HOJA DE METRADO

ACERO KG/ML
PROYECTO : AMPLIACION DE INFRAESTRUCTURA DE LA INSTITUCION EDUCATIVA"SAN JORGE" EN EL CENTRO POBLADO SUPTE SAN JORGE 1/4" 0.250
3/8" 0.580
FECHA : SETIEMBRE DEL 2011 HECHO POR: DAMS 1/2" 1.020
5/8" 1.60
SUB FORMULA : ESTRUCTURAS 3/4" 2.260
1" 4.040
CENTRO POBLADO : SUPTE SAN JORGE DISTRITO : RUPA RUPA PROVINCIA : LEONCIO PRADO

MEDIDAS N SUB TOTAL


N DESCRIPCION DE TOTAL
UND LARGO ANCHO ALTO VECES LONG. AREA VOL. KG.

01.00.00 ESTRUCTURAS
01.01.00 OBRAS PROVISIONALES
01.01.01 ALMACEN, OFICINA Y CASETA DE GUARDIANIA 152.00
- Oficina del Contratistas M2 5.00 4.00 1.00 20.00
- Oficina del Supervisor M2 4.00 4.00 1.00 16.00
- Almacenes M2 12.00 5.00 1.00 60.00

- Talleres M2 8.00 5.00 1.00 40.00


- Guardiana y enfermera M2 4.00 4.00 1.00 16.00

01.01.02 CARTEL DE OBRA C/PLANCHA METALICA DE 2.40x3.60m UND 1.00 1.00

01.01.03 LIMPIEZA DE TERRENO MANUAL M2 1357.94

acondicionamiento y limpieza administrativo 10.22 5.16 52.74

acondicionamiento y limpieza vereda 4.53 2.65 12.00

acondicionamiento y limpieza vereda 42.60 2.65 112.89

acondicionamiento y limpieza aulas 33.65 12.25 412.21

acondicionamiento y limpieza ss.hh. 10.40 11.25 117.00

acondicionamiento y limpieza losa y tribuna 22.39 29.08 651.10

01.01.04 TRAZO, NIVELES Y REPLANTEO PRELIMINAR M2 1357.94

acondicionamiento y limpieza administrativo 10.22 5.16 52.74

acondicionamiento y limpieza vereda 4.53 2.65 12.00

acondicionamiento y limpieza vereda 42.60 2.65 112.89

acondicionamiento y limpieza aulas 33.65 12.25 412.21

acondicionamiento y limpieza ss.hh. 10.40 11.25 117.00

acondicionamiento y limpieza losa y tribuna 22.39 29.08 651.10

TRNASPORTE DE MATERIALES DE HUANUCO A OBRA

01.01.05 MOVILIZACION Y DESMOVILIZACION DE EQUIPO GLB 1.00 1.00

01.01.06 VIGILANCIA COMPLEMENTARIA DIA 210.00 210.00

01.01.07 ACORDONAMIENTO DE SEGURIDAD M 1500.00

perimetro alrededor de las obras a ejecutar 1500.00 1.00 1500.00

01.01.08 TRANSPORTE DE MATERIALES DE HUANUCO A OBRA KG VER HOJA DE CALCULO

01.02.00 MOVIMIENTOS DE TIERRAS


01.02.01 CORTE SUPERFICIAL LATERAL CON MAQUINARIA M3 H=PROM. 339.49

rea sacado con autocad 0.25 1357.94 339.49

01.02.02 PERFILADO Y COPMPACTADO, NIVELACION EN ZONA DE CORT M2 1357.94

rea sacado con autocad 1357.94

01.02.03 EXCAVACION DE ZANJAS P/CIMIENTOS (MANUAL) M3 143.61

AULAS

EJE F-F / 5-4 M3 1.26 0.60 3.10 1.00 2.34

EJE F-F / 6-5 M3 1.30 0.60 3.10 1.00 2.42

EJE F-F / 7-6 M3 1.30 0.60 3.10 1.00 2.42

EJE F-F / 8-7 M3 1.30 0.60 3.10 1.00 2.42

EJE F-F / 9-8 M3 1.30 0.60 3.10 1.00 2.42

EJE F-F / 10-9 M3 1.26 0.60 3.10 1.00 2.34

EJE A-A / 5-4 M3 1.69 0.60 3.10 1.00 3.14

EJE A-A / 6-5 M3 1.27 0.60 3.10 1.00 2.36

1/87
HOJA DE METRADO
ACERO KG/ML
PROYECTO : AMPLIACION DE INFRAESTRUCTURA DE LA INSTITUCION EDUCATIVA"SAN JORGE" EN EL CENTRO POBLADO SUPTE SAN JORGE 1/4" 0.250
3/8" 0.580
FECHA : SETIEMBRE DEL 2011 HECHO POR: DAMS 1/2" 1.020
5/8" 1.60
SUB FORMULA : ESTRUCTURAS 3/4" 2.260
1" 4.040
CENTRO POBLADO : SUPTE SAN JORGE DISTRITO : RUPA RUPA PROVINCIA : LEONCIO PRADO

MEDIDAS N SUB TOTAL


N DESCRIPCION DE TOTAL
UND LARGO ANCHO ALTO VECES LONG. AREA VOL. KG.

EJE A-A / 7-6 M3 1.28 0.60 3.10 1.00 2.38

EJE A-A. / 8-7 M3 1.27 0.60 3.10 1.00 2.36

EJE A-A / 9-8 M3 1.28 0.60 3.10 1.00 2.38

EJE A-A / 10-9 M3 1.69 0.60 3.10 1.00 3.14

EJE 10-10 M3 4.37 0.60 3.10 1.00 8.13

EJE 8-8 M3 3.64 0.60 3.10 1.00 6.77

EJE 6-6 M3 3.64 0.60 3.10 1.00 6.77

EJE 4-4 M3 4.37 0.60 3.10 1.00 8.13

SS.HH.

EJE B-B / 1-2 M3 1.84 0.60 2.95 1.00 3.26

EJE B-B/2-3 M3 1.84 0.60 2.95 1.00 3.26

EJE F-F/1-2 M3 1.84 0.60 2.95 1.00 3.26

EJE F-F / 2-3 M3 1.84 0.60 2.95 1.00 3.26

EJE 1-1 / B-E M3 1.43 0.60 2.95 1.00 2.53

EJE 1-1 / E-F M3 1.43 0.60 2.95 1.00 2.53

EJE 3-3 / B-E M3 1.43 0.60 2.95 1.00 2.53

EJE 3-3 / E-F M3 1.43 0.60 2.95 1.00 2.53

EJE 2-2 / B-E M3 1.43 0.60 2.95 1.00 2.53

EJE 2-2 / E-F M3 1.43 0.60 2.95 1.00 2.53

ENTRE EJE 1-3 / B-F M3 2.16 0.30 0.60 4.00 1.56

M3 0.80 0.30 0.60 4.00 0.58

M3 1.41 0.30 0.60 8.00 2.03

AREA ADMINISTRATIVA Y SS. HH.

EJE H-H / 13-14 M3 1.93 0.60 2.95 1.00 3.42

EJE H-H / 14-15 M3 1.23 0.60 2.95 1.00 2.18

EJE I-I / 13-14 M3 2.27 0.60 2.95 1.00 4.02

EJE I-I / 14-15 M3 1.49 0.60 2.95 1.00 2.64

EJE 13-13 / H-I M3 1.93 0.60 2.95 1.00 3.42

EJE 14-14 / I-H M3 1.93 0.60 2.95 1.00 0.69

EJE 15-15 / I-H M3 1.93 0.60 2.95 1.00 3.42

01.02.04 EXCAVACION PARA ZAPATAS DE H=3.10 m DE PROFUNDIDAD M3 787.14


AULAS

Z-1 M3 2.80 2.80 3.20 3.00 75.26

Z-2 M3 4.00 3.60 3.20 2.00 92.16

Z-3 M3 2.10 2.10 3.20 3.00 42.34

Z-4 M3 4.35 4.25 3.20 2.00 118.32

Z-5 M3 3.40 3.08 3.20 2.00 67.02

Z-5 M3 3.65 3.40 3.20 2.00 79.42

SS.HH.

Z-6 M3 2.30 2.30 3.05 6.00 96.81

Z-7 M3 2.30 2.30 3.05 3.00 48.40

AREA ADMINISTRATIVA Y SS.HH.

Z-8 M3 2.30 2.12 3.05 1.00 14.87

M3 2.00 1.90 3.05 2.00 23.18

Z-9 M3 2.03 1.90 3.05 1.00 11.76

Z-10 M3 2.40 2.30 3.05 2.00 33.67

ESCALERA

M3 5.92 4.43 3.20 1.00 83.92

01.02.05 RELLENO Y COMPACTADO ZANJAS CON MATERIAL PROPIO C/E M3 657.90


AULAS

2/87
HOJA DE METRADO
ACERO KG/ML
PROYECTO : AMPLIACION DE INFRAESTRUCTURA DE LA INSTITUCION EDUCATIVA"SAN JORGE" EN EL CENTRO POBLADO SUPTE SAN JORGE 1/4" 0.250
3/8" 0.580
FECHA : SETIEMBRE DEL 2011 HECHO POR: DAMS 1/2" 1.020
5/8" 1.60
SUB FORMULA : ESTRUCTURAS 3/4" 2.260
1" 4.040
CENTRO POBLADO : SUPTE SAN JORGE DISTRITO : RUPA RUPA PROVINCIA : LEONCIO PRADO

MEDIDAS N SUB TOTAL


N DESCRIPCION DE TOTAL
UND LARGO ANCHO ALTO VECES LONG. AREA VOL. KG.

Relleno en zapatas hasta nivel de cimiento

Z-1 M3 2.80 2.80 2.60 3.00 61.15

Z-2 M3 4.00 3.60 2.60 2.00 74.88

Z-3 M3 2.10 2.10 2.60 3.00 34.40

Z-4 M3 4.35 4.25 2.60 2.00 96.14

Z-5 M3 3.40 3.08 2.60 2.00 54.45

M3 3.65 3.40 2.60 2.00 64.53

SS.HH.

Z-6 M3 2.30 2.30 2.50 6.00 79.35

Z-7 M3 2.30 2.30 2.50 3.00 39.68

AREA ADMINISTRATIVA Y SS. HH.

Z-8 M3 2.30 2.12 2.50 1.00 12.19

M3 2.00 1.90 2.50 2.00 19.00

Z-9 M3 2.03 1.90 2.50 1.00 9.64

Z-10 M3 2.40 2.30 2.50 2.00 27.60

ESCALERA

M3 5.92 4.43 2.60 1.00 68.19

DESCUEAULAS

descuento de vigas de cimentacion M3 1.25 0.35 0.30 6.00 -0.79

AULAS EJES 4-4, 6-6, 8-8, 10-10, A-A, F-F. M3 1.50 0.35 0.30 4.00 -0.63

M3 2.30 0.60 0.80 2.00 -2.21

M3 0.90 0.35 0.30 6.00 -0.57

M3 1.88 0.35 0.30 4.00 -0.79

M3 2.43 0.60 0.80 2.00 -2.33

M3 1.53 0.35 0.30 2.00 -0.32

M3 2.00 0.60 0.80 2.00 -1.92

M3 1.45 0.35 0.30 2.00 -0.30

M3 2.00 0.60 0.80 2.00 -1.92

descuento de columnas M3 0.60 0.30 2.30 6.00 -2.48

AULAS EJES 4-4, 6-6, 8-8, 10-10, A-A, F-F. M3 0.60 0.30 1.80 8.00 -2.59

descuento de cimiento y falso cimiento M3 1.25 0.60 0.85 6.00 -3.83

AULAS EJES 4-4, 6-6, 8-8, 10-10, A-A, F-F. M3 1.50 0.60 0.85 4.00 -3.06

M3 2.30 0.60 0.85 2.00 -2.35

M3 0.90 0.60 0.85 6.00 -2.75

M3 1.88 0.60 0.85 4.00 -3.84

M3 2.43 0.60 0.85 2.00 -2.48

M3 1.53 0.60 0.85 2.00 -1.56

M3 2.00 0.60 0.85 2.00 -2.04

M3 1.45 0.60 0.85 2.00 -1.48

M3 2.00 0.60 0.85 2.00 -2.04

SS.HH.

SS.HH. EJES 1-1, 2-2, 3-3, B-B,F-F

descuento de vigas de cimentacion M3 1.00 0.30 0.20 20.00 -1.20

descuento de columnas M3 0.30 0.30 2.40 9.00 -1.94

descuento de cimiento M3 1.00 0.60 0.60 20.00 -7.20

descuento de sobrecimiento armado M3 1.00 0.16 0.50 20.00 -1.60

AREA ADMINISTRATIVA Y SS.HH.

descuento de vigas de cimentacion M3 1.70 0.30 0.20 1.00 -0.10

ADMINISTRATIVO 13-13, 14-14, 15-15, I-I, H-H M3 1.00 0.30 0.20 1.00 -0.06

M3 1.60 0.30 0.20 2.00 -0.19

M3 1.58 0.30 0.20 1.00 -0.09

M3 1.00 0.30 0.20 4.00 -0.24

3/87
HOJA DE METRADO
ACERO KG/ML
PROYECTO : AMPLIACION DE INFRAESTRUCTURA DE LA INSTITUCION EDUCATIVA"SAN JORGE" EN EL CENTRO POBLADO SUPTE SAN JORGE 1/4" 0.250
3/8" 0.580
FECHA : SETIEMBRE DEL 2011 HECHO POR: DAMS 1/2" 1.020
5/8" 1.60
SUB FORMULA : ESTRUCTURAS 3/4" 2.260
1" 4.040
CENTRO POBLADO : SUPTE SAN JORGE DISTRITO : RUPA RUPA PROVINCIA : LEONCIO PRADO

MEDIDAS N SUB TOTAL


N DESCRIPCION DE TOTAL
UND LARGO ANCHO ALTO VECES LONG. AREA VOL. KG.

M3 0.80 0.30 0.20 3.00 -0.14

descuento de columnas M3 0.40 0.30 2.30 6.00 -1.66

descuento de cimiento y falso cimiento M3 1.70 0.85 0.85 1.00 -1.23

ADMINISTRATIVO 13-13, 14-14, 15-15, I-I, H-H M3 1.00 0.85 0.60 1.00 -0.51

M3 1.60 0.85 0.60 2.00 -1.63

M3 1.58 0.85 0.60 1.00 -0.81

M3 1.00 0.85 0.60 4.00 -2.04

M3 0.80 0.85 0.60 3.00 -1.22

descuento de sobrecimiento armado M3 1.70 0.16 0.50 1.00 -0.14

ADMINISTRATIVO 13-13, 14-14, 15-15, I-I, H-H M3 1.00 0.16 0.50 1.00 -0.08

M3 1.60 0.16 0.50 2.00 -0.26

M3 1.58 0.16 0.50 1.00 -0.13

M3 1.00 0.16 0.50 4.00 -0.32

M3 0.80 0.16 0.50 3.00 -0.19

ESCALERA

descuento de columnas M3 0.30 0.30 2.60 4.00 -0.94

descuento de placa M3 2.98 0.15 2.60 1.00 -1.16

AULAS

RELLENO EN CIMIENTOS

EJE F-F / 5-4 M3 1.26 0.60 3.10 1.00 2.34

EJE F-F / 6-5 M3 1.30 0.60 3.10 1.00 2.42

EJE F-F / 7-6 M3 1.30 0.60 3.10 1.00 2.42

EJE F-F / 8-7 M3 1.30 0.60 3.10 1.00 2.42

EJE F-F / 9-8 M3 1.30 0.60 3.10 1.00 2.42

EJE F-F / 10-9 M3 1.26 0.60 3.10 1.00 2.34

EJE A-A / 5-4 M3 1.69 0.60 3.10 1.00 3.14

EJE A-A / 6-5 M3 1.27 0.60 3.10 1.00 2.36

EJE A-A / 7-6 M3 1.27 0.60 3.10 1.00 2.36

EJE A-A. / 8-7 M3 1.27 0.60 3.10 1.00 2.36

EJE A-A / 9-8 M3 1.27 0.60 3.10 1.00 2.36

EJE A-A / 10-9 M3 1.69 0.60 3.10 1.00 3.14

EJE 10-10 M3 4.37 0.80 3.10 1.00 10.84

EJE 8-8 M3 3.64 0.80 3.10 1.00 9.03

EJE 6-6 M3 3.64 0.80 3.10 1.00 9.03

EJE 4-4 M3 4.37 0.80 3.10 1.00 10.84

descuento de cimiento y falso cimiento

AULAS EJES 4-4, 6-6, 8-8, 10-10, A-A, F-F. M3 1.26 0.60 0.85 1.00 -0.64

M3 1.30 0.60 0.85 1.00 -0.66

M3 1.30 0.60 0.85 1.00 -0.66

M3 1.30 0.60 0.85 1.00 -0.66

M3 1.30 0.60 0.85 1.00 -0.66

M3 1.26 0.60 0.85 1.00 -0.64

M3 1.69 0.60 0.85 1.00 -0.86

M3 1.27 0.60 0.85 1.00 -0.65

M3 1.27 0.60 0.85 1.00 -0.65

M3 1.27 0.60 0.85 1.00 -0.65

M3 1.27 0.60 0.85 1.00 -0.65

M3 1.69 0.60 0.85 1.00 -0.86

M3 4.37 0.80 0.85 1.00 -2.97

M3 3.64 0.80 0.85 1.00 -2.48

M3 3.64 0.80 0.85 1.00 -2.48

M3 4.37 0.80 0.85 1.00 -2.97

4/87
HOJA DE METRADO
ACERO KG/ML
PROYECTO : AMPLIACION DE INFRAESTRUCTURA DE LA INSTITUCION EDUCATIVA"SAN JORGE" EN EL CENTRO POBLADO SUPTE SAN JORGE 1/4" 0.250
3/8" 0.580
FECHA : SETIEMBRE DEL 2011 HECHO POR: DAMS 1/2" 1.020
5/8" 1.60
SUB FORMULA : ESTRUCTURAS 3/4" 2.260
1" 4.040
CENTRO POBLADO : SUPTE SAN JORGE DISTRITO : RUPA RUPA PROVINCIA : LEONCIO PRADO

MEDIDAS N SUB TOTAL


N DESCRIPCION DE TOTAL
UND LARGO ANCHO ALTO VECES LONG. AREA VOL. KG.

RELLENO EN SS.HH.

M3 1.84 0.60 2.95 1.00 3.26

M3 1.84 0.60 2.95 1.00 3.26

M3 1.84 0.60 2.95 1.00 3.26

M3 1.84 0.60 2.95 1.00 3.26

M3 1.43 0.60 2.95 1.00 2.53

M3 1.43 0.60 2.95 1.00 2.53

M3 1.43 0.60 2.95 1.00 2.53

M3 1.43 0.60 2.95 1.00 2.53

M3 1.43 0.60 2.95 1.00 2.53

M3 1.43 0.60 2.95 1.00 2.53

descuento de cimiento y falso cimiento

SS.HH. EJES 1-1, 2-2, 3-3, B-B, F-F M3 1.84 0.60 0.85 1.00 -0.94

M3 1.84 0.60 0.85 1.00 -0.94

M3 1.84 0.60 0.85 1.00 -0.94

M3 1.84 0.60 0.85 1.00 -0.94

M3 1.43 0.60 0.85 1.00 -0.73

M3 1.43 0.60 0.85 1.00 -0.73

M3 1.43 0.60 0.85 1.00 -0.73

M3 1.43 0.60 0.85 1.00 -0.73

M3 1.43 0.60 0.85 1.00 -0.73

M3 1.43 0.60 0.85 1.00 -0.73

RELLENO EN ADMINISTRATIVO

M3 1.93 0.60 2.95 1.00 3.42

M3 1.23 0.60 2.95 1.00 2.18

M3 2.27 0.60 2.95 1.00 4.02

M3 1.49 0.60 2.95 1.00 2.64

M3 1.93 0.60 2.95 1.00 3.42

M3 1.93 0.60 0.60 1.00 0.69

M3 1.93 0.60 2.95 1.00 3.42

descuento de cimiento y falso cimiento

ADMINISTRATIVOS 13-13, 14-14, 15-15, I-I, H-H M3 1.93 0.60 0.85 1.00 -0.98

M3 1.23 0.60 0.85 1.00 -0.63

M3 2.27 0.60 0.85 1.00 -1.16

M3 1.49 0.60 0.85 1.00 -0.76

M3 1.93 0.60 0.85 1.00 -0.98

M3 1.93 0.60 0.85 1.00 -0.98

M3 1.93 0.60 0.85 1.00 -0.98

01.02.06 RELLENO Y COMPACTADO CON MATERIAL DE PRESTAMO C/EQUIPO LIVIANO 193.46


AULA 1 M3 8.81 7.91 0.40 1.00 27.87

AULA 2 M3 8.78 7.91 0.35 1.00 24.31

AULA 3 M3 8.81 7.91 0.35 1.00 24.39

SS.HH. M3 7.34 4.06 0.35 2.00 20.86

AREA ADMINISTRATIVA M3 4.30 4.84 0.25 2.00 10.41

VEREDA EN ESCALERA, AULAS Y SS.HH. M3 46.56 2.25 0.35 1.00 36.67

VEREDA EN ESCALERA Y AULAS M3 5.85 0.90 0.35 1.00 1.84

M3 3.95 0.90 0.35 1.00 1.24

M3 3.45 0.90 0.35 1.00 1.09

M3 27.30 1.00 0.35 1.00 9.56

M3 9.30 0.90 0.35 1.00 2.93

VEREDAS EN SS.HH. M3 8.70 0.90 0.35 1.00 2.74

5/87
HOJA DE METRADO
ACERO KG/ML
PROYECTO : AMPLIACION DE INFRAESTRUCTURA DE LA INSTITUCION EDUCATIVA"SAN JORGE" EN EL CENTRO POBLADO SUPTE SAN JORGE 1/4" 0.250
3/8" 0.580
FECHA : SETIEMBRE DEL 2011 HECHO POR: DAMS 1/2" 1.020
5/8" 1.60
SUB FORMULA : ESTRUCTURAS 3/4" 2.260
1" 4.040
CENTRO POBLADO : SUPTE SAN JORGE DISTRITO : RUPA RUPA PROVINCIA : LEONCIO PRADO

MEDIDAS N SUB TOTAL


N DESCRIPCION DE TOTAL
UND LARGO ANCHO ALTO VECES LONG. AREA VOL. KG.

