

I-05 1 M2 Lantai Keramik Corak 10 x 20 cm setara Mulia


Keramik corak 10 x
- 20 cm m2 1 56,000.00 56,000.00

- Semen portland Kg 8 1,406.00 11,248.00

- Pasir pasang M3 0.0215 233,400.00 5,018.10

- Semen warna Kg 0.013 15,700.00 204.1


- Pekerja Oh 0.25 42,000.00 10,500.00

- Tukang batu Oh 0.12 65,000.00 7,800.00

- Kepala tukang Oh 0.012 75,000.00 900


- Mandor Oh 0.0125 80,000.00 1,000.00
Jumlah 92,670.20
Dibulatkan 92,670.00

1 M2 Lantai Keramik corak 20 x


I-06 20 cm setara Mulia

Keramik corak 20 x
- 20 cm m2 1 62,500.00 62,500.00

- Semen portland Kg 8 1,406.00 11,248.00

- Pasir pasang M3 0.0215 233,400.00 5,018.10

- Semen warna Kg 0.013 15,700.00 204.1


- Pekerja Oh 0.25 42,000.00 10,500.00

- Tukang batu Oh 0.12 65,000.00 7,800.00

- Kepala tukang Oh 0.012 75,000.00 900


- Mandor Oh 0.0125 80,000.00 1,000.00
Jumlah 99,170.20
Dibulatkan 99,170.00

1 M2 Lantai Keramik polos 30 x


I-07 30 cm setara Mulia

Keramik polos 30 x
- 30 cm m2 1 53,000.00 53,000.00
- Semen portland Kg 8 1,406.00 11,248.00

- Pasir pasang M3 0.0215 233,400.00 5,018.10

- Semen warna Kg 0.013 15,700.00 204.1


- Pekerja Oh 0.25 42,000.00 10,500.00

- Tukang batu Oh 0.12 65,000.00 7,800.00

- Kepala tukang Oh 0.012 75,000.00 900


- Mandor Oh 0.0125 80,000.00 1,000.00
Jumlah 89,670.20
Dibulatkan 89,670.00

1 M2 Lantai Keramik corak 30 x


I-08 30 cm Setara Mulia

Keramik corak 30 x
- 30 cm m2 1 58,000.00 58,000.00

- Semen portland Kg 8 1,406.00 11,248.00

- Pasir pasang M3 0.0215 233,400.00 5,018.10

- Semen warna Kg 0.013 15,700.00 204.1


- Pekerja Oh 0.25 42,000.00 10,500.00

- Tukang batu Oh 0.12 65,000.00 7,800.00

- Kepala tukang Oh 0.012 75,000.00 900


- Mandor Oh 0.0125 80,000.00 1,000.00
Jumlah 94,670.20
Dibulatkan 94,670.00

1 M2 Lantai Keramik polos 40 x


I-09 40 cm Setara Mulia

Keramik polos 40 x
- 40 cm m2 1 56,800.00 56,800.00

- Semen portland Kg 8 1,406.00 11,248.00

- Pasir pasang M3 0.0215 233,400.00 5,018.10


- Semen warna Kg 0.013 15,700.00 204.1
- Pekerja Oh 0.25 42,000.00 10,500.00

- Tukang batu Oh 0.12 65,000.00 7,800.00

- Kepala tukang Oh 0.012 75,000.00 900


- Mandor Oh 0.0125 80,000.00 1,000.00
Jumlah 93,470.20
Dibulatkan 93,470.00

1 M2 Lantai Keramik corak 40 x


I-10 40 cm Setara Mulia

Keramik corak 40 x
- 40 cm m2 1 65,500.00 65,500.00

- Semen portland Kg 8 1,406.00 11,248.00

- Pasir pasang M3 0.0215 233,400.00 5,018.10

- Semen warna Kg 0.013 15,700.00 204.1


- Pekerja Oh 0.25 42,000.00 10,500.00

- Tukang batu Oh 0.12 65,000.00 7,800.00

- Kepala tukang Oh 0.012 75,000.00 900


- Mandor Oh 0.0125 80,000.00 1,000.00
Jumlah 102,170.20
Dibulatkan 102,170.00
1 M2 Lantai Keramik Corak 10 x 20 cm setara
I-11 Roman

Keramik corak 10 x
- 20 cm m2 1 72,200.00 72,200.00

- Semen portland Kg 8 1,406.00 11,248.00

- Pasir pasang M3 0.0215 233,400.00 5,018.10

- Semen warna Kg 0.013 15,700.00 204.1


- Pekerja Oh 0.25 42,000.00 10,500.00

- Tukang batu Oh 0.12 65,000.00 7,800.00


- Kepala tukang Oh 0.012 75,000.00 900
- Mandor Oh 0.0125 80,000.00 1,000.00
Jumlah 108,870.20
Dibulatkan 108,870.00

1 M2 Lantai Keramik corak 20 x


I-12 20 cm setara Roman

Keramik corak 20 x
- 20 cm m2 1 75,200.00 75,200.00

- Semen portland Kg 8 1,406.00 11,248.00

- Pasir pasang M3 0.0215 233,400.00 5,018.10

- Semen warna Kg 0.013 15,700.00 204.1


- Pekerja Oh 0.25 42,000.00 10,500.00

- Tukang batu Oh 0.12 65,000.00 7,800.00

- Kepala tukang Oh 0.012 75,000.00 900


- Mandor Oh 0.0125 80,000.00 1,000.00
Jumlah 111,870.20
Dibulatkan 111,870.00

1 M2 Lantai Keramik polos 30 x


I-13 30 cm setara Roman

Keramik polos 30 x
- 30 cm m2 1 68,900.00 68,900.00

- Semen portland Kg 8 1,406.00 11,248.00

- Pasir pasang M3 0.0215 233,400.00 5,018.10

- Semen warna Kg 0.013 15,700.00 204.1


- Pekerja Oh 0.25 42,000.00 10,500.00

- Tukang batu Oh 0.12 65,000.00 7,800.00

- Kepala tukang Oh 0.012 75,000.00 900


- Mandor Oh 0.0125 80,000.00 1,000.00
Jumlah 105,570.20
Dibulatkan 105,570.00

1 M2 Lantai Keramik corak 30 x


I-14 30 cm Setara Roman

Keramik corak 30 x
- 30 cm M2 1 76,600.00 76,600.00

- Semen portland Kg 8 1,406.00 11,248.00

- Pasir pasang M3 0.0215 233,400.00 5,018.10

- Semen warna Kg 0.013 15,700.00 204.1


- Pekerja Oh 0.25 42,000.00 10,500.00

- Tukang batu Oh 0.12 65,000.00 7,800.00

- Kepala tukang Oh 0.012 75,000.00 900


- Mandor Oh 0.0125 80,000.00 1,000.00
Jumlah 113,270.20
Dibulatkan 113,270.00

1 M2 Lantai Keramik polos 40 x


I-15 40 cm setara Roman

Keramik polos 40 x
- 40 cm m2 1 72,500.00 72,500.00

- Semen portland Kg 8 1,406.00 11,248.00

- Pasir pasang M3 0.0215 233,400.00 5,018.10

- Semen warna Kg 0.013 15,700.00 204.1


- Pekerja Oh 0.25 42,000.00 10,500.00

- Tukang batu Oh 0.12 65,000.00 7,800.00

- Kepala tukang Oh 0.012 75,000.00 900


- Mandor Oh 0.0125 80,000.00 1,000.00
Jumlah 109,170.20
Dibulatkan 109,170.00
1 M2 Lantai Keramik corak 40 x
I-16 40 cm Setara Roman

Keramik corak 40 x
- 40 cm m2 1 77,000.00 77,000.00

- Semen portland Kg 8 1,406.00 11,248.00

- Pasir pasang M3 0.0215 233,400.00 5,018.10

- Semen warna Kg 0.013 15,700.00 204.1


- Pekerja Oh 0.25 42,000.00 10,500.00

- Tukang batu Oh 0.12 65,000.00 7,800.00

- Kepala tukang Oh 0.012 75,000.00 900


- Mandor Oh 0.0125 80,000.00 1,000.00
Jumlah 113,670.20
Dibulatkan 113,670.00

I-17 1 M2 Lantai Marmer


- Marmer m2 1.06 550,000.00 583,000.00

- Semen portland Kg 8.19 1,406.00 11,515.14

- Pasir pasang M3 0.045 233,400.00 10,503.00

- Semen warna Kg 0.65 15,700.00 10,205.00


- Pekerja Oh 0.7 42,000.00 29,400.00

- Tukang batu Oh 0.35 65,000.00 22,750.00

- Kepala tukang Oh 0.035 75,000.00 2,625.00


- Mandor Oh 0.035 80,000.00 2,800.00
Jumlah 672,798.14
Dibulatkan 672,798.00

I-18 1 M2 Lantai Parquet Jati

- Parquet jati M2 1.05 375,400.00 394,170.00

- Lem vinyl Kg 0.6 44,000.00 26,400.00


- Pekerja Oh 0.65 42,000.00 27,300.00
- Tukang Oh 0.35 65,000.00 22,750.00
- Kepala tukang Oh 0.035 75,000.00 2,625.00
- Mandor Oh 0.0325 80,000.00 2,600.00
Jumlah 475,845.00
Dibulatkan 475,845.00
J. ANALISA HARGA SATUAN PEKERJAAN KAYU

No. URAIAN SATUAN VOLUME HARGA SATUAN HARGA

1 M3 Kusen Pintu & jendela


J-01 kayu Kamper Samarinda

Kayu Balok
- Kamper Samarinda m3 1.2 8,633,700.00 10,360,440.00
- Pekerja Oh 6 42,000.00 252,000.00

- Tukang Kayu Oh 18 65,000.00 1,170,000.00

- Kepala Tukang Oh 2 75,000.00 150,000.00


- Mandor Oh 0.3 80,000.00 24,000.00
Jumlah 11,956,440.00
Dibulatkan 11,956,440.00

M3 Kusen Pintu &


jendela kayu
Kamper
J-02 1 Medan/Kruing

Kayu Balok
- Kamper Medan M3 1.2 5,692,600.00 6,831,120.00
- Pekerja Oh 6 42,000.00 252,000.00

- Tukang Kayu Oh 18 65,000.00 1,170,000.00

- Kepala Tukang Oh 2 75,000.00 150,000.00


- Mandor Oh 0.3 80,000.00 24,000.00
Jumlah 8,427,120.00
Dibulatkan 8,427,120.00

M3 Kusen Pintu &


jendela kayu
J-03 1 Borneo Super
Kayu Borneo Balok
- Super M3 1.2 5,280,000.00 6,336,000.00
- Pekerja Oh 6 42,000.00 252,000.00

- Tukang Kayu Oh 18 65,000.00 1,170,000.00

- Kepala Tukang Oh 2 75,000.00 150,000.00


- Mandor Oh 0.3 80,000.00 24,000.00
Jumlah 7,932,000.00
Dibulatkan 7,932,000.00
1 M2 Pintu Panel Kayu Kamper
J-04 Samarinda

Kayu Papan
- Kamper Samarinda M3 0.04 8,633,700.00 345,348.00

- Paku Biasa 2" - 5" Kg 0.05 23,400.00 1,170.00


- Pekerja Oh 1 42,000.00 42,000.00

- Tukang Kayu Oh 2.5 65,000.00 162,500.00

- Kepala Tukang Oh 0.25 75,000.00 18,750.00


- Mandor Oh 0.05 80,000.00 4,000.00
Jumlah 573,768.00
Dibulatkan 573,768.00

J-05 1 M2 Pintu Panel Kayu Kamper Medan/Kruing

Kayu Papan
- Kamper Medan M3 0.04 5,692,600.00 227,704.00

- Paku Biasa 2" - 5" Kg 0.05 23,400.00 1,170.00


- Pekerja Oh 1 42,000.00 42,000.00

- Tukang Kayu Oh 2.5 65,000.00 162,500.00

- Kepala Tukang Oh 0.25 75,000.00 18,750.00


- Mandor Oh 0.05 80,000.00 4,000.00
Jumlah 456,124.00
Dibulatkan 456,124.00

J-06 1 M2 Pintu & Jendela Kaca Kayu Kamper Medan

Kayu Papan
- Kamper Medan M3 0.035 5,692,600.00 199,241.00
- Pekerja Oh 0.8 42,000.00 33,600.00

- Tukang Kayu Oh 2 65,000.00 130,000.00

- Kepala Tukang Oh 0.2 75,000.00 15,000.00


- Mandor Oh 0.04 80,000.00 3,200.00
Jumlah 381,041.00
Dibulatkan 381,041.00

M2 Pintu &
Jendela Kaca Kayu
J-07 1 Borneo

Kayu Papan
- Borneo Super M3 0.035 5,595,800.00 195,853.00
- Pekerja Oh 0.8 42,000.00 33,600.00

- Tukang Kayu Oh 2 65,000.00 130,000.00

- Kepala Tukang Oh 0.2 75,000.00 15,000.00


- Mandor Oh 0.04 80,000.00 3,200.00
Jumlah 377,653.00
Dibulatkan 377,653.00

M2 Pintu &
Jendela Jalusi
Kayu Kamper
J-08 1 Medan

Kayu Papan
- Kamper Medan M3 0.064 5,692,600.00 364,326.40
- Pekerja Oh 1 42,000.00 42,000.00
- Tukang Kayu Oh 3 65,000.00 195,000.00

- Kepala Tukang Oh 0.3 75,000.00 22,500.00


- Mandor Oh 0.5 80,000.00 40,000.00
Jumlah 663,826.40
Dibulatkan 663,826.00

M2 Pintu Triplek
Rangkap, Rangka
Tertutup Kayu
J-09 1 Kamper Medan

Kayu Papan
- Kamper Medan M3 0.0196 5,692,600.00 111,574.96

- Paku Biasa " - 1" Kg 0.03 23,800.00 714

- Lem Kayu Ltr 0.3 23,900.00 7,170.00

Triplek 120 x 240 x


- 0,4 cm Lbr 1 64,400.00 64,400.00
- Pekerja Oh 0.6 42,000.00 25,200.00

- Tukang Kayu Oh 2 65,000.00 130,000.00

- Kepala Tukang Oh 0.2 75,000.00 15,000.00


- Mandor Oh 0.03 80,000.00 2,400.00
Jumlah 356,458.96
Dibulatkan 356,459.00

J-10 1 M2 Jalusi Mati Kusen Kayu kamper Medan

Kayu Papan
- Kamper Medan M3 0.06 5,692,600.00 341,556.00

- Paku Biasa " - 1" Kg 0.15 23,800.00 3,570.00


- Pekerja Oh 0.5 42,000.00 21,000.00
- Tukang Kayu Oh 2 65,000.00 130,000.00

- Kepala Tukang Oh 0.2 75,000.00 15,000.00


- Mandor Oh 0.025 80,000.00 2,000.00
Jumlah 513,126.00
Dibulatkan 513,126.00

J-11 1 M2 Pintu Triplek Rangkap, Rangka Kayu Borneo Super

Kayu Papan
- Borneo Super M3 0.0196 5,595,800.00 109,677.68

- Paku Biasa " - 1" Kg 0.03 23,800.00 714

- Lem Kayu Ltr 0.3 23,900.00 7,170.00

Triplek 120 x 240 x


- 0,4 cm Lbr 1 64,400.00 64,400.00
- Pekerja Oh 0.6 42,000.00 25,200.00

- Tukang Kayu Oh 2 65,000.00 130,000.00

- Kepala Tukang Oh 0.2 75,000.00 15,000.00


- Mandor Oh 0.03 80,000.00 2,400.00
Jumlah 354,561.68
Dibulatkan 354,562.00

M2 Pintu
Teakwood
Rangkap, rangka
Kayu Kamper
J-12 1 Medan

Kayu Papan
- Kamper Medan M3 0.0196 5,692,600.00 111,574.96

- Paku Biasa " - 1" Kg 0.3 23,800.00 7,140.00

- Lem Kayu Ltr 0.3 23,900.00 7,170.00


- Teakwood 4 mm Lbr 1 131,700.00 131,700.00
- Pekerja Oh 0.6 42,000.00 25,200.00

- Tukang Kayu Oh 2 65,000.00 130,000.00

- Kepala Tukang Oh 0.2 75,000.00 15,000.00


- Mandor Oh 0.03 80,000.00 2,400.00
Jumlah 430,184.96
Dibulatkan 430,185.00

M2 Pintu Triplek &


Formika, Rangka
Kayu Kamper
J-13 1 Medan

Kayu Papan
- Kamper Medan M3 0.0196 5,692,600.00 111,574.96

- Paku Biasa " - 1" Kg 0.3 23,800.00 7,140.00

- Lem Kayu Ltr 0.8 23,900.00 19,120.00

Triplek 120 x 240 x


- 0,4 cm Lbr 1 64,400.00 64,400.00

- Formica 3" x 6" Lbr 0.5 132,900.00 66,450.00


- Pekerja Oh 0.8 42,000.00 33,600.00

- Tukang Kayu Oh 2.5 65,000.00 162,500.00

- Kepala Tukang Oh 0.25 75,000.00 18,750.00


- Mandor Oh 0.04 80,000.00 3,200.00
Jumlah 486,734.96
Dibulatkan 486,735.00
M2 Pintu
Teakwood &
Formika, Rangka
Kayu Kamper
J-14 1 Medan (dipolitur)

