Conclusion

From this practical, we were able to setup the compass survey stations and their
equipment correctly. We have taken the 90 left and right to do a grid. We have measure 5
m for every point until 15 m for horizontal and 2 m for every point until 10 m. Good
communication between the observer, data recorder, and the pole person is very important
in order to minimize the human errors that can affected the precision of the survey job. We
have learned how to pick up all details by cross- section and long- section while traversing.
The detail is very important for engineer to get precise value of ground height and detail
position for the development planning. Typical details have collected such as trees, existing
roads, walls, cutting, drainage, lamp post and so on. In cross-section and long-section work,
we found that the error of reading from chainage to chainage. May be the error was come
from the equipment and human error.