M3 8.60 0.90 0.35 1.00 2.71

M3 8.70 0.90 0.35 1.00 2.74

VEREDA EN ADMINISTRATIVO M3 5.16 0.90 0.25 1.00 1.16

VEREDA EN ACCESO M3 43.00 2.25 0.25 1.00 24.19

M3 4.56 2.25 0.25 1.00 2.57

M3 16.60 1.50 0.25 1.00 6.23

DESCUENTO EN AREAS DE Z APATAS

Descuento de sobrecimiento armado M3 1.25 0.16 0.50 6.00 -0.60

AULAS EJES 4-4, 6-6, 8-8, 10-10, A-A,F-F M3 1.50 0.16 0.50 4.00 -0.48

M3 2.30 0.23 0.50 2.00 -0.53

M3 0.90 0.16 0.50 6.00 -0.43

M3 1.88 0.16 0.50 4.00 -0.60

M3 2.43 0.23 0.50 2.00 -0.56

M3 1.53 0.16 0.50 2.00 -0.24

M3 2.00 0.23 0.50 2.00 -0.46

M3 1.45 0.16 0.50 2.00 -0.23

M3 2.00 0.23 0.50 2.00 -0.46

DESCUENTO EN AULAS EN CIMIENTOS

descuento de sobrecimiento armado

AULA EJES 4-4, 6-6, 8-8, 10-10, A-A, F-F M3 1.26 0.16 0.50 1.00 -0.10

M3 1.30 0.16 0.50 1.00 -0.10

M3 1.30 0.16 0.50 1.00 -0.10

M3 1.30 0.16 0.50 1.00 -0.10

M3 1.30 0.16 0.50 1.00 -0.10

M3 1.26 0.16 0.50 1.00 -0.10

M3 1.69 0.16 0.50 1.00 -0.14

M3 1.27 0.16 0.50 1.00 -0.10

M3 1.27 0.16 0.50 1.00 -0.10

M3 1.27 0.16 0.50 1.00 -0.10

M3 1.27 0.16 0.50 1.00 -0.10

M3 1.69 0.16 0.50 1.00 -0.14

M3 4.37 0.23 0.50 1.00 -0.50

M3 3.64 0.23 0.50 1.00 -0.42

M3 3.64 0.23 0.50 1.00 -0.42

M3 4.37 0.23 0.50 1.00 -0.50

DESCUENTO EN SS.HH. CIMIENTOS

descuento de sobrecimiento armado

SS.HH. EJES 1-1, 2-2, 3-3, B-B, F-F M3 1.84 0.16 0.50 1.00 -0.15

M3 1.84 0.16 0.50 1.00 -0.15

M3 1.84 0.16 0.50 1.00 -0.15

M3 1.84 0.16 0.50 1.00 -0.15

M3 1.43 0.16 0.50 1.00 -0.11

M3 1.43 0.16 0.50 1.00 -0.11

M3 1.43 0.16 0.50 1.00 -0.11

M3 1.43 0.16 0.50 1.00 -0.11

M3 1.43 0.16 0.50 1.00 -0.11

M3 1.43 0.16 0.50 1.00 -0.11

DESCUENTO EN ADMINISTRATIVOS CIMIENTOS

descuento de sobrecimiento armado

ADMINISTRATIVOS EJES 13-13, 14-14, 15-15, I-I, H-H M3 1.93 0.16 0.50 0.10 -0.15

M3 1.23 0.16 0.50 0.10 -0.10

M3 2.27 0.16 0.50 0.10 -0.18

6/87
HOJA DE METRADO
ACERO KG/ML
PROYECTO : AMPLIACION DE INFRAESTRUCTURA DE LA INSTITUCION EDUCATIVA"SAN JORGE" EN EL CENTRO POBLADO SUPTE SAN JORGE 1/4" 0.250
3/8" 0.580
FECHA : SETIEMBRE DEL 2011 HECHO POR: DAMS 1/2" 1.020
5/8" 1.60
SUB FORMULA : ESTRUCTURAS 3/4" 2.260
1" 4.040
CENTRO POBLADO : SUPTE SAN JORGE DISTRITO : RUPA RUPA PROVINCIA : LEONCIO PRADO

MEDIDAS N SUB TOTAL


N DESCRIPCION DE TOTAL
UND LARGO ANCHO ALTO VECES LONG. AREA VOL. KG.

M3 1.49 0.16 0.50 0.10 -0.12

M3 1.93 0.16 0.50 0.10 -0.15

M3 1.93 0.16 0.50 0.10 -0.15

M3 1.93 0.16 0.50 0.10 -0.15

01.02.07 ELIMINACION DE MATERIAL EXCEDENTE C/MAQUINARIA DIST. =5KM 580.81


M3 580.81

01.02.08 NIV. INTERIOR Y APISONADO P/RECIBIR FALSO PISO M2 347.64


AULA 1 M2 8.81 7.91 1.00 89.69

AULA 2 M2 8.78 7.91 1.00 69.45

AULA 3 M2 8.81 7.91 1.00 69.69

SS.HH. M2 7.34 4.06 2.00 59.60

AREA ADMINISTRATIVA Y SS.HH. M2 4.30 4.84 2.00 41.62

ESCALERA M2 5.92 4.43 1.00 26.23

01.02.09 AFIRMADO DE 4" PARA VEREDAS C/EQUIPO M2 351.66


VEREDA EN ESCALERA, AULAS Y SS.HH. M2 46.56 2.25 1.00 104.76

VEREDA EN ESCALERA Y AULAS M2 5.85 0.90 1.00 5.27

M2 3.95 0.90 1.00 3.56

M2 3.45 0.90 1.00 3.11

M2 27.30 1.00 1.00 27.30

M2 9.30 0.90 1.00 8.37

VEREDAS EN SS.HH. M2 8.70 0.90 1.00 7.83

M2 8.60 0.90 1.00 7.74

M2 8.70 0.90 1.00 7.83

VEREDA EN AREA ADMINISTRATIVA Y SS.HH. M2 5.16 0.90 1.00 4.64

VEREDA EN ACCESO M2 43.00 2.25 1.00 96.75

M2 4.56 2.25 1.00 10.26

M2 16.60 1.50 1.00 24.90

01.03.00 OBRAS DE CONCRETO SIMPLE


01.03.01 SOLADOS
01.03.01.01 SOLADOS E=4" EN ZAPATAS MEZCLA 1:12 CEMENTO HORMIG M2 249.50
AULAS

Z-1 M2 2.80 2.80 3.00 23.52

Z-2 M2 4.00 3.60 2.00 28.80

Z-3 M2 2.10 2.10 3.00 13.23

Z-4 M2 4.35 4.25 2.00 36.98

Z-5 M2 3.40 3.08 2.00 20.94

Z-5 M2 3.65 3.40 2.00 24.82

SS.HH.

Z-6 M2 2.30 2.30 6.00 31.74

Z-7 M2 2.30 2.30 3.00 15.87

AREA ADMINISTRATIVA Y SS.HH.

Z-8 M2 2.30 2.12 1.00 4.88

M2 2.00 1.90 2.00 7.60

Z-9 M2 2.03 1.90 1.00 3.86

Z-10 M2 2.40 2.30 2.00 11.04

ESCALERA

M2 5.92 4.43 1.00 26.23

7/87
HOJA DE METRADO
ACERO KG/ML
PROYECTO : AMPLIACION DE INFRAESTRUCTURA DE LA INSTITUCION EDUCATIVA"SAN JORGE" EN EL CENTRO POBLADO SUPTE SAN JORGE 1/4" 0.250
3/8" 0.580
FECHA : SETIEMBRE DEL 2011 HECHO POR: DAMS 1/2" 1.020
5/8" 1.60
SUB FORMULA : ESTRUCTURAS 3/4" 2.260
1" 4.040
CENTRO POBLADO : SUPTE SAN JORGE DISTRITO : RUPA RUPA PROVINCIA : LEONCIO PRADO

MEDIDAS N SUB TOTAL


N DESCRIPCION DE TOTAL
UND LARGO ANCHO ALTO VECES LONG. AREA VOL. KG.

01.03.02 CIMIENTO CORRIDOS


01.03.02.01 FALZA CIMENTACION MEZCLA 1:12 C-H + 30% PG M3 26.45
AULAS

EJE F-F / 5-4 M3 4.16 0.60 0.25 1.00 0.62

EJE F-F / 6-5 M3 4.18 0.60 0.25 1.00 0.63

EJE F-F / 7-6 M3 4.19 0.60 0.25 1.00 0.63

EJE F-F / 8-7 M3 4.19 0.60 0.25 1.00 0.63

EJE F-F / 9-8 M3 4.19 0.60 0.25 1.00 0.63

EJE F-F / 10-9 M3 4.17 0.60 0.25 1.00 0.63

EJE A-A / 5-4 M3 4.16 0.60 0.25 1.00 0.62

EJE A-A / 6-5 M3 4.18 0.60 0.25 1.00 0.63

EJE A-A / 7-6 M3 4.19 0.60 0.25 1.00 0.63

EJE A-A / 8-7 M3 4.19 0.60 0.25 1.00 0.63

EJE A-A / 9-8 M3 4.19 0.60 0.25 1.00 0.63

EJE A-A / 10-9 M3 4.17 0.60 0.25 1.00 0.63

EJE 10-10 M3 6.92 0.60 0.25 1.00 1.04

EJE 8-8 M3 6.92 0.60 0.25 1.00 1.04

EJE 6-6 M3 6.92 0.60 0.25 1.00 1.04

EJE 4-4 M3 6.92 0.60 0.25 1.00 1.04

SS.HH.

EJE B-B / 1-2 M3 1.84 0.60 0.25 1.00 0.28

EJE B-B / 2-3 M3 1.84 0.60 0.25 1.00 0.28

EJE F-F / 1-2 M3 1.84 0.60 0.25 1.00 0.28

EJE F-F / 2-3 M3 1.84 0.60 0.25 1.00 0.28

EJE 1-1 / B-E M3 1.43 0.60 0.25 1.00 0.21

EJE 1-1 / E-F M3 1.43 0.60 0.25 1.00 0.21

EJE 3-3 / B-E M3 1.43 0.60 0.25 1.00 0.21

EJE 3-3 / E-F M3 1.43 0.60 0.25 1.00 0.21

EJE 2-2 / B-E M3 1.43 0.60 0.25 1.00 0.21

EJE 2-2 / E-F M3 1.43 0.60 0.25 1.00 0.21

ENTRE EJE 1-3 / B-F M3 2.16 0.30 0.25 4.00 0.65

M3 0.80 0.30 0.25 4.00 0.24

M3 1.41 0.30 0.25 8.00 0.85

AREA ADMINISTRATIVA Y SS.HH.

EJE H-H / 13-14 M3 1.93 0.60 0.25 1.00 0.29

EJE H-H / 14-15 M3 1.23 0.60 0.25 1.00 0.18

EJE I-I / 13-14 M3 2.27 0.60 0.25 1.00 0.34

EJE I-I / 14-15 M3 1.49 0.60 0.25 1.00 0.22

EJE 13-13 / H-I M3 1.93 0.60 0.25 1.00 0.29

EJE 14-14 / I-H M3 1.93 0.60 0.25 1.00 0.29

EJE 15-15 / I-H M3 1.93 0.60 0.25 1.00 0.29

ESCALERA

M3 5.92 4.43 0.25 1.00 6.56

01.03.02.02 CIMIENTO CORRIDOS MEZCLA 1:10 C-H + 30% PG 60.13


AULAS

EJE F-F / 5-4 M3 4.16 0.60 0.60 1.00 1.50

EJE F-F / 6-5 M3 4.18 0.60 0.60 1.00 1.50

EJE F-F / 7-6 M3 4.19 0.60 0.60 1.00 1.51

EJE F-F / 8-7 M3 4.19 0.60 0.60 1.00 1.51

EJE F-F / 9-8 M3 4.19 0.60 0.60 1.00 1.51

EJE F-F / 10-9 M3 4.17 0.60 0.60 1.00 1.50

8/87
HOJA DE METRADO
ACERO KG/ML
PROYECTO : AMPLIACION DE INFRAESTRUCTURA DE LA INSTITUCION EDUCATIVA"SAN JORGE" EN EL CENTRO POBLADO SUPTE SAN JORGE 1/4" 0.250
3/8" 0.580
FECHA : SETIEMBRE DEL 2011 HECHO POR: DAMS 1/2" 1.020
5/8" 1.60
SUB FORMULA : ESTRUCTURAS 3/4" 2.260
1" 4.040
CENTRO POBLADO : SUPTE SAN JORGE DISTRITO : RUPA RUPA PROVINCIA : LEONCIO PRADO

MEDIDAS N SUB TOTAL


N DESCRIPCION DE TOTAL
UND LARGO ANCHO ALTO VECES LONG. AREA VOL. KG.

EJE A-A / 5-4 M3 4.16 0.60 0.60 1.00 1.50

EJE A-A / 6-5 M3 4.18 0.60 0.60 1.00 1.50

EJE A-A / 7-6 M3 4.19 0.60 0.60 1.00 1.51

EJE A-A / 8-7 M3 4.19 0.60 0.60 1.00 1.51

EJE A-A / 9-8 M3 4.19 0.60 0.60 1.00 1.51

EJE A-A / 10-9 M3 4.17 0.60 0.60 1.00 1.50

EJE 10-10 M3 6.92 0.60 0.60 1.00 2.49

EJE 8-8 M3 6.92 0.60 0.60 1.00 2.49

EJE 6-6 M3 6.92 0.60 0.60 1.00 2.49

EJE 4-4 M3 6.92 0.60 0.60 1.00 2.49

SS.HH.

EJE B-B / 1-2 M3 3.76 0.60 0.60 1.00 1.35

EJE B-B / 2-3 M3 3.76 0.60 0.60 1.00 1.35

EJE F-F / 1-2 M3 3.76 0.60 0.60 1.00 1.35

EJE F-F / 2-3 M3 3.76 0.60 0.60 1.00 1.35

EJE 1-1 / B-E M3 3.35 0.60 0.60 1.00 1.21

EJE 1-1 / E-F M3 3.35 0.60 0.60 1.00 1.21

EJE 3-3 / B-E M3 3.35 0.60 0.60 1.00 1.21

EJE 3-3 / E-F M3 3.35 0.60 0.60 1.00 1.21

EJE 2-2 / B-E M3 3.35 0.60 0.60 1.00 1.21

EJE 2-2 / E-F M3 3.35 0.60 0.60 1.00 1.21

ENTRE EJE 1-3 / B-F M3 2.16 0.30 0.60 4.00 1.56

M3 0.80 0.30 0.60 4.00 0.58

M3 1.41 0.30 0.60 8.00 2.03

AREA ADMINISTRATIVA Y SS.HH.

EJE H-H / 13-14 M3 3.85 0.60 0.60 1.00 1.39

EJE H-H / 14-15 M3 3.85 0.60 0.60 1.00 1.39

EJE I-I / 13-14 M3 3.85 0.60 0.60 1.00 1.39

EJE I-I / 14-15 M3 3.85 0.60 0.60 1.00 1.39

EJE 13-13 / H-I M3 4.45 0.60 0.60 1.00 1.60

EJE 14-14 / I-H M3 3.57 0.60 0.60 1.00 1.29

EJE 15-15 / I-H M3 4.45 0.60 0.60 1.00 1.60

01.03.03 SOBRECIMIENTOS
01.03.03.01 CONCRETO EN SOBRECIMIENTO 1:8 C H + 25% PG 8.37
EJE F-F / 5-4 M3 4.16 0.13 0.25 1.00 0.12

EJE F-F / 6-5 M3 4.18 0.13 0.25 1.00 0.14

EJE F-F / 7-6 M3 4.19 0.13 0.25 1.00 0.14

EJE F-F / 8-7 M3 4.19 0.13 0.25 1.00 0.14

EJE F-F / 9-8 M3 4.19 0.13 0.25 1.00 0.14

EJE F-F / 10-9 M3 4.17 0.13 0.25 1.00 0.14

EJE A-A / 5-4 M3 4.16 0.13 0.25 1.00 0.14

EJE A-A / 6-5 M3 4.18 0.13 0.25 1.00 0.14

EJE A-A / 7-6 M3 4.19 0.13 0.25 1.00 0.14

EJE A-A / 8-7 M3 4.19 0.13 0.25 1.00 0.14

EJE A-A / 9-8 M3 4.19 0.13 0.25 1.00 0.14

EJE A-A / 10-9 M3 4.17 0.13 0.25 1.00 0.14

EJE 10-10 M3 6.92 0.23 0.25 2.00 0.80

EJE 8-8 M3 6.92 0.23 0.25 2.00 0.80

EJE 6-6 M3 6.92 0.23 0.25 2.00 0.80

EJE 4-4 M3 6.92 0.23 0.25 2.00 0.80

MENOS ZONA DE VANOS

9/87
HOJA DE METRADO
ACERO KG/ML
PROYECTO : AMPLIACION DE INFRAESTRUCTURA DE LA INSTITUCION EDUCATIVA"SAN JORGE" EN EL CENTRO POBLADO SUPTE SAN JORGE 1/4" 0.250
3/8" 0.580
FECHA : SETIEMBRE DEL 2011 HECHO POR: DAMS 1/2" 1.020
5/8" 1.60
SUB FORMULA : ESTRUCTURAS 3/4" 2.260
1" 4.040
CENTRO POBLADO : SUPTE SAN JORGE DISTRITO : RUPA RUPA PROVINCIA : LEONCIO PRADO

MEDIDAS N SUB TOTAL


N DESCRIPCION DE TOTAL
UND LARGO ANCHO ALTO VECES LONG. AREA VOL. KG.

M3 1.10 0.25 0.25 3.00 -0.21

SS.HH.

EJE B-B / 1-2 M3 3.76 0.13 0.25 1.00 0.12

EJE B-B / 2-3 M3 3.76 0.13 0.25 1.00 0.12

EJE F-F / 1-2 M3 2.78 0.13 0.25 1.00 0.09

EJE F-F / 2-3 M3 2.78 0.13 0.25 1.00 0.09

EJE 1-1 / B-E M3 3.35 0.13 0.25 1.00 0.11

EJE 1-1 / E-F M3 3.35 0.13 0.25 1.00 0.11

EJE 3-3 / B-E M3 3.35 0.13 0.25 1.00 0.11

EJE 3-3 / E-F M3 3.35 0.13 0.25 1.00 0.11

EJE 2-2 / B-E M3 3.35 0.13 0.25 1.00 0.11

EJE 2-2 / E-F M3 3.35 0.13 0.25 1.00 0.11

ENTRE EJE 1-3 / B-F M3 2.16 0.13 0.25 4.00 0.28

M3 0.80 0.13 0.25 4.00 0.10

M3 1.41 0.13 0.25 8.00 0.37

AREA ADMINISTRATIVA Y SS.HH.

EJE H-H / 13-14 M3 3.85 0.13 0.25 1.00 0.13

EJE H-H / 14-15 M3 3.85 0.13 0.25 1.00 0.13

EJE I-I / 13-14 M3 3.85 0.13 0.25 1.00 0.13

EJE I-I / 14-15 M3 3.85 0.13 0.25 1.00 0.13

EJE 13-13 / H-I M3 3.47 0.13 0.25 1.00 0.11

EJE 14-14 / I-H M3 3.57 0.13 0.25 1.00 0.12

EJE 15-15 / I-H M3 4.45 0.13 0.25 1.00 0.14

ESCALERA

M3 4.32 0.23 0.25 2.00 0.50

M3 3.24 0.13 0.25 1.00 0.11

01.03.03.02 ENCOFRADO Y DESENCOFRADO NORMAL DE SOBRECIMIENTO H=0.40 79.08


AULAS

EJE F-F / 5-4 M2 4.16 0.25 2.00 2.08

EJE F-F / 6-5 M2 4.18 0.25 2.00 2.09

EJE F-F / 7-6 M2 4.19 0.25 2.00 2.10

EJE F-F / 8-7 M2 4.19 0.25 2.00 2.10

EJE F-F / 9-8 M2 4.19 0.25 2.00 2.10

EJE F-F / 10-9 M2 4.17 0.25 2.00 2.09

EJE A-A / 5-4 M2 4.16 0.25 2.00 2.08

EJE A-A / 6-5 M2 4.18 0.25 2.00 2.09

EJE A-A / 7-6 M2 4.19 0.25 2.00 2.10

EJE A-A / 8-7 M2 4.19 0.25 2.00 2.10

EJE A-A / 9-8 M2 4.19 0.25 2.00 2.10

EJE A-A / 10-9 M2 4.17 0.25 2.00 2.09

EJE 10-10 M2 6.92 0.25 4.00 6.92

EJE 8-8 M2 6.92 0.25 4.00 6.92

EJE 6-6 M2 6.92 0.25 4.00 6.92

EJE 4-4 M2 6.92 0.25 4.00 6.92

MENOS ZONA DE VANOS M2 1.10 0.25 4.00 -1.10

SS.HH.

EJE B-B / 1-2 M2 3.76 0.25 1.00 0.94

EJE B-B / 2-3 M2 3.76 0.25 1.00 0.94

EJE F-F / 1-2 M2 2.78 0.25 1.00 0.70

EJE F-F / 2-3 M2 2.78 0.25 1.00 0.70

EJE 1-1 / B-E M2 3.35 0.25 1.00 0.84

10/87
HOJA DE METRADO
ACERO KG/ML
PROYECTO : AMPLIACION DE INFRAESTRUCTURA DE LA INSTITUCION EDUCATIVA"SAN JORGE" EN EL CENTRO POBLADO SUPTE SAN JORGE 1/4" 0.250
3/8" 0.580
FECHA : SETIEMBRE DEL 2011 HECHO POR: DAMS 1/2" 1.020
5/8" 1.60
SUB FORMULA : ESTRUCTURAS 3/4" 2.260
1" 4.040
CENTRO POBLADO : SUPTE SAN JORGE DISTRITO : RUPA RUPA PROVINCIA : LEONCIO PRADO

MEDIDAS N SUB TOTAL


N DESCRIPCION DE TOTAL
UND LARGO ANCHO ALTO VECES LONG. AREA VOL. KG.

EJE 1-1 / E-F M2 3.35 0.25 1.00 0.84

EJE 3-3 / B-E M2 3.35 0.25 1.00 0.84

EJE 3-3 / E-F M2 3.35 0.25 1.00 0.84

EJE 2-2 / B-E M2 3.35 0.25 1.00 0.84

EJE 2-2 / E-F M2 3.35 0.25 1.00 0.84

ENTRE EJE 1-3 / B-F M2 2.16 0.25 4.00 2.16

M2 0.80 0.25 4.00 0.80

M2 1.41 0.25 8.00 2.82

AREA ADMINISTRATIVA Y SS.HH.

EJE H-H / 13-14 M2 3.85 0.25 1.00 0.96

EJE H-H / 14-15 M2 3.85 0.25 1.00 0.96

EJE I-I / 13-14 M2 3.85 0.25 1.00 0.96

EJE I-I / 14-15 M2 3.85 0.25 1.00 0.96

EJE 13-13 / H-I M2 3.47 0.25 1.00 0.87

EJE 14-14 / I-H M2 3.57 0.25 1.00 0.89

EJE 15-15 / I-H M2 4.45 0.25 1.00 1.11

ESCALERA

M2 4.32 0.25 2.00 2.16

M2 3.24 0.25 1.00 0.81

01.03.04 BASE DE ASTA DE BANDERA

01.03.04.01 CONCRETO EN BASE DE ASTA DE BANDERA F'C=175 KG/CM2 M3 0.79

01.04.00 OBRAS DE CONCRETO ARMADO


01.04.01 ZAPATAS
01.04.01.01 CONCRETO EN ZAPATAS F'C =210 KG/CM2 M3 124.75
AULAS

Z-1 M3 2.80 2.80 0.50 3.00 11.76

Z-2 M3 4.00 3.60 0.50 2.00 14.40

Z-3 M3 2.10 2.10 0.50 3.00 6.62

Z-4 M3 4.35 4.25 0.50 2.00 18.49

Z-5 M3 3.40 3.08 0.50 2.00 10.47

Z-5 M3 3.65 3.40 0.50 2.00 12.41

SS.HH.

Z-6 M3 2.30 2.30 0.50 6.00 15.87

Z-7 M3 2.30 2.30 0.50 3.00 7.94

AREA ADMINISTRATIVA Y SS.HH.

Z-8 M3 2.30 2.12 0.50 1.00 2.44

M3 2.00 1.90 0.50 2.00 3.80

Z-9 M3 2.03 1.90 0.50 1.00 1.93

Z-10 M3 2.40 2.30 0.50 2.00 5.52

ESCALERA

M3 5.92 4.43 0.50 1.00 13.11

01.04.01.02 ACERO PARA ZAPATAS FY=4200KG/CM2 - GRADO 60 KG 3562.64


AULAS

ZAPATA-1 CANT. KG/ML

5/8" @0.22
2.80 13.00 1.550 3.00 169.26
13 fierros 2.80 13.00 1.550 3.00 169.26
5/8" @0.22

13 fierros

11/87
HOJA DE METRADO
ACERO KG/ML
PROYECTO : AMPLIACION DE INFRAESTRUCTURA DE LA INSTITUCION EDUCATIVA"SAN JORGE" EN EL CENTRO POBLADO SUPTE SAN JORGE 1/4" 0.250
3/8" 0.580
FECHA : SETIEMBRE DEL 2011 HECHO POR: DAMS 1/2" 1.020
5/8" 1.60
SUB FORMULA : ESTRUCTURAS 3/4" 2.260
1" 4.040
CENTRO POBLADO : SUPTE SAN JORGE DISTRITO : RUPA RUPA PROVINCIA : LEONCIO PRADO
5/8" @0.22

MEDIDAS N SUB TOTAL


N DESCRIPCION DE TOTAL
UND LARGO ANCHO ALTO VECES LONG. AREA VOL. KG.