Kayu Papan
- Kamper Medan M3 0.0196 5,692,600.00 111,574.96

- Paku Biasa " - 1" Kg 0.3 23,800.00 7,140.00

- Lem Kayu Ltr 0.8 23,900.00 19,120.00

Teakwood 120 x
- 240 x 0,4 cm Lbr 1 131,700.00 131,700.00

- Formica 4" x 8" Lbr 0.5 238,100.00 119,050.00


- Pekerja Oh 0.8 42,000.00 33,600.00

- Tukang Kayu Oh 2.5 65,000.00 162,500.00

- Kepala Tukang Oh 0.25 75,000.00 18,750.00


- Mandor Oh 0.04 80,000.00 3,200.00
Jumlah 606,634.96
Dibulatkan 606,635.00

J-15 1 M3 Kuda-kuda Kayu Kamper Medan

Kayu Balok
- Kamper Medan M3 1.1 5,692,600.00 6,261,860.00

- Besi Strip Kg 15 26,800.00 402,000.00

- Paku Biasa 2" - 5" Kg 0.8 23,800.00 19,040.00


- Pekerja Oh 4 42,000.00 168,000.00

- Tukang Kayu Oh 12 65,000.00 780,000.00


- Kepala Tukang Oh 1.2 75,000.00 90,000.00
- Mandor Oh 0.2 80,000.00 16,000.00
Jumlah 7,736,900.00
Dibulatkan 7,736,900.00

M3 Kuda-kuda
J-16 1 Kayu Borneo Super

Kayu balok Borneo


- super M3 1.1 5,280,000.00 5,808,000.00

- Besi Strip Kg 15 26,800.00 402,000.00

- Paku Biasa 2" - 5" Kg 0.8 23,800.00 19,040.00


- Pekerja Oh 4 42,000.00 168,000.00

- Tukang Kayu Oh 12 65,000.00 780,000.00

- Kepala Tukang Oh 1.2 75,000.00 90,000.00


- Mandor Oh 0.2 80,000.00 16,000.00
Jumlah 7,283,040.00
Dibulatkan 7,283,040.00

M2 Kaso + Reng
Genteng Plentong
J-17 1 Kayu Borneo Super

Kayu balok Borneo


- super m3 0.012 5,280,000.00 63,360.00

- Paku Biasa 2" - 5" Kg 0.15 23,800.00 3,570.00


- Pekerja Oh 0.1 42,000.00 4,200.00

- Tukang Kayu Oh 0.1 65,000.00 6,500.00


- Kepala Tukang Oh 0.01 75,000.00 750
- Mandor Oh 0.005 80,000.00 400
Jumlah 78,780.00
Dibulatkan 78,780.00

M2 Kaso + Reng
Genteng Beton
J-18 1 Kayu Borneo Super

Kayu balok Borneo


- super M3 0.014 5,280,000.00 73,920.00

- Paku Biasa 2" - 5" Kg 0.15 23,800.00 3,570.00


- Pekerja Oh 0.1 42,000.00 4,200.00

- Tukang Kayu Oh 0.1 65,000.00 6,500.00

- Kepala Tukang Oh 0.01 75,000.00 750


- Mandor Oh 0.005 80,000.00 400
Jumlah 89,340.00
Dibulatkan 89,340.00

M' Lisplang uk
(3x20)cm, Kayu
J-19 1 Kamper Medan

Kayu Papan
- Kamper Medan M3 0.0072 5,823,400.00 41,928.48

- Paku Biasa 2" - 5" Kg 0.05 23,800.00 1,190.00


- Pekerja Oh 0.1 42,000.00 4,200.00

- Tukang Kayu Oh 0.2 65,000.00 13,000.00

- Kepala Tukang Oh 0.02 75,000.00 1,500.00


- Mandor Oh 0.005 80,000.00 400
Jumlah 62,218.48
Dibulatkan 62,218.00

J-20 1 M' Lisplang uk (3x30)cm, Kayu Kamper Medan

Kayu Papan
- Kamper Medan M3 0.011 5,692,600.00 62,618.60

- Paku Biasa 2" - 5" Kg 0.05 23,800.00 1,190.00


- Pekerja Oh 0.11 42,000.00 4,620.00

- Tukang Kayu Oh 0.22 65,000.00 14,300.00

- Kepala Tukang Oh 0.022 75,000.00 1,650.00


- Mandor Oh 0.005 80,000.00 400
Jumlah 84,778.60
Dibulatkan 84,779.00

J-21 1 M List Plafond + kayu Profil 10 cm

- Kayu Profil 10 cm M' 1.05 29,400.00 30,870.00


- Pekerja Oh 0.021 42,000.00 882

- Tukang Kayu Oh 0.021 65,000.00 1,365.00

- Kepala Tukang Oh 0.002 75,000.00 150


- Mandor Oh 0.001 80,000.00 80
Jumlah 33,347.00
Dibulatkan 33,347.00
VOLUM
No. URAIAN SAT E HARGA SAT HARGA
(Rp) (Rp)

K-01 1 Kg Besi profil

- Besi profil WF Kg 1.1 24,000.00 26,400.00

- Meni besi Kg 0.08 30,400.00 2,432.00


- Pekerja Oh 0.06 42,000.00 2,520.00

- Tukang besi Oh 0.006 65,000.00 390

- Kepala tukang Oh 0.006 75,000.00 450


- Mandor Oh 0.0003 80,000.00 24
Jumlah 32,216.00
Dibulatkan 32,216.00

K-02 1 Kg Perakitan baja


- Solar m' 0.01 7,150.00 71.5

- Minyak pelumas m' 0.001 55,000.00 55

- Sewa alat jam 0.008 100,000.00 800


- Pekerja Oh 0.001 42,000.00 42

- Tukang besi Oh 0.00001 65,000.00 0.65

- Kepala tukang Oh 0.00001 75,000.00 0.75


- Mandor Oh 0.00005 80,000.00 4
Jumlah 973.9
Dibulatkan 974

1 Cm Pengelasan dengan las


K-03 listrik

- kawat las kg 0.04 23,600.00 944


- Solar ltr 0.03 7,150.00 214.5

- Minyak pelumas ltr 0.004 55,000.00 220


- Sewa alat jam 0.017 100,000.00 1,700.00
- Pekerja org 0.004 42,000.00 168
- Tukang org 0.002 65,000.00 130

- Kepala Tukang org 0.0002 75,000.00 15


- Mandor org 0.0002 80,000.00 16
Jumlah 2,463.50
Dibulatkan 2,464.00

K-04 1 m2 Pintu Rolling Door

- Rolling door M2 1 306,600.00 306,600.00


- Pekerja Oh 1.05 42,000.00 44,100.00

- Tukang besi Oh 1.5 65,000.00 97,500.00

- Kepala tukang Oh 0.105 75,000.00 7,875.00


- Mandor Oh 0.0052 80,000.00 416
Jumlah 456,491.00
Dibulatkan 456,491.00

1 m2 Pintu Alluminium
K-05 Natural

Pintu alluminium
- natural m2 1 211,800.00 211,800.00
- Pekerja Oh 1.05 42,000.00 44,100.00

- Tukang besi Oh 1.05 65,000.00 68,250.00

- Kepala tukang Oh 0.105 75,000.00 7,875.00


- Mandor Oh 0.0052 80,000.00 416
Jumlah 332,441.00
Dibulatkan 332,441.00
K-06 1 m2 Terali Besi

- Besi strip 2 x 3 m' 11.5 5,500.00 63,250.00


- Pekerja Oh 1.2 42,000.00 50,400.00

- Tukang las Oh 1.2 65,000.00 78,000.00


- Kepala tukang Oh 0.012 75,000.00 900
- Mandor Oh 0.0006 80,000.00 48
Jumlah 192,598.00
Dibulatkan 192,598.00

K-07 1 m2 Kawat Harmonika 4 cm

- Kawat harmonika M2 1.1 35,900.00 39,490.00

- Paku biasa " - 1" kg 0.02 23,800.00 476

- Papan kayu kamper M2 0.0018 5,692,600.00 10,246.68


- Pekerja Oh 0.1 42,000.00 4,200.00

- Tukang kayu Oh 0.1 65,000.00 6,500.00

- Kepala tukang Oh 0.01 75,000.00 750


- Mandor Oh 0.005 80,000.00 400
Jumlah 62,062.68
Dibulatkan 62,063.00

1 m' Talang Datar, Seng


K-08 BJLS 28 lebar 90 cm

Seng plat 3' x 6'


- BJLS 30 m' 1.05 20,801.00 21,841.05

- Paku biasa " - 1" Kg 0.015 23,800.00 357

Kayu papan borneo


- super M3 0.0096 5,595,800.00 53,719.68

- Flincote / meni besi Kg 0.25 30,400.00 7,600.00


- Pekerja Oh 0.15 42,000.00 6,300.00
- Tukang kayu Oh 0.4 65,000.00 26,000.00

- Kepala tukang Oh 0.025 75,000.00 1,875.00


- Mandor Oh 0.0013 80,000.00 104
Jumlah 117,796.73
Dibulatkan 117,797.00

1 m' Talang Miring, Seng


K-09 BJLS 28 lebar 90 cm

Seng plat 3' x 6'


- BJLS 30 m' 1.05 20,801.00 21,841.05

- Paku biasa " - 1" Kg 0.015 23,800.00 357

Kayu papan borneo


- super M3 0.019 5,595,800.00 106,320.20

- Flincote / meni besi Kg 0.3 30,400.00 9,120.00


- Pekerja Oh 0.2 42,000.00 8,400.00

- Tukang kayu Oh 0.4 65,000.00 26,000.00

- Kepala tukang Oh 0.025 75,000.00 1,875.00


- Mandor Oh 0.0013 80,000.00 100
Jumlah 174,013.25
Dibulatkan 174,013.00

1 m' Talang 1/2 lingkaran D-


15 cm, seng pelat BJLS 28
K-10 lebar 90 cm

Seng plat 3' x 6'


- BJLS 30 m' 1.05 20,801.00 21,841.05
- Paku biasa " - 1" Kg 0.1 23,800.00 2,380.00

Kayu papan borneo


- super kg 0.019 5,595,800.00 106,320.20

- Besi strip Kg 0.5 26,800.00 13,400.00


- Pekerja Oh 0.15 42,000.00 6,300.00

- Tukang kayu Oh 0.3 65,000.00 19,500.00

- Kepala tukang Oh 0.03 75,000.00 2,250.00


- Mandor Oh 0.008 80,000.00 640
Jumlah 172,631.25
Dibulatkan 172,631.00

1 m' Pasang kusen


pintu/jendela alluminium
K-11 natural 4"

Alumunium profil
- natural 4" m' 1.1 151,100.00 166,210.00

- Skrup fixer bh 2 250 500


- Sealant m' 1 7,500.00 7,500.00
- Pekerja Oh 0.043 42,000.00 1,806.00

- Tukang kayu Oh 0.043 65,000.00 2,795.00

- Kepala tukang Oh 0.0043 75,000.00 322.5


- Mandor Oh 0.0021 80,000.00 168
Jumlah 179,301.50
Dibulatkan 179,302.00

1 m' Pasang kusen


pintu/jendela alluminium
K-12 warna 4"
Alumunium profil
- warna 4" m' 1.1 163,000.00 179,300.00

- Skrup fixer bh 2 250 500


- Sealant m' 1 7,500.00 7,500.00
- Pekerja Oh 0.043 42,000.00 1,806.00

- Tukang kayu Oh 0.043 65,000.00 2,795.00

- Kepala tukang Oh 0.0043 75,000.00 322.5


- Mandor Oh 0.0021 80,000.00 168
Jumlah 192,391.50
Dibulatkan 192,392.00

1 m' Pasang kusen


pintu/jendela alluminium
K-13 natural 3"

Alumunium profil
- natural 3" m' 1.1 81,000.00 89,100.00

- Skrup fixer bh 2 250 500


- Sealant m' 1 7,500.00 7,500.00
- Pekerja Oh 0.043 42,000.00 1,806.00

- Tukang kayu Oh 0.043 65,000.00 2,795.00

- Kepala tukang Oh 0.0043 75,000.00 322.5


- Mandor Oh 0.0021 80,000.00 168
Jumlah 102,191.50
Dibulatkan 102,192.00

1 m' Pasang kusen


pintu/jendela alluminium
K-14 warna 3"
Alumunium profil
- warna 3" m' 1.1 102,000.00 112,200.00

- Skrup fixer bh 2 250 500


- Sealant m' 1 7,500.00 7,500.00
- Pekerja Oh 0.043 42,000.00 1,806.00

- Tukang kayu Oh 0.043 65,000.00 2,795.00

- Kepala tukang Oh 0.0043 75,000.00 322.5


- Mandor Oh 0.0021 80,000.00 168
Jumlah 125,291.50
Dibulatkan 125,292.00

1 m2 Pintu alluminium strip


K-15 lebar 8 cm

Alumunium profil 4"


- natural m' 4.4 151,100.00 664,840.00

Alumunium strip
- 6mm m2 1.05 171,800.00 180,390.00
- Pekerja Oh 0.085 42,000.00 3,570.00

- Tukang kayu Oh 0.085 65,000.00 5,525.00

- Kepala tukang Oh 0.0085 75,000.00 637.5


- Mandor Oh 0.0042 80,000.00 336
Jumlah 855,298.50
Dibulatkan 855,299.00

1 m2 Pintu/jendela kaca
K-16 rangka alluminium natural 4"

Alumunium profil
- natural 4" m' 4.4 151,100.00 664,840.00
- Profil alluminium T m' 4.5 12,200.00 54,900.00
- Sealant tube 0.27 7,500.00 2,025.00
- Pekerja Oh 0.085 42,000.00 3,570.00

- Tukang kayu Oh 0.085 65,000.00 5,525.00

- Kepala tukang Oh 0.0085 75,000.00 637.5


- Mandor Oh 0.005 80,000.00 400
Jumlah 731,897.50
Dibulatkan 731,898.00

1 m2 Pintu/jendela kaca
K-17 rangka alluminium warna 4"

Alumunium profil
- warna 4" m' 4.4 163,000.00 717,200.00

- Profil alluminium T m' 4.5 12,200.00 54,900.00


- Sealant tube 0.27 7,500.00 2,025.00
- Pekerja Oh 0.085 42,000.00 3,570.00

- Tukang kayu Oh 0.085 65,000.00 5,525.00

- Kepala tukang Oh 0.0085 75,000.00 637.5


- Mandor Oh 0.005 80,000.00 400
Jumlah 784,257.50
Dibulatkan 784,258.00

1 m2 Jendela nako & teralis


K-18 (10 klips)

Jendela nako
(rangka + kaca 5
- mm) m2 1.1 300,000.00 330,000.00
Paku skrup 1cm -
- 2,5cm bh 10 250 2,500.00