ZAPATA -2

5/8" @0.22

4.00 18.00 1.550 2.00 223.20

18 fierros 3.60 16.00 1.550 2.00 178.56


5/8" @0.22

16 fierros

ZAPATA -3

5/8" @0.22

2.10 10.00 1.550 3.00 97.65

10 fierros 2.10 10.00 1.550 3.00 97.65


5/8" @0.22

10 fierros

ZAPATA -4

5/8" @0.22

20 fierros 4.35 20.00 1.550 2.00 269.70


5/8" @0.22

4.25 19.00 1.550 2.00 250.33

19 fierros

ZAPATA -5

5/8" @0.22

3.65 17.00 1.550 2.00 192.36

17 fierros 3.40 16.00 1.550 2.00 168.64


5/8" @0.22

16 fierros

ZAPATA -5

5/8" @0.22 3.40 16.00 1.550 2.00 168.64

3.08 14.00 1.550 2.00 133.67

16 fierros
5/8" @0.22

14 fierros

SS.HH.

ZAPATA -6

5/8" @0.22 2.30 10.00 1.550 6.00 213.90

12/87
HOJA DE METRADO
ACERO KG/ML
PROYECTO : AMPLIACION DE INFRAESTRUCTURA DE LA INSTITUCION EDUCATIVA"SAN JORGE" EN EL CENTRO POBLADO SUPTE SAN JORGE 1/4" 0.250
3/8" 0.580
FECHA : SETIEMBRE DEL 2011 HECHO POR: DAMS 1/2" 1.020
5/8" 1.60
SUB FORMULA : ESTRUCTURAS 3/4" 2.260
1" 4.040
CENTRO POBLADO : SUPTE SAN JORGE DISTRITO : RUPA RUPA PROVINCIA : LEONCIO PRADO

MEDIDAS N SUB TOTAL


N DESCRIPCION DE TOTAL
UND LARGO ANCHO ALTO VECES LONG. AREA VOL. KG.

2.30 10.00 1.550 6.00 213.90

10 fierros
5/8" @0.22

10 fierros

ZAPATA -7

5/8" @0.22 2.30 10.00 1.550 3.00 106.95

2.30 10.00 1.550 3.00 106.95

10 fierros
5/8" @0.22

10 fierros

AREA ADMINISTRATIVA Y SS.HH.

ZAPATA -8

5/8" @0.22 2.30 10.00 1.550 1.00 35.65

2.12 10.00 1.550 1.00 32.86

10 fierros 2.00 9.00 1.550 2.00 55.80


5/8" @0.22

1.90 9.00 1.550 2.00 53.01

10 fierros

ZAPATA -9

5/8" @0.22 2.00 9.00 1.550 1.00 27.90

1.90 9.00 1.550 1.00 26.51

13 fierros
5/8" @0.22

13 fierros

ZAPATA -10

5/8" @0.22 2.40 11.00 1.550 2.00 81.84

2.30 10.00 1.550 2.00 71.30

11 fierros
5/8" @0.22

10 fierros

ESCALERA

ZAPATA -ESCALERA

5/8" @0.20 5.92 29.00 1.550 1.00 266.10

4.43 22.00 1.550 1.00 151.06

29 fierros
5/8" @0.20

13/87
HOJA DE METRADO
ACERO KG/ML
PROYECTO : AMPLIACION DE INFRAESTRUCTURA DE LA INSTITUCION EDUCATIVA"SAN JORGE" EN EL CENTRO POBLADO SUPTE SAN JORGE 1/4" 0.250
3/8" 0.580
FECHA : SETIEMBRE DEL 2011 HECHO POR: DAMS 1/2" 1.020
5/8" 1.60
SUB FORMULA : ESTRUCTURAS 3/4" 2.260
1" 4.040
CENTRO POBLADO : SUPTE SAN JORGE DISTRITO : RUPA RUPA PROVINCIA : LEONCIO PRADO

MEDIDAS N SUB TOTAL


N DESCRIPCION DE TOTAL
UND LARGO ANCHO ALTO VECES LONG. AREA VOL. KG.
5/8" @0.20

22 fierros

01.04.02 VIGAS DE CIMENTACION


01.04.02.01 CONCRETO EN VIGAS DE CIMENTACION F'C= 210 KG/CM2 M3 35.07
AULAS

EJE A-A / 4-10 M3 8.40 0.35 0.70 3.00 6.17

EJE F-F / 4-10 M3 8.40 0.35 0.70 3.00 6.17

EJE 4-4 / A-F M3 8.37 0.60 1.20 1.00 6.03

EJE 6-6 / A-F M3 8.37 0.60 1.20 1.00 6.03

EJE 8-8 / A-F M3 8.37 0.60 1.20 1.00 6.03

EJE 10-10 / A-F M3 8.37 0.60 1.20 1.00 6.03

DESCUENTO DE EJE A-A /4-10 EN ZAPATA M3 18.80 0.35 0.40 -1.00 -2.63

DESCUENTO DE EJE F-F /4-10 EN ZAPATA M3 18.80 0.35 0.40 -1.00 -2.63

DESCUENTO DE EJE 4-4 / A-F, 10-10/ A-F EN ZAPATA M3 4.00 0.60 0.40 -2.00 -1.92

DESCUENTO DE EJE 6-6 /A-F, 8-8/ A-F EN ZAPATA M3 4.73 0.60 0.40 -2.00 -2.27

SS.HH.

EJE B-B / 1-3 M3 3.83 0.30 0.60 2.00 1.38

EJE F-F / 1-3 M3 3.83 0.30 0.60 2.00 1.38

EJE 1-1 / B-F M3 7.77 0.30 0.60 1.00 1.40

EJE 2-2 / B-F M3 7.77 0.30 0.60 1.00 1.40

EJE 3-3 / B-F M3 7.77 0.30 0.60 1.00 1.40

DESCUENTO DE EJE B-B / 1-3, F-F / 1-3 EN ZAPATA M3 4.30 0.30 0.40 -2.00 -1.03

DESCUENTO DE EJE 1-1 / B-F, 2-2 / B-F, 3-3 /B-F EN ZAPATA M3 4.30 0.30 0.40 -3.00 -1.55

AREA ADMINISTRATIVA Y SS.HH.

EJE H-H / 13-15 M3 9.06 0.30 0.60 1.00 1.63

EJE I-I / 13-15 M3 8.93 0.30 0.60 1.00 1.61

EJE 13-13 / H-I M3 4.53 0.30 0.60 1.00 0.82

EJE 15-15 / H-I M3 4.53 0.30 0.60 1.00 0.82

DESCUENTO DE EJE H-H / 13-15 EN ZAPATA M3 5.91 0.30 0.40 -1.00 -0.71

DESCUENTO DE EJE I-I / 13-15 EN ZAPATA M3 5.18 0.30 0.40 -1.00 -0.62

DESCUENTO DE EJE 13-13 / H-I, 15-15 / H-I M3 2.60 0.30 0.40 -2.00 -0.62

01.04.02.02 ENCOFRADO Y DESENCOFRADO EN VIGAS DE CIMENTACION M2 180.96


AULAS

EJE A-A / 4-10 M2 8.40 0.70 6.00 35.28

EJE F-F / 4-10 M2 8.40 0.70 6.00 35.28

EJE 4-4 / A-F M2 8.37 1.20 2.00 20.09

EJE 6-6 / A-F M2 8.37 1.20 2.00 20.09

EJE 8-8 / A-F M2 8.37 1.20 2.00 20.09

EJE 10-10 / A-F M2 8.37 1.20 2.00 20.09

DESCUENTO DE EJE A-A /4-10 EN ZAPATA M2 18.80 0.40 0.20 -15.04

DESCUENTO DE EJE F-F /4-10 EN ZAPATA M2 18.80 0.40 -2.00 -15.04

DESCUENTO DE EJE 4-4 / A-F, 10-10/ A-F EN ZAPATA M2 4.00 0.40 -4.00 -6.40

14/87
HOJA DE METRADO
ACERO KG/ML
PROYECTO : AMPLIACION DE INFRAESTRUCTURA DE LA INSTITUCION EDUCATIVA"SAN JORGE" EN EL CENTRO POBLADO SUPTE SAN JORGE 1/4" 0.250
3/8" 0.580
FECHA : SETIEMBRE DEL 2011 HECHO POR: DAMS 1/2" 1.020
5/8" 1.60
SUB FORMULA : ESTRUCTURAS 3/4" 2.260
1" 4.040
CENTRO POBLADO : SUPTE SAN JORGE DISTRITO : RUPA RUPA PROVINCIA : LEONCIO PRADO

MEDIDAS N SUB TOTAL


N DESCRIPCION DE TOTAL
UND LARGO ANCHO ALTO VECES LONG. AREA VOL. KG.

DESCUENTO DE EJE 6-6 /A-F, 8-8/ A-F EN ZAPATA M2 4.73 0.40 -4.00 -7.56

SS.HH.

EJE B-B / 1-3 M2 3.83 0.60 4.00 9.19

EJE F-F / 1-3 M2 3.83 0.60 4.00 9.19

EJE 1-1 / B-F M2 7.77 0.60 2.00 9.32

EJE 2-2 / B-F M2 7.77 0.60 2.00 9.32

EJE 3-3 / B-F M2 7.77 0.60 2.00 9.32

DESCUENTO DE EJE B-B / 1-3, F-F / 1-3 EN ZAPATA M2 4.30 0.40 -4.00 -6.88

DESCUENTO DE EJE 1-1 / B-F, 2-2 / B-F, 3-3 /B-F EN ZAPATA M2 4.30 0.40 -6.00 -10.32

AREA ADMINISTRATIVA Y SS.HH.

EJE H-H / 13-15 M2 9.06 0.60 4.00 21.74

EJE I-I / 13-15 M2 8.93 0.60 4.00 21.43

EJE 13-13 / H-I M2 4.53 0.60 2.00 5.44

EJE 15-15 / H-I M2 4.53 0.60 2.00 5.44

DESCUENTO DE EJE H-H / 13-15 EN ZAPATA M2 5.91 0.40 -2.00 -4.73

DESCUENTO DE EJE I-I / 13-15 EN ZAPATA M2 5.18 0.40 -2.00 -4.14

DESCUENTO DE EJE 13-13 / H-I, 15-15 / H-I M2 2.60 0.40 -4.00 -4.16

01.04.02.03 ACERO FY = 4200 KG/CM2 GRADO 60 EN VIGAS DE CIMENTACI KG 4088.77


AULAS

VIGA CIMENTACION EJE A-A; EJE F-F CANT. KG/ML

Refuerzo lon.

33/4"

0.30 18.94 0.30 kg 2.00 1.02 2.00 19.54 79.72

0.3 33/4" 0.30 3.00 1.02 2.00 19.98 122.28

19.38

33/4" 3.00 1.02 2.00 15.23 93.21

15.23

43/4"

0.30 8.70 4.00 1.02 2.00 9.00 73.44

43/4"

5.50 0.30 4.00 1.02 2.00 5.80 47.33

0.30 33/4"

7.30 3.00 1.02 2.00 7.60 46.51

33/4" 0.30

3.01 3.00 1.02 2.00 3.31 20.26

estribos

### 1@0.05 , 3@0.10,RESTO @0.30m 120.00 0.58 2.00 1.21 168.43

0.29

VIGA CIMENTACION EJE 4-4; EJE 6-6; EJE 8-8; EJE 10-10 CANT. KG/ML

Refuerzo lon.

43/4"

0.30 8.37 0.30 4.00 1.02 4.00 8.97 146.39

15/87
HOJA DE METRADO
ACERO KG/ML
PROYECTO : AMPLIACION DE INFRAESTRUCTURA DE LA INSTITUCION EDUCATIVA"SAN JORGE" EN EL CENTRO POBLADO SUPTE SAN JORGE 1/4" 0.250
3/8" 0.580
FECHA : SETIEMBRE DEL 2011 HECHO POR: DAMS 1/2" 1.020
5/8" 1.60
SUB FORMULA : ESTRUCTURAS 3/4" 2.260
1" 4.040
CENTRO POBLADO : SUPTE SAN JORGE DISTRITO : RUPA RUPA PROVINCIA : LEONCIO PRADO

MEDIDAS N SUB TOTAL


N DESCRIPCION DE TOTAL
UND LARGO ANCHO ALTO VECES LONG. AREA VOL. KG.

43/4" 4.00 1.02 4.00 8.67 141.49

0.30 8.37 0.30

4.00 1.02 4.00 8.37 136.60

0.30 25/8" 0.30

8.37

0.30 23/4" 0.30 4.00 1.02 4.00 8.97 146.39

8.37

0.3 25/8" 0.30 4.00 0.58 4.00 8.97 83.24

8.37

1@0.05 , 3@0.10,RESTO @0.30m 30.00 0.58 2.00 0.90 31.32

### 3/8"

0.60

SS.HH.

VIGA CIMENTACION EJE 1-1; EJE 2-2; EJE 3-3 CANT. KG/ML

Refuerzo lon.

33/4"

0.30 7.77 0.30 3.00 1.02 3.00 8.37 76.84

0.3 23/4" 0.30 2.00 1.02 3.00 8.37 51.22

7.77

estribos

### 1@0.05 , 3@0.10,RESTO @0.30m 38.00 0.58 3.00 1.06 70.09

0.24

VIGA CIMENTACION EJE B-B; EJE F-F CANT. KG/ML

Refuerzo lon.

33/4"

0.30 8.57 0.30 3.00 1.02 2.00 9.17 56.12

0.3 23/4" 0.30 2.00 1.02 2.00 9.17 37.41

8.57

estribos

### 1@0.05 , 3@0.10,RESTO @0.30m 40.00 0.58 2.00 1.06 49.18

0.24

AREA ADMINISTRATIVA Y SS.HH.

VIGA CIMENTACION EJE 13-13; EJE 15-15; CANT. KG/ML

Refuerzo lon.

33/4"

0.30 5.13 0.30 3.00 1.02 2.00 5.73 35.07

0.3 23/4" 0.30 2.00 1.02 2.00 5.73 23.38

5.13

estribos

### 1@0.05 , 3@0.10,RESTO @0.30m 22.00 0.58 2.00 1.06 27.05

0.24

VIGA CIMENTACION EJE H-H; EJE I-I CANT. KG/ML

Refuerzo lon.

16/87
HOJA DE METRADO
ACERO KG/ML
PROYECTO : AMPLIACION DE INFRAESTRUCTURA DE LA INSTITUCION EDUCATIVA"SAN JORGE" EN EL CENTRO POBLADO SUPTE SAN JORGE 1/4" 0.250
3/8" 0.580
FECHA : SETIEMBRE DEL 2011 HECHO POR: DAMS 1/2" 1.020
5/8" 1.60
SUB FORMULA : ESTRUCTURAS 3/4" 2.260
1" 4.040
CENTRO POBLADO : SUPTE SAN JORGE DISTRITO : RUPA RUPA PROVINCIA : LEONCIO PRADO

MEDIDAS N SUB TOTAL


N DESCRIPCION DE TOTAL
UND LARGO ANCHO ALTO VECES LONG. AREA VOL. KG.

33/4"

0.30 9.06 0.30 3.00 1.02 2.00 9.66 59.12

0.3 23/4" 0.30 2.00 1.02 2.00 9.53 38.88

8.93

estribos

### 1@0.05 , 3@0.10,RESTO @0.30m 38.00 0.58 2.00 1.06 46.72

0.24

01.04.03 FALSO PISO


01.04.03.01 CONCRETO EN FALSO PISO DE 4" DE 1:8C:H PARA PSO PULIDO 349.27
AULA 1 M2 8.81 7.91 1.00 69.69

AULA 2 M2 8.78 7.91 1.00 69.45

AULA 3 M2 8.81 7.91 1.00 69.69

SS.HH. M2 7.34 4.06 2.00 59.60

AREA ADMINISTRATIVA Y SS.HH. M2 4.30 4.84 2.00 41.62

ESCALERA M2 7.05 3.95 1.00 27.85

01.04.03.02 ACERO EN FALSO PISO FY=4200 GRADO 60 591.75

AULAS KG 382.50

SS.HH 108.00

AREA ADMINISTRATIVA Y SERVICIOS HIGIENICOS 101.25

01.04.04 SOBRECIMIENTO ARMADO

01.04.04.01 CONCRETO EN SOBRECIMIENTO ARMADO F'C=175 KG/CM2 M3 11.30


AULAS

EJE 4-4 ENTRE F-F Y A-A M3 6.95 0.22 0.50 1.00 0.76

EJE 6-6 ENTRE F-F Y A-A M3 6.95 0.22 0.50 1.00 0.76

EJE 8-8 ENTRE F-F Y A-A M3 6.95 0.22 0.50 1.00 0.76

EJE 10-10 ENTRE F-F Y A-A M3 6.95 0.22 0.50 1.00 0.76

EJE F-F ENTRE 10-4 M3 4.16 0.13 0.50 1.00 0.27

M3 4.18 0.13 0.50 1.00 0.27

M3 4.19 0.13 0.50 1.00 0.27

M3 4.19 0.13 0.50 1.00 0.27

M3 4.19 0.13 0.50 1.00 0.27

M3 4.17 0.13 0.50 1.00 0.27

EJE A-A ENTRE 10-4 M3 4.16 0.13 0.50 1.00 0.27

M3 4.18 0.13 0.50 1.00 0.27

M3 4.19 0.13 0.50 1.00 0.27

M3 4.19 0.13 0.50 1.00 0.27

M3 4.19 0.13 0.50 1.00 0.27

M3 4.17 0.13 0.50 1.00 0.27

SS.HH.

EJE 1-1 / B-E M3 3.35 0.13 0.50 1.00 0.22

EJE 1-1 / E-F M3 3.35 0.13 0.50 1.00 0.22

EJE 2-2 / B-E M3 3.35 0.13 0.50 1.00 0.22

EJE 2-2 / E-F M3 3.35 0.13 0.50 1.00 0.22

EJE 3-3 / B-E M3 3.35 0.13 0.50 1.00 0.22

17/87
HOJA DE METRADO
ACERO KG/ML
PROYECTO : AMPLIACION DE INFRAESTRUCTURA DE LA INSTITUCION EDUCATIVA"SAN JORGE" EN EL CENTRO POBLADO SUPTE SAN JORGE 1/4" 0.250
3/8" 0.580
FECHA : SETIEMBRE DEL 2011 HECHO POR: DAMS 1/2" 1.020
5/8" 1.60
SUB FORMULA : ESTRUCTURAS 3/4" 2.260
1" 4.040
CENTRO POBLADO : SUPTE SAN JORGE DISTRITO : RUPA RUPA PROVINCIA : LEONCIO PRADO

MEDIDAS N SUB TOTAL


N DESCRIPCION DE TOTAL
UND LARGO ANCHO ALTO VECES LONG. AREA VOL. KG.

EJE 3-3 / E-F M3 3.35 0.13 0.50 1.00 0.22

EJE B-B /1-3 M3 3.75 0.13 0.50 1.00 0.24

EJE F-F / 1-3 M3 3.75 0.13 0.50 1.00 0.24

AREA ADMINISTRATIVA Y SS.HH.

EJE 13-13 / H-I M3 4.45 0.13 0.50 1.00 0.29

EJE 15-15 / H-I M3 4.45 0.13 0.50 1.00 0.29

EJE H-H / 13-14 M3 3.85 0.13 0.50 1.00 0.25

EJE H-H / 14-15 M3 3.85 0.13 0.50 1.00 0.25

EJE I-I / 13-15 M3 3.85 0.13 0.50 1.00 0.25

EJE I-I / 14-15 M3 3.85 0.13 0.50 1.00 0.25

01.04.04.02 ENCOFRADO Y DESENCOFRADO DE SOBRECIMIENTO ARMAD M2 152.59


AULAS

EJE 4-4 ENTRE F-F Y A-A M3 6.95 0.22 0.50 1.00 0.76

EJE 6-6 ENTRE F-F Y A-A M3 6.95 0.22 0.50 1.00 0.76

EJE 8-8 ENTRE F-F Y A-A M3 6.95 0.22 0.50 1.00 0.76

EJE 10-10 ENTRE F-F Y A-A M3 6.95 0.22 0.50 1.00 0.76

EJE F-F ENTRE 10-4 M3 4.16 0.13 0.50 1.00 0.27

M3 4.18 0.13 0.50 1.00 0.27

M3 4.19 0.13 0.50 1.00 0.27

M3 4.19 0.13 0.50 1.00 0.27

M3 4.19 0.13 0.50 1.00 0.27

M3 4.17 0.13 0.50 1.00 0.27

EJE A-A ENTRE 10-4 M3 4.16 0.13 0.50 1.00 0.27

M3 4.18 0.13 0.50 1.00 0.27

M3 4.19 0.13 0.50 1.00 0.27

M3 4.19 0.13 0.50 1.00 0.27

M3 4.19 0.13 0.50 1.00 0.27

M3 4.17 0.13 0.50 1.00 0.27

SS.HH.

EJE 1-1 / B-E M3 3.35 0.13 0.50 1.00 0.22

EJE 1-1 / E-F M3 3.35 0.13 0.50 1.00 0.22

EJE 2-2 / B-E M3 3.35 0.13 0.50 1.00 0.22

EJE 2-2 / E-F M3 3.35 0.13 0.50 1.00 0.22

EJE 3-3 / B-E M3 3.35 0.13 0.50 1.00 0.22

EJE 3-3 / E-F M3 3.35 0.13 0.50 1.00 0.22

EJE B-B /1-3 M3 3.75 0.13 0.50 1.00 0.24

EJE F-F / 1-3 M3 3.75 0.13 0.50 1.00 0.24

AREA ADMINISTRATIVA Y SS.HH.

EJE 13-13 / H-I M3 4.45 0.13 0.50 1.00 0.29

EJE 15-15 / H-I M3 4.45 0.13 0.50 1.00 0.29

EJE H-H / 13-14 M3 3.85 0.13 0.50 1.00 0.25

EJE H-H / 14-15 M3 3.85 0.13 0.50 1.00 0.25

EJE I-I / 13-15 M3 3.85 0.13 0.50 1.00 0.25

EJE I-I / 14-15 M3 3.85 0.13 0.50 1.00 0.25

01.04.04.03 ACERO EN VIGA DE SOBRECIMIENTO FY=4200 KG/CM2 GRADO KG 1193.99


AULAS

EJE F-F Y A-A ENTRE 10-4 CANT. KG/ML

Refuerzo lon.

0.40 27.20 0.40 4.00 1.02 2.00 28.00 228.48 224.00

18/87
HOJA DE METRADO
ACERO KG/ML
PROYECTO : AMPLIACION DE INFRAESTRUCTURA DE LA INSTITUCION EDUCATIVA"SAN JORGE" EN EL CENTRO POBLADO SUPTE SAN JORGE 1/4" 0.250
3/8" 0.580
FECHA : SETIEMBRE DEL 2011 HECHO POR: DAMS 1/2" 1.020
5/8" 1.60
SUB FORMULA : ESTRUCTURAS 3/4" 2.260
1" 4.040
CENTRO POBLADO : SUPTE SAN JORGE DISTRITO : RUPA RUPA PROVINCIA : LEONCIO PRADO

MEDIDAS N SUB TOTAL


N DESCRIPCION DE TOTAL
UND LARGO ANCHO ALTO VECES LONG. AREA VOL. KG.