- Besi strip m' 7 5,500.00 38,500.00


- Pekerja Oh 0.2 42,000.00 8,400.00

- Tukang kayu Oh 0.2 65,000.00 13,000.00

- Kepala tukang Oh 0.02 75,000.00 1,500.00


- Mandor Oh 0.001 80,000.00 80
Jumlah 393,980.00
Dibulatkan 393,980.00
1 m2 Pintu pelat baja tebal 2mm rangkap,
K-19 rangka baja siku

- Besi siku L 30.30.3 Kg 15 24,000.00 360,000.00

- Baja pelat Kg 32.8 24,000.00 787,200.00

- kawat las Kg 0.05 23,600.00 1,180.00


- Pekerja Oh 0.2 42,000.00 8,400.00

- Tukang kayu Oh 0.2 65,000.00 13,000.00

- Kepala tukang Oh 0.02 75,000.00 1,500.00


- Mandor Oh 0.001 80,000.00 80
Jumlah 1,171,360.00
Dibulatkan 1,171,360.00

1 m2 Rangka jendela besi


K-20 square tube (5 x 5) cm

- Besi square tube M 4.76 7,300.00 34,748.00

Besi lis kaca (1 x 1)


- cm Kg 4.522 24,000.00 108,528.00

- Pengelasan Cm 20 2,464.00 49,280.00


- Pekerja Oh 0.65 42,000.00 27,300.00
- Tukang kayu Oh 0.65 65,000.00 42,250.00

- Kepala tukang Oh 0.065 75,000.00 4,875.00


- Mandor Oh 0.032 80,000.00 2,560.00
Jumlah 269,541.00
Dibulatkan 269,541.00

1 m2 Pintu lipat (folding door)


K-21 bahan besi

- Pintu lipat M2 1 501,700.00 501,700.00


- Pekerja Oh 1.05 42,000.00 44,100.00

- Tukang kayu Oh 1.05 65,000.00 68,250.00

- Kepala tukang Oh 0.105 75,000.00 7,875.00


- Mandor Oh 0.0052 80,000.00 416
Jumlah 622,341.00
Dibulatkan 622,341.00

1 m2 Tirai (venetions blinds


K-22 and vertical blinds)
- Tirai M2 1 537,300.00 537,300.00
- Pekerja Oh 0.35 42,000.00 14,700.00

- Tukang kayu Oh 0.35 65,000.00 22,750.00

- Kepala tukang Oh 0.035 75,000.00 2,625.00


- Mandor Oh 0.0018 80,000.00 144
Jumlah 577,519.00
Dibulatkan 577,519.00
VOLUM
No. URAIAN SAT E HARGA SAT HARGA
(Rp) (Rp)

K-01 1 Kg Besi profil

- Besi profil WF Kg 1.1 24,000.00 26,400.00

- Meni besi Kg 0.08 30,400.00 2,432.00


- Pekerja Oh 0.06 42,000.00 2,520.00

- Tukang besi Oh 0.006 65,000.00 390

- Kepala tukang Oh 0.006 75,000.00 450


- Mandor Oh 0.0003 80,000.00 24
Jumlah 32,216.00
Dibulatkan 32,216.00

K-02 1 Kg Perakitan baja


- Solar m' 0.01 7,150.00 71.5

- Minyak pelumas m' 0.001 55,000.00 55

- Sewa alat jam 0.008 100,000.00 800


- Pekerja Oh 0.001 42,000.00 42

- Tukang besi Oh 0.00001 65,000.00 0.65

- Kepala tukang Oh 0.00001 75,000.00 0.75


- Mandor Oh 0.00005 80,000.00 4
Jumlah 973.9
Dibulatkan 974

1 Cm Pengelasan dengan
K-03 las listrik

- kawat las kg 0.04 23,600.00 944


- Solar ltr 0.03 7,150.00 214.5

- Minyak pelumas ltr 0.004 55,000.00 220


- Sewa alat jam 0.017 100,000.00 1,700.00
- Pekerja org 0.004 42,000.00 168
- Tukang org 0.002 65,000.00 130

- Kepala Tukang org 0.0002 75,000.00 15


- Mandor org 0.0002 80,000.00 16
Jumlah 2,463.50
Dibulatkan 2,464.00

K-04 1 m2 Pintu Rolling Door

- Rolling door M2 1 306,600.00 306,600.00


- Pekerja Oh 1.05 42,000.00 44,100.00

- Tukang besi Oh 1.5 65,000.00 97,500.00

- Kepala tukang Oh 0.105 75,000.00 7,875.00


- Mandor Oh 0.0052 80,000.00 416
Jumlah 456,491.00
Dibulatkan 456,491.00

1 m2 Pintu Alluminium
K-05 Natural

Pintu alluminium
- natural m2 1 211,800.00 211,800.00
- Pekerja Oh 1.05 42,000.00 44,100.00

- Tukang besi Oh 1.05 65,000.00 68,250.00

- Kepala tukang Oh 0.105 75,000.00 7,875.00


- Mandor Oh 0.0052 80,000.00 416
Jumlah 332,441.00
Dibulatkan 332,441.00
K-06 1 m2 Terali Besi

- Besi strip 2 x 3 m' 11.5 5,500.00 63,250.00


- Pekerja Oh 1.2 42,000.00 50,400.00

- Tukang las Oh 1.2 65,000.00 78,000.00


- Kepala tukang Oh 0.012 75,000.00 900
- Mandor Oh 0.0006 80,000.00 48
Jumlah 192,598.00
Dibulatkan 192,598.00

K-07 1 m2 Kawat Harmonika 4 cm

- Kawat harmonika M2 1.1 35,900.00 39,490.00

- Paku biasa " - 1" kg 0.02 23,800.00 476

Papan kayu
- kamper M2 0.0018 5,692,600.00 10,246.68
- Pekerja Oh 0.1 42,000.00 4,200.00

- Tukang kayu Oh 0.1 65,000.00 6,500.00

- Kepala tukang Oh 0.01 75,000.00 750


- Mandor Oh 0.005 80,000.00 400
Jumlah 62,062.68
Dibulatkan 62,063.00

1 m' Talang Datar, Seng


K-08 BJLS 28 lebar 90 cm

Seng plat 3' x 6'


- BJLS 30 m' 1.05 20,801.00 21,841.05

- Paku biasa " - 1" Kg 0.015 23,800.00 357

Kayu papan
- borneo super M3 0.0096 5,595,800.00 53,719.68

- Flincote / meni besi Kg 0.25 30,400.00 7,600.00


- Pekerja Oh 0.15 42,000.00 6,300.00
- Tukang kayu Oh 0.4 65,000.00 26,000.00

- Kepala tukang Oh 0.025 75,000.00 1,875.00


- Mandor Oh 0.0013 80,000.00 104
Jumlah 117,796.73
Dibulatkan 117,797.00

1 m' Talang Miring, Seng


K-09 BJLS 28 lebar 90 cm

Seng plat 3' x 6'


- BJLS 30 m' 1.05 20,801.00 21,841.05

- Paku biasa " - 1" Kg 0.015 23,800.00 357

Kayu papan
- borneo super M3 0.019 5,595,800.00 106,320.20

- Flincote / meni besi Kg 0.3 30,400.00 9,120.00


- Pekerja Oh 0.2 42,000.00 8,400.00

- Tukang kayu Oh 0.4 65,000.00 26,000.00

- Kepala tukang Oh 0.025 75,000.00 1,875.00


- Mandor Oh 0.0013 80,000.00 100
Jumlah 174,013.25
Dibulatkan 174,013.00

1 m' Talang 1/2 lingkaran D-


15 cm, seng pelat BJLS 28
K-10 lebar 90 cm

Seng plat 3' x 6'


- BJLS 30 m' 1.05 20,801.00 21,841.05
- Paku biasa " - 1" Kg 0.1 23,800.00 2,380.00

Kayu papan
- borneo super kg 0.019 5,595,800.00 106,320.20

- Besi strip Kg 0.5 26,800.00 13,400.00


- Pekerja Oh 0.15 42,000.00 6,300.00

- Tukang kayu Oh 0.3 65,000.00 19,500.00

- Kepala tukang Oh 0.03 75,000.00 2,250.00


- Mandor Oh 0.008 80,000.00 640
Jumlah 172,631.25
Dibulatkan 172,631.00

1 m' Pasang kusen


pintu/jendela alluminium
K-11 natural 4"

Alumunium profil
- natural 4" m' 1.1 151,100.00 166,210.00

- Skrup fixer bh 2 250 500


- Sealant m' 1 7,500.00 7,500.00
- Pekerja Oh 0.043 42,000.00 1,806.00

- Tukang kayu Oh 0.043 65,000.00 2,795.00

- Kepala tukang Oh 0.0043 75,000.00 322.5


- Mandor Oh 0.0021 80,000.00 168
Jumlah 179,301.50
Dibulatkan 179,302.00

1 m' Pasang kusen


pintu/jendela alluminium
K-12 warna 4"
Alumunium profil
- warna 4" m' 1.1 163,000.00 179,300.00

- Skrup fixer bh 2 250 500


- Sealant m' 1 7,500.00 7,500.00
- Pekerja Oh 0.043 42,000.00 1,806.00

- Tukang kayu Oh 0.043 65,000.00 2,795.00

- Kepala tukang Oh 0.0043 75,000.00 322.5


- Mandor Oh 0.0021 80,000.00 168
Jumlah 192,391.50
Dibulatkan 192,392.00

1 m' Pasang kusen


pintu/jendela alluminium
K-13 natural 3"

Alumunium profil
- natural 3" m' 1.1 81,000.00 89,100.00

- Skrup fixer bh 2 250 500


- Sealant m' 1 7,500.00 7,500.00
- Pekerja Oh 0.043 42,000.00 1,806.00

- Tukang kayu Oh 0.043 65,000.00 2,795.00

- Kepala tukang Oh 0.0043 75,000.00 322.5


- Mandor Oh 0.0021 80,000.00 168
Jumlah 102,191.50
Dibulatkan 102,192.00

1 m' Pasang kusen


pintu/jendela alluminium
K-14 warna 3"
Alumunium profil
- warna 3" m' 1.1 102,000.00 112,200.00

- Skrup fixer bh 2 250 500


- Sealant m' 1 7,500.00 7,500.00
- Pekerja Oh 0.043 42,000.00 1,806.00

- Tukang kayu Oh 0.043 65,000.00 2,795.00

- Kepala tukang Oh 0.0043 75,000.00 322.5


- Mandor Oh 0.0021 80,000.00 168
Jumlah 125,291.50
Dibulatkan 125,292.00

1 m2 Pintu alluminium strip


K-15 lebar 8 cm

Alumunium profil 4"


- natural m' 4.4 151,100.00 664,840.00

Alumunium strip
- 6mm m2 1.05 171,800.00 180,390.00
- Pekerja Oh 0.085 42,000.00 3,570.00

- Tukang kayu Oh 0.085 65,000.00 5,525.00

- Kepala tukang Oh 0.0085 75,000.00 637.5


- Mandor Oh 0.0042 80,000.00 336
Jumlah 855,298.50
Dibulatkan 855,299.00

1 m2 Pintu/jendela kaca
K-16 rangka alluminium natural 4"

Alumunium profil
- natural 4" m' 4.4 151,100.00 664,840.00
- Profil alluminium T m' 4.5 12,200.00 54,900.00
- Sealant tube 0.27 7,500.00 2,025.00
- Pekerja Oh 0.085 42,000.00 3,570.00

- Tukang kayu Oh 0.085 65,000.00 5,525.00

- Kepala tukang Oh 0.0085 75,000.00 637.5


- Mandor Oh 0.005 80,000.00 400
Jumlah 731,897.50
Dibulatkan 731,898.00

1 m2 Pintu/jendela kaca
K-17 rangka alluminium warna 4"

Alumunium profil
- warna 4" m' 4.4 163,000.00 717,200.00

- Profil alluminium T m' 4.5 12,200.00 54,900.00


- Sealant tube 0.27 7,500.00 2,025.00
- Pekerja Oh 0.085 42,000.00 3,570.00

- Tukang kayu Oh 0.085 65,000.00 5,525.00

- Kepala tukang Oh 0.0085 75,000.00 637.5


- Mandor Oh 0.005 80,000.00 400
Jumlah 784,257.50
Dibulatkan 784,258.00

1 m2 Jendela nako & teralis


K-18 (10 klips)

Jendela nako
(rangka + kaca 5
- mm) m2 1.1 300,000.00 330,000.00
Paku skrup 1cm -
- 2,5cm bh 10 250 2,500.00

- Besi strip m' 7 5,500.00 38,500.00


- Pekerja Oh 0.2 42,000.00 8,400.00

- Tukang kayu Oh 0.2 65,000.00 13,000.00

- Kepala tukang Oh 0.02 75,000.00 1,500.00


- Mandor Oh 0.001 80,000.00 80
Jumlah 393,980.00
Dibulatkan 393,980.00
1 m2 Pintu pelat baja tebal 2mm rangkap,
K-19 rangka baja siku

- Besi siku L 30.30.3 Kg 15 24,000.00 360,000.00

- Baja pelat Kg 32.8 24,000.00 787,200.00

- kawat las Kg 0.05 23,600.00 1,180.00


- Pekerja Oh 0.2 42,000.00 8,400.00

- Tukang kayu Oh 0.2 65,000.00 13,000.00

- Kepala tukang Oh 0.02 75,000.00 1,500.00


- Mandor Oh 0.001 80,000.00 80
Jumlah 1,171,360.00
Dibulatkan 1,171,360.00

1 m2 Rangka jendela besi


K-20 square tube (5 x 5) cm

- Besi square tube M 4.76 7,300.00 34,748.00

Besi lis kaca (1 x 1)


- cm Kg 4.522 24,000.00 108,528.00

- Pengelasan Cm 20 2,464.00 49,280.00


- Pekerja Oh 0.65 42,000.00 27,300.00
- Tukang kayu Oh 0.65 65,000.00 42,250.00

- Kepala tukang Oh 0.065 75,000.00 4,875.00


- Mandor Oh 0.032 80,000.00 2,560.00
Jumlah 269,541.00
Dibulatkan 269,541.00

1 m2 Pintu lipat (folding


K-21 door) bahan besi

- Pintu lipat M2 1 501,700.00 501,700.00


- Pekerja Oh 1.05 42,000.00 44,100.00

- Tukang kayu Oh 1.05 65,000.00 68,250.00

- Kepala tukang Oh 0.105 75,000.00 7,875.00


- Mandor Oh 0.0052 80,000.00 416
Jumlah 622,341.00
Dibulatkan 622,341.00

1 m2 Tirai (venetions blinds


K-22 and vertical blinds)
- Tirai M2 1 537,300.00 537,300.00
- Pekerja Oh 0.35 42,000.00 14,700.00

- Tukang kayu Oh 0.35 65,000.00 22,750.00

- Kepala tukang Oh 0.035 75,000.00 2,625.00


- Mandor Oh 0.0018 80,000.00 144
Jumlah 577,519.00
Dibulatkan 577,519.00
VOLUM
No. URAIAN SAT E HARGA SAT
(Rp)
M-01 1 Buah Closet jongkok Porselen Standar

Closet jongkok bh 1 188,200.00

P.C (50 gk) Kg 6 1,406.00

Pasir pasang m3 0.01 233,400.00


Pekerja org 1 42,000.00

Tukang batu org 1.5 65,000.00

Kepala Tukang org 1.5 75,000.00


Mandor org 0.16 80,000.00
Jumlah

Dibulatkan

M-02 1 Buah Urinoir


Urinoir bh 1 1,773,400.00

P.C (50 gk) Kg 6 1,406.00

Pasir pasang m3 0.01 233,400.00


Pekerja org 1 42,000.00

Tukang batu org 1 65,000.00

Kepala Tukang org 0.1 75,000.00


Mandor org 0.001 80,000.00

Perlengkapan 30 %
harga urinoir lot 0.3 1,773,400.00
Jumlah

Dibulatkan

M-03 1 Buah Wastafel


wastafel standar unit 1 1,012,700.00

P.C (50 gk) Kg 6 1,406.00

Pasir pasang m3 0.01 233,400.00


Pekerja org 1.2 42,000.00

Tukang batu org 1.45 65,000.00

Kepala Tukang org 0.15 75,000.00


Mandor org 0.1 80,000.00

Perlengkapan 12 %
harga wastafel lot 0.12 1,773,400.00
Jumlah

Dibulatkan

M-04 1 Buah bak Mandi Fibreglass Volume 0,30 m3

Bak fibreglass
0.60m x 0.60m bh 1 255,300.00
Pekerja org 1.8 42,000.00

Tukang batu org 2.7 65,000.00

Kepala Tukang org 0.54 75,000.00


Mandor org 0.11 80,000.00

Perlengkapan 18 %
harga bak lot 0.18 255,300.00
Jumlah

Dibulatkan
M-05 1 M' Saluran Air Limbah Buis beton d = 30 cm - 60 cm

Buis beton 30 cm bh 1.1 61,700.00

Bata merah bh 25 775

P.C (50 gk) Kg 10.3 1,406.00

Pasir pasang m3 0.061 233,400.00

Pasir urug m3 0.069 175,300.00


Pekerja org 0.38 42,000.00

Tukang batu org 0.19 65,000.00

Kepala Tukang org 0.019 75,000.00


Mandor org 0.019 80,000.00
Jumlah

Dibulatkan

M-06 1 Buah Bak Kontrol Pas Bata Merah Uk (60 x 60) cm

Bata merah bh 186 775

P.C (50 gk) Kg 114 1,406.00

Pasir pasang m3 0.184 233,400.00

Batu pecah 2/3 m3 0.033 211,100.00

Besi beton m3 4.85 16,500.00

Pasir beton m3 0.12 255,400.00


Pekerja org 2.16 42,000.00

Tukang batu org 0.72 65,000.00

Kepala Tukang org 0.072 75,000.00


Mandor org 0.108 80,000.00
Tukang gali org 0.1 42,000.00
Jumlah

Dibulatkan

M-07 1 Buah Bak Kontrol Pas Bata Merah Uk (30 x 30) cm

Bata merah bh 53 775

P.C (50 gk) Kg 44 1,406.00

Pasir pasang m3 0.07 233,400.00

Batu pecah 2/3 m3 0.07 211,100.00

Besi beton m3 1.6 16,500.00

Pasir beton m3 0.06 255,400.00


Pekerja org 3.2 42,000.00

Tukang batu org 1.015 65,000.00

Kepala Tukang org 0.0015 75,000.00


Mandor org 0.016 80,000.00
Jumlah

Dibulatkan

1 M' Pipa PVC


M-08 1/2" (AW)

Pipa pvc 1/2" m' 1.2 10,025.00


Pekerja org 0.036 42,000.00

Tukang batu org 0.06 65,000.00

Kepala Tukang org 0.006 75,000.00


Mandor org 0.0018 80,000.00
Perlengkapan 35 %
harga pipa lot 0.35 12,030.00
Jumlah

Dibulatkan

1 M' Pipa PVC 1"


M-09 (AW)

Pipa pvc 1" m' 1.2 15,800.00


Pekerja org 0.036 42,000.00

Tukang batu org 0.06 65,000.00

Kepala Tukang org 0.006 75,000.00


Mandor org 0.0018 80,000.00

Perlengkapan 35 %
harga pipa lot 0.35 18,960.00
Jumlah

Dibulatkan

1 M' Pipa PVC


M-10 11/2" (AW)

Pipa pvc 11/2" m' 1.2 26,475.00


Pekerja org 0.036 42,000.00

Tukang batu org 0.06 65,000.00

Kepala Tukang org 0.006 75,000.00


Mandor org 0.0018 80,000.00
Perlengkapan 35 %
harga pipa lot 0.35 31,770.00
Jumlah

Dibulatkan

1 M' Pipa PVC 2"


M-11 (AW)

Pipa pvc 2" m' 1.2 27,675.00


Pekerja org 0.036 42,000.00

Tukang batu org 0.06 65,000.00

Kepala Tukang org 0.006 75,000.00


Mandor org 0.0018 80,000.00

Perlengkapan 35 %
harga pipa lot 0.35 31,770.00
Jumlah

Dibulatkan

1 M' Pipa PVC 4"


M-12 (AW)

Pipa pvc 4" m' 1.2 86,975.00


Pekerja org 0.081 42,000.00

Tukang batu org 0.135 65,000.00

Kepala Tukang org 0.0135 75,000.00


Mandor org 0.0041 80,000.00
Perlengkapan 35 %
harga pipa lot 0.35 104,370.00
Jumlah

Dibulatkan

1 M' Pipa PVC


M-13 3/4" (AW)

Pipa pvc 3/4" m' 1.2 13,050.00


Pekerja org 0.081 42,000.00

Tukang batu org 0.135 65,000.00

Kepala Tukang org 0.0135 75,000.00


Mandor org 0.0041 80,000.00

Perlengkapan 35 %
harga pipa lot 0.35 15,660.00
Jumlah

Dibulatkan
M-14 1 Buah Bak Cuci piring Stainless steel

Bak cuci stainless


steel + asesoris
lengkap bh 1 397,800.00
Pekerja org 0.03 42,000.00

Tukang batu org 0.3 65,000.00

Kepala Tukang org 0.03 75,000.00


Mandor org 0.0015 80,000.00
Jumlah

Dibulatkan

1 Buah Kran 1/2" -


M-15 3/4"
Kran air bh 1 40,900.00

Seal tape bh 0.025 4,200.00


Pekerja org 0.01 42,000.00

Tukang batu org 0.1 65,000.00

Kepala Tukang org 0.01 75,000.00


Mandor org 0.005 80,000.00
Jumlah

Dibulatkan

M-16 1 Buah Floor Drain

Floor drain bh 1 66,600.00


Pekerja org 0.01 42,000.00

Tukang batu org 0.1 65,000.00

Kepala Tukang org 0.01 75,000.00


Mandor org 0.005 80,000.00
Jumlah

Dibulatkan

M-17 1 M' Grafel beton U 20 cm -60 cm

Pipa beton U bh 1.1 44,300.00

Bata merah bh 12 775

P.C (50 gk) zak 0.103 1,406.00

Pasir pasang m3 0.0305 233,400.00


Pasir urug m3 0.0345 175,300.00
Pekerja org 0.01 42,000.00

Tukang batu org 0.1 65,000.00

Kepala Tukang org 0.01 75,000.00


Mandor org 0.005 80,000.00
Jumlah

Dibulatkan

M-18 1 M' Pasang Talang Plastik PVC U 15 cm (AW)

Talang plastik PVC m' 1.05 60,000.00

Perlengkapan 35 %
harga talang lot 0.35 63,000.00
Pekerja org 0.15 42,000.00

Tukang batu org 0.4 65,000.00

Kepala Tukang org 0.025 75,000.00


Mandor org 0.0013 80,000.00
Jumlah

Dibulatkan
1 M' Saluran Air Limbah Buis Beton
M-19 60 cm

Buis beton 60 cm bh 1.1 130,900.00

Bata merah bh 25 775

P.C (50 gk) zak 0.206 1,406.00

Pasir pasang m3 0.061 233,400.00

Pasir urug m3 0.069 175,300.00


Pekerja org 0.38 42,000.00
Tukang batu org 0.19 65,000.00

Kepala Tukang org 0.019 75,000.00


Mandor org 0.019 80,000.00
Jumlah

Dibulatkan

1 M' Pasang Talang


M-20 Seng Datar

Seng pelat 3" x 6" lbr 0.5 20,801.00


Paku kg 0.015 23,400.00

Kayu kelas II m3 0.0096 2,850,000.00

Meni besi kg 0.25 30,400.00


Pekerja org 0.15 42,000.00

Tukang batu org 0.4 65,000.00

Kepala Tukang org 0.025 75,000.00


Mandor org 0.0013 80,000.00
Jumlah

Dibulatkan

1 Buah Closet
M-21 Duduk

Closet duduk bh 1 1,724,700.00


Pekerja org 3.3 42,000.00

Tukang batu org 1.1 65,000.00

Kepala Tukang org 0.001 75,000.00


Mandor org 0.16 80,000.00
Perlengkapan 6 %
harga closet lot 0.06 1,724,700.00
Jumlah

Dibulatkan
M-22 1 Buah Tangki Air fibreglass Volume 1 m3

Bak fibreglass
kapasitas 1 m3 bh 1 1,316,400.00
Pekerja org 3.3 42,000.00

Tukang batu org 1.1 65,000.00

Kepala Tukang org 0.001 75,000.00


Mandor org 0.16 80,000.00

Perlengkapan 6 %
harga bak lot 0.06 1,316,400.00
Jumlah

Dibulatkan

M-23 1 Unit Septictank 2x1,50x1,50 m + Rembesan

Galian tanah m3 4.5 26,252.00

Pasir urug m3 0.214 175,300.00

lantai kerja m3 2.25 716,798.00

Pas bata adk 1pc :


3ps m2 15 220,267.10
Pelat beton K-225 m3 0.3 6,438,864.00

Plesteran adk 1pc :


3ps m2 15 41,301.82

Pipa PVC 4" jenis


AW m' 5.4 256,800.00

Pipa GIP 1 1/2" m' 5 46,750.00

Galian tanah untuk


rembesan m3 3.375 20,000.00
Pas ijuk kg 5.4 23,400.00

Urugan kerikil 3/5 m3 1.05 205,000.00

Pipa PVC 4"


berlubang jenis AW m' 9 36,700.00

Urugan dan
perataan tanah m3 1.125 34,584.00
Jumlah

Dibulatkan

M-24 1 Unit Septictank 1x1,50x1,50 m + Rembesan

Galian tanah m3 2.25 20,000.00

Pasir urug m3 0.107 175,300.00

lantai kerja m3 1.125 716,798.00


Pas bata adk 1pc :
3ps m2 7.5 220,267.10

Pelat beton K-225 m3 0.15 6,438,864.00

Plesteran adk 1pc :


3ps m2 7.5 41,301.82

Pipa PVC 4" jenis


AW m' 9 256,800.00

Pipa GIP 1 1/2" m' 2.5 46,750.00

Galian tanah untuk


rembesan m3 1.688 20,000.00
Pas ijuk kg 2.7 23,400.00

Urugan kerikil 3/5 m3 0.525 205,000.00

Pipa PVC 4"


berlubang jenis AW m' 9 36,700.00

Urugan dan
perataan tanah m3 0.563 34,584.00
Jumlah

Dibulatkan
HARGA
(Rp)

188,200.00

8,436.00

2,334.00
42,000.00

97,500.00

112,500.00
12,800.00
463,770.00

463,770.00

1,773,400.00

8,436.00

2,334.00
42,000.00

65,000.00

7,500.00
80

532,020.00
2,430,770.00

2,430,770.00
1,012,700.00

8,436.00

2,334.00
50,400.00

94,250.00

11,250.00
8,000.00

212,808.00
1,400,178.00

1,400,178.00

255,300.00
75,600.00

175,500.00

40,500.00
8,800.00

45,954.00
601,654.00

601,654.00
0 cm

67,870.00

19,375.00

14,481.80

14,237.40

12,095.70
15,960.00

12,350.00

1,425.00
1,520.00
159,314.90

159,315.00

cm

144,150.00

160,284.00

42,945.60

6,966.30

80,025.00

30,648.00
90,720.00

46,800.00

5,400.00
8,640.00
4,200.00
620,778.90

620,779.00

cm

41,075.00

61,864.00

16,338.00

14,777.00

26,400.00

15,324.00
134,400.00

65,975.00

112.5
1,280.00
377,545.50

377,546.00

12,030.00
1,512.00

3,900.00

450
144
4,210.50
22,246.50

22,247.00

18,960.00
1,512.00

3,900.00

450
144

6,636.00
31,602.00

31,602.00

31,770.00
1,512.00

3,900.00

450
144
11,119.50
48,895.50

48,896.00

33,210.00
1,512.00

3,900.00

450
144

11,119.50
50,335.50

50,336.00

104,370.00
3,402.00

8,775.00

1,012.50
328
36,529.50
154,417.00

154,417.00

15,660.00
3,402.00

8,775.00

1,012.50
328

5,481.00
34,658.50

34,659.00

397,800.00
1,260.00

19,500.00

2,250.00
120
420,930.00

420,930.00

40,900.00

105
420

6,500.00

750
400
49,075.00

49,075.00

66,600.00
420

6,500.00

750
400
74,670.00

74,670.00

48,730.00

9,300.00

144.82

7,118.70
6,047.85
420

6,500.00

750
400
79,411.37

79,411.00

63,000.00

22,050.00
6,300.00

26,000.00

1,875.00
100
119,325.00

119,325.00

143,990.00

19,375.00

289.64

14,237.40

12,095.70
15,960.00
12,350.00

1,425.00
1,520.00
221,242.74

221,243.00

10,400.50
351

27,360.00

7,600.00
6,300.00

26,000.00

1,875.00
100
79,986.50

79,987.00

1,724,700.00
138,600.00

71,500.00

75
12,800.00
103,482.00
2,051,157.00

2,051,157.00

1,316,400.00
138,600.00

71,500.00

75
12,800.00

78,984.00
1,618,359.00

1,618,359.00

118,134.00

37,514.20

1,612,795.50

3,304,006.50
1,931,659.20

619,527.30

1,386,720.00

233,750.00

67,500.00
126,360.00

215,250.00

330,300.00

38,907.00
10,022,423.70

10,022,424.00

45,000.00

18,757.10

806,397.75
1,652,003.25

965,829.60

309,763.65

2,311,200.00

116,875.00

33,760.00
63,180.00

107,625.00

330,300.00

19,470.79
6,780,162.14

6,780,162.00
VOLUM
No. URAIAN SAT E HARGA SAT

N-01 1 M2 Mengikis / Mengerok Permukaan Cat Tembok Lama

- Soda api Kg 0.05 35,600.00


- Pekerja Oh 0.15 42,000.00
- Mandor Oh 0.0025 80,000.00
Jumlah
Dibulatkan
N-02 1 M2 Mendempul Dan Menggosok Kayu
- Dempul Kg 0.08 35,800.00

- Minyak cat Kg 0.02 38,400.00

- Batu apung Kg 0.01 29,600.00


- Pekerja Oh 0.04 42,000.00

- Tukang cat Oh 0.04 65,000.00

- Kepala tukang Oh 0.004 75,000.00


- Mandor Oh 0.0025 80,000.00
Jumlah
Dibulatkan

N-03 1 M2 Pengecatan Bidang Kayu Lama Setara Sieve


- Plamir Kg 0.15 25,000.00

- Cat dasar Kg 0.17 30,000.00

Cat penutup
- setara sieve 2x Kg 0.17 41,700.00
- Pekerja Oh 0.07 42,000.00

- Tukang cat Oh 0.075 65,000.00

- Kepala tukang Oh 0.0075 75,000.00


- Mandor Oh 0.0025 80,000.00
Jumlah
Dibulatkan
N-04 1 M2 Pengecatan Bidang Kayu Baru Setara Sieve

- Cat meni Kg 0.2 30,400.00


- Plamir Kg 0.15 25,000.00

- Cat dasar Kg 0.17 30,000.00

Cat penutup 3x
- setara sieve Kg 0.35 41,700.00
- Pekerja Oh 0.07 42,000.00

- Tukang cat Oh 0.105 65,000.00

- Kepala tukang Oh 0.004 75,000.00


- Mandor Oh 0.0025 80,000.00
Jumlah
Dibulatkan

N-05 1 M2 Pelaburan Bidang Kayu dengan Politur


- Politur Ltr 0.15 48,000.00

- Politur jadi Ltr 0.372 112,700.00

- Ampelas Lbr 2 5,000.00

- Tukang cat Oh 0.06 65,000.00

- Kepala tukang Oh 0.016 75,000.00


- Mandor Oh 0.0025 80,000.00
Jumlah
Dibulatkan

N-06 1 M2 Pelaburan Bidang Kayu dengan Cat Residu dan Ter

- Residu atau ter Ltr 0.35 8,100.00


- Pekerja Oh 0.1 42,000.00
- Mandor Oh 0.006 80,000.00
Jumlah
Dibulatkan
1 M2 Pengecatan Tembok Baru Setara
N-07 ICI
- Plamir tembok Kg 0.1 25,000.00