27.20 2.00 1.02 2.00 27.20 110.98 108.80

332.80

estribos

### 1@0.05 , RESTO @0.20m 126.00 0.58 2.00 1.62 236.78 408.24

0.20

EJE 10-10.,8-8,6-6,4-4 ENTRE F-F Y A-A CANT. KG/ML

Refuerzo lon.

0.40 8.23 0.40 4.00 1.02 4.00 9.03 147.37 144.48

8.23 2.00 1.02 4.00 8.23 67.16 65.84

210.32

estribos

### 1@0.05 , RESTO @0.20m 36.00 0.58 4.00 1.62 135.30 233.28

0.20 109.80

SS.HH.

EJE 1-1 ; EJE 2-2; EJE 3-3 ENTRE B-F CANT. KG/ML

Refuerzo lon.

0.40 3.35 0.40 4.00 1.02 6.00 4.15 101.59 99.60

3.35 2.00 1.02 6.00 3.35 41.00 40.20

139.80

estribos

### 1@0.05 , RESTO @0.20m 16.00 0.58 6.00 1.62 90.20 155.52

0.20

EJE B-B; EJE F-F ENTRE 1-3 CANT. KG/ML

Refuerzo lon.

0.40 3.75 0.40 4.00 1.02 4.00 4.55 74.26 72.80

3.75 2.00 1.02 4.00 3.75 30.60 30.00

102.80

estribos

### 1@0.05 , RESTO @0.20m 18.00 0.58 4.00 1.62 67.65 116.64

0.20 109.80

AREA ADMINISTRATIVA Y SS.HH.

EJE 13-13; EJE 15-15 ENTRE H-I CANT. KG/ML

Refuerzo lon.

0.40 4.45 0.40 4.00 1.02 2.00 5.25 42.84 42.00

4.45 2.00 1.02 2.00 4.45 18.16 17.80

estribos

### 1@0.05 , RESTO @0.20m 22.00 1.02 2.00 1.62 72.71 71.28

0.20

19/87
HOJA DE METRADO
ACERO KG/ML
PROYECTO : AMPLIACION DE INFRAESTRUCTURA DE LA INSTITUCION EDUCATIVA"SAN JORGE" EN EL CENTRO POBLADO SUPTE SAN JORGE 1/4" 0.250
3/8" 0.580
FECHA : SETIEMBRE DEL 2011 HECHO POR: DAMS 1/2" 1.020
5/8" 1.60
SUB FORMULA : ESTRUCTURAS 3/4" 2.260
1" 4.040
CENTRO POBLADO : SUPTE SAN JORGE DISTRITO : RUPA RUPA PROVINCIA : LEONCIO PRADO

MEDIDAS N SUB TOTAL


N DESCRIPCION DE TOTAL
UND LARGO ANCHO ALTO VECES LONG. AREA VOL. KG.

EJE H-H; EJE I-I ENTRE 13-14-15 CANT. KG/ML

Refuerzo lon.

0.40 3.85 0.40 4.00 1.02 4.00 4.65 75.89 74.40

3.85 2.00 1.02 4.00 3.85 31.42 30.80

105.20

estribos

### 1@0.05 , RESTO @0.20m 19.00 0.58 4.00 1.62 71.41 123.12

0.20 109.80

01.04.05 COLUMNAS
01.04.05.01 CONCRETO EN COLUMNETAS F'C=175 KG/CM2 M3 9.20
AULAS

EJE F-F M3 0.20 0.13 2.85 6.00 0.44

M3 0.20 0.13 1.35 12.00 0.42

EJE A-A M3 0.20 0.13 1.95 12.00 0.61

2DO PISO

EJE F-F M3 0.20 0.13 2.90 6.00 0.45

M3 0.20 0.13 1.30 12.00 0.41

EJE A-A M3 0.20 0.13 1.95 12.00 0.61

PARAPETOS M3 0.25 0.13 1.05 10.00 0.34

SS.HH.

EJE 1-1 ENTRE B-F M3 0.20 0.13 3.20 4.00 0.33

EJE 2-2 ENTRE B-F M3 0.20 0.13 4.10 4.00 0.43

EJE 3-3 ENTRE B-F M3 0.20 0.13 3.20 4.00 0.33

EJE B-B ENTRE 1-3 M3 0.20 0.13 4.35 4.00 0.45

EJE F-F ENTRE 1-3 M3 0.20 0.13 4.35 4.00 0.45

ENTRE 2-2 / B-F M3 0.20 0.13 3.30 24.00 2.06

AREA ADMINISTRATIVA Y SS.HH.

EJE 13-13 ENTRE H-I M3 0.20 0.13 2.20 2.00 0.11

EJE 14-14 ENTRE H-I M3 0.20 0.13 4.10 2.00 0.21

EJE 15-15 ENTRE H-I M3 0.20 0.13 3.30 2.00 0.17

EJE H-H ENTRE 13-15 M3 0.20 0.13 4.10 4.00 0.43

EJE I-I ENTRE 13-15 M3 0.20 0.13 4.10 4.00 0.43

ESCALERA

EJE C-C ENTRE 11-12 M3 0.20 0.13 2.73 2.00 0.14

01.04.05.02 CONCRETO EN COLUMNAS F'C=210 KG/CM2 M3 39.62


AULAS

1ER PISO

COLUMNA TIPO 1 PRIMER PISO M3 0.60 0.30 6.70 6.00 7.24 17.96

COLUMNA TIPO 2 PRIMER PISO M3 0.60 0.30 6.70 8.00 9.65

COLUMNA TIPO 3 PRIMER PISO M3 0.25 0.22 4.85 4.00 1.07

2DO PISO

COLUMNA TIPO 1 PRIMER PISO M3 0.60 0.30 3.67 6.00 3.96 10.29

COLUMNA TIPO 2 PRIMER PISO M3 0.60 0.30 3.67 8.00 5.28

COLUMNA TIPO 3 PRIMER PISO M3 0.25 0.22 4.75 4.00 1.05

20/87
HOJA DE METRADO
ACERO KG/ML
PROYECTO : AMPLIACION DE INFRAESTRUCTURA DE LA INSTITUCION EDUCATIVA"SAN JORGE" EN EL CENTRO POBLADO SUPTE SAN JORGE 1/4" 0.250
3/8" 0.580
FECHA : SETIEMBRE DEL 2011 HECHO POR: DAMS 1/2" 1.020
5/8" 1.60
SUB FORMULA : ESTRUCTURAS 3/4" 2.260
1" 4.040
CENTRO POBLADO : SUPTE SAN JORGE DISTRITO : RUPA RUPA PROVINCIA : LEONCIO PRADO

MEDIDAS N SUB TOTAL


N DESCRIPCION DE TOTAL
UND LARGO ANCHO ALTO VECES LONG. AREA VOL. KG.

SS.HH.

COLUMNA TIPO 4 M3 0.30 0.30 6.37 6.00 3.44

M3 0.30 0.30 7.38 3.00 1.99

AREA ADMINISTRATIVA Y SS.HH.

COLUMNA TIPO 5 M3 0.40 0.30 5.50 6.00 3.96

ESCALERA

EJE 11/C M3 0.30 0.30 10.81 1.00 0.97

EJE 11/F M3 0.30 0.30 9.97 1.00 0.90

EJE 12/C M3 0.30 0.30 10.81 1.00 0.97

EJE 12/F M3 0.30 0.30 9.97 1.00 0.90

ENTRE EJE 11-12/C-F M3 0.30 0.15 10.84 2.00 0.98

01.04.05.03 ENCOFRADO Y DESENCOFRADO EN COLUMNAS M2 699.50


AULAS

1ER PISO

COLUMNA TIPO 1 PRIMER PISO M2 1.80 6.70 6.00 72.36

COLUMNA TIPO 2 PRIMER PISO M2 1.80 6.70 8.00 96.48

COLUMNA TIPO 3 PRIMER PISO M2 0.94 4.85 4.00 18.24

2DO PISO 0.00

COLUMNA TIPO 1 PRIMER PISO M2 1.80 3.67 6.00 39.64

COLUMNA TIPO 2 PRIMER PISO M2 1.80 3.67 8.00 52.85

COLUMNA TIPO 3 PRIMER PISO M2 0.94 4.75 4.00 17.86

COLUMNETAS 1 ER PISO

EJE A-A ENTRE EJES 10-4 M2 0.20 3.50 24.00 16.80

M2 0.13 3.50 12.00 5.46

EJE F-F ENTRE 10-4 M2 0.20 2.95 24.00 14.16

M2 0.13 2.95 12.00 4.60

M2 0.20 4.50 12.00 10.80

M2 0.13 4.50 6.00 3.51

COLUMNETAS 2DO PISO

EJE A-A ENTRE EJES 10-4 M2 0.20 1.90 24.00 9.12

M2 0.13 1.90 12.00 2.96

EJE F-F ENTRE 10-4 M2 0.20 1.30 24.00 6.24

M2 0.13 1.30 12.00 2.03

M2 0.20 2.90 12.00 6.96

M2 0.13 2.90 6.00 2.26

PARAPETOS

M2 0.25 1.05 20.00 5.25

M2 0.15 1.05 20.00 3.15

SS.HH.

COLUMNAS TIPO 4 M2 1.20 6.37 6.00 45.86

M2 1.20 7.38 3.00 26.57

COLUMNETAS

EJE 1-1 ENTRE B-F M2 0.66 3.20 4.00 8.45

EJE 2-2 ENTRE B-F M2 0.66 4.10 4.00 10.82

EJE 3-3 ENTRE B-F M2 0.66 3.20 4.00 8.45

EJE B-B ENTRE 1-3 M2 0.66 4.35 4.00 11.48

EJE F-F ENTRE 1-3 M2 0.66 4.35 4.00 11.48

21/87
HOJA DE METRADO
ACERO KG/ML
PROYECTO : AMPLIACION DE INFRAESTRUCTURA DE LA INSTITUCION EDUCATIVA"SAN JORGE" EN EL CENTRO POBLADO SUPTE SAN JORGE 1/4" 0.250
3/8" 0.580
FECHA : SETIEMBRE DEL 2011 HECHO POR: DAMS 1/2" 1.020
5/8" 1.60
SUB FORMULA : ESTRUCTURAS 3/4" 2.260
1" 4.040
CENTRO POBLADO : SUPTE SAN JORGE DISTRITO : RUPA RUPA PROVINCIA : LEONCIO PRADO

MEDIDAS N SUB TOTAL


N DESCRIPCION DE TOTAL
UND LARGO ANCHO ALTO VECES LONG. AREA VOL. KG.

ENTRE 2-2 / B-F M2 0.66 3.30 24.00 52.27

AREA ADMINISTRATIVA Y SS.HH.

COLUMNAS TIPO 5 M2 1.40 5.50 6.00 46.20

COLUMNETAS

EJE 13-13 ENTRE H-I M2 0.66 2.20 2.00 2.90

EJE 14-14 ENTRE H-I M2 0.66 4.10 2.00 5.41

EJE 15-15 ENTRE H-I M2 0.66 3.30 2.00 4.36

EJE H-H ENTRE 13-15 M2 0.66 4.10 4.00 10.82

EJE I-I ENTRE 13-15 M2 0.66 4.10 4.00 10.82

ESCALERA

EJE 11/C M2 1.20 10.81 1.00 12.97

EJE 11/F M2 1.20 9.97 1.00 11.96

EJE 12/C M2 1.20 10.81 1.00 12.97

EJE 12/F M2 1.20 9.97 1.00 11.96

ENTRE EJE 11-12/C-F M2 0.75 10.84 2.00 16.26

COLUMNETAS

EJE C-C ENTRE 11-12 M2 0.20 2.73 4.00 2.18

01.04.05.04 ACERO EN COLUMNAS FY=4200KG/CM2 - GRADO 60 KG 7542.39


AULAS

COLUMNA-1 CANT. KG/ML

### 6 5/8 6.00 1.60 6.00 10.93 629.57

###

### 2 3/4 2.00 2.26 6.00 11.00 298.32

###

0.52 ESTRIBOS 68.00 0.58 6.00 1.74 411.75 709.92

3/8 2@0.05,3@0.1,3@0.15,resto a 0.25

0.25

COLUMNA-2 CANT. KG/ML

### 8 5/8 8.00 1.60 8.00 10.93 1119.23 699.52

###

0.52 ESTRIBOS 68.00 0.58 8.00 1.74 549.00 946.56

3/8 2@0.05,3@0.1,3@0.15,resto a 0.25

0.25

COLUMNA-3 CANT. KG/ML

### 6 1/2 6.00 1.02 4.00 10.25 250.92 246.00

22/87
HOJA DE METRADO
ACERO KG/ML
PROYECTO : AMPLIACION DE INFRAESTRUCTURA DE LA INSTITUCION EDUCATIVA"SAN JORGE" EN EL CENTRO POBLADO SUPTE SAN JORGE 1/4" 0.250
3/8" 0.580
FECHA : SETIEMBRE DEL 2011 HECHO POR: DAMS 1/2" 1.020
5/8" 1.60
SUB FORMULA : ESTRUCTURAS 3/4" 2.260
1" 4.040
CENTRO POBLADO : SUPTE SAN JORGE DISTRITO : RUPA RUPA PROVINCIA : LEONCIO PRADO

MEDIDAS N SUB TOTAL


N DESCRIPCION DE TOTAL
UND LARGO ANCHO ALTO VECES LONG. AREA VOL. KG.

###

0.20 ESTRIBOS 66.00 0.58 6.00 0.95 218.20 376.20


3/8 2@0.05,3@0.1,3@0.15,resto a 0.25

0.20

COLUMNA-AMARRE EJE A-A CANT. KG/ML

PRIMER PISO

### 4 3/8 4.00 0.58 12.00 3.55 98.83 170.40

###

0.15 ESTRIBOS 16.00 0.25 12.00 0.63 30.24 120.96

1 /4 1@0.05,2@0.1,resto a 0.25

0.09

SEGUNDO PISO

### 4 3/8 4.00 0.58 12.00 2.15 59.86

###

0.15 ESTRIBOS 16.00 0.25 12.00 0.63 30.24

1 /4 1@0.05,2@0.1,resto a 0.25

0.09

COLUMNA-AMARRE EJE F-F

PRIMER PIS MURO FRONTAL H=1.40

0.20

### 4 3/8 4.00 0.58 12.00 3.12 86.86

###

0.15 ESTRIBOS 14.00 0.25 12.00 0.63 26.46

1 /4 1@0.05,2@0.1,resto a 0.25

0.09

SEGUNDO PISO

0.25

23/87
HOJA DE METRADO
ACERO KG/ML
PROYECTO : AMPLIACION DE INFRAESTRUCTURA DE LA INSTITUCION EDUCATIVA"SAN JORGE" EN EL CENTRO POBLADO SUPTE SAN JORGE 1/4" 0.250
3/8" 0.580
FECHA : SETIEMBRE DEL 2011 HECHO POR: DAMS 1/2" 1.020
5/8" 1.60
SUB FORMULA : ESTRUCTURAS 3/4" 2.260
1" 4.040
CENTRO POBLADO : SUPTE SAN JORGE DISTRITO : RUPA RUPA PROVINCIA : LEONCIO PRADO

MEDIDAS N SUB TOTAL


N DESCRIPCION DE TOTAL
UND LARGO ANCHO ALTO VECES LONG. AREA VOL. KG.

### 4 3/8 4.00 0.58 12.00 2.15 59.86

###

0.15 ESTRIBOS 12.00 0.25 12.00 0.63 22.68

1 /4 1@0.05,2@0.1,resto a 0.25

0.09

PRIMER PIS MURO ALTO H=2.95

0.20

### 4 3/8 4.00 0.58 6.00 3.80 52.90 91.20

###

0.15 ESTRIBOS 24.00 0.25 6.00 0.63 22.68 90.72

1 /4 1@0.05,2@0.1,resto a 0.25

0.09

SEGUNDO PISO

0.25

### 4 3/8 4.00 0.58 6.00 3.90 54.29

###

0.15 ESTRIBOS 25.00 0.25 6.00 0.63 23.63

1 /4 1@0.05,2@0.1,resto a 0.25

0.09

PARAPETO

### 4 3/8 4.00 0.58 7.00 1.50 24.36

###

0.15 ESTRIBOS 24.00 0.25 7.00 0.54 22.68

24/87
HOJA DE METRADO
ACERO KG/ML
PROYECTO : AMPLIACION DE INFRAESTRUCTURA DE LA INSTITUCION EDUCATIVA"SAN JORGE" EN EL CENTRO POBLADO SUPTE SAN JORGE 1/4" 0.250
3/8" 0.580
FECHA : SETIEMBRE DEL 2011 HECHO POR: DAMS 1/2" 1.020
5/8" 1.60
SUB FORMULA : ESTRUCTURAS 3/4" 2.260
1" 4.040
CENTRO POBLADO : SUPTE SAN JORGE DISTRITO : RUPA RUPA PROVINCIA : LEONCIO PRADO

MEDIDAS N SUB TOTAL


N DESCRIPCION DE TOTAL
UND LARGO ANCHO ALTO VECES LONG. AREA VOL. KG.

1 /4 1@0.05,2@0.1,resto a 0.25

0.09

SS.HH.

COLUMNA-4 CANT. KG/ML

### 4 5/8 8.52 4 5/8 4.00 0.58 6.00 7.96 110.80

4.00 0.58 3.00 8.77 61.04

### 0.25

### 4 1/2 8.52 4 1/2 4.00 1.60 6.00 7.96 305.66

4.00 1.02 3.00 8.77 107.34

### 0.25

0.25 ESTRIBOS 43.00 0.58 6.00 1.20 179.57 309.60

3/8 2@0.05,3@0.1,3@0.15,resto a 0.25 54.00 0.58 3.00 1.20 112.75

0.25

COLUMNETAS CANT. KG/ML

EJE 1-1: EJE 3-3 ENTRE B-F

0.20

### 4 3/8 4.00 0.58 8.00 3.65 67.74

###

0.15 ESTRIBOS 16.00 0.25 8.00 0.63 20.16

1 /4 1@0.05,2@0.1,resto a 0.25

0.09

EJE 2-2:ENTRE B-F CANT. KG/ML

0.20

### 4 3/8 4.00 0.58 4.00 4.55 42.22

###

0.15 ESTRIBOS 20.00 0.25 4.00 0.63 12.60

1 /4 1@0.05,2@0.1,resto a 0.25

0.09

EJE B-B: EJE F-F ENTRE 1-3 CANT. KG/ML

0.20

### 4 3/8 4.00 0.58 8.00 4.80 89.09

25/87
HOJA DE METRADO
ACERO KG/ML
PROYECTO : AMPLIACION DE INFRAESTRUCTURA DE LA INSTITUCION EDUCATIVA"SAN JORGE" EN EL CENTRO POBLADO SUPTE SAN JORGE 1/4" 0.250
3/8" 0.580
FECHA : SETIEMBRE DEL 2011 HECHO POR: DAMS 1/2" 1.020
5/8" 1.60
SUB FORMULA : ESTRUCTURAS 3/4" 2.260
1" 4.040
CENTRO POBLADO : SUPTE SAN JORGE DISTRITO : RUPA RUPA PROVINCIA : LEONCIO PRADO

MEDIDAS N SUB TOTAL


N DESCRIPCION DE TOTAL
UND LARGO ANCHO ALTO VECES LONG. AREA VOL. KG.

###

0.15 ESTRIBOS 21.00 0.25 8.00 0.63 26.46

1 /4 1@0.05,2@0.1,resto a 0.25

0.09

ENTRE EJE 2-2: EJE B-F CANT. KG/ML

0.20

### 4 3/8 4.00 0.58 24.00 3.65 203.23

###

0.15 ESTRIBOS 16.00 0.25 24.00 0.63 60.48

1 /4 1@0.05,2@0.1,resto a 0.25

0.09

AREA ADMINISTRATIVA Y SS.HH.

COLUMNA-5 CANT. KG/ML

### 4 5/8 4.00 0.58 6.00 5.75 80.04

###

### 4 1/2 4.00 0.58 6.00 5.75 80.04

###

0.32 ESTRIBOS 46.00 0.58 6.00 1.34 214.51 369.84

3/8 2@0.05,3@0.1,3@0.15,resto a 0.25

0.25

COLUMNETAS CANT. KG/ML

EJE 13-13: ENTRE H-I

0.20

### 4 3/8 4.00 0.58 2.00 2.65 12.30

###

0.15 ESTRIBOS 11.00 0.25 2.00 0.63 3.47

1 /4 1@0.05,2@0.1,resto a 0.25

0.09

EJE 14-14: ENTRE H-I CANT. KG/ML

0.20

### 4 3/8 4.00 #REF! 2.00 4.55 #REF!

26/87
HOJA DE METRADO
ACERO KG/ML
PROYECTO : AMPLIACION DE INFRAESTRUCTURA DE LA INSTITUCION EDUCATIVA"SAN JORGE" EN EL CENTRO POBLADO SUPTE SAN JORGE 1/4" 0.250
3/8" 0.580
FECHA : SETIEMBRE DEL 2011 HECHO POR: DAMS 1/2" 1.020
5/8" 1.60
SUB FORMULA : ESTRUCTURAS 3/4" 2.260
1" 4.040
CENTRO POBLADO : SUPTE SAN JORGE DISTRITO : RUPA RUPA PROVINCIA : LEONCIO PRADO

MEDIDAS N SUB TOTAL


N DESCRIPCION DE TOTAL
UND LARGO ANCHO ALTO VECES LONG. AREA VOL. KG.

###

0.15 ESTRIBOS 20.00 0.25 2.00 0.63 6.30

1 /4 1@0.05,2@0.1,resto a 0.25

0.09

EJE 15-15: ENTRE H-I CANT. KG/ML

0.20

### 4 3/8 4.00 0.58 2.00 3.75 17.40

###

0.15 ESTRIBOS 16.00 0.25 2.00 0.63 5.04

1 /4 1@0.05,2@0.1,resto a 0.25

0.09

EJE H-H: EJE I-I ENTRE 13-15 CANT. KG/ML

0.20

### 4 3/8 4.00 0.58 8.00 4.55 84.45

###

0.15 ESTRIBOS 20.00 0.25 8.00 0.63 25.20

1 /4 1@0.05,2@0.1,resto a 0.25

0.09

ESCALERA

COLUMNA-4 CANT. KG/ML

### 4 5/8" 8.52 4 5/8" 4.00 0.58 2.00 11.71 54.33

4.00 0.58 2.00 8.77 40.69

### 0.25

### 4 1/2 8.52 4 1/2 4.00 1.02 2.00 11.71 95.55

4.00 1.02 2.00 8.77 71.56

### 0.25

0.25 ESTRIBOS 81.00 0.58 4.00 1.20 225.50 388.80

3/8 2@0.05,3@0.1,3@0.15,resto a 0.25 71.00 0.58 4.00 1.20 197.66

0.25

COLUMNA-PLACA

### 4 1/2 4.00 1.02 2.00 11.48 93.68

27/87
HOJA DE METRADO
ACERO KG/ML
PROYECTO : AMPLIACION DE INFRAESTRUCTURA DE LA INSTITUCION EDUCATIVA"SAN JORGE" EN EL CENTRO POBLADO SUPTE SAN JORGE 1/4" 0.250
3/8" 0.580
FECHA : SETIEMBRE DEL 2011 HECHO POR: DAMS 1/2" 1.020
5/8" 1.60
SUB FORMULA : ESTRUCTURAS 3/4" 2.260
1" 4.040
CENTRO POBLADO : SUPTE SAN JORGE DISTRITO : RUPA RUPA PROVINCIA : LEONCIO PRADO

MEDIDAS N SUB TOTAL


N DESCRIPCION DE TOTAL
UND LARGO ANCHO ALTO VECES LONG. AREA VOL. KG.

###

0.25 ESTRIBOS 67.00 0.58 4.00 0.70 108.81 187.60

3/8 2@0.05,3@0.1,3@0.15,resto a 0.25

COLUMNETAS CANT. KG/ML

EJE C-C ENTRE 11-12

0.20

### 4 3/8 4.00 0.58 2.00 3.65 16.94

###

0.15 ESTRIBOS 16.00 0.25 2.00 0.63 5.04

1 /4 1@0.05,2@0.1,resto a 0.25

0.09

01.04.06 PLACA
01.04.06.01 CONCRETO EN PLACA F'C= 210 KG/CM2 M3 3.75
ESCALERA M3 10.84 2.40 10.00 1.00 25.01 3.75

01.04.06.02 ENCOFRADO Y DESENCOFRADO NORMAL EN PLACA M2 70.45


ESCALERA M2 10.84 2.40 10.00 1.00 25.01

01.04.06.03 ACERO EN PLACA F'Y=4200 KG/CM2-GRADO 60 KG 440.61


ESCALERA CANT. KG/ML

KG 2.91 54.00 1.02 20.00 3.11 3425.98

KG 11.17 11.00 0.58 20.00 11.37 1450.81

01.04.07 VIGAS
01.04.07.01 CONCRETO EN VIGUETAS F'C=175 KG/CM2 M3 2.53
AULAS

VIGUETAS DE ARRIOSTRE 1ER PISO

PARA VANOS 3 M3 1.35 0.13 0.10 3.00 0.05 0.58

PARA VANOS 2 M3 4.15 0.13 0.10 3.00 0.16

PARA VANOS 1 M3 4.15 0.13 0.10 6.00 0.32

TABIQUE ALTO M3 1.30 0.13 0.10 3.00 0.05

VIGUETAS DE ARRIOSTRE 2DO PISO

PARA VANOS 3 M3 1.35 0.13 0.10 3.00 0.05

PARA VANOS 2 M3 4.15 0.13 0.10 3.00 0.16

PARA VANOS 1 M3 4.15 0.13 0.10 6.00 0.32

TABIQUE ALTO M3 1.30 0.13 0.10 3.00 0.05

SS.HH.

EJE B-B / 1-3 M3 3.75 0.13 0.10 2.00 0.10

EJE F-F / 1-3 M3 2.78 0.13 0.10 2.00 0.07

EJE 1-1 / B-F M3 3.35 0.13 0.10 2.00 0.09

EJE 2-2 / B-F M3 3.35 0.13 0.10 2.00 0.09

EJE 3-3 / B-F M3 3.35 0.13 0.10 2.00 0.09

28/87
HOJA DE METRADO
ACERO KG/ML
PROYECTO : AMPLIACION DE INFRAESTRUCTURA DE LA INSTITUCION EDUCATIVA"SAN JORGE" EN EL CENTRO POBLADO SUPTE SAN JORGE 1/4" 0.250
3/8" 0.580
FECHA : SETIEMBRE DEL 2011 HECHO POR: DAMS 1/2" 1.020
5/8" 1.60
SUB FORMULA : ESTRUCTURAS 3/4" 2.260
1" 4.040
CENTRO POBLADO : SUPTE SAN JORGE DISTRITO : RUPA RUPA PROVINCIA : LEONCIO PRADO

MEDIDAS N SUB TOTAL


N DESCRIPCION DE TOTAL
UND LARGO ANCHO ALTO VECES LONG. AREA VOL. KG.

ENTRE EJE 2-2 / B-F M3 2.94 0.13 0.10 2.00 0.08

M3 2.82 0.13 0.10 2.00 0.07

M3 1.41 0.13 0.10 8.00 0.15

AREA ADMINISTRATIVA Y SS.HH.

EJE H-H / 13-15 M3 3.85 0.13 0.10 2.00 0.10

EJE I-I / 13-15 M3 3.85 0.13 0.10 2.00 0.10

EJE 13-13 / H-I M3 3.50 0.13 0.10 1.00 0.05

EJE 14-14 / H-I M3 3.57 0.13 0.10 1.00 0.05

EJE 15-15 / H-I M3 4.45 0.13 0.10 1.00 0.06

ESCALERA

EJE C-C/11-12 M3 3.24 0.13 0.10 2.00 0.08

EJE F-F/11-12 M3 1.88 0.13 0.10 1.00 0.02

M3 1.94 0.13 0.10 1.00 0.03

M3 3.93 0.13 0.10 1.00 0.05

01.04.07.02 CONCRETO EN VIGAS F'C=210 KG/CM2 M3 74.01


AULAS

VIGA 1ER PISO

VIGA PRINCIPAL P-1 EJE 9-9,7-7,5-5 M3 7.17 0.30 0.70 3.00 4.52 17.83

VIGA SECUNDARIA S-1 10-10,8-8,6-6,4-4 M3 3.48 0.30 0.50 4.00 2.09

VIGA SECUNDARIA S-2 10-10,8-8,6-6,4-4 M3 3.48 0.30 0.50 4.00 2.09

VIGA SECUNDARIA S-3 10-10,8-8,6-6,4-4 M3 2.20 0.30 0.40 4.00 1.06

M3 2.20 0.30 0.40 4.00 0.53

VIGA P-2 , F-F M3 4.19 0.30 0.50 6.00 3.77

VIGA P-3 , A-A M3 4.19 0.30 0.50 6.00 3.77

VIGA 2DO PISO

VIGA SECUNDARIA S-4 M3 12.85 0.30 0.50 7.00 13.49 32.57

TRIANGULO M3 0.75 0.30 0.20 7.00 0.16

TRIANGULO M3 2.08 0.30 0.60 7.00 1.31

VIGA SECUNDARIA S-1 10-10,8-8,6-6,4-4 M3 3.36 0.30 0.50 4.00 2.01

VIGA SECUNDARIA S-2 10-10,8-8,6-6,4-4 M3 3.36 0.30 0.50 4.00 2.02

VIGA P-2 , F-F M3 4.19 0.30 0.50 6.00 3.77

VIGA P-3 , A-A M3 4.19 0.30 0.50 6.00 3.77

VIGA CUMBRERA M3 4.19 0.60 0.20 6.00 3.02

VIGA VOLADO M3 4.19 0.15 0.40 12.00 3.02

SS.HH.

EJE B-B / 1-3 M3 3.83 0.30 0.50 2.00 1.15

EJE E-E / 1-3 M3 3.83 0.30 0.50 2.00 1.15

EJE F-F / 1-3 M3 3.83 0.30 0.50 2.00 1.15

EJE 1-1 / B-F M3 7.77 0.30 0.50 1.00 1.17

EJE 2-2 / B-F M3 7.77 0.30 0.50 1.00 1.17

EJE 3-3 / B-F M3 7.77 0.30 0.50 1.00 1.17

TRIANGULO M3 11.76 0.30 0.50 3.00 2.65

VIGA CUMBRERA M3 8.60 0.25 0.20 2.00 0.86

VIGA VOLADO M3 2.26 0.30 0.30 6.00 1.22

VIGA BORDE M3 8.60 0.15 0.40 2.00 1.03

AREA ADMINISTRATIVA Y SS.HH.

EJE H-H / 13-15 M3 10.21 0.30 0.40 1.00 1.23

EJE I-I / 13-15 M3 10.08 0.30 0.40 1.00 1.21

EJE 13-13 / H-I M3 4.53 0.30 0.40 1.00 0.54

EJE 14-14 / H-I M3 4.53 0.30 0.40 1.00 0.54

29/87
HOJA DE METRADO
ACERO KG/ML
PROYECTO : AMPLIACION DE INFRAESTRUCTURA DE LA INSTITUCION EDUCATIVA"SAN JORGE" EN EL CENTRO POBLADO SUPTE SAN JORGE 1/4" 0.250
3/8" 0.580
FECHA : SETIEMBRE DEL 2011 HECHO POR: DAMS 1/2" 1.020
5/8" 1.60
SUB FORMULA : ESTRUCTURAS 3/4" 2.260
1" 4.040
CENTRO POBLADO : SUPTE SAN JORGE DISTRITO : RUPA RUPA PROVINCIA : LEONCIO PRADO

MEDIDAS N SUB TOTAL


N DESCRIPCION DE TOTAL
UND LARGO ANCHO ALTO VECES LONG. AREA VOL. KG.

EJE 15-15 / H-I M3 4.53 0.30 0.40 1.00 0.54

ESCALERA

EJE 11-11/C-G M3 7.18 0.30 0.40 1.00 0.86

M3 4.92 0.30 0.40 1.00 0.59

EJE 12-12/C-G M3 7.18 0.30 0.40 1.00 0.86

M3 4.92 0.30 0.40 1.00 0.59

EJE C-C/11-12 M3 3.32 0.30 0.40 2.00 0.80

EJE F-F / 11-12 M3 3.32 0.30 0.20 2.00 0.40

M3 3.32 0.15 0.40 1.00 0.20

DESCANSO M3 3.32 0.30 0.10 2.00 0.20

TECHO M3 8.16 0.30 0.30 2.00 1.47

CUMBRERA M3 3.92 0.25 0.20 2.00 0.39

M3 3.92 0.15 0.40 2.00 0.47

01.04.07.03 ENCOFRADO Y DESENCOFRADO NORMAL EN VIGAS 575.28


AULAS

VIGUETAS DE ARRIOSTRE 1ER PISO

PARA VANOS 3 M2 1.35 0.10 6.00 0.81

PARA VANOS 2 M2 4.15 0.10 6.00 2.49

PARA VANOS 1 M2 4.15 0.10 12.00 4.98

TABIQUE ALTO M2 1.30 0.10 6.00 0.78

VIGUETAS DE ARRIOSTRE 2DO PISO

PARA VANOS 3 M2 1.35 0.10 6.00 0.81

PARA VANOS 2 M2 4.15 0.10 6.00 2.49

PARA VANOS 1 M2 4.15 0.10 12.00 4.98

TABIQUE ALTO M2 1.30 0.10 6.00 0.78

VIGA 1ER PISO

VIGA PRINCIPAL P-1 EJE 9-9,7-7,5-5 M2 7.17 0.70 6.00 30.11

7.17 0.30 6.00 12.91

VIGA SECUNDARIA S-1 10-10,8-8,6-6,4-4 M2 3.48 0.50 8.00 13.92

VIGA SECUNDARIA S-2 10-10,8-8,6-6,4-4 M2 3.48 0.50 8.00 13.92

VIGA SECUNDARIA S-3 10-10,8-8,6-6,4-4 M2 2.20 0.40 8.00 7.04

M2 2.20 0.40 8.00 7.04

VIGA P-2 , F-F M2 4.19 0.50 12.00 25.14

VIGA P-3 , A-A M2 4.19 0.50 12.00 25.14

VIGA 2DO PISO

VIGA SECUNDARIA S-4 M2 12.85 0.50 7.00 44.98

12.85 0.30 7.00 26.99

TRIANGULO M2 0.75 0.20 14.00 1.05

TRIANGULO M2 2.08 0.60 14.00 8.74

VIGA SECUNDARIA S-1 10-10,8-8,6-6,4-4 M2 3.48 0.50 8.00 13.92

VIGA SECUNDARIA S-2 10-10,8-8,6-6,4-4 M2 3.48 0.50 8.00 13.92

VIGA P-2 , F-F M2 4.19 0.50 12.00 25.14

VIGA P-3 , A-A M2 4.19 0.50 12.00 25.14

VIGA CUMBRERA M2 4.19 0.20 12.00 10.06

VIGA VOLADO M2 4.19 0.40 12.00 20.11

SS.HH.

EJE B-B / 1-3 M2 3.83 0.50 4.00 7.66

BASE M2 3.83 0.30 2.00 2.30

30/87
HOJA DE METRADO
ACERO KG/ML
PROYECTO : AMPLIACION DE INFRAESTRUCTURA DE LA INSTITUCION EDUCATIVA"SAN JORGE" EN EL CENTRO POBLADO SUPTE SAN JORGE 1/4" 0.250
3/8" 0.580
FECHA : SETIEMBRE DEL 2011 HECHO POR: DAMS 1/2" 1.020
5/8" 1.60
SUB FORMULA : ESTRUCTURAS 3/4" 2.260
1" 4.040
CENTRO POBLADO : SUPTE SAN JORGE DISTRITO : RUPA RUPA PROVINCIA : LEONCIO PRADO

MEDIDAS N SUB TOTAL


N DESCRIPCION DE TOTAL
UND LARGO ANCHO ALTO VECES LONG. AREA VOL. KG.

EJE E-E / 1-3 M2 3.83 0.50 4.00 7.66

BASE M2 3.83 0.30 2.00 2.30

EJE F-F / 1-3 M2 3.83 0.50 4.00 7.66

BASE M2 3.83 0.30 2.00 2.30

EJE 1-1 / B-F M2 7.47 0.50 2.00 7.47

BASE M2 7.47 0.30 1.00 2.24

EJE 2-2 / B-F M2 7.47 0.50 2.00 7.47

BASE M2 7.47 0.30 1.00 2.24

EJE 3-3 / B-F M2 7.47 0.50 2.00 7.47

BASE M2 7.47 0.30 1.00 2.24

TRIANGULO M2 11.16 0.50 6.00 33.48

BASE M2 11.16 0.30 3.00 10.04

VIGA CUMBRERA M2 7.70 0.25 2.00 3.85

VIGA VOLADO M2 2.26 0.30 12.00 8.14

BASE M2 2.26 0.30 6.00 4.07

VIGA BORDE M2 7.70 0.40 4.00 12.32

BASE M2 7.70 0.15 2.00 2.31

AREA ADMINISTRATIVA Y SS.HH.

EJE H-H / 13-15 M2 9.01 0.20 2.00 3.60

BASE M2 9.01 0.30 1.00 2.70

EJE I-I / 13-15 M2 8.88 0.20 2.00 3.55

BASE M2 8.88 0.30 1.00 2.66

EJE 13-13 / H-I M2 4.53 0.20 2.00 1.81

BASE M2 4.53 0.30 1.00 1.36

EJE 14-14 / H-I M2 4.53 0.20 2.00 1.81

BASE M2 4.53 0.30 1.00 1.36

EJE 15-15 / H-I M2 4.53 0.20 2.00 1.81

BASE M2 4.53 0.30 1.00 1.36

ESCALERA

VIGUETAS

EJE C-C/11-12 M3 3.24 0.10 4.00 1.30

EJE F-F/11-12 M3 1.88 0.10 2.00 0.38

M3 1.94 0.10 2.00 0.39

M3 3.93 0.10 2.00 0.79

VIGAS

EJE 11-11/C-G M3 7.18 0.40 2.00 5.74

M3 7.18 0.30 1.00 2.15

M3 4.92 0.40 2.00 3.94

M3 4.92 0.30 1.00 1.48

EJE 12-12/C-G M3 7.18 0.40 2.00 5.74

M3 7.18 0.30 1.00 2.15

M3 4.92 0.40 2.00 3.94

M3 4.92 0.30 1.00 1.48

EJE C-C/11-12 M3 3.32 0.40 4.00 5.31

M3 3.32 0.30 2.00 1.99

EJE F-F / 11-12 M3 3.32 0.20 4.00 2.66

M3 3.32 0.30 2.00 1.99

M3 3.32 0.40 2.00 2.66

M3 3.32 0.15 1.00 0.50

DESCANSO M3 3.32 0.10 4.00 1.33

M3 3.32 0.30 2.00 1.99

TECHO M3 8.16 0.30 4.00 9.79

31/87
HOJA DE METRADO
ACERO KG/ML
PROYECTO : AMPLIACION DE INFRAESTRUCTURA DE LA INSTITUCION EDUCATIVA"SAN JORGE" EN EL CENTRO POBLADO SUPTE SAN JORGE 1/4" 0.250
3/8" 0.580
FECHA : SETIEMBRE DEL 2011 HECHO POR: DAMS 1/2" 1.020
5/8" 1.60
SUB FORMULA : ESTRUCTURAS 3/4" 2.260
1" 4.040
CENTRO POBLADO : SUPTE SAN JORGE DISTRITO : RUPA RUPA PROVINCIA : LEONCIO PRADO

MEDIDAS N SUB TOTAL


N DESCRIPCION DE TOTAL
UND LARGO ANCHO ALTO VECES LONG. AREA VOL. KG.

M3 8.16 0.30 2.00 4.90

CUMBRERA M3 3.92 0.20 4.00 3.14

M3 3.92 0.25 2.00 1.96

M3 3.92 0.40 4.00 6.27

01.04.07.04 ACERO FY=4200 KG/CM2 GRADO 60 EN VIGAS KG 9309.28


AULAS

VIGA PRINCIPAL P-1 Y VIGA P-3 CANT. KG/ML

Refuerzo lon.

23/4"+15/8"

0.40 10.35 0.20 2.00 2.26 3.00 10.95 148.48

2.00 1.60 3.00 10.35 99.36

0.35 23/4"+15/8" 0.15 2.00 2.26 3.00 10.85 147.13

10.35

ACERO NEGATIVO

45/8"

0.40 2.60 4.00 1.60 3.00 3.00 57.60

45/8"

2.86 0.40 4.00 1.60 3.00 3.26 62.59

45/8"

2.50 0.35 2.00 1.60 3.00 2.85 27.36

estribos

### 1@0.05 , 7@0.1,9@0.15,RESTO @0.20m 57.00 0.58 3.00 2.02 200.34

0.24

VIGA SEGUNDARIA S-1 , S-2 1ER PISO CANT. KG/ML

Refuerz45/8"

0.35 10.23 0.35 4.00 1.60 4.00 10.93 279.81

3.90 0.30 3.00 1.60 4.00 4.20 80.64

estribos

### 1@0.05 , RESTO @0.20m 47.00 0.58 4.00 1.70 185.37

0.24

VIGA SEGUNDARIA S-1 , S-2 2do PISO CANT. KG/ML

Refuerz45/8"

0.35 8.00 0.35 4.00 1.60 4.00 8.70 222.72

estribos

### 1@0.05 , RESTO @0.20m 36.00 0.58 4.00 1.70 141.98

0.24

VIGA SEGUNDARIA S-4 2do PISO CANT. KG/ML

5.00

32/87
HOJA DE METRADO
ACERO KG/ML
PROYECTO : AMPLIACION DE INFRAESTRUCTURA DE LA INSTITUCION EDUCATIVA"SAN JORGE" EN EL CENTRO POBLADO SUPTE SAN JORGE 1/4" 0.250
3/8" 0.580
FECHA : SETIEMBRE DEL 2011 HECHO POR: DAMS 1/2" 1.020
5/8" 1.60
SUB FORMULA : ESTRUCTURAS 3/4" 2.260
1" 4.040
CENTRO POBLADO : SUPTE SAN JORGE DISTRITO : RUPA RUPA PROVINCIA : LEONCIO PRADO

MEDIDAS N SUB TOTAL


N DESCRIPCION DE TOTAL
UND LARGO ANCHO ALTO VECES LONG. AREA VOL. KG.

5.00 1.25 4.00 1.60 7.00 6.60 295.68

5.73 0.40 4.00 1.60 7.00 7.45 333.76

6.94 4.00 1.60 7.00 8.61 385.73

0.35

### 7.30 0.32 4.00 1.60 7.00 8.02 359.30

CUMBRERA
1.00 1.60 7.00 2.64 29.57

1.32 1.32

VOLADO 0.3

0.15 1.35 0.55 1.00 1.60 7.00 2.35 26.32

0.3

1 2.35 0.15 1.00 1.60 7.00 3.75 42.00

VIGA P-1 Y P-2

Refuerz65/8"

0.35 27.19 0.35 6.00 1.60 4.00 27.89 1070.98

estribos

### 1@0.05 , RESTO @0.20m

126.00 0.58 4.00 1.62 473.56

0.24

VIGA CUMBRERA

Refuerz65/8"

27.19 6.00 1.60 1.00 27.19 261.02

estribos

0.15 1@0.05 , RESTO @0.20m

### 126.00 0.58 2.00 1.60 233.86

0.15 1@0.05 , RESTO @0.20m

###

VIGA P-5

Refuerz43/8"

0.35 27.19 0.35 4.00 0.58 3.00 27.89 194.11

estribos

### 1/4" 1@0.05 , RESTO @0.20m

126.00 0.58 3.00 1.14 249.93

0.10

SS.HH.

VIGA PRINCIPAL P-4 EJE 1-1/B-F; EJE 2-2/B-F; EJE 3-3/B-F CANT. KG/ML

Refuerzo lon.

35/8"

0.40 7.61 0.40 3.00 0.58 3.00 8.41 43.90

33/87
HOJA DE METRADO
ACERO KG/ML
PROYECTO : AMPLIACION DE INFRAESTRUCTURA DE LA INSTITUCION EDUCATIVA"SAN JORGE" EN EL CENTRO POBLADO SUPTE SAN JORGE 1/4" 0.250
3/8" 0.580
FECHA : SETIEMBRE DEL 2011 HECHO POR: DAMS 1/2" 1.020
5/8" 1.60
SUB FORMULA : ESTRUCTURAS 3/4" 2.260
1" 4.040
CENTRO POBLADO : SUPTE SAN JORGE DISTRITO : RUPA RUPA PROVINCIA : LEONCIO PRADO

MEDIDAS N SUB TOTAL


N DESCRIPCION DE TOTAL
UND LARGO ANCHO ALTO VECES LONG. AREA VOL. KG.

0.4 35/8" 0.40 3.00 0.58 3.00 8.41 43.90

7.61

estribos

### 1@0.05 , RESTO @0.20m 36.00 0.25 3.00 1.82 49.14

0.24

VIGA SEGUNDARIA P-4 EJE B-B/1-3; EJE E-E/1-3; EJE F-F/1-3 CANT. KG/ML

Refuerz35/8"

0.35 8.60 0.35 3.00 0.58 3.00 9.30 48.55

35/8"

0.35 8.60 0.35 3.00 0.58 3.00 9.30 48.55

estribos

### 1@0.05 , RESTO @0.20m 42.00 0.58 3.00 1.82 133.01

0.24

VIGA TRIANGULO

6.75 0.44 3.00 0.58 3.00 7.44 38.84

6.66 0.44 3.00 0.58 3.00 7.45 38.89

5.57 3.00 0.58 3.00 6.17 32.21

0.25

### 5.03 0.35 3.00 0.58 3.00 5.78 30.17

3.05 2.00 0.58 3.00 3.05 10.61

CUMBRERA

2.00 0.58 1.00 8.60 9.98

4.3 4.3

VOLADO 0.2

0.25 2.1 0.90 3.00 0.58 3.00 3.45 18.01

0.2

0 0.75 0.25 1.00 0.58 7.00 1.60 6.50

estribos

### 1@0.05 , RESTO @0.20m

34/87
HOJA DE METRADO
ACERO KG/ML
PROYECTO : AMPLIACION DE INFRAESTRUCTURA DE LA INSTITUCION EDUCATIVA"SAN JORGE" EN EL CENTRO POBLADO SUPTE SAN JORGE 1/4" 0.250
3/8" 0.580
FECHA : SETIEMBRE DEL 2011 HECHO POR: DAMS 1/2" 1.020
5/8" 1.60
SUB FORMULA : ESTRUCTURAS 3/4" 2.260
1" 4.040
CENTRO POBLADO : SUPTE SAN JORGE DISTRITO : RUPA RUPA PROVINCIA : LEONCIO PRADO

MEDIDAS N SUB TOTAL


N DESCRIPCION DE TOTAL
UND LARGO ANCHO ALTO VECES LONG. AREA VOL. KG.

44.00 0.58 3.00 1.62 124.03

0.24 17.00 0.58 3.00 1.78 52.71

VIGA CUMBRERA

Refuerz65/8"

8.60 4.00 0.58 2.00 8.60 39.90

estribos

0.15 1@0.05 , RESTO @0.20m

### 46.00 0.58 2.00 1.00 53.36

0.15 1@0.05 , RESTO @0.20m

###

VIGA P-5

Refuerz43/8"

0.35 8.60 0.35 4.00 0.58 2.00 9.30 43.15

estribos

### 1/4" 1@0.05 , RESTO @0.20m

46.00 0.25 2.00 1.14 26.22

0.10

AREA ADMINISTRATIVA Y SS.HH.