- Cat dasar Kg 0.1 30,000.00

Cat penutup 2x
- setara ICI Kg 0.26 75,000.00
- Pekerja Oh 0.02 42,000.00

- Tukang cat Oh 0.063 65,000.00

- Kepala tukang Oh 0.0063 75,000.00


- Mandor Oh 0.0025 80,000.00
Jumlah
Dibulatkan
N-08 1 M2 Pengecatan Tembok Lama Setara ICI

- Cat dasar Kg 0.12 30,000.00

Cat penutup 2
- x Kg 0.18 75,000.00
- Pekerja Oh 0.028 42,000.00

- Tukang cat Oh 0.042 65,000.00

- Kepala tukang Oh 0.0042 75,000.00


- Mandor Oh 0.0025 80,000.00
Jumlah
Dibulatkan
N-09 1 M2 Pengecatan Plafond ( 3x ) Setara ICI

Cat tembok
- setara ICI Kg 0.2 75,000.00

- Plamir tembok Kg 0.16 25,000.00


- Rol cat Bh 0.01 32,500.00

- Steger werk Ls 1 1,000.00

- Ampelas Lbr 0.5 5,000.00


- Pekerja Oh 0.2 42,000.00
- Tukang cat Oh 0.3 65,000.00

- Kepala tukang Oh 0.03 75,000.00


- Mandor Oh 0.01 80,000.00
Jumlah
Dibulatkan

N-10 1 M2 Pengecatan Plafond ( 3x ) Setara Vinilex

Cat tembok
- setara Vinilex Kg 0.2 25,000.00

- Plamir tembok Kg 0.16 25,000.00


- Rol cat Bh 0.01 32,500.00

- Steger werk Ls 1 1,000.00

- Ampelas Lbr 0.5 5,000.00


- Pekerja Oh 0.2 42,000.00

- Tukang cat Oh 0.3 65,000.00

- Kepala tukang Oh 0.03 75,000.00


- Mandor Oh 0.01 80,000.00
Jumlah
Dibulatkan
N-10-r' 1 M2 Pengecatan Plafond ( 2x ) Setara Vinilex

Cat tembok
- setara Vinilex Kg 0.13 25,000.00

- Plamir tembok Kg 0.11 25,000.00


- Rol cat Bh 0.1 32,500.00

- Steger werk Ls 0.67 1,000.00

- Ampelas Lbr 0.33 5,000.00


- Pekerja Oh 0.13 42,000.00

- Tukang cat Oh 0.2 65,000.00


- Kepala tukang Oh 0.02 75,000.00
- Mandor Oh 0.01 80,000.00
Jumlah
Dibulatkan
N-11 1 M2 Memasang Wallpaper

- Wallpaper m2 1.2 55,700.00

- Lem Perekat Kg 0.25 35,700.00


- Pekerja Oh 0.35 42,000.00

- Tukang cat Oh 0.175 65,000.00

- Kepala tukang Oh 0.017 75,000.00


- Mandor Oh 0.0017 80,000.00
Jumlah
Dibulatkan
N-12 1 M2 Pengecatan Permukaan Baja dengan Meni Besi

- Meni besi Kg 0.1 30,400.00


- Kuas 3" Bh 0.01 16,000.00
- Pekerja Oh 0.02 42,000.00

- Tukang cat Oh 0.2 65,000.00

- Kepala tukang Oh 0.02 75,000.00


- Mandor Oh 0.01 80,000.00
Jumlah
Dibulatkan

N-13 1 M2 Pengecatan Permukaan Baja dengan Meni Besi dan Perancah

- Meni besi Kg 0.1 30,400.00


- Kuas 3" Bh 0.01 16,000.00

- Kayu perancah m3 0.002 2,069,800.00


- Pekerja Oh 0.25 42,000.00

- Tukang cat Oh 0.225 65,000.00

- Kepala tukang Oh 0.0225 75,000.00


- Mandor Oh 0.0075 80,000.00
Jumlah
Dibulatkan

N-14 1 M2 Pengecatan Permukaan Baja Lapis seng (galbani) secara manual 1 lps cat 2 um

Cat besi setara


- ICI Kg 0.3 67,700.00
- Pekerja Oh 0.006 42,000.00

- Tukang cat Oh 0.06 65,000.00

- Kepala tukang Oh 0.012 75,000.00


- Mandor Oh 0.006 80,000.00
Jumlah
Dibulatkan

N-15 1 M2 Pengecatan Tembok Baru Setara Vinilex (2 x laburan)

- Plamir tembok Kg 0.1 25,000.00

- Cat dasar Kg 0.1 30,000.00

Cat penutup 2x
- setara vinilex Kg 0.26 25,000.00
- Pekerja Oh 0.02 42,000.00

- Tukang cat Oh 0.063 65,000.00

- Kepala tukang Oh 0.0063 75,000.00


- Mandor Oh 0.0025 80,000.00
Jumlah
Dibulatkan

N-15r' 1 M2 Pengecatan Tembok Baru Setara Vinilex (3 x laburan)

- Plamir tembok Kg 0.1 25,000.00

- Cat dasar Kg 0.1 30,000.00


Cat penutup 3x
- setara vinilex Kg 0.39 25,000.00
- Pekerja Oh 0.03 42,000.00

- Tukang cat Oh 0.0945 65,000.00

- Kepala tukang Oh 0.0095 75,000.00


- Mandor Oh 0.0038 80,000.00
Jumlah
Dibulatkan
N-16 1 M2 Pengecatan Tembok Lama Setara Vinilex

- Cat dasar Kg 0.12 30,000.00

Cat penutup 2
- x Kg 0.18 25,000.00
- Pekerja Oh 0.028 42,000.00

- Tukang cat Oh 0.042 65,000.00

- Kepala tukang Oh 0.0042 75,000.00


- Mandor Oh 0.0025 80,000.00
Jumlah
Dibulatkan
HARGA

1,780.00
6,300.00
200
8,280.00
8,280.00

2,864.00

768

296
1,680.00

2,600.00

300
200
8,708.00
8,708.00

3,750.00

5,100.00

7,089.00
2,940.00

4,875.00

562.5
200
24,516.50
24,517.00
6,080.00
3,750.00

5,100.00

14,595.00
2,940.00

6,825.00

300
200
39,790.00
39,790.00

7,200.00

41,924.40

10,000.00

3,900.00

1,200.00
200
64,424.40
64,424.00

2,835.00
4,200.00
480
7,515.00
7,515.00
2,500.00

3,000.00

19,500.00
840

4,095.00

472.5
200
30,607.50
30,608.00

3,600.00

13,500.00
1,176.00

2,730.00

315
200
21,521.00
21,521.00

15,000.00

4,000.00
325

1,000.00

2,500.00
8,400.00
19,500.00

2,250.00
800
53,775.00
53,775.00

5,000.00

4,000.00
325

1,000.00

2,500.00
8,400.00

19,500.00

2,250.00
800
43,775.00
43,775.00

3,250.00

2,750.00
3,250.00

670

1,650.00
5,460.00

13,000.00
1,500.00
800
32,330.00
32,330.00

66,840.00

8,925.00
14,700.00

11,375.00

1,275.00
136
103,251.00
103,251.00

3,040.00
160
840

13,000.00

1,500.00
800
19,340.00
19,340.00

erancah

3,040.00
160

4,139.60
10,500.00

14,625.00

1,687.50
600
34,752.10
34,752.00

ara manual 1 lps cat 2 um

20,310.00
252

3,900.00

900
480
25,842.00
25,842.00

2,500.00

3,000.00

6,500.00
840

4,095.00

472.5
200
17,607.50
17,608.00

2,500.00

3,000.00
9,750.00
1,260.00

6,142.50

712.5
304
23,669.00
23,669.00

3,600.00

4,500.00
1,176.00

2,730.00

315
200
12,521.00
12,521.00
NO. URAIAN KOEF SAT. HARGA SAT. (Rp)
O-01 1 Lubang (70x70x70) cm, tanam pohon pelindung tinggi 2m
Pupuk kandang 0.08 krg 25,000.00

Furadan 0.001 kg 24,000.00


Pohon pelindung 1 btng 25,000.00
Pekerja 0.025 org 42,000.00
Mandor 0.0025 org 80,000.00
Jumlah
Dibulatkan
O-02 1 Lubang (70x70x70) cm, tanam bambu krisik/jepang
Pupuk kandang 0.08 krg 25,000.00

Furadan 0.001 kg 24,000.00


Bambu krisik/jepang 1 btng 50,000.00
Pekerja 0.025 org 42,000.00
Mandor 0.0025 org 80,000.00
Jumlah
Dibulatkan
O-03 1 Lubang (40x40x40) cm, tanam pohon perdu (polibag)
Pupuk kandang 0.04 krg 25,000.00

Furadan 0.001 kg 24,000.00


Pohon perdu 1 btng 10,000.00
Pekerja 0.02 org 42,000.00
Mandor 0.002 org 80,000.00
Jumlah
Dibulatkan
O-04 1 M2 Tanam rumput gajah (silang papan catur)
Pupuk kandang 0.04 krg 25,000.00
Rumput gajah mini 0.5 m2 15,000.00
Pekerja 0.04 org 42,000.00
Mandor 0.004 org 80,000.00
Jumlah
Dibulatkan
HARGA (Rp)

2,000.00

24
25,000.00
1,050.00
200
28,274.00
28,274.00

2,000.00

24
50,000.00
1,050.00
200
53,274.00
53,274.00

1,000.00

24
10,000.00
840
160
12,024.00
12,024.00

1,000.00
7,500.00
1,680.00
320
10,500.00
10,500.00
NO URAIAN SATUAN UPAH (Rp.)

1 Mandor Org/hr Rp 80,000.00

Kepala Tukang
2 Batu Org/hr Rp 75,000.00

Kepala Tukang
3 Kayu Org/hr Rp 75,000.00

Kepala Tukang
4 Besi Org/hr Rp 75,000.00

Kepala Tukang
5 Cat Org/hr Rp 75,000.00

Kepala Tukang
6 Listrik Org/hr Rp 75,000.00

7 Kepala Tukang Org/hr Rp 75,000.00

8 Tukang Batu Org/hr Rp 65,000.00

9 Tukang Kayu Org/hr Rp 65,000.00

Tukang
10 Besi/Baja Org/hr Rp 65,000.00

11 Tukang Cat Org/hr Rp 65,000.00

12 Tukang Listrik Org/hr Rp 65,000.00

13 Tukang Pipa Org/hr Rp 65,000.00


14 Tukang Plitur Org/hr Rp 65,000.00

15 Tukang Taman Org/hr Rp 65,000.00

16 Tukang Org/hr Rp 65,000.00

Pembantu
17 Tukang Org/hr Rp 42,000.00

18 Pekerja Biasa Org/hr Rp 42,000.00

19 Penjaga Malam Org/hr Rp 42,000.00

20 Sopir Org/hr Rp 65,000.00

21 Operator Org/hr Rp 75,000.00

22 Mekanik Org/hr Rp 65,000.00

23 Pembantu Sopir Org/hr Rp 42,000.00

Pembantu
24 Operator Org/hr Rp 50,000.00

Pembantu
25 Mekanik Org/hr Rp 42,000.00
NO MATERIAL SAT HARGA (Rp)

AGREGAT KASAR,BAHAN
PEREKAT & BAHAN
A. JADINYA

1 Pasir Urug m3 175,300.00

2 Tanah Urug Pilihan m3 89,200.00


3 Sirtu m3 203,500.00

4 Pasir Teras m3 174,200.00

5 Pasir Pasang Kali m3 233,400.00

6 Pasir Beton m3 255,400.00


7 Abu Batu m3 259,000.00

8 Batu Gosok ( Apung ) kg 29,600.00

9 Batu Pecah Mesin 1/2 m3 223,600.00

10 Batu Pecah Mesin 2/3 m3 211,100.00

11 Batu Pecah Mesin 3/5 m3 205,000.00

12 Batu Pecah Mesin 5/7 m3 196,000.00


13 Batu Belah Pondasi m3 205,500.00

Batu Bronjol ( Untuk


14 Bronjong ) m3 180,800.00

15 Batu Koral Beton Kali m3 172,600.00

16 Batu Tempel Hitam m3 96,600.00

Batu Pinggir Beton 10 x 20


17 x 35 bh 14,100.00

Batu Pinggir Beton 15 x 35


18 x 50 ( K-225 ) bh 73,700.00

19 Batu Telor m3 97,800.00

20 Batako Kecil 8 x 10 x 20 bh 2,000.00

21 Batako Besar 8 x 20 x 30 bh 2,400.00

22 Con Blok 8 x 20 x 40 bh 5,400.00

23 Bata Merah Bakar kelas I bh 775

24 Bata Merah Bakar kelas II bh 675


Bata Merah Oven ( Klingker
25 ) bh 1,800.00

26 Roster Beton 20 x 20 bh 14,800.00

27 Roster Beton 30 x 30 bh 15,500.00

28 Grass Blok 20 x 20 bh 9,700.00

29 Grass Blok 30 x 30 bh 22,500.00

30 Paving Blok Natural 8 cm m2 81,100.00

31 Paving Blok Warna 8 cm m2 108,600.00

32 Paving Blok Natural 6 cm m2 76,000.00

33 Paving Blok Warna 6 cm m2 86,000.00

34 Canstin Paving Blok m1 34,900.00

35 Semen PC /50 kg zak 70,300.00


1,406.00

36 Semen Putih zak 92,700.00


Kanstin Jalan Ukuran Besar
37 ( Bina Marga ) 1bh =60cm bh 58,900.00

Readymix Beton K500,


38 Tanpa Pompa ( Selang ) m3 1,105,000.00

Readymix Beton K400,


39 Tanpa Pompa ( Selang ) m3 903,500.00

Readymix Beton K350,


40 Tanpa Pompa ( Selang ) m3 877,500.00

Readymix Beton K300,


41 Tanpa Pompa ( Selang ) m3 925,000.00

Readymix Beton K225,


42 Tanpa Pompa ( Selang ) m3 850,000.00

Readymix Beton K175,


43 Tanpa Pompa ( Selang ) m3 825,000.00
Kapur Pasang / Kapur
44 Tembok m3 353,300.00

45 Kapur Sirih kg 18,300.00

46 Semen Warna kg 15,700.00

47 Tanah liat m3 31,300.00


48 Air ltr 3

49 Formite/spacer bh 2,500.00

Hollow/Con Blok 8 x 20 x
50 40 bh 5,000.00

Hollow/Con Blok 8 x 15 x
51 40 bh 4,000.00

Hollow/Con Blok 8 x 10 x
52 40 bh 3,000.00

LABURAN,PENGISI DAN
B ALATNYA

1 Plamir Tembok kg 25,000.00

Cat Tembok ICI Eksterior


2 ( Beton ) lt 120,000.00

Cat Tembok ICI Interior


3 ( Plafon Dan Dinding ) lt 75,000.00
4 Cat Tembok Vinilex kg 25,000.00

Cat Dasar ICI untuk Interior


5 ( 2 Pelapis ) lt 75,000.00

6 Cat Tembok Sanlek kg 20,000.00


7 Cat Dasar kg 30,000.00

8 Cat Tahan Asam lt 40,000.00

Pelapis Alkali ICI ( Cat


9 Dasar Beton Ekterior ) kg 90,000.00

10 Cat Marka / Spotlight kg 185,000.00

11 Water Profing Emulsion ml 70,000.00

12 Water Profing Membrance bh 62,500.00

13 Rool Cat Tembok bh 32,500.00

14 Kape Tembok bh 8,500.00

15 Kape Kayu 5 lt 10,000.00

16 Soligneum 1 Blek kg 25,000.00


17 Plincote m3 29,000.00

18 Penawetan Kayu m3 382,600.00

19 Pegopenan Kayu bh 370,000.00


20 Kwas 3" bh 16,000.00
21 Oker bks 22,000.00
22 Oyan bks 5,200.00

23 Oten ( Pewarna Plitur ) lt 5,500.00


24 Spirtus kg 15,000.00

Bahan Pelitur Kripik ( Sirlak


25 India ) kg 110,000.00

26 Dempul Lilin kg 34,200.00

27 Dempul Plitur kg 37,700.00

Dempul Halus / Imfra


28 ( Wood Filler ) lt 37,700.00

29 Dempul Jadi kg 35,800.00


30 Politur lt 48,000.00

31 Politur Jadi lt 112,700.00

32 Terpentin kg 19,500.00
33 Tiner A kg 23,900.00
34 Tiner B kg 21,400.00
35 Kumpon lbr 30,800.00
36 Melamik kg 52,500.00