VIGA PRINCIPAL P-6 EJE H-H/13-15; EJE I-I/13-15; CANT. KG/ML

Refuerzo lon.

35/8"

0.25 10.00 0.25 3.00 0.58 2.00 10.50 36.54

0.25 35/8" 0.25 3.00 0.58 2.00 10.50 36.54

10.00

estribos

### 1@0.05 , RESTO @0.20m 56.00 0.25 2.00 1.82 50.96

0.24

VIGA SEGUNDARIA P-4 EJE 13-13/H-I; EJE 14-14/H-I; EJE 15-15/H-I CANT. KG/ML

Refuerz35/8"

0.25 8.60 0.25 3.00 0.58 3.00 9.10 47.50

35/8"

0.25 8.60 0.25 3.00 0.58 3.00 9.10 47.50

estribos

### 1@0.05 , RESTO @0.20m 40.00 0.25 3.00 1.82 54.60

0.24

ESCALERA

VIGA PRINCIPAL P-6 EJE 11-11/C-F; EJE 12-12/C-F; CANT. KG/ML

Refuerzo lon.

35/8"

0.25 7.02 0.25 3.00 0.58 4.00 7.52 52.34

25/8"

4.20

0.25 35/8" 0.25 3.00 0.58 4.00 7.52 52.34

35/87
HOJA DE METRADO
ACERO KG/ML
PROYECTO : AMPLIACION DE INFRAESTRUCTURA DE LA INSTITUCION EDUCATIVA"SAN JORGE" EN EL CENTRO POBLADO SUPTE SAN JORGE 1/4" 0.250
3/8" 0.580
FECHA : SETIEMBRE DEL 2011 HECHO POR: DAMS 1/2" 1.020
5/8" 1.60
SUB FORMULA : ESTRUCTURAS 3/4" 2.260
1" 4.040
CENTRO POBLADO : SUPTE SAN JORGE DISTRITO : RUPA RUPA PROVINCIA : LEONCIO PRADO

MEDIDAS N SUB TOTAL


N DESCRIPCION DE TOTAL
UND LARGO ANCHO ALTO VECES LONG. AREA VOL. KG.

7.02

estribos

### 1@0.05 , RESTO @0.20m 41.00 0.25 4.00 1.42 58.22

0.24

VIGA SEGUNDARIA P-6 EJE C-C/11-12; EJE F-F/11-12; CANT. KG/ML

Refuerz35/8"

0.25 3.92 0.25 3.00 0.58 4.00 4.42 30.76

35/8"

0.25 3.92 0.25 3.00 0.58 4.00 4.42 30.76

estribos

### 1@0.05 , RESTO @0.20m 21.00 0.25 4.00 1.42 29.82

0.24

VIGA TRIANGULO

1.40 0.44 3.00 0.58 2.00 2.09 7.27

1.42 3.00 0.58 2.00 1.77 6.16

6.87 3.00 0.58 2.00 7.47 26.00

0.25

6.87 0.35 3.00 0.58 2.00 7.22 25.13

3.47 2.00 0.58 2.00 3.47 8.05

CUMBRERA

2.00 0.58 1.00 0.88 1.02

0.44 0.44

VOLADO

0.5 2.4 0.25 3.00 0.58 2.00 3.15 10.96

1 2.4 0.25 1.00 0.58 2.00 3.15 3.65

estribos

### 1@0.05 , RESTO @0.20m

41.00 0.25 2.00 1.62 33.21

0.24 10.00 0.25 2.00 1.78 8.91

VIGA CUMBRERA

Refuerz65/8"

36/87
HOJA DE METRADO
ACERO KG/ML
PROYECTO : AMPLIACION DE INFRAESTRUCTURA DE LA INSTITUCION EDUCATIVA"SAN JORGE" EN EL CENTRO POBLADO SUPTE SAN JORGE 1/4" 0.250
3/8" 0.580
FECHA : SETIEMBRE DEL 2011 HECHO POR: DAMS 1/2" 1.020
5/8" 1.60
SUB FORMULA : ESTRUCTURAS 3/4" 2.260
1" 4.040
CENTRO POBLADO : SUPTE SAN JORGE DISTRITO : RUPA RUPA PROVINCIA : LEONCIO PRADO

MEDIDAS N SUB TOTAL


N DESCRIPCION DE TOTAL
UND LARGO ANCHO ALTO VECES LONG. AREA VOL. KG.

3.92 4.00 0.58 2.00 3.92 18.19

estribos

0.15 1@0.05 , RESTO @0.20m

### 21.00 0.25 2.00 1.00 10.50

0.15 1@0.05 , RESTO @0.20m

###

VIGA P-5

Refuerz43/8"

0.35 3.92 0.35 4.00 0.58 2.00 4.62 21.44

estribos

### 1/4" 1@0.05 , RESTO @0.20m

21.00 0.25 2.00 1.14 11.97

0.10

01.04.08 LOSA ALIGERADA H=0.20M


01.04.08.01 CONCRETO EN LOSAS ALIGERADAS F'C=210 KG/CM2. M3 61.54
AULAS

1ER PISO

VIGUETAS EJE 10-9 M3 4.19 0.10 0.15 19.00 1.19

EJE 9-8 M3 4.20 0.10 0.15 19.00 1.20

EJE 8-7 M3 4.20 0.10 0.15 19.00 1.20

EJE 7-6 M3 4.20 0.10 0.15 19.00 1.20

EJE 6-5 M3 4.20 0.10 0.15 19.00 1.20

EJE 5-4 M3 4.20 0.10 0.15 19.00 1.20

VIGUETAS EN VOLADO

EJE 10-9 M3 4.19 0.10 0.15 6.00 0.38

EJE 9-8 M3 4.20 0.10 0.15 6.00 0.38

EJE 8-7 M3 4.20 0.10 0.15 6.00 0.38

EJE 7-6 M3 4.20 0.10 0.15 6.00 0.38

EJE 6-5 M3 4.20 0.10 0.15 6.00 0.38

EJE 5-4 M3 4.20 0.10 0.15 6.00 0.38

LOSA DE e=0.05 M

EJE 10-9 M3 7.57 4.19 0.05 1.00 1.59

EJE 9-8 M3 7.57 4.20 0.05 1.00 1.59

EJE 8-7 M3 7.57 4.20 0.05 1.00 1.59

EJE 7-6 M3 7.57 4.20 0.05 1.00 1.59

EJE 6-5 M3 7.57 4.20 0.05 1.00 1.59

EJE 5-4 M3 7.57 4.20 0.05 1.00 1.59

LOSA EN VOLADO

EJE 10-9 M3 2.20 4.19 0.05 1.00 0.46

EJE 9-8 M3 2.20 4.20 0.05 1.00 0.46

EJE 8-7 M3 2.20 4.20 0.05 1.00 0.46

EJE 7-6 M3 2.20 4.20 0.05 1.00 0.46

EJE 6-5 M3 2.20 4.20 0.05 1.00 0.46

EJE 5-4 M3 2.20 4.20 0.05 1.00 0.46

2DO PISO

VIGUETAS EJE 10-9 M3 4.19 0.10 0.15 20.00 1.26

EJE 9-8 M3 4.20 0.10 0.15 20.00 1.26

EJE 8-7 M3 4.20 0.10 0.15 20.00 1.26

EJE 7-6 M3 4.20 0.10 0.15 20.00 1.26

37/87
HOJA DE METRADO
ACERO KG/ML
PROYECTO : AMPLIACION DE INFRAESTRUCTURA DE LA INSTITUCION EDUCATIVA"SAN JORGE" EN EL CENTRO POBLADO SUPTE SAN JORGE 1/4" 0.250
3/8" 0.580
FECHA : SETIEMBRE DEL 2011 HECHO POR: DAMS 1/2" 1.020
5/8" 1.60
SUB FORMULA : ESTRUCTURAS 3/4" 2.260
1" 4.040
CENTRO POBLADO : SUPTE SAN JORGE DISTRITO : RUPA RUPA PROVINCIA : LEONCIO PRADO

MEDIDAS N SUB TOTAL


N DESCRIPCION DE TOTAL
UND LARGO ANCHO ALTO VECES LONG. AREA VOL. KG.

EJE 6-5 M3 4.20 0.10 0.15 20.00 1.26

EJE 5-4 M3 4.20 0.10 0.15 20.00 1.26

VIGUETAS EN VOLADO

EJE 10-9 M3 4.19 0.10 0.15 9.00 0.57

EJE 9-8 M3 4.20 0.10 0.15 9.00 0.57

EJE 8-7 M3 4.20 0.10 0.15 9.00 0.57

EJE 7-6 M3 4.20 0.10 0.15 9.00 0.57

EJE 6-5 M3 4.20 0.10 0.15 9.00 0.57

EJE 5-4 M3 4.20 0.10 0.15 9.00 0.57

LOSA DE e=0.05 M

EJE 10-9 M3 8.00 4.19 0.05 1.00 1.68

EJE 9-8 M3 8.00 4.20 0.05 1.00 1.68

EJE 8-7 M3 8.00 4.20 0.05 1.00 1.68

EJE 7-6 M3 8.00 4.20 0.05 1.00 1.68

EJE 6-5 M3 8.00 4.20 0.05 1.00 1.68

EJE 5-4 M3 8.00 4.20 0.05 1.00 1.68

LOSA EN VOLADO

EJE 10-9 M3 4.29 4.19 0.05 1.00 0.90

EJE 9-8 M3 4.29 4.20 0.05 1.00 0.90

EJE 8-7 M3 4.29 4.20 0.05 1.00 0.90

EJE 7-6 M3 4.29 4.20 0.05 1.00 0.90

EJE 6-5 M3 4.29 4.20 0.05 1.00 0.90

EJE 5-4 M3 4.29 4.20 0.05 1.00 0.90

SS.HH.

VIGUETAS ENTRE EJE B-E/1-2 M3 3.84 0.10 0.15 10.00 0.58

ENTRE EJE B-E/2-3 M3 3.84 0.10 0.15 10.00 0.58

ENTRE EJE E-F/1-2 M3 3.84 0.10 0.15 8.00 0.46

ENTRE EJE E-F/2-3 M3 3.84 0.10 0.15 8.00 0.46

VOLADO ENTRE EJE F-G/1-2 M3 3.84 0.10 0.15 5.00 0.29

ENTRE EJE F-G/2-3 M3 3.84 0.10 0.15 5.00 0.29

LOSA DE e=0.05 M

ENTRE EJE B-E/1-2 M3 3.84 0.95 0.05 1.00 0.18

M3 3.84 3.30 0.05 1.00 0.63

ENTRE EJE B-E/2-3 M3 3.84 0.95 0.05 1.00 0.18

M3 3.84 3.30 0.05 1.00 0.63

ENTRE EJE E-F/1-2 M3 3.84 3.29 0.05 1.00 0.63

ENTRE EJE E-F/2-3 M3 3.84 3.29 0.05 1.00 0.63

ENTRE EJE F-G/1-2 M3 3.84 2.13 0.05 1.00 0.41

ENTRE EJE F-G/2-3 M3 3.84 2.13 0.05 1.00 0.41

AREA ADMINISTRATIVA Y SS.HH.

VIGUETAS ENTRE EJE H-I/15-14 M3 4.08 0.10 0.15 11.00 0.67

ENTRE EJE H-I/14-13 M3 4.08 0.10 0.15 11.00 0.67

VOLADO ENTRE EJE H-I/VOL M3 1.00 0.10 0.15 11.00 0.17

LOSA DE e=0.05 M

ENTRE EJE H-I/15-14 M3 4.53 4.08 0.05 1.00 0.92

ENTRE EJE H-I/14-13 M3 4.53 4.08 0.05 1.00 0.92

VOLADO ENTRE EJE H-I/VOL M3 4.53 1.00 0.05 1.00 0.23

ESCALERA

VIGUETAS M3 3.32 0.10 0.15 20.00 1.00

M3 3.32 0.10 0.15 4.00 0.20

LOSA DE e=0.05 M M3 8.16 3.32 0.05 1.00 1.35

38/87
HOJA DE METRADO
ACERO KG/ML
PROYECTO : AMPLIACION DE INFRAESTRUCTURA DE LA INSTITUCION EDUCATIVA"SAN JORGE" EN EL CENTRO POBLADO SUPTE SAN JORGE 1/4" 0.250
3/8" 0.580
FECHA : SETIEMBRE DEL 2011 HECHO POR: DAMS 1/2" 1.020
5/8" 1.60
SUB FORMULA : ESTRUCTURAS 3/4" 2.260
1" 4.040
CENTRO POBLADO : SUPTE SAN JORGE DISTRITO : RUPA RUPA PROVINCIA : LEONCIO PRADO

MEDIDAS N SUB TOTAL


N DESCRIPCION DE TOTAL
UND LARGO ANCHO ALTO VECES LONG. AREA VOL. KG.

M3 3.32 1.78 0.05 1.00 0.30

01.04.08.02 ENCOFRADO Y DESENCOFRADO NORMAL EN LOSAS ALIGERADAS 694.63


AULAS

1ER PISO M2 7.57 4.19 1.00 31.72

M2 7.57 4.20 1.00 31.79

M2 7.57 4.18 1.00 31.64

M2 4.19 2.20 1.00 9.22

M2 4.20 2.20 1.00 9.24

M2 4.18 2.20 1.00 9.20

2DO PISO

M2 8.20 4.19 1.00 34.36 154.11


M2 8.20 4.20 1.00 34.44

M2 8.20 4.18 1.00 34.28

M2 2.55 4.19 1.00 10.68

M2 2.55 4.20 1.00 10.71

M2 2.55 4.18 1.00 10.66

M2 1.51 4.19 1.00 6.33

M2 1.51 4.20 1.00 6.34

M2 1.51 4.18 1.00 6.31

SS.HH.

ENTRE EJE B-E/1-2 M2 3.84 0.95 1.00 3.65

M2 3.84 3.30 1.00 12.67

ENTRE EJE B-E/2-3 M2 3.84 0.95 1.00 3.65

M2 3.84 3.30 1.00 12.67

ENTRE EJE E-F/1-2 M2 3.84 3.29 1.00 12.63

ENTRE EJE E-F/2-3 M2 3.84 3.29 1.00 12.63

ENTRE EJE F-G/1-2 M2 3.84 2.13 1.00 8.18

ENTRE EJE F-G/2-3 M2 3.84 2.13 1.00 8.18

AREA ADMINISTRATIVA Y SS.HH.

ENTRE EJE H-I/15-14 M2 4.53 4.08 1.00 18.48

ENTRE EJE H-I/14-13 M2 4.53 4.08 1.00 18.48

ENTRE EJE H-I/VOL M2 4.53 1.00 1.00 4.53

ESCALERA

M2 8.16 3.32 1.00 27.09

M2 3.32 1.78 1.00 5.91

01.04.08.03 ACERO FY=4200 KG/CM2 GRADO 60 EN LOSAS ALIGERADAS KG 3324.02


AULAS

ALIGERADO PRIMER PISO

Refuerz11/2" CANT. KG/ML

0.15 27.19 0.15 24.00 1.02 1.00 27.49 672.96

11/2"

0.15 1.35 24.00 1.02 2.00 1.35 66.10

11/2"

2.50 24.00 1.02 5.00 2.50 306.00

13/8"

2.00 24.00 1.02 5.00 2.00 244.80

39/87
HOJA DE METRADO
ACERO KG/ML
PROYECTO : AMPLIACION DE INFRAESTRUCTURA DE LA INSTITUCION EDUCATIVA"SAN JORGE" EN EL CENTRO POBLADO SUPTE SAN JORGE 1/4" 0.250
3/8" 0.580
FECHA : SETIEMBRE DEL 2011 HECHO POR: DAMS 1/2" 1.020
5/8" 1.60
SUB FORMULA : ESTRUCTURAS 3/4" 2.260
1" 4.040
CENTRO POBLADO : SUPTE SAN JORGE DISTRITO : RUPA RUPA PROVINCIA : LEONCIO PRADO

MEDIDAS N SUB TOTAL


N DESCRIPCION DE TOTAL
UND LARGO ANCHO ALTO VECES LONG. AREA VOL. KG.

ALIGERADO SEGUNDO PISO

Refuerz11/2"

0.15 27.19 0.15 28.00 1.02 1.00 27.49 785.11

11/2"

0.15 1.35 28.00 1.02 2.00 1.35 77.11

11/2"

2.50 28.00 1.02 5.00 2.50 357.00

13/8"

2.00 28.00 0.58 5.00 2.00 162.40

SS.HH.

Refuerz11/2" CANT. KG/ML

0.15 8.55 0.15 23.00 1.02 1.00 8.85 207.62

11/2"

0.15 1.35 23.00 1.02 2.00 1.35 63.34

11/2"

2.50 23.00 1.02 1.00 2.50 58.65

13/8"

2.00 23.00 0.58 1.00 2.00 26.68

AREA ADMINISTRATIVA Y SS.HH.

Refuerz11/2" CANT. KG/ML

0.15 9.80 0.15 11.00 1.02 1.00 10.10 113.32

11/2"

0.15 1.35 11.00 1.02 2.00 1.35 30.29

11/2"

2.50 11.00 1.02 1.00 2.50 28.05

13/8"

2.00 11.00 0.58 1.00 2.00 12.76

ESCALERA

Refuerz11/2" CANT. KG/ML

0.15 8.16 0.15 11.00 1.02 1.00 8.46 94.92

11/2"

0.15 1.35 11.00 1.02 2.00 1.35 30.29

11/2"

2.50 11.00 1.02 1.00 2.50 28.05

13/8"

2.00 11.00 0.58 4.00 2.00 51.04

01.04.08.04 LADRILLO HUECO ARCILLA 15x30x30 P/TECHO ALIGERADO UND 5841.63


AULAS

1ER PISO UND 25.09 9.97 8.33 2083.73

2DO PISO UND 25.09 12.27 8.33 2564.43

40/87
HOJA DE METRADO
ACERO KG/ML
PROYECTO : AMPLIACION DE INFRAESTRUCTURA DE LA INSTITUCION EDUCATIVA"SAN JORGE" EN EL CENTRO POBLADO SUPTE SAN JORGE 1/4" 0.250
3/8" 0.580
FECHA : SETIEMBRE DEL 2011 HECHO POR: DAMS 1/2" 1.020
5/8" 1.60
SUB FORMULA : ESTRUCTURAS 3/4" 2.260
1" 4.040
CENTRO POBLADO : SUPTE SAN JORGE DISTRITO : RUPA RUPA PROVINCIA : LEONCIO PRADO

MEDIDAS N SUB TOTAL


N DESCRIPCION DE TOTAL
UND LARGO ANCHO ALTO VECES LONG. AREA VOL. KG.

SS.HH.

UND 3.84 0.95 8.33 30.39

UND 3.84 3.30 8.33 105.56

UND 3.84 0.95 8.33 30.39

UND 3.84 3.30 8.33 105.56

UND 3.84 3.29 8.33 105.24

UND 3.84 3.29 8.33 105.24

UND 3.84 2.13 8.33 68.13

UND 3.84 2.13 8.33 68.13

AREA ADMINISTRATIVA Y SS.HH.

UND 4.53 4.08 8.33 153.96

UND 4.53 4.08 8.33 153.96

UND 4.53 1.00 8.33 37.73

ESCALERA

UND 8.16 3.32 8.33 225.67

UND 3.32 1.78 8.33 49.23

01.04.09 ALERO DE VENTANA

01.04.09.01 CONCRETO EN ALERO DE VENTANA F'C=175 KG/CM2 M3 1.34


AULAS 27.30 0.70 0.07 1.34

01.04.09.02 ENCOFRADO Y DESENCOFRADO EN ALERO DE VENTANA M2 21.02


AULAS 27.30 0.77 21.02

01.04.09.03 ACERO EN ALERO DE VENTANA GRADO 60 KG 78.30


AULAS

01.04.10 ESCALERA
01.04.10.01 CONCRETO EN ESCALERA F'C= 210 KG/CM2 M3 12.45
M3 1.65 20.00 0.30 9.90

M3 3.30 1.65 0.14 1.00 0.76

M3 3.95 2.26 0.20 1.00 1.79

01.04.10.02 ENCOFRADO Y DESENCOFRADO NORMAL EN ESCALERA M2 32.85


M2 1.65 0.56 20.00 18.48

M2 3.30 1.65 1.00 5.45

M2 3.95 2.26 1.00 8.93

01.04.10.03 ACERO EN ESCALERA F'Y=4200 KG/CM2-GRADO 60 KG 187.94


CANT. KG/ML

KG 1.75 2.00 1.60 20.00 1.95 124.80

KG 1.75 2.00 1.60 20.00 1.95 124.80

KG 3.38 10.00 1.60 1.00 3.58 57.28

KG 1.32 21.00 0.58 1.00 1.52 18.51

01.04.11 GARGOLAS
01.04.11.01 CONCRETO EN GARGOLAS F'C= 210 KG/CM2 M3 0.08
M3 0.35 0.10 0.25 6.00 0.05

M3 0.35 0.10 0.25 3.00 0.03

01.04.11.02 ENCOFRADO Y DESENCOFRADO NORMAL EN GARGOLAS M2 0.52


M2 0.35 0.25 3.00 0.26

M2 0.35 0.25 3.00 0.26

41/87
HOJA DE METRADO
ACERO KG/ML
PROYECTO : AMPLIACION DE INFRAESTRUCTURA DE LA INSTITUCION EDUCATIVA"SAN JORGE" EN EL CENTRO POBLADO SUPTE SAN JORGE 1/4" 0.250
3/8" 0.580
FECHA : SETIEMBRE DEL 2011 HECHO POR: DAMS 1/2" 1.020
5/8" 1.60
SUB FORMULA : ESTRUCTURAS 3/4" 2.260
1" 4.040
CENTRO POBLADO : SUPTE SAN JORGE DISTRITO : RUPA RUPA PROVINCIA : LEONCIO PRADO

MEDIDAS N SUB TOTAL


N DESCRIPCION DE TOTAL
UND LARGO ANCHO ALTO VECES LONG. AREA VOL. KG.

01.04.11.03 ACERO EN GARGOLAS F'Y=4200 KG/CM2-GRADO 60 KG 4.95


11/4"

### 0.20 4.00 0.25 3.00 0.55 1.65

0.15

13/8"

### 4.00 0.25 3.00 1.10 3.30

42/87
HOJA DE METRADO

PROYECTO : AMPLIACION DE INFRAESTRUCTURA DE LA INSTITUCION EDUCATIVA"SAN JORGE" EN EL CENTRO POBLADO SUPTE SAN JORGE

FECHA : SETIEMBRE DEL 2011 HECHO POR: DAMS

SUB FORMULA : ARQUITECTURA

CENTRO POBLADO : SUPTE SAN JORGE DISTRITO : RUPA RUPA PROVINCIA : LEONCIO PRADO

MEDIDAS N SUB TOTAL


N DESCRIPCION DE TOTAL
UND LARGO ANCHO ALTO VECES LONG. AREA VOL. KG.