37 Dempul Plastik kg 39,200.00

38 Dempul Duco kg 35,800.00


39 Ampelas lbr 5,000.00

40 Dempul Kayu Cap Kucing kg 24,400.00

41 Meni Kayu / Besi kg 30,400.00

42 Sincromat kg 40,900.00
43 Cat Kayu Sieve lt 41,700.00
44 Cat Besi lt 44,000.00

Cat Besi Duco Danaglos /


45 ICI bh 76,300.00
46 Cat Bron kg 67,700.00
47 Karet lis bh 3,300.00

48 Minyak cat kg 38,400.00

49 Glass beet kg 50,100.00


50 Residu lt 8,100.00

BAHAN KAYU BERIKUT


C BAHAN JADINYA

1 Bambu 5 s.d 7 bt 17,700.00

2 Bambu 7 s.d 10 bt 25,000.00

3 Bambu Gombong bt 37,200.00

Kayu Kamper Singkil /


Kapur ( Kayu Samarinda kls
4 II ) m3 7,094,450.00

5 Kayu Balok Borneo Super m3 5,280,000.00

6 Kayu Papan Borneo Super m3 5,595,800.00


Kayu Balok Kamper Medan
7 (Kruing ) m3 5,692,600.00

Kayu Papan Kamper


8 Medan (Kruing ) m3 5,823,400.00

9 Kayu Balok Kamper Banjar m3 6,363,600.00

10 Kayu Papan Kamper Banjar m3 6,645,300.00

Kayu Balok Kamper


11 Samarinda m3 8,633,700.00

Kayu Papan Kamper


12 Samarinda m3 8,724,300.00

13 Kayu Balok Rasamala m3 2,658,000.00

Kayu Jati Jatim Tua dia. 40


14 cm m3 20,772,000.00

Kayu Jati Jateng Tua dia. 40


15 cm m3 22,188,400.00

Kayu Jati Jabar Tua dia. 40


16 cm m3 13,625,400.00
Kayu Jati Jabar Tua dia. 40
17 cm kebawah m3 12,736,100.00

Kayu Hutan Kelas I


18 ( Segeng,Mahoni, Laban ) m3 2,069,800.00

19 Kayu Balok Albasia m3 1,870,500.00

20 Kayu Papan Albasia m3 2,071,700.00

21 Dolken 5 s/d 7 bt 22,600.00

22 Dolken 7 s/d 10 bt 28,000.00

23 List Profil Kamper 1 cm m1 8,900.00

24 List Profil Kamper 2 cm m1 10,000.00

25 List Profil Kamper 4 cm m1 14,300.00

26 List Profil Kamper 5 cm m1 17,200.00

27 List Profil Kamper 10 cm m1 29,400.00

28 Pegangan Tangga Profil Jati m1 160,100.00


Pegangan Tangga Profil
29 Kamper m1 122,500.00

30 Kayu Kaso 4/6 m3 2,772,000.00

Kayu Kaso 5/7 Kamper


31 Medan m3 3,356,800.00

Kayu Reng 2/3 Borneo


32 Super m1 2,500.00

Kayu Reng 2/3 Kamper


33 Banjar m1 3,300.00

Kayu Reng 3/4 Kamper


34 Medan m3 4,000.00

35 Kayu Papan Terentang m3 2,850,000.00

36 Kayu Balok Terentang m3 2,640,000.00

37 Batang Kelapa bt 139,500.00


38 Tali Ijuk kg 23,400.00

39 lapisan Ijuk tebal 10 cm m2 22,000.00

40 Venetion Blind m2 537,300.00

41 Vertikal Blind m2 351,200.00


BAHAN PENUTUP RANGKA
D PLAFOND

1 Plafond Enternit 4 mm m2 17,400.00

Plafond hardpleks 5 mm
2 120 x 240 lbr 62,400.00

Plafond Asbes Semen 5


3 mm m2 22,500.00

Plafond Asbes Semen 3,5


4 mm m2 19,500.00

Gypsum 120 x 240 t= 9 mm


5 ex DN lbr 79,800.00

Gypsum 120 x 240 t= 9 mm


6 ex Luar lbr 83,800.00

7 Tepung gypsum kg 12,500.00

8 Acustik Amstrong 60 x 120 lbr 132,800.00

9 Cotton Plester bh 15,000.00

GRC (120 x 240) cm, t = 4


10 mm lbr 67,500.00

11 Cornice Coumpound zak 75,000.00


12 List gypsum m' 8,500.00

E BAHAN KAYU LAPIS

1 Triplek 3 mm 120 x 240 lbr 61,700.00

2 Triplek 4 mm 120 x 240 lbr 64,400.00

3 Triplek 4 mm ukuran Pintu lbr 56,200.00

4 Triplek 6 mm 120 x 240 lbr 92,000.00

5 Triplek 9 mm 120 x 240 lbr 166,600.00

6 Jabar Wood 4 mm lbr 119,000.00

7 Bilik Bambu ( tanpa kulit ) m2 19,800.00

8 Bilik Bambu ( dengan kulit ) m2 22,700.00

9 Bilik Bambu Hitam Variasi m2 34,200.00

10 Wall paper m2 55,700.00

11 MultiPlek 9 mm 120 x 240 lbr 151,100.00

12 MultiPlek 12 mm 120 x 240 lbr 195,000.00


13 MultiPlek 18 mm 120 x 240 lbr 255,400.00

14 Ply Wood 18 mm 120 x 240 lbr 323,900.00

15 Ply Wood 9 mm 120 x 240 lbr 235,000.00

16 Ply Wood 4 mm 120 x 240 lbr 140,000.00

Teak Wood 3 mm 120 x


17 240 lbr 129,100.00

Teak Wood 4 mm 120 x


18 240 lbr 131,700.00

Teak Wood 3 mm 120 x


19 240 ukuran Pintu lbr 127,200.00

Teak Wood ukuran Pintu 4


20 mm lbr 114,700.00

21 Tacon ( Tahan Bakar ) m2 128,200.00

22 Supercon m2 57,900.00

23 Melamin 4 mm 120 x 240 lbr 89,200.00

24 Melamin TOK 4 mm lbr 133,400.00


25 Formika 120 x 240 lbr 170,000.00

26 Formika ukuran Pintu lbr 132,900.00

27 Formika Warna 4" x 8" lbr 238,100.00

BAHAN LANTAI DAN


F PELAPIS DINDING

1 Tegel PC 20 x 20 bh 3,400.00

2 Plin Tegel PC 10 x 20 bh 2,400.00

3 Tegel PC 30 x 30 bh 3,400.00

4 Plin Tegel PC 15 x 30 bh 2,800.00

5 Tegel Warna 20 x 20 bh 3,600.00

6 Plin Tegel Warna 10 x 20 bh 3,400.00

7 Tegel Warna 30 x 30 bh 5,700.00

8 Plin Tegel Warna 15 x 30 bh 6,300.00

9 Tegel Wafel PC 20 x 20 bh 3,200.00

10 Tegel Wafel Warna 20 x 20 bh 2,500.00


11 Tegel Badak PC 30 x 30 bh 4,100.00

Poslin 11 x 11 Warna
12 Standar DN m2 63,300.00

Poslin 11 x 11 Warna
13 khusus DN m2 67,300.00

Keramik 10 x 20 dan 20 x
20 KW I DN Putih / Polos
14 Mulia m2 54,500.00

Keramik 10 x 20 KW I DN
Corak/Warna/Anti Slip
15 Mulia m2 56,000.00

Keramik 20 x 20 (KM) KW I
DN Corak/Warna /Anti Slip
16 Mulia m2 62,500.00

Keramik 20 x 20 (KM) KW I
17 DN Putih Polos Mulia m2 54,500.00
Keramik 20 x 25 Dinding
18 KM KW I DN Corak Mulia m2 62,500.00

Keramik 30 x 30 KWI DN
19 Putih Polos Mulia m2 53,000.00

Keramik 30 x 30 KWI DN
Warna/Corak (ANTI SLIP)
20 Mulia m2 58,000.00

Keramik 40 x 40 KWI DN
21 Putih Polos Mulia m2 56,800.00

Keramik 40 x 40 KWI DN
Warna/Corak (ANTI SLIP)
22 Mulia m2 65,500.00

Keramik 10 x 20 dan 20 x
20 KW I DN Putih / Polos
23 Roman m2 64,400.00
Keramik 10 x 20 KW I DN
Corak/Warna/Anti Slip
24 Roman m2 72,200.00

Keramik 20 x 20 (KM) KW I
DN Corak/Warna/Anti Slip
25 Roman m2 75,200.00

Keramik 20 x 20 (KM) KW I
26 DN Putih Polos Roman m2 72,900.00

Keramik 20 x 25 Dinding
27 KM KW I DN Corak Roman m2 75,200.00

Keramik 20 x 25 KW I DN
28 Putih Polos Roman m2 72,900.00

Keramik 30 x 30 KW I DN
29 Polos Roman m2 68,900.00
Keramik 30 x 30 KW I DN
Warna/Corak (ANTI SLIP)
30 Roman m2 76,600.00

Keramik 40 x 40 KW I DN
31 Polos Roman m2 72,500.00

Keramik 40 x 40 KW I DN
Warna/Corak (ANTI SLIP)
32 Roman m2 77,000.00

33 Vinyl Lantai Standar m2 56,000.00

34 Karpet Kelas Baik LN m2 1,025,500.00

35 Karpet Kelas Sedang LN m2 353,500.00

36 Parquet Jati m2 375,400.00

37 Stairnosing Keramik 10/20 bh 13,700.00

38 Stairnosing Fiber m 25,000.00

39 Taraso Kerang 30 x 30 m2 31,800.00

40 Plin Taraso 10 x 30 bh 13,500.00


Granit Alam LN Ukuran
41 Besar m2 1,848,400.00

Granit Alam LN Ukuran


42 Kecil m2 1,612,900.00

Granit Alam DN Ukuran


43 Besar m2 1,331,100.00

Granit Alam DN Ukuran


44 Kecil m2 1,299,400.00

Granito Tile Essenza


45 Ukuran 40 x 40 Polis m2 345,000.00

Granito Tile Essenza


46 Ukuran 30 x 30 m2 322,800.00

Granito Tile Essenza


47 Ukuran 40 x 40 UnPolis m2 204,900.00
48 Marmer m2 550,000.00

Marmer Alam Lampung


49 Ukuran Besar m2 550,200.00

Marmer Alam Lampung


50 Ukuran kecil m2 345,700.00
Marmer Alam Citatah
51 Ukuran Besar m2 340,800.00

Marmer Alam Citatah


52 Ukuran Kecil m2 237,600.00

53 Marmer Sintetis m2 157,900.00

Granito Tile Essenza 60 x


54 60 Polis m2 358,100.00

Granito Tile Essenza 60 x


55 60 UnPolis m2 231,800.00

56 Batu Tempel Hitam m2 96,500.00

57 Bata Karawang bh 600

Campuran untuk Kedap Air


58 ( AM ) ltr 37,600.00

59 Plint keramik 10 x 20 bh 3,000.00

60 Plint keramik 10 x 25 bh 3,250.00

61 Plint keramik 10 x 30 bh 3,500.00

62 Plint keramik 10 x 40 bh 4,000.00


63 Plint keramik 15 x 30 bh 4,500.00

64 Plint keramik 15 x 40 bh 5,250.00

65 Plint granito 10 x 30 bh 25,900.00

66 Plint granito 10 x 40 bh 27,600.00

67 Plint granito 15 x 30 bh 31,100.00

68 Plint granito 15 x 40 bh 41,300.00

BAHAN SALURAN AIR


G KOTOR / BERSIH

1 Grafel U 20 cm' m1 44,300.00

2 Grafel U 30 cm' m1 56,400.00

3 Grafel U 40 cm' m1 74,200.00

4 Buis Beton 20 cm ( 1 M' ) m1 49,200.00

5 Buis Beton 30 cm ( 1 M' ) m1 61,700.00

6 Buis Beton 40 cm ( 1 M' ) m1 80,900.00


7 Buis Beton 50 cm ( 1 M' ) stk 94,300.00

8 Buis Beton 60 cm ( 1 M' ) stk 130,900.00

Buis Beton 100 cm ( 0.50


9 M' ) stk 299,800.00

Buis Beton 80 cm ( 0.50


10 M' ) stk 298,500.00

BuisTanah 10 cm ( 0.50
11 M' ) stk 9,600.00

BuisTanah 15 cm ( 0.50
12 M' ) stk 12,700.00

BuisTanah 20 cm ( 0.50
13 M' ) stk 16,800.00

BuisTanah 25 cm ( 0.50
14 M' ) stk 22,800.00
15 Injuk kg 17,400.00

BAHAN LOGAM DAN


H BAHAN JADINYA

1 Besi Beton U-24 Rata-rata kg 16,500.00

Besi Beton U-39 / U-32


2 Rata-rata kg 20,700.00
Pagar BRC lengkap tiang
3 ( Tanpa Pondasi ) m2 171,300.00
4 Bondek m2 185,000.00

5 Besi WF Ex DN SII kg 24,000.00

6 Besi WF Ex Jepang kg 23,900.00

7 Besi Profil DN SII kg 18,300.00

8 Besi Profil Ex LN kg 21,600.00

9 Besi C Lip Chanel kg 19,200.00

10 Ongkos Galfanis Besi kg 10,600.00

11 Kawat Beton kg 27,700.00

12 Kawat Duri kg 63,500.00

13 Kawat Pengikat m1 1,000.00

14 Kawat Bronjong 4 mm kg 28,200.00

15 Kawat Tembaga kg 41,400.00

16 Ram Nyamuk Hijau m2 13,400.00

17 Ram Kawat 1 x 1 cm m2 15,300.00

18 Ram Ayam m2 14,900.00


19 Kawat Kasa 1 x 1 ( Putih ) m2 32,100.00

20 Kawat Harmonika 4 cm m2 35,900.00

21 Kawat Harmonika 2 cm m2 28,600.00

22 Kawat Las Listrik kg 23,600.00

23 Wiremesh M8 m2 51,900.00

24 Wiremesh M6 m2 38,700.00
25 Timah kg 46,300.00

26 Timah Hitam kg 43,300.00

27 Ram nyamuk Alumunium m2 32,400.00

Plat Srip 2 x 30 mm ( 6
28 m1 ) bt 33,000.00

Plat Srip 3 x 30 mm ( 6
29 m1 ) bt 33,100.00
30 Plat Strip bt 18,200.00

31 Besi Strip kg 26,800.00

32 Plat Alumunium 0.2 mm m2 89,800.00

33 Plat Alumunium 0.3 mm m2 110,500.00


34 Plat Alumunium 0.4 mm m2 141,400.00

35 Plat Alumunium 0.5 mm m2 143,100.00

36 Plat Alumunium 0.6 mm m2 171,800.00

37 Plat Alumunium 0.1 mm m2 56,300.00

Kusen Alumunium Natural


38 1.3 mm t= 1,3 mm ( 4 " ) m1 151,100.00

Kusen Alumunium Warna


39 1.3 mm t= 1,3 mm ( 4 " ) m1 163,000.00

Kusen Alumunium Natural


40 1.3 mm t= 1,3 mm ( 3 " ) m1 81,000.00
Kusen Alumunium Warna
41 1.3 mm t= 1,3 mm ( 3 " ) m1 102,000.00

Daun Jendela Alumunium


Natural ( tanpa kaca dan
42 accessories ) m2 98,800.00

Daun Jendela Alumunium


Warna ( tanpa kaca dan
43 accessories ) m2 148,800.00

Daun Pintu Alumunium


Natural ( tanpa kaca dan
44 accessories ) m2 211,800.00

Daun Pintu Alumunium


Warna ( tanpa kaca dan
45 accessories ) m2 207,500.00
Handle Alumunium
( Tarikan Pintu
46 Alumunium ) bh 345,200.00

47 Kait Angin Alumunium ps 104,500.00

Karet Asisoris Kusen / Pintu


48 Alumunium m1 7,500.00

49 Jalusi Alluminium m' 35,000.00

50 Sunscreen Almunium m2 380,200.00

Seng Plat BJLS 30 60 cm


51 ( 100 m1 ) roll 1,581,500.00

Seng Plat BJLS 30 90 cm


52 ( 100 m1 ) roll 2,080,100.00

53 Plat Besi Tipis 1 mm kg 16,800.00

54 Plat Besi Tipis 0.5 mm kg 17,700.00

55 Plat Besi 2 mm s/d 5 mm kg 14,100.00

56 Plat Besi 6 mms/d 10 mm kg 14,100.00


57 Plat Besi 10 mm keatas kg 14,700.00

58 Kabel presstressed polos kg 26,700.00

59 Jaring Kawat Baja kg 28,900.00

60 Lem Kuning ( Aibond ) kg 35,700.00


61 Lem Fox kg 23,900.00

62 Lem Vinyl kg 44,000.00

63 Besi Strip Kaca Nako kg 11,000.00

64 Profil alumunium "T" m1 12,200.00

Besi Hallow ( 2 x 4 x 4) cm
65 (400cm) btg 22,600.00

Besi Hallow ( 4 x 4) cm
66 (400 cm) btg 29,200.00

67 Besi Rail Pengamanan kg 459,300.00

68 Jendela Besi m2 390,200.00

69 Jendela Besi tahan api m2 501,700.00

70 Pintu gulung besi m2 501,700.00


71 Pintu Roliing Door m2 306,600.00

Jendela nako kaca ryben +


72 tralis 6 klips set 170,000.00

Jendela nako kaca ryben +


73 tralis 7 klips set 200,000.00

Jendela nako kaca ryben +


74 tralis 8 klips set 230,000.00

Jendela nako kaca ryben +


75 tralis 10 klips set 290,000.00

Jendela nako kaca bening +


76 tralis 4 klips set 120,000.00

Jendela nako kaca bening +


77 tralis 5 klips set 140,000.00

Jendela nako kaca bening +


78 tralis 6 klips set 170,000.00
Jendela nako kaca bening +
79 tralis 7 klips set 210,000.00

Jendela nako kaca bening +


80 tralis 8 klips set 230,000.00

Jendela nako kaca bening +


81 tralis 10 klips set 300,000.00

I BAHAN KACA

1 Kaca Polos 2 mm ( ASAHI ) m2 69,000.00

2 Kaca Polos 3 mm ( ASAHI ) m2 87,400.00

3 Kaca Polos 5 mm ( ASAHI ) m2 111,000.00

4 Kaca Polos 8 mm ( ASAHI ) m2 183,100.00

Kaca Rayband 5 mm
5 ( ASAHI ) m2 148,700.00

Kaca Rayband 8 mm
6 ( ASAHI ) m2 323,400.00
Kaca Rayband 12 mm
7 ( ASAHI ) m2 627,000.00

8 Kaca cermin 5 mm m2 150,500.00

9 Kaca cermin 6 mm m2 186,400.00

10 Kaca cermin 8 mm m2 234,300.00

Kaca Patri Lokal Terpasang


11 ( ASAHI ) m2 1,621,100.00

Kaca Patri Ex Luar Negeri


12 Terpasang m2 3,425,700.00

13 Kaca 6 mm Gravver m2 1,263,900.00

Glass Block DN 20 x 20
14 ( Kedawung ) bh 22,000.00

Glass Block DN 20 x 20 Ex
15 LN bh 125,700.00
16 Sealant kg 211,800.00

17 Jendela Nako bh 109,200.00


BAHAN PAKU DAN MUR
J BAUT

1 Paku 1/2" s/d 2" kg 23,800.00

2 Paku 2" s/d 5" kg 23,400.00

3 Paku 8 cm s/d 15 cm kg 20,000.00

4 Paku Beton 2 cm s/d 5 cm bh 1,600.00

5 Paku Kait Lengkap bh 900

6 Paku Cacing kg 57,100.00

7 Besi Beugel Kuda - Kuda kg 21,700.00

8 Duk Angker bh 7,500.00

Angker Mur Baut dia. 19 /


9 Panjang 60 cm bh 71,800.00

Mur Baut HTB dia. 19 s/d


10 16 ( 5 cm ) bh 15,900.00

Mur Baut Biasa dia. 19 s/d


11 16 ( 5 cm ) bh 9,300.00

12 Piser dia.12 s/d 20 cm bh 5,300.00


13 Paku skrup 3" bh 800

14 Ramset / Dinabolt bh 7,200.00

15 Baut Besar bh 600

16 Baut Kecil bh 300

17 Paku GRC kg 35,000.00

18 Paku gypsum kg 17,500.00

19 Sekrup fixer bh 250

K BAHAN PERPIPAAN

Besi Pipa Untuk Hydrant


1 BSP 1" bt 166,700.00

Besi Pipa Untuk Hydrant


2 BSP 1.25" bt 210,200.00

Besi Pipa Untuk Hydrant


3 BSP 1.5" bt 298,000.00

Besi Pipa Untuk Hydrant


4 BSP 2" bt 351,800.00

Besi Pipa Untuk Hydrant


5 BSP 2.5" bt 439,300.00

Besi Pipa Untuk Hydrant


6 BSP 3" bt 595,000.00
Besi Pipa Untuk Hydrant
7 BSP 4" bt 869,600.00

Besi Pipa Untuk Hydrant


8 BSP 6" bt 1,423,400.00

Besi Pipa Hitam 1" t = 2


9 mm bt 172,300.00

Besi Pipa Hitam 2" t = 2


10 mm bt 227,900.00

11 Besi Pipa Hitam 3" t = 2mm bt 365,800.00

Besi Pipa Hitam 4" t = 2


12 mm bt 573,100.00

Besi Pipa Hitam 6" t = 2


13 mm bt 772,400.00

Pipa GIP Medium A 1/2"


14 ( 6 m1 ) bt 109,100.00

Pipa GIP Medium A 3/4"


15 ( 6 m1 ) bt 159,400.00

Pipa GIP Medium A 1" ( 6


16 m1 ) bt 181,500.00

Pipa GIP Medium A 1 1/4"


17 ( 6 m1 ) bt 259,300.00

Pipa GIP Medium A 1 1/2"


18 ( 6 m1 ) bt 280,500.00
Pipa GIP Medium A 1 3/4"
19 ( 6 m1 ) bt 326,400.00

Pipa GIP Medium A 2" ( 6


20 m1 ) bt 467,400.00

Pipa GIP Medium A 2 1/2"


21 ( 6 m1 ) bt 672,100.00

Pipa GIP Medium A 3" ( 6


22 m1 ) bt 849,900.00

Pipa GIP Medium A 4" ( 6


23 m1 ) bt 920,300.00

Macam2 Sambungan GIP


24 1/2" bh 6,300.00

Macam2 Sambungan GIP


25 3/4" bh 8,600.00

Macam2 Sambungan GIP


26 1" bh 16,700.00

Macam2 Sambungan GIP 1


27 1/4" bh 19,800.00

Macam2 Sambungan GIP 1


28 1/2" bh 20,700.00

Macam2 Sambungan GIP 1


29 3/4" bh 22,700.00
Macam2 Sambungan GIP
30 2" bh 51,200.00

Macam2 Sambungan GIP 2


31 1/2" bh 60,400.00

Macam2 Sambungan GIP


32 3" bh 75,900.00

Macam2 Sambungan GIP


33 4" bh 118,600.00

Pipa PVC RUCIKA type AW


34 1/2" bt 40,100.00

Pipa PVC RUCIKA type AW


35 3/4" bt 52,200.00

Pipa PVC RUCIKA type AW


36 1" bt 63,200.00

Pipa PVC RUCIKA type AW


37 1 1/4" bt 79,900.00

Pipa PVC RUCIKA type AW


38 1 1/2" bt 105,900.00

Pipa PVC RUCIKA type AW


39 2" bt 110,700.00

Pipa PVC RUCIKA type AW


40 2 1/2" bt 167,100.00

Pipa PVC RUCIKA type AW


41 3" bt 205,100.00
Pipa PVC RUCIKA type AW
42 4" bt 347,900.00

Pipa PVC RUCIKA type AW


43 6" bt 640,000.00

Pipa PVC RUCIKA type AW


44 8" bt 818,300.00

Pipa PVC MASPION ABU


45 ( AW ) 1/2" bt 22,500.00

Pipa PVC MASPION ABU


46 ( AW ) 3/4" bt 27,800.00

Pipa PVC MASPION ABU


47 ( AW ) 1" bt 40,500.00

Pipa PVC MASPION ABU


48 ( AW ) 1 1/4" bt 58,500.00

Pipa PVC MASPION ABU


49 ( AW ) 1 1/2" bt 60,200.00

Pipa PVC MASPION ABU


50 ( AW ) 2" bt 75,800.00

Pipa PVC MASPION ABU


51 ( AW ) 2 1/2" bt 126,300.00
Pipa PVC MASPION ABU
52 ( AW ) 3" bt 145,700.00

Pipa PVC MASPION ABU


53 ( AW ) 4" bt 256,800.00

Macam2 Sambungan
54 Paralon 1/2" bh 4,400.00

Macam2 Sambungan
55 Paralon 3/4" bh 4,700.00

Macam2 Sambungan
56 Paralon 1" bh 4,900.00

Macam2 Sambungan
57 Paralon 1 1/4" bh 7,200.00

Macam2 Sambungan
58 Paralon 1 1/2" bh 9,500.00

Macam2 Sambungan
59 Paralon 1 3/4" bh 13,500.00

Macam2 Sambungan
60 Paralon 2" bh 15,800.00
Macam2 Sambungan
61 Paralon 2 1/2" bh 26,400.00

Macam2 Sambungan
62 Paralon 3" bh 29,700.00

Macam2 Sambungan
63 Paralon 4" bh 34,000.00

Sambungan Pipa PVC Jenis


64 AW 4" TY bh 89,900.00

65 Lem Paralon tb 10,100.00

66 Solatip Ledeng gl 4,200.00

Pipa PVC 4" Berlobang


67 Jenis AW m1 36,700.00

68 PVC Waterstop lebar 150 m1 53,500.00

69 PVC Waterstop lebar 200 m1 57,900.00

70 PVC Waterstop lebar 230 m1 65,700.00

71 PVC Waterstop lebar 250 m1 74,700.00


72 PVC Waterstop lebar 300 m1 83,600.00

73 PVC Waterstop lebar 320 m1 92,500.00

L BAHAN SANITAIR

1 Stop Kran 3/4" KIT bh 103,900.00

2 Stop Kran 1" KIT bh 124,200.00

3 Stop Kran 1 1/2" KIT bh 208,000.00

4 Stop Kran 2" KIT bh 267,900.00

5 Stop Kran 2 1/2" KIT bh 713,200.00

6 Stop Kran 3" KIT bh 830,300.00

7 Check Valve 1/2" bh 86,400.00

8 Double Neple 1/2" bh 32,400.00

9 Water Mur 1/2" bh 40,200.00

10 Gate walve 1/2" bh 55,500.00


Saringan Air Lt. KM
11 Stainless Steel bh 66,600.00

12 Apooer Bath Tube bh 267,800.00

13 Kran Stainless Lokal Kait bh 46,100.00

14 Shower Dengan Tiang bh 221,000.00

15 Shower Tanpa Tiang bh 134,800.00

Kran Tembok Sun Eui dia.


16 1/2" bh 86,900.00

17 Kran Tembok ITAP dia. 1/2" bh 40,900.00

18 Kran Bebek Sun Eui 1/2" bh 144,600.00

19 Kran Bebek ITAP 1/2" bh 51,500.00

Kran Panas Dingin San Eui


20 Standard bh 228,400.00

21 Bath Cape Washteren unit 2,098,700.00

22 Tempat Sabun Poslin bh 46,300.00


Wastafel Lengkap TOTO LW
23 230 unit 1,012,700.00

24 Wastafel Lengkap INA unit 699,900.00

Closet Jongkok Poslin


25 Warna TOTO unit 205,600.00

Closet Jongkok Standard


26 Putih Poslin TOTO unit 188,200.00

Closet Jongkok Lengkap


27 Sistem Jet TOTO unit 2,032,900.00

Closet Duduk Warna


Standard TOTO C 240
28 Lengkap unit 1,724,700.00

Wastafel Bulat Warna


29 Standard Lengkap unit 910,800.00

Closet Duduk Warna


30 Standard INA Lengkap bh 1,272,100.00
Urinoir Lengkap TOTO
31 Warna Standard Lengkap unit 1,773,400.00

Penyekat Poslin Urinoar


32 TOTO lbr 495,900.00

Kitchen Zink Stainless


33 Standard Lokal ( 1 Lubang ) bh 397,800.00

Kitchen Zink Stainless Non


Standard Franke ( 1 Lubang
34 ) bh 1,272,300.00

Kitchen Zink Stainless Non


Standard Franke ( 2 Lubang
35 ) bh 1,650,200.00

36 Talang PVC U - 15 cm btng 60,000.00

M BAHAN PENUTUP ATAP

Atap Plastik Gelombang 80


1 x 180 lbr 33,100.00
Atap Fiber Glass Tipis 80 x
2 180 ( Gelombang ) lbr 47,100.00

Atap Fiber Glass Tebal 80 x


3 180 ( Gelombang ) lbr 100,000.00

Atap Alumunium Natural


4 USR 26 ( JAINDO ) m2 140,600.00

Atap Alumunium Warna


5 USR 26 ( JAINDO ) m2 164,700.00

Atap Asbes Gel. Kecil 80 x


6 180 x 4 mm lbr 77,200.00

Atap Asbes Gel. Besar 80 x


7 180 x 5 mm lbr 111,100.00

Atap Seng Gelombang 80


8 cm x 180 cm x 3 mm lbr 62,900.00
Atap Seng Gelombang 80
9 cm x 180 cm x 5 mm lbr 83,100.00

Atap Seng Gelombang 270


10 cm x 105 cm x 4mm lbr 73,300.00

Atap Seng Gelombang 240


11 cm x 105 cm x 4mm lbr 65,900.00

Atap Seng Gelombang 210


12 cm x 105 cm x 4mm lbr 58,500.00

Atap Seng Gelombang 150


13 cm x 105 cm x 4mm lbr 42,300.00

Atap Seng Gelombang 150


14 cm x 102 cm x 5mm lbr 78,500.00
Atap Seng Gelombang 180
15 cm x 102 cm x 5mm lbr 97,200.00