02.00.00 ARQUITECTURA
02.01.00 MUROS Y TABIQUES DE ALBAILERIA
02.01.01 MURO DE CABEZA LADRILLO KING-KONG 18 HUECOS DE ARCILLA 245.53
AULAS

1ER PISO M2 3.46 2.95 8.00 81.66

2DO PISO M2 3.46 3.00 8.00 83.04

M2 3.44 0.56 4.00 7.71

ESCALERA

M2 4.32 3.04 2.00 26.27

M2 4.32 3.03 2.00 26.18

M2 1.59 0.52 3.79 2.00 8.00

M2 1.59 1.44 0.53 2.00 1.61

02.01.02 MURO DE SOGA LADRILLO KING-KONG 18 HUECOS DE ARCILLA M2 374.89


AULAS

1ER PISO M2 0.85 2.95 1.00 2.51

M2 1.39 1.35 1.00 1.88

M2 3.75 1.35 1.00 5.06

M2 0.85 2.95 1.00 2.51

M2 1.39 1.35 1.00 1.88

M2 3.75 1.35 1.00 5.06

M2 0.75 2.95 1.00 2.21

M2 1.31 1.35 1.00 1.77

M2 3.75 1.35 1.00 5.06

M2 3.74 2.00 2.00 14.96

M2 3.75 2.00 4.00 30.00

2DO PISO

M2 0.85 2.90 1.00 2.47

M2 1.39 1.30 1.00 1.81

M2 3.75 1.30 1.00 4.88

M2 0.85 2.90 1.00 2.47

M2 1.39 1.30 1.00 1.81

M2 3.75 1.30 1.00 4.88

M2 0.75 2.90 1.00 2.18

M2 1.31 1.3 1.00 1.70

M2 3.75 1.30 1.00 4.88

M2 3.74 1.95 2.00 14.59

M2 3.75 1.95 4.00 29.25

PARAPETO M2 3.17 2.00 6.34

PARAPETO M2 3.14 4.00 12.56

M2 1.54 1.45 1.00 2.23

SS.HH.

EJE 1-1/B-F M2 2.95 1.80 2.00 10.62

EJE 2-2/B-F M2 2.95 2.70 2.00 15.93

EJE 3-3/B-F M2 2.95 1.80 2.00 10.62

EJE B-B/1-3 M2 3.36 2.70 2.00 18.14

EJE F-F/1-3 M2 2.38 2.70 2.00 12.85

EJE 1-3/B-F M2 2.16 2.12 4.00 18.32

M2 0.66 2.12 4.00 5.60

M2 0.78 2.12 4.00 6.61

M2 1.41 2.12 8.00 23.91

AREA ADMINISTRATIVA Y SS.HH.

1/87
HOJA DE METRADO

PROYECTO : AMPLIACION DE INFRAESTRUCTURA DE LA INSTITUCION EDUCATIVA"SAN JORGE" EN EL CENTRO POBLADO SUPTE SAN JORGE

FECHA : SETIEMBRE DEL 2011 HECHO POR: DAMS

SUB FORMULA : ARQUITECTURA

CENTRO POBLADO : SUPTE SAN JORGE DISTRITO : RUPA RUPA PROVINCIA : LEONCIO PRADO

MEDIDAS N SUB TOTAL


N DESCRIPCION DE TOTAL
UND LARGO ANCHO ALTO VECES LONG. AREA VOL. KG.

EJE H-H/13-15 M2 3.45 2.70 2.00 18.63

EJE I-I/13-15 M2 3.45 2.70 2.00 18.63

EJE 13-13/H-I M2 3.07 0.80 1.00 2.46

EJE 14-14/H-I M2 3.17 2.70 1.00 8.56

EJE 15-15/H-I M2 4.05 2.70 1.00 10.94

ESCALERA

M2 2.84 1.53 1.00 4.35

M2 2.84 1.41 1.00 4.00

PARAPETO M2 1.96 1.05 1.00 2.06

M2 1.62 1.05 1.00 1.70

M2 1.00 1.31

02.02.00 REVOQUES ENLUCIDOS Y MOLDURAS


02.02.01 TERRAJEO DE INTERIORES ACABADO CON C:A-1:4 M2 692.33
AULAS

1ER PISO

EJE F-F ENTRE EJE 4-6 M2 0.85 2.95 1.00 2.51

M2 1.39 1.35 1.00 1.88

M2 3.75 1.35 1.00 5.06

EJE F-F ENTRE EJE 6-8 M2 0.85 2.95 1.00 2.51

M2 1.39 1.35 1.00 1.88

M2 3.75 1.35 1.00 5.06

EJE F-F ENTRE EJE 8-10 M2 0.75 2.95 1.00 2.21

M2 1.31 1.35 1.00 1.77

M2 3.75 1.35 1.00 5.06

EJE A-A ENTRE EJE 10-4 M2 3.74 1.85 2.00 13.84

M2 3.75 1.85 4.00 27.75

EJE 10-8-6-4 ENTRE EJE F-A M2 3.46 2.95 12.00 122.48

2DO PISO

EJE F-F ENTRE EJE 4-6 M2 0.85 2.90 1.00 2.47

M2 1.39 1.30 1.00 1.81

M2 3.75 1.30 1.00 4.88

EJE F-F ENTRE EJE 6-8 M2 0.85 2.90 1.00 2.47

M2 1.39 1.30 1.00 1.81

M2 3.75 1.30 1.00 4.88

EJE F-F ENTRE EJE 8-10 M2 0.75 2.90 1.00 2.18

M2 1.31 1.3 1.00 1.70

M2 3.75 1.30 1.00 4.88

EJE A-A ENTRE EJE 10-4 M2 3.74 1.85 2.00 13.84

M2 3.75 1.85 4.00 27.75

PARAPETO M2 2.00 1.54

PARAPETO M2 4.00 1.53

M2 3.46 3.00 8.00 83.04

M2 3.44 0.56 4.00 7.71

SS.HH.

EJE 1-1/B-F M2 2.95 1.80 2.00 10.62

EJE 2-2/B-F M2 2.95 2.70 4.00 31.86

EJE 3-3/B-F M2 2.95 1.80 2.00 10.62

EJE B-B/1-3 M2 3.36 2.70 2.00 18.14

EJE F-F/1-3 M2 2.38 2.70 2.00 12.85

EJE 1-3/B-F M2 2.16 2.12 8.00 36.63

M2 0.66 2.12 8.00 11.19

2/87
HOJA DE METRADO

PROYECTO : AMPLIACION DE INFRAESTRUCTURA DE LA INSTITUCION EDUCATIVA"SAN JORGE" EN EL CENTRO POBLADO SUPTE SAN JORGE

FECHA : SETIEMBRE DEL 2011 HECHO POR: DAMS

SUB FORMULA : ARQUITECTURA

CENTRO POBLADO : SUPTE SAN JORGE DISTRITO : RUPA RUPA PROVINCIA : LEONCIO PRADO

MEDIDAS N SUB TOTAL


N DESCRIPCION DE TOTAL
UND LARGO ANCHO ALTO VECES LONG. AREA VOL. KG.

M2 0.78 2.12 8.00 13.23

M2 1.41 2.12 16.00 47.83

AREA ADMINISTRATIVA Y SS.HH.

EJE H-H/13-15 M2 3.45 2.70 1.00 9.32

EJE I-I/13-15 M2 3.45 2.70 1.00 9.32

EJE 13-13/H-I M2 3.07 0.80 1.00 2.46

EJE 14-14/H-I M2 3.17 2.70 1.00 8.56

EJE 15-15/H-I M2 4.05 2.70 1.00 10.94

ESCALERA

M2 2.84 1.53 1.00 4.35

M2 2.84 1.41 1.00 4.00

PARAPETO M2 1.96 1.05 1.00 2.06

M2 1.62 1.05 1.00 1.70

M2 1.00 1.31

02.02.02 TERRAJEO EN EXTERIORES ACABADO CON C:A-1:4 330.53


AULAS

1ER PISO

EJE F-F ENTRE EJE 4-6 M2 0.85 2.95 1.00 2.51

M2 1.39 1.35 1.00 1.88

M2 3.75 1.35 1.00 5.06

EJE F-F ENTRE EJE 6-8 M2 0.85 2.95 1.00 2.51

M2 1.39 1.35 1.00 1.88

M2 3.75 1.35 1.00 5.06

EJE F-F ENTRE EJE 8-10 M2 0.75 2.95 1.00 2.21

M2 1.31 1.35 1.00 1.77

M2 3.75 1.35 1.00 5.06

EJE A-A ENTRE EJE 10-4 M2 3.74 2.00 2.00 14.96

M2 3.75 2.00 4.00 30.00

2DO PISO

EJE F-F ENTRE EJE 4-6 M2 0.85 2.90 1.00 2.47

M2 1.39 1.30 1.00 1.81

M2 3.75 1.30 1.00 4.88

EJE F-F ENTRE EJE 6-8 M2 0.85 2.90 1.00 2.47

M2 1.39 1.30 1.00 1.81

M2 3.75 1.30 1.00 4.88

EJE F-F ENTRE EJE 8-10 M2 0.75 2.90 1.00 2.18

M2 1.31 1.3 1.00 1.70

M2 3.75 1.30 1.00 4.88

EJE A-A ENTRE EJE 10-4 M2 3.74 1.95 2.00 14.59

M2 3.75 1.95 4.00 29.25

PARAPETO M2 2.00 1.54

PARAPETO M2 4.00 1.53

M2 2.10 1.00 1.00 2.10

SS.HH.

EJE 1-1/B-F M2 2.95 1.80 2.00 10.62

EJE 3-3/B-F M2 2.95 1.80 2.00 10.62

EJE B-B/1-3 M2 3.36 2.70 2.00 18.14

EJE F-F/1-3 M2 2.38 2.70 2.00 12.85

AREA ADMINISTRATIVA Y SS.HH.

3/87
HOJA DE METRADO

PROYECTO : AMPLIACION DE INFRAESTRUCTURA DE LA INSTITUCION EDUCATIVA"SAN JORGE" EN EL CENTRO POBLADO SUPTE SAN JORGE

FECHA : SETIEMBRE DEL 2011 HECHO POR: DAMS

SUB FORMULA : ARQUITECTURA

CENTRO POBLADO : SUPTE SAN JORGE DISTRITO : RUPA RUPA PROVINCIA : LEONCIO PRADO

MEDIDAS N SUB TOTAL


N DESCRIPCION DE TOTAL
UND LARGO ANCHO ALTO VECES LONG. AREA VOL. KG.

EJE H-H/13-15 M2 3.45 2.70 1.00 9.32

EJE 13-13/H-I M2 3.07 0.80 1.00 2.46

EJE 15-15/H-I M2 4.05 2.70 1.00 10.94

ESCALERA

M2 2.84 1.53 1.00 4.35

M2 2.84 1.41 1.00 4.00

PARAPETO M2 1.96 1.05 1.00 2.06

M2 1.62 1.05 1.00 1.70

M2 1.00 1.31

02.02.03 TERRAJEO DE SUPERFICIES DE COLUMNAS CON C-A 1:4 M2 378.61


AULAS

1ER PISO

INTERIOR

EJE F-F Y 4-4 M2 0.45 2.88 1.00 1.30

EJE F-F Y 5-5 M2 1.04 2.88 1.00 3.00

EJE F-F Y 6-6 M2 0.82 2.88 1.00 2.36

EJE F-F Y 7-7 M2 1.04 2.88 1.00 3.00

EJE F-F Y 8-8 M2 0.82 2.88 1.00 2.36

EJE F-F Y 9-9 M2 1.04 2.88 1.00 3.00

EJE F-F Y 10-10 M2 0.45 2.88 1.00 1.30

EJE D-D Y 4-4 M2 0.25 2.74 1.00 0.69

EJE D-D Y 6-6 M2 0.25 2.88 2.00 1.44

EJE D-D Y 8-8 M2 0.25 2.88 2.00 1.44

EJE D-D Y 10-8 M2 0.25 2.88 1.00 0.72

EJE A-A Y 4-4 M2 0.45 2.88 1.00 1.30

EJE A-A Y 5-5 M2 1.04 2.88 1.00 3.00

EJE A-A Y 6-6 M2 0.82 2.88 1.00 2.36

EJE A-A Y 7-7 M2 1.04 2.88 1.00 3.00

EJE A-A Y 8-8 M2 0.82 2.88 1.00 2.36

EJE A-A Y 9-9 M2 1.04 2.88 1.00 3.00

EJE A-A Y 10-10 M2 0.45 2.88 1.00 1.30

EXTERIOR

EJE F-F Y 4-4 M2 1.00 2.88 1.00 2.88

EJE F-F Y 5-5 M2 0.50 2.88 1.00 1.44

EJE F- Y 6-6 M2 0.50 2.88 1.00 1.44

EJE F-F Y 7-7 M2 0.50 2.88 1.00 1.44

EJE F-F Y 8-8 M2 0.50 2.88 1.00 1.44

EJE F-F Y 9-9 M2 0.50 2.88 1.00 1.44

EJE F-F Y 10-10 M2 1.00 2.88 1.00 2.88

EJE A-A Y 4-4 M2 1.00 2.88 1.00 2.88

EJE A-A Y 5-5 M2 0.50 2.88 1.00 1.44

EJE A-A Y 5-6 M2 0.50 2.88 1.00 1.44

EJE A-A Y 7-7 M2 0.50 2.88 1.00 1.44

EJE A-A Y 8-8 M2 0.50 2.88 1.00 1.44

EJE A-A Y 9-9 M2 0.50 2.88 1.00 1.44

EJE A-A Y 10-10 M2 1.00 2.88 1.00 2.88

COLUMNETAS

EJE F-F ENTRE 4-5/6-7/8-9 M2 0.20 2.95 12.00 7.08

M2 0.13 2.95 6.00 2.30

EJE F-F ENTRE 10-4 M2 0.20 1.35 24.00 6.48

M2 0.13 1.35 12.00 2.11

4/87
HOJA DE METRADO

PROYECTO : AMPLIACION DE INFRAESTRUCTURA DE LA INSTITUCION EDUCATIVA"SAN JORGE" EN EL CENTRO POBLADO SUPTE SAN JORGE

FECHA : SETIEMBRE DEL 2011 HECHO POR: DAMS

SUB FORMULA : ARQUITECTURA

CENTRO POBLADO : SUPTE SAN JORGE DISTRITO : RUPA RUPA PROVINCIA : LEONCIO PRADO

MEDIDAS N SUB TOTAL


N DESCRIPCION DE TOTAL
UND LARGO ANCHO ALTO VECES LONG. AREA VOL. KG.

EJE A-A ENTRE 10-4 M2 0.20 1.98 24.00 9.50

M2 0.13 1.98 12.00 3.09

2DO PISO

EJE F-F Y 4-4 M2 0.45 2.90 1.00 1.31

EJE F-F Y 5-5 M2 1.04 2.90 1.00 3.02

EJE F-F Y 6-6 M2 0.82 2.90 1.00 2.38

EJE F-F Y 7-7 M2 1.04 2.90 1.00 3.02

EJE F-F Y 8-8 M2 0.82 2.90 1.00 2.38

EJE F-F Y 9-9 M2 1.04 2.90 1.00 3.02

EJE F-F Y 10-10 M2 0.45 2.90 1.00 1.31

EJE D-D Y 4-4 M2 0.25 2.95 1.00 0.74

M2 0.25 1.12 1.00 0.28

EJE D-D Y 6-6 M2 0.25 2.95 2.00 1.48

M2 0.25 1.12 2.00 0.56

EJE D-D Y 8-8 M2 0.25 2.95 2.00 1.48

M2 0.25 1.12 2.00 0.56

EJE D-D Y 10-10 M2 0.25 2.95 1.00 0.74

M2 0.25 1.12 1.00 0.28

EJE A-A Y 4-4 M2 0.45 2.90 1.00 1.31

EJE A-A Y 5-5 M2 1.04 2.90 1.00 3.02

EJE A-A Y 6-6 M2 0.82 2.90 1.00 2.38

EJE A-A Y 7-7 M2 1.04 2.90 1.00 3.02

EJE A-A Y 8-8 M2 0.82 2.90 1.00 2.38

EJE A-A Y 9-9 M2 1.04 2.90 1.00 3.02

EJE A-A Y 10-10 M2 0.45 2.90 1.00 1.31

EXTERIOR

EJE F-F Y 4-4 M2 1.13 2.90 1.00 3.28

EJE F-F Y 5-5 M2 0.76 2.90 1.00 2.20

EJE F-F Y 6-6 M2 0.76 2.90 1.00 2.20

EJE F-F Y 7-7 M2 0.76 2.90 1.00 2.20

EJE F-F Y 8-8 M2 0.76 2.90 1.00 2.20

EJE F-F Y 9-9 M2 0.76 2.90 1.00 2.20

EJE F-F Y 10-10 M2 1.13 2.90 1.00 3.28

EJE A-A Y 4-4 M2 1.13 2.90 1.00 3.28

EJE A-A Y 5-5 M2 0.76 2.90 1.00 2.20

EJE A-A Y 6-6 M2 0.76 2.90 1.00 2.20

EJE A-A Y 7-7 M2 0.76 2.90 1.00 2.20

EJE A-A Y 8-8 M2 0.76 2.90 1.00 2.20

EJE A-A Y 9-9 M2 0.76 2.90 1.00 2.20

EJE A-A Y 10-10 M2 1.13 2.90 1.00 3.28

COLUMNATES

EJE F-F ENTRE 4-5/6-7/8-9 M2 0.20 2.90 12.00 6.96

M2 0.13 2.90 6.00 2.26

EJE F-F ENTRE 10-4 M2 0.20 1.30 24.00 6.24

M2 0.13 1.30 12.00 2.03

EJE A-A ENTRE 10-4 M2 0.20 1.95 24.00 9.36

M2 0.13 1.95 12.00 3.04

SS.HH.

INTERIOR

EJE 1/B M2 0.24 3.87 1.00 0.93

5/87
HOJA DE METRADO

PROYECTO : AMPLIACION DE INFRAESTRUCTURA DE LA INSTITUCION EDUCATIVA"SAN JORGE" EN EL CENTRO POBLADO SUPTE SAN JORGE

FECHA : SETIEMBRE DEL 2011 HECHO POR: DAMS

SUB FORMULA : ARQUITECTURA

CENTRO POBLADO : SUPTE SAN JORGE DISTRITO : RUPA RUPA PROVINCIA : LEONCIO PRADO

MEDIDAS N SUB TOTAL


N DESCRIPCION DE TOTAL
UND LARGO ANCHO ALTO VECES LONG. AREA VOL. KG.

EJE 1/E M2 0.60 4.88 1.00 2.93

EJE 1/F M2 0.45 3.87 1.00 1.74

EJE 2/B M2 0.32 3.87 1.00 1.24

EJE 2/E M2 0.90 4.88 1.00 4.39

EJE 2/F M2 0.32 3.87 1.00 1.24

EJE 3/B M2 0.24 3.87 1.00 0.93

EJE 3/E M2 0.60 4.88 1.00 2.93

EJE 3/F M2 0.45 3.87 1.00 1.74

COLUMNETAS

EJE 1-1 ENTRE B-F M2 0.20 2.00 4.00 1.60

EJE 2-2 ENTRE B-F M2 0.20 2.90 4.00 2.32

EJE 3-3 ENTRE B-F M2 0.20 2.00 4.00 1.60

EJE B-B ENTRE 1-3 M2 0.20 2.90 4.00 2.32

EJE F-F ENTRE 1-3 M2 0.20 2.90 4.00 2.32

ENTRE 2-2 / B-F M2 0.20 2.12 24.00 10.18

EXTERIOR

EJE 1/B M2 0.24 3.87 1.00 0.93

EJE 1/E M2 0.60 4.88 1.00 2.93

EJE 1/F M2 0.45 3.87 1.00 1.74

EJE 2/B M2 0.32 3.87 1.00 1.24

EJE 2/E M2 0.90 4.88 1.00 4.39

EJE 2/F M2 0.32 3.87 1.00 1.24

EJE 3/B M2 0.24 3.87 1.00 0.93

EJE 3/E M2 0.60 4.88 1.00 2.93

EJE 3/F M2 0.45 3.87 1.00 1.74

COLUMNETAS

EJE 1-1 ENTRE B-F M2 0.20 2.00 4.00 1.60

EJE 3-3 ENTRE B-F M2 0.20 2.00 4.00 1.60

EJE B-B ENTRE 1-3 M2 0.20 2.90 4.00 2.32

EJE F-F ENTRE 1-3 M2 0.20 2.90 4.00 2.32

AREA ADMINISTRATIVA Y SS.HH.

INTERIOR

EJE 13/H M2 0.42 3.00 1.00 1.26

EJE 13/I M2 0.56 3.00 1.00 1.68

EJE 14/H M2 0.56 3.00 1.00 1.68

EJE 14/I M2 0.72 3.00 1.00 2.16

EJE 15/H M2 0.42 3.00 1.00 1.26

EJE 15/I M2 0.42 3.00 1.00 1.26

COLUMNETAS

EJE 13-13 ENTRE H-I M2 0.20 1.00 2.00 0.40

EJE 14-14 ENTRE H-I M2 0.20 2.90 4.00 2.32

EJE 15-15 ENTRE H-I M2 0.20 2.20 2.00 0.88

EJE H-H ENTRE 13-15 M2 0.20 2.90 4.00 2.32

EJE I-I ENTRE 13-15 M2 0.20 2.90 4.00 2.32

EXTERIOR

EJE 13/H M2 0.70 3.00 1.00 2.10

EJE 13/I M2 0.30 3.00 1.00 0.90

EJE 14/H M2 0.40 3.00 1.00 1.20

EJE 15/H M2 0.70 3.00 1.00 2.10

EJE 15/I M2 0.30 3.00 1.00 0.90

COLUMNETAS

EJE 13-13 ENTRE H-I M2 0.20 1.00 2.00 0.40

6/87
HOJA DE METRADO

PROYECTO : AMPLIACION DE INFRAESTRUCTURA DE LA INSTITUCION EDUCATIVA"SAN JORGE" EN EL CENTRO POBLADO SUPTE SAN JORGE

FECHA : SETIEMBRE DEL 2011 HECHO POR: DAMS

SUB FORMULA : ARQUITECTURA

CENTRO POBLADO : SUPTE SAN JORGE DISTRITO : RUPA RUPA PROVINCIA : LEONCIO PRADO

MEDIDAS N SUB TOTAL


N DESCRIPCION DE TOTAL
UND LARGO ANCHO ALTO VECES LONG. AREA VOL. KG.

EJE 15-15 ENTRE H-I M2 0.20 2.20 2.00 0.88

EJE H-H ENTRE 13-15 M2 0.20 2.90 4.00 2.32

ESCALERA

INTERIOR

EJE 11/C M2 0.36 8.40 1.00 3.02

EJE 11/F M2 0.36 7.40 1.00 2.66

EJE 12/C M2 0.23 3.00 1.00 0.69

M2 0.36 5.40 1.00 1.94

EJE 12/F M2 0.23 3.00 1.00 0.69

M2 0.36 5.40 1.00 1.94

PLACA M2 0.30 8.24 2.00 4.94

PLACA M2 0.30 7.40 2.00 4.44

COLUMNETA

EJE C-C/11-12 M2 0.20 1.51 2.00 0.60

M2 0.20 1.25 2.00 0.50

M2 0.20 1.05 4.00 0.84

EXTERIOR

EJE 11/C M2 0.30 8.40 1.00 2.52

EJE 11/F M2 0.30 7.40 1.00 2.22

EJE 12/C M2 0.60 8.40 1.00 5.04

EJE 12/F M2 7.40 7.40 1.00 54.76

COLUMNETA

EJE C-C/11-12 M2 0.20 1.51 2.00 0.60

M2 0.20 1.25 2.00 0.50

M2 0.20 1.05 3.00 0.63

02.02.04 TERRAJEO EN SUPERFICIE DE VIGAS CON CEMENTO ARENA 1:4 M2 570.45


AULAS

VIGUETAS DE ARRIOSTRE 1ER PISO

EJE F-F ENTRE 4-5 M2 1.25 0.10 2.00 0.25

M2 1.79 0.10 2.00 0.36

EJE F-F ENTRE 5-6 M2 4.15 0.10 2.00 0.83

EJE F-F ENTRE 6-7 M2 1.25 0.10 2.00 0.25

M2 1.79 0.10 2.00 0.36

EJE F-F ENTRE 7-8 M2 4.15 0.10 1.00 0.42

EJE F-F ENTRE 8-9 M2 1.25 0.10 2.00 0.25

M2 1.81 0.10 2.00 0.36

EJE F-F ENTRE 9-10 M2 1.25 0.10 2.00 0.25

M2 1.79 0.10 2.00 0.36

EJE A-A ENTRE EJES 10-9-8-7-6-5-4- M2 4.15 0.10 12.00 4.98

VIGA 1ER PISO

EJE F-F / 4-5 LATERAL M2 4.19 0.30 1.00 1.26

BASE M2 4.19 0.50 2.00 4.19

EJE F-F/5-6-7-8-9 LATERAL M2 4.20 0.30 4.00 5.04

BASE. M2 4.20 0.50 8.00 16.80

EJE F-F /9-10 LATERAL M2 4.18 0.30 1.00 1.25

BASE M2 4.18 0.50 2.00 4.18

EJE A-A ENTRE EJES 4-5 M2 4.19 0.30 1.00 1.26

M2 4.19 0.50 2.00 4.19

EJE A-A/5-6-7-8-9 M2 4.20 0.30 4.00 5.04

M2 4.20 0.50 8.00 16.80

EJE A-A/10-9 M2 4.18 0.30 1.00 1.25

7/87
HOJA DE METRADO

PROYECTO : AMPLIACION DE INFRAESTRUCTURA DE LA INSTITUCION EDUCATIVA"SAN JORGE" EN EL CENTRO POBLADO SUPTE SAN JORGE

FECHA : SETIEMBRE DEL 2011 HECHO POR: DAMS

SUB FORMULA : ARQUITECTURA

CENTRO POBLADO : SUPTE SAN JORGE DISTRITO : RUPA RUPA PROVINCIA : LEONCIO PRADO

MEDIDAS N SUB TOTAL


N DESCRIPCION DE TOTAL
UND LARGO ANCHO ALTO VECES LONG. AREA VOL. KG.