Atap Asbes Gelombang


16 300 cm x 105 cm x 4 mm lbr 80,000.00

Atap Tegola Kubota,


17 lengkap m2 487,100.00

Atap Tegola Kwalitas


18 Sedang m2 283,600.00

19 Alumunium Foile m2 19,600.00

Atap Genteng Plentong


20 pres Bakar KW I bh 1,900.00

Atap Genteng Plentong


21 pres Molen Oven KW I bh 2,700.00

Atap Genteng Flam pres


22 Molen Oven Jatiwangi bh 2,300.00
Bubung Genteng pres Bulat
23 Ex Jatiwangi bh 7,500.00

Genteng Bubungan Ex
24 Jatiwangi Segi Tiga bh 4,800.00

25 Genteng Bubungan Beton bh 10,500.00

Genteng Metal ( Rainbow


26 Roof ) m2 203,100.00

27 Genteng Metal Hana m2 172,700.00

Nok Atas Metal ( Rainbow


28 Roof ) lbr 138,500.00

29 Nok Atas Metal Hana lbr 80,900.00

Nok Pingir Metal ( Rainbow


30 Roof ) lbr 105,300.00

31 Nok Pingir Metal Hana lbr 100,800.00

Wall Flasing ( Rainbow


32 Roof ) lbr 83,900.00

33 Wall Flasing Hana lbr 88,700.00


Atap Genteng Beton Warna
34 14.5/m2 m2 96,700.00

35 Genteng Beton Natural bh 8,500.00

36 Sirap Kelas I ( 80 / m2 ) m2 26,400.00

Genteng Keramik Natural


37 Intan 14.5 / m2 m2 112,400.00

Genteng Keramik Glasur


38 Standard 14.5 /m2 m2 142,200.00

Genteng Keramik Glasur


39 Special 14.5 /m2 m2 139,300.00

Genteng Keramik Glasur


40 Premium 14.5 /m2 m2 145,100.00

Genteng Murando Natural


41 1m2 = 18 bh bh 2,700.00

Genteng Murando Glasur


42 1m2 = 18 bh bh 4,000.00

43 Bubung Murando Natural bh 7,500.00


44 Bubung Murando Glasur bh 10,700.00

Bubungan Genteng
45 Keramik bh 10,000.00

46 Atap Genteng Kodok bh 3,000.00

47 Bubungan Genteng Kodok bh 4,500.00

Bubungan Genteng
48 Plentong bh 6,000.00

49 Bubungan Stel Gelombang bh 7,500.00

50 Nok Stel Gelombang lbr 38,100.00

51 Nok Atap Seng lbr 37,500.00

Nok standar 40 cm 18,


52 SWG 22 m2 75,000.00

53 Pelat Asbes tebal 4 mm lbr 21,000.00

54 Pelat Asbes tebal 3.5 mm lbr 16,400.00

Trusses ZAM-75 t=0.8


55 Rangka Utama m1 34,500.00
Trusses ZAM-75 t=0.5
56 Rangka Utama m1 22,000.00

Reng 16-DB Roof Battens


57 t=0.48 mm m1 11,000.00

58 Foot Plate t= 1.22 mm m1 7,200.00

59 PLD - Diafragma Plate bh 2,200.00

60 WIND Bracing m1 1,700.00

Tensioner ( Pengaku Tali


61 angin ) bh 7,200.00

N BAHAN MEKANIKAL

Jockey Pump kap. 80


gln/menit 100 m1 ( 18.6
1 kW ) unit 71,396,400.00

Electrical Pump kap. 750


gln/menit 120 m1 ( 90
2 kW ) unit 216,358,900.00
Diesel Pump kap. 750
gln/menit 120 m1 ( 105
3 kW ) unit 591,647,100.00

Presure Tank kap. 500 liter


4 lengkap unit 36,997,300.00

Hydran Box dlm Gedung


5 ( Lengkap ) unit 6,854,400.00

Fire House 1.5 x 30 m +


6 nose unit 4,866,100.00

Exhose Fan H 360 W 60 x


7 60 cm unit 6,862,900.00

Exhose Fan H 380 W CFM


8 55 x 55 cm unit 5,491,100.00

Exhose Fan H 100 W 40 x


9 40 cm unit 1,092,600.00

AC Split 3 PK Setara
10 TOSHIBA unit 30,791,800.00

AC Split 2 PK Setara
11 TOSHIBA unit 21,926,500.00
AC Split 1 PK Setara
12 TOSHIBA unit 5,174,100.00

Mesin AC Split DAIKIN


13 ( Indoor / Outdoor Unit ) 1 BTU 4,200,000.00

O BAHAN ELEKTRIKAL

Kabel NYA 1 x 1.5 Prima ( 1


1 rol = 50 m' ) ROLL 102,700.00

Kabel NYA 1 x 2.5 Prima ( 1


2 rol = 50 m' ) ROLL 151,700.00

Kabel NYM 2 x 1.5 Prima


3 ( 1 rol = 50 m' ) m' 6,600.00

Kabel NYM 3 x 1.5 Prima


4 ( 1 rol = 50 m' ) m' 7,600.00

Kabel NYM 2 x 2.5 Prima


5 ( 1 rol = 50 m' ) m' 4,900.00

Kabel NYM 3 x 2.5 Prima


6 ( 1 rol = 50 m' ) m' 10,900.00
Kabel NYM 4 x 2.5 Prima
7 ( 1 rol = 50 m' ) m' 7,600.00

Kabel NYM 2 x 4 Prima ( 1


8 rol = 50 m' ) m' 6,300.00

Kabel NYM 3 x 4 Prima ( 1


9 rol = 50 m' ) m' 15,400.00

Kabel NYM 4 x 4 Prima ( 1


10 rol = 50 m' ) m' 20,700.00

Kabel NYM 2 x 6 Supreme (


11 1 rol = 50 m' ) m' 11,800.00

Kabel NYM 3 x 6 Supreme (


12 1 rol = 50 m' ) m' 13,700.00

Kabel NYM 4 x 6 Supreme (


13 1 rol = 50 m' ) m' 18,600.00

Kabel NYM 2 x 10 Supreme


14 ( 1 rol = 50 m' ) m' 17,600.00
Kabel NYM 3 x 10 Supreme
15 ( 1 rol = 50 m' ) m' 119,700.00

Kabel NYM 4 x 10 Supreme


16 ( 1 rol = 50 m' ) m' 26,500.00

Kabel NYM 4 x 16 Supreme


17 ( 1 rol = 50 m' ) m' 29,700.00

Kabel NYY 2 x 4 Supreme


18 ( 1 rol = 50 m' ) m' 12,000.00

Kabel NYY 3 x 4 Supreme


19 ( 1 rol = 50 m' ) m' 19,300.00

Kabel NYY 4 x 4 Supreme


20 ( 1 rol = 50 m' ) m' 23,800.00

Kabel NYY 2 x 6 Supreme


21 ( 1 rol = 50 m' ) m' 14,500.00

Kabel NYY 3 x 6 Supreme


22 ( 1 rol = 50 m' ) m' 19,200.00
Kabel NYY 4 x 6 Supreme
23 ( 1 rol = 50 m' ) m' 18,500.00

Kabel NYY 2 x 10 Supreme


24 ( 1 rol = 50 m' ) m' 20,400.00

Kabel NYY 3 x 10 Supreme


25 ( 1 rol = 50 m' ) m' 25,800.00

Kabel NYY 4 x 10 Supreme


26 ( 1 rol = 50 m' ) m' 35,500.00

Kabel NYY 4 x 16 Supreme


27 ( 1 rol = 50 m' ) m' 41,900.00

28 NSFB FUJI EA - 100 A bh 841,900.00

29 NSFB FUJI EA - 150 A bh 2,182,600.00

Rumah Panel 30 x 60 cm
30 ( Kosong ) unt 153,500.00

31 Skring Kas 2 grop Biasa unt 204,800.00


32 Skring Kas 3 grop Biasa unt 222,600.00

33 Skring Kas 5 grop Biasa unt 468,800.00

34 MCB 1 PAS bh 55,100.00

35 MCB 3 PAS bh 106,000.00

36 Tahanan 50 A Merk Fuji bh 521,100.00

Saklar Broko Tunggal


37 Standard ( 1 Phase ) bh 23,800.00

Saklar Broko Seri Standard


38 ( 1 Phase ) bh 26,300.00

Stop Kontak Broko


39 Standard ( 1 Phase ) bh 23,800.00

Stop Kontak Broko 3 Phase


40 (Out Bow) bh 87,700.00

Stop Kontak Broko 3 Phase


41 ( In Bow) bh 144,900.00
Stop Kontak Handle 3
42 Phase bh 87,800.00

Instalas Titik Lampu / Stop


43 Kontak (Upah dan Alat) ttk 179,600.00

Lampu pijar 25 Watt s/d


44 100 Watt bh 61,200.00

Lampu Neon Phillips 20


45 Watt bh 29,700.00

Lampu Neon Phillips 40


46 Watt bh 35,200.00

47 Trapo TL 20 W (Phillips) bh 41,800.00

48 Trapo TL 40 W (Phillips) bh 37,900.00

49 Trapo TL 20 W (Sinar) bh 40,600.00

50 Trapo TL 40 W (sinar) bh 41,300.00

51 Stater Neon Phillips bh 8,300.00

52 Stater Neon Biasa bh 6,500.00


Rumah TL In Bow / Out
53 Bow 2 x 20 W (kosongan) bh 144,000.00

54 Down Light + SL 25 W bh 306,900.00

55 Lampu SL Philip 25 W bh 306,900.00

Lampu Sirkel TL 20 W
56 Lengkap bh 67,900.00

57 Lampu Mercuri 80 W bh 147,400.00

Lampu Taman + Tiang +


58 Lampu 1 Buah bh 307,600.00

59 Lampu Baret 30 cm + Neon bh 221,700.00

Lampu Neon Arcrilik 2 x 40


60 W Lengkap bh 738,000.00

61 Jarum Penangkal Petir 16 bh 101,500.00

62 Kawat BC ( Tembaga ) kg 65,100.00


Pentanahan Penangkal
63 Petir ttk 423,700.00

64 Pentanahan Panel ttk 296,100.00

BAHAN ALAT
PENGANTUNG DAN
P KUNCI

Kunci Silinder ALFA


1 untuk Pintu Alumunium bh 410,900.00

2 Tarikan Pintu Alumunium bh 408,600.00

3 Kunci 2 Slaag ROYAL bh 126,500.00

4 Rel Henderson Lengkap bh 864,300.00

5 Rel maraton I Pintu unt 193,100.00

Kunci 2 Slaag Silinder


SEIS Asli type 210 s/d
6 type 226 bh 335,900.00

7 Kunci 2 Slaag Ancor Asli bh 165,300.00


8 Kunci 2 Slaag ISO bh 207,300.00

Kunci KM Bulat Kualitas


9 Biasa bh 54,400.00

10 Kunci kM Bulat ALFA bh 102,700.00

Kunci 2 Slaag Silinder


11 Utama Standard bh 586,600.00

12 Kunci Gembok Besar bh 85,200.00

Kunci 2 Slaag Kuda


13 Terbang bh 94,500.00

14 Kunci Lemari bh 46,800.00

15 Espangolet ps 51,600.00

16 Grendel 15 cm bh 49,800.00

17 Grendel 5 cm bh 5,500.00

Hak Angin Kait Jendela


18 Biasa ps 7,100.00

19 Hak Angin Jendela Antik ps 29,000.00


Hak Angin Sendok
20 Stainless / Kuningan bh 32,200.00

Sloot Pintu Berikut


21 Rantai bh 31,500.00

22 Sloot Jendela Tunggal bh 33,000.00

Engsel Pintu Unilon


23 Standard ps 21,000.00

24 Engsel Jendela Unilon ps 15,000.00

25 Engsel Patrun ps 13,700.00

26 Engsel Harmonika m1 9,100.00

Door Closer Kelas


Standard ( Kelas
27 Sedang ) unt 420,000.00

Door Closer Kelas


28 Standard ( Kelas Baik ) unt 597,500.00

Door Closer Kelas


29 Rendah unt 200,000.00
30 Door Holder unt 205,400.00

31 Door Stoper unt 255,500.00

32 Tarikan Almari Rata-rata bh 19,500.00

Seng BJLS 30 Lebar 60


33 cm ( 1 rol 50 m' ) m1 43,500.00

Seng BJLS 30 Lebar 90


34 cm ( 1 rol 50 m' ) m1 53,500.00

Seng BJLS 30 / 3 x 0.3


35 mm lbr 86,900.00

36 Seng Plat lbr 50,100.00

Waterstop Lebar 200


37 mm m1 57,900.00

BAHAN PENGIKAT
UNTUK KONSTRUKSI
Q JALAN

1 Aspal Bitumen kg 12,459.00

2 Aspal Emulsi kg 12,459.00

3 Aspal Curah kg 10,890.00


Aspal Concrete / Laston(
4 AC -WC) ton 1,348,300.00

Aspal Threated Base


5 ( ATB ) ton 1,200,200.00

Lataston /Hot Rolls


6 Sheet ( HRS ) ton 1,666,900.00

BAHAN PENGISAP AIR


R SUMUR DALAM

1 Pompa Kodok unit 172,600.00

2 Pompa Dragon Tegal unit 243,800.00

3 Pompa Dragon Asli unit 718,500.00

Mesin Pompa Air 100 W


4 - Sanyo unit 1,100,200.00

Mesin Pompa Air 150 W


5 - Sanyo unit 1,890,700.00

Pompa Zet Pump 250 W


6 - Sanyo unit 4,961,500.00
Pompa Zet Pump 450 W
7 - Sanyo unit 7,878,000.00

Pompa Submersible
kap. 150 liter / menit 3
8 KW unit 27,151,200.00

Gear Pump Kap. 60


9 liter / menit unit 15,702,700.00

Deep Well dengan


kelengkapannya kap.
10 150 liter / menit unit 172,052,500.00

11 Hand Oil Pump unit 5,195,300.00

BAHAN PENAMPUNG
S AIR

Tangki Air Fiber Glass


1 0.5 m3 ( Excel ) bh 1,172,500.00

Tangki Air Fiber Glass 1


2 m3 ( Excel ) bh 1,316,400.00

Tangki Air Fiber Glass 2


3 m3 ( Excel ) bh 1,954,200.00
4 Bak KM Fiber 60 x 60 bh 255,300.00

5 Bak Taraso WC 40 x 40 bh 118,500.00

6 Bak KM Taraso 60 x 60 bh 161,100.00

T ALAT TUKANG

1 Palu 0.5 kg bh 39,300.00


2 Cangkul bh 24,500.00
3 Singkup bh 41,400.00
4 Sekrop bh 50,100.00
5 Pengki bh 12,300.00
6 Linggis bh 41,700.00

Rool Meter 30 meter


7 ( Bahan Plastik ) bh 101,000.00

Rool Meter 5 meter


8 ( Bahan Besi ) bh 37,800.00

Selang Plastik untuk


9 Water Pas dia. 0.5 cm m 1,600.00

Water Pas Alumunium


10 60 cm bh 88,200.00
BAHAN BAKAR DAN
U PELUMAS

1 Minyak Tanah lt 18,000.00

Kayu Bakar dari Kayu


2 Karet m3 151,100.00

3 Bahan Bakar Residu lt 28,435.00

4 Minyak Solar lt 7,150.00

5 Bensin Premium lt 7,800.00


6 Plus Oil lt 3,300.00

7 Oil Mesran 40 SAE lt 55,000.00

8 Elpiji / botol 15 kg 104,600.00

9 Asitilin / Botol 15.1 kg btl 88,900.00

10 Angin ( O2 ) / botol btl 66,400.00


11 Karbit kg 19,400.00

12 Minyak Bekisting ltr 40,500.00

13 Rapidrant Gln 15,700.00

14 Soda Api kg 35,600.00


15 Sabun kg 2,400.00

16 Arang Kayu kg 11,100.00

17 Kawat Las bh 1,400.00


V BAHAN PAGAR

1 Panel Beton Pracetak lbr 199,200.00

2 Kolom Beton Pracetak btg 264,000.00

B. BIDANG PERTAMANAN

1 Aglonema batang 50,000.00

2 Bambu krisik/jepang batang 50,000.00


3 Furadan kg 24,000.00

4 Kompos/pupuk kandang karung 25,000.00

5 M atoa (2 m) batang 40,000.00

Palm (botol, ekor tupai,


6 putri, dll) tinggi 2 m batang 100,000.00
7 Philo batang 75,000.00

Pohon pelindung
(angsana, mahoni,
8 kamboja dll) tinggi 2m batang 25,000.00
Pohon perdu (kaca
piring, puring, mawar,
9 melati, dll) batang 10,000.00

10 Rumput gajah mini m2 15,000.00

You might also like