M2 4.18 0.50 2.00 4.18

EJE F-F ENTRE EJES 4 AL 10 M2 25.17 0.40 1.00 10.07

M2 25.17 0.15 1.00 3.78

M2 25.17 0.21 1.00 5.29

EJE 10-8-6-4 ENTRE EJES F-F Y A-A M2 7.91 0.30 6.00 14.24

M2 8.37 0.50 2.00 8.37

M2 7.17 0.08 4.00 2.29

EJE 9-7-5 ENTRE EJES F-F Y A-A M2 7.17 0.30 3.00 6.45

M2 7.91 0.50 6.00 23.73

EJE 10-9-8-7-6-5-4/ F-F M2 1.01 1.00 7.00 7.07

2DO PISO

VIGUETA DE ARRIOSTRE

EJE F-F ENTRE 4-5 M2 1.25 0.10 2.00 0.25

M2 1.79 0.10 2.00 0.36

EJE F-F ENTRE 5-6 M2 4.15 0.10 2.00 0.83

EJE F-F ENTRE 6-7 M2 1.25 0.10 2.00 0.25

M2 1.79 0.10 2.00 0.36

EJE F-F ENTRE 7-8 M2 4.15 0.10 2.00 0.83

EJE F-F ENTRE 8-9 M2 1.25 0.10 2.00 0.25

M2 1.81 0.10 2.00 0.36

EJE F-F ENTRE 9-10 M2 1.25 0.10 2.00 0.25

M2 1.79 0.10 2.00 0.36

EJE A-A ENTRE EJES 10-9-8-7-6-5-4- M2 4.15 0.10 12.00 4.98

VIGA

EJE A-A / 4-5 LATERAL M2 4.19 0.30 1.00 1.26

BASE M2 4.19 0.50 2.00 4.19

EJE F-F/5-6-7-8-9 LATERAL M2 4.20 0.30 4.00 5.04

BASE. M2 4.20 0.50 8.00 16.80

EJE F-F /9-10 LATERAL M2 4.18 0.30 1.00 1.25

BASE M2 4.18 0.50 2.00 4.18

EJE A-A ENTRE EJES 4-5 M2 4.19 0.30 1.00 1.26

M2 4.19 0.50 2.00 4.19

EJE A-A/5-6-7-8-9 M2 4.20 0.30 4.00 5.04

M2 4.20 0.50 8.00 16.80

EJE A-A/10-9 M2 4.18 0.30 1.00 1.25

M2 4.18 0.50 2.00 4.18

EJE F-F ENTRE EJES 4 AL 10 M3 2.05 14.00 28.70

M3 0.78 14.00 10.92

VIGA TECHO M3 4.26 0.30 14.00 17.89

M3 4.26 0.30 7.00 8.95

EJE 10-8-6-4 / F-F Y A-A ARRIOSTRE M2 7.91 0.40 8.00 25.31

M2 7.17 0.08 4.00 2.29

CUIMBRERA M2 4.26 1.20 6.00 30.67

SS.HH.

VIGAS

INTERIOR

EJE 1-1/B-F M2 3.45 0.50 2.00 3.45

M2 3.45 0.30 2.00 2.07

M2 3.45 0.17 2.00 1.17

TRIANGULAR M2 6.25 0.47 1.00 2.94

TRIANGULAR M2 5.05 0.47 1.00 2.37

EJE 2-2/B-F M2 3.45 0.50 2.00 3.45

8/87
HOJA DE METRADO

PROYECTO : AMPLIACION DE INFRAESTRUCTURA DE LA INSTITUCION EDUCATIVA"SAN JORGE" EN EL CENTRO POBLADO SUPTE SAN JORGE

FECHA : SETIEMBRE DEL 2011 HECHO POR: DAMS

SUB FORMULA : ARQUITECTURA

CENTRO POBLADO : SUPTE SAN JORGE DISTRITO : RUPA RUPA PROVINCIA : LEONCIO PRADO

MEDIDAS N SUB TOTAL


N DESCRIPCION DE TOTAL
UND LARGO ANCHO ALTO VECES LONG. AREA VOL. KG.

M2 3.45 0.16 2.00 1.10

TRIANGULAR M2 6.25 0.46 1.00 2.88

TRIANGULAR M2 5.05 0.46 1.00 2.32

EJE 3-3/B-F M2 3.45 0.50 2.00 3.45

M2 3.45 0.30 2.00 2.07

M2 3.45 0.17 2.00 1.17

TRIANGULAR M2 6.25 0.47 1.00 2.94

TRIANGULAR M2 5.05 0.47 1.00 2.37

EJE B-B/1-3 M2 3.84 0.50 2.00 3.84

M2 3.84 0.30 2.00 2.30

DESCUENTO MURO M2 2.82 0.16 2.00 -0.90

EJE F-F/1-3 M2 3.84 0.50 2.00 3.84

M2 3.84 0.30 2.00 2.30

DESCUENTO MURO M2 3.84 0.16 2.00 -1.23

VIGUETAS

EJE 1-1/B-F M2 3.36 0.10 2.00 0.67

EJE 2-2/B-F M2 3.36 0.10 2.00 0.67

M2 2.92 0.10 2.00 0.58

M2 2.82 0.10 2.00 0.56

M2 1.41 0.10 8.00 1.13

EJE 3-3/B-F M2 3.36 0.10 2.00 0.67

EJE B-B/1-3 M2 3.75 0.10 2.00 0.75

EJE F-F/1-3 M2 2.78 0.10 2.00 0.56

EXTERIOR

EJE 1-1/B-F M2 3.88 0.50 2.00 3.88

TRIANGULAR M2 6.25 0.50 1.00 3.13

TRIANGULAR M2 5.05 0.50 1.00 2.53

TRIANGULAR M2 2.11 0.50 1.00 1.06

TRIANGULAR M2 0.95 0.50 1.00 0.48

EJE 2-2/B-FTRIANGULAR M2 2.11 0.50 1.00 1.06

TRIANGULAR M2 0.95 0.50 1.00 0.48

EJE 3-3/B-F M2 3.88 0.50 2.00 3.88

TRIANGULAR M2 6.25 0.50 1.00 3.13

TRIANGULAR M2 5.05 0.50 1.00 2.53

TRIANGULAR M2 2.11 0.50 1.00 1.06

TRIANGULAR M2 0.95 0.50 1.00 0.48

EJE B-B/1-3 M2 4.28 0.50 2.00 4.28

BORDE M2 8.60 0.78 1.00 6.71

EJE F-F/1-3 M2 4.28 0.50 2.00 4.28

BORDE M2 8.60 1.23 1.00 10.58

VIGUETAS

EJE 1-1/B-F M2 3.36 0.10 2.00 0.67

EJE 3-3/B-F M2 3.36 0.10 2.00 0.67

EJE B-B/1-3 M2 3.75 0.10 2.00 0.75

EJE F-F/1-3 M2 2.78 0.10 2.00 0.56

AREA ADMINISTRATIVA Y SS.HH.

VIGAS

INTERIOR

EJE 13-13/H-I M2 4.53 0.20 1.00 0.91

BASE M2 4.53 0.30 1.00 1.36

EJE 14-14/H-I M2 4.53 0.20 2.00 1.81

M2 4.53 0.30 1.00 1.36

9/87
HOJA DE METRADO

PROYECTO : AMPLIACION DE INFRAESTRUCTURA DE LA INSTITUCION EDUCATIVA"SAN JORGE" EN EL CENTRO POBLADO SUPTE SAN JORGE

FECHA : SETIEMBRE DEL 2011 HECHO POR: DAMS

SUB FORMULA : ARQUITECTURA

CENTRO POBLADO : SUPTE SAN JORGE DISTRITO : RUPA RUPA PROVINCIA : LEONCIO PRADO

MEDIDAS N SUB TOTAL


N DESCRIPCION DE TOTAL
UND LARGO ANCHO ALTO VECES LONG. AREA VOL. KG.

DESCUENTO DE MURO M2 3.60 0.16 1.00 -0.58

EJE 15-15/H-I M2 4.53 0.20 1.00 0.91

M2 4.53 0.30 1.00 1.36

EJE H-H/13-14 M2 4.05 0.20 1.00 0.81

M2 3.93 0.17 1.00 0.67

EJE H-H/14-15 M2 4.05 0.20 1.00 0.81

M2 3.93 0.17 1.00 0.67

EJE I-I/13-14 M2 4.05 0.20 1.00 0.81

M2 3.93 0.17 1.00 0.67

EJE I-I/14-15 M2 4.05 0.20 1.00 0.81

M2 3.93 0.17 1.00 0.67

VIGUETAS

EJE 13-13/H-I M2 3.47 0.10 1.00 0.35

EJE 14-14/H-I M2 3.57 0.10 1.00 0.36

EJE 15-15/H-I M2 4.45 0.10 1.00 0.45

EJE H-H/13-14 M2 3.85 0.10 1.00 0.39

EJE H-H/14-15 M2 3.85 0.10 1.00 0.39

EJE I-I/13-14 M2 3.85 0.10 1.00 0.39

EJE I-I/14-15 M2 3.85 0.10 1.00 0.39

EXTERIOR

EJE 13-13/H-I M2 5.13 0.40 1.00 2.05

EJE 15-15/H-I M2 5.13 0.40 1.00 2.05

EJE H-H/13-14 M2 4.53 0.40 1.00 1.81

VOLADO M2 1.15 1.10 1.00 1.27

EJE H-H/14-15 M2 4.53 0.40 1.00 1.81

EJE I-I/13-14 VOLADO M2 1.15 0.50 1.00 0.58

VIGUETAS

EJE 13-13/H-I M2 3.47 0.10 1.00 0.35

EJE 15-15/H-I M2 4.45 0.10 1.00 0.45

EJE H-H/13-14 M2 3.85 0.10 1.00 0.39

EJE H-H/14-15 M2 3.85 0.10 1.00 0.39

ESCALERA

VIGAS

INTERIOR

EJE 11-11/C-F M2 4.92 0.40 1.00 1.97

M2 4.32 0.08 1.00 0.35

ARRIOSTRE M2 4.32 0.40 1.00 1.73

ARRIOSTRE M2 4.32 0.16 1.00 0.69

M2 3.94 0.16 1.00 0.63

M2 0.52 0.16 1.00 0.08

EJE 12-12/C-F M2 4.92 0.40 1.00 1.97

M2 4.32 0.08 1.00 0.35

ARRIOSTRE M2 4.32 0.40 1.00 1.73

ARRIOSTRE M2 4.32 0.16 1.00 0.69

M2 3.94 0.16 1.00 0.63

M2 0.52 0.16 1.00 0.08

EJE C-C/11-12 M2 3.32 0.30 1.00 1.00

M2 3.32 0.40 1.00 1.33

ARRIOSTRE M2 3.32 0.40 1.00 1.33

ARRIOSTRE M2 3.32 0.60 1.00 1.99

EJE F-F/11-12 M2 3.32 0.30 1.00 1.00

10/87
HOJA DE METRADO

PROYECTO : AMPLIACION DE INFRAESTRUCTURA DE LA INSTITUCION EDUCATIVA"SAN JORGE" EN EL CENTRO POBLADO SUPTE SAN JORGE

FECHA : SETIEMBRE DEL 2011 HECHO POR: DAMS

SUB FORMULA : ARQUITECTURA

CENTRO POBLADO : SUPTE SAN JORGE DISTRITO : RUPA RUPA PROVINCIA : LEONCIO PRADO

MEDIDAS N SUB TOTAL


N DESCRIPCION DE TOTAL
UND LARGO ANCHO ALTO VECES LONG. AREA VOL. KG.

M2 3.32 0.30 1.00 1.00

ARRIOSTRE M2 3.32 0.40 1.00 1.33

ARRIOSTRE M2 3.32 0.60 1.00 1.99

VIGUETAS

EJE C-C/11-12 M2 3.24 0.10 2.00 0.65

ENTRE EJE F-F/11-12 M2 3.92 0.10 1.00 0.39

M2 2.10 0.10 1.00 0.21

M2 1.82 0.10 1.00 0.18

DESCANSO M2 3.45 0.47 1.00 1.62

EXTERIOR

EJE 11-11/C-F M2 2.26 0.20 1.00 0.45

M2 2.26 0.30 1.00 0.68

M2 2.56 0.40 1.00 1.02

M2 0.48 0.40 1.00 0.19

EJE 12-12/C-F M2 7.19 0.40 1.00 2.88

M2 2.26 0.30 1.00 0.68

M2 2.26 0.20 1.00 0.45

ARRIOSTRE M2 4.92 0.40 1.00 1.97

M2 2.56 0.70 1.00 1.79

M2 0.48 0.70 1.00 0.34

EJE C-C/11-12 M2 3.92 0.40 1.00 1.57

ARRIOSTRE M2 3.92 0.40 1.00 1.57

M2 3.92 0.68 1.00 2.67

EJE F-F/11-12 M2 3.92 0.80 1.00 3.14

M2 3.32 0.30 1.00 1.00

ARRIOSTRE M2 3.32 0.40 1.00 1.33

ARRIOSTRE M2 3.32 0.60 1.00 1.99

M2 3.92 0.75 1.00 2.94

M2 3.92 0.98 1.00 3.84

VIGUETAS

EJE C-C/11-12 M2 3.24 0.10 2.00 0.65

ENTRE EJE F-F/11-12 M2 3.92 0.10 1.00 0.39

M2 2.10 0.10 1.00 0.21

M2 1.82 0.10 1.00 0.18

02.02.05 TERRAJEO PULIDO BOLEADO GRIS EN PARAPETO ML 70.27


AULAS ML 15.91 2.00 31.82

ML 11.24 2.00 22.48

ML 5.97 2.00 11.94

ESCALERA ML 2.45 1.00 2.45

ML 0.79 2.00 1.58

02.02.06 VESTIDURA DE DERRAMES ANCHO = 0.15 M ML 375.30


AULAS

1ER PISO

EJE F-F ENTRE EJES 10 AL 4 ML 0.85 1.00 0.85

ML 1.39 1.00 1.39

ML 3.75 1.00 3.75

ML 0.85 1.00 0.85

ML 1.39 1.00 1.39

11/87
HOJA DE METRADO

PROYECTO : AMPLIACION DE INFRAESTRUCTURA DE LA INSTITUCION EDUCATIVA"SAN JORGE" EN EL CENTRO POBLADO SUPTE SAN JORGE

FECHA : SETIEMBRE DEL 2011 HECHO POR: DAMS

SUB FORMULA : ARQUITECTURA

CENTRO POBLADO : SUPTE SAN JORGE DISTRITO : RUPA RUPA PROVINCIA : LEONCIO PRADO

MEDIDAS N SUB TOTAL


N DESCRIPCION DE TOTAL
UND LARGO ANCHO ALTO VECES LONG. AREA VOL. KG.

ML 3.75 1.00 3.75

ML 0.75 1.00 0.75

ML 1.81 1.00 1.81

ML 3.74 1.00 3.74

EJE A-A ENTRE EJES 10 AL 4 ML 3.74 2.00 7.48

ML 3.75 4.00 15.00

2DO PISO

EJE F-F ENTRE EJES 10 AL 4 ML 0.85 1.00 0.85

ML 1.39 1.00 1.39

ML 3.75 1.00 3.75

ML 0.85 1.00 0.85

ML 1.39 1.00 1.39

ML 3.75 1.00 3.75

ML 0.75 1.00 0.75

ML 1.81 1.00 1.81

ML 3.74 1.00 3.74

EJE A-A ENTRE EJES 10 AL 4 ML 3.74 2.00 7.48

ML 3.75 4.00 15.00

SS.HH.

EJE 1-1/B-F ML 3.35 2.00 6.70

EJE 3-3/B-F ML 3.35 2.00 6.70

EJE F-F/B-F ML 2.90 2.00 5.80

ENTRE EJE 2-2/EJE B-F ML 2.94 2.00 5.88

ML 2.82 2.00 5.64

ML 1.41 8.00 11.28

ML 2.12 12.00 25.44

AREA ADMINISTRATIVA Y SS.HH.

EJE 13-13/H-I ML 3.47 1.00 3.47

ML 1.00 1.00 1.00

EJE 14-14/H-I ML 3.00 1.00 3.00

EJE 15-15/H-I ML 4.45 1.00 4.45

ESCALERA

EJE C-C/11-12 ML 3.32 1.00 3.32

ENTRE EJE F-F/11-12 ML 3.92 1.00 3.92

ML 2.10 1.00 2.10

ML 1.82 1.00 1.82

02.02.07 BRUAS E = 1 CM ML 856.35


AULAS

1ER PISO.

EJE F-F ENTRE EJES 4-5 ML 2.64 4.00 10.56

ML 0.87 2.00 1.74

ML 1.34 2.00 2.68

ML 1.04 4.00 4.16

EJE F-F ENTRE EJES 5-6 ML 3.72 2.00 7.44

ML 1.04 4.00 4.16

EJE F-F ENTRE EJES 6-7 ML 2.64 4.00 10.56

ML 0.87 2.00 1.74

ML 1.34 2.00 2.68

ML 1.04 4.00 4.16

EJE F-F ENTRE EJES 7-8 ML 3.72 2.00 7.44

ML 1.04 4.00 4.16

12/87
HOJA DE METRADO

PROYECTO : AMPLIACION DE INFRAESTRUCTURA DE LA INSTITUCION EDUCATIVA"SAN JORGE" EN EL CENTRO POBLADO SUPTE SAN JORGE

FECHA : SETIEMBRE DEL 2011 HECHO POR: DAMS

SUB FORMULA : ARQUITECTURA

CENTRO POBLADO : SUPTE SAN JORGE DISTRITO : RUPA RUPA PROVINCIA : LEONCIO PRADO

MEDIDAS N SUB TOTAL


N DESCRIPCION DE TOTAL
UND LARGO ANCHO ALTO VECES LONG. AREA VOL. KG.

EJE F-F ENTRE EJES 7-9 ML 2.64 4.00 10.56

ML 0.87 2.00 1.74

EJE F-F ENTRE EJES 9-10 ML 3.70 2.00 7.40

ML 1.04 4.00 4.16

EJE A-A ENTRE EJES 10 AL 4 ML 3.72 12.00 44.64

ML 1.69 24.00 40.56

EJE 10-8-6-4 ENTRE EJES F-F Y A-A ML 2.68 12.00 32.16

2DO PISO

EJE F-F ENTRE EJES 4-5 ML 2.59 4.00 10.36

ML 0.87 2.00 1.74

ML 1.34 2.00 2.68

ML 1.00 4.00 4.00

EJE F-F ENTRE EJES 5-6 ML 3.72 2.00 7.44

ML 1.00 4.00 4.00

EJE F-F ENTRE EJES 6-7 ML 2.59 4.00 10.36

ML 0.87 2.00 1.74

ML 1.34 2.00 2.68

ML 1.00 4.00 4.00

EJE F-F ENTRE EJES 7-8 ML 3.72 2.00 7.44

ML 1.00 4.00 4.00

EJE F-F ENTRE EJES 8-9 ML 2.59 4.00 10.36

ML 0.87 2.00 1.74

EJE F-F ENTRE EJES 9-10 ML 3.70 2.00 7.40

ML 1.00 4.00 4.00

EJE A-A ENTRE EJES 10 AL 4 ML 3.72 12.00 44.64

ML 1.60 24.00 38.40

EJE 10-8-6-4 ENTRE EJES F-F Y A-A ML 2.75 12.00 33.00

ML 1.12 12.00 13.44

ML 3.44 24.00 82.56

SS.HH.

EJE 1-1/B-F ML 2.10 8.00 16.80

EJE 2-2/B-F ML 3.00 8.00 24.00

ML 3.35 4.00 13.40

EJE 3-3/B-F ML 2.10 8.00 16.80

EJE B-B/1-3 ML 3.00 8.00 24.00

ML 3.75 4.00 15.00

EJE F-F/1-3 ML 3.00 4.00 12.00

ML 2.78 4.00 11.12

AREA ADMINISTRATIVA Y SS.HH.

EJE 13-13/H-I ML 1.10 2.00 2.20

EJE 14-14/H-I ML 3.00 2.00 6.00

3.60 2.00 7.20

EJE 15-15/H-I ML 2.20 4.00 8.80

EJE H-H/13-15 ML 3.85 4.00 15.40

ML 3.00 8.00 24.00

EJE I-I/13-15 ML 3.85 4.00 15.40

ML 3.00 8.00 24.00

ESCALERA

EJE 11-11/C-F ML 3.04 2.00 6.08

ML 3.92 2.00 7.84

ML 3.03 2.00 6.06

ML 1.44 1.00 1.44

13/87
HOJA DE METRADO

PROYECTO : AMPLIACION DE INFRAESTRUCTURA DE LA INSTITUCION EDUCATIVA"SAN JORGE" EN EL CENTRO POBLADO SUPTE SAN JORGE

FECHA : SETIEMBRE DEL 2011 HECHO POR: DAMS

SUB FORMULA : ARQUITECTURA

CENTRO POBLADO : SUPTE SAN JORGE DISTRITO : RUPA RUPA PROVINCIA : LEONCIO PRADO

MEDIDAS N SUB TOTAL


N DESCRIPCION DE TOTAL
UND LARGO ANCHO ALTO VECES LONG. AREA VOL. KG.

ML 0.52 1.00 0.52

ML 4.50 1.00 4.50

EJE 12-12/C-F ML 3.04 4.00 12.16

ML 3.92 4.00 15.68

ML 3.03 4.00 12.12

ML 1.44 2.00 2.88

ML 0.52 2.00 1.04

ML 4.50 1.00 4.50

EJE C-C/11-12 ML 3.29 1.00 3.29

ML 2.86 4.00 11.44

02.02.08 CUBIERTA LADRILLO PASTELERO ARCILLA 3x25x25 ASENT. C/MORTERO DE C-A+IMPERMEAB. 467.58
AULAS

EJE F-F ENTRE 10-4 M2 27.30 6.65 1.00 181.55

M2 27.30 5.92 1.00 161.62

SS.HH.

M2 8.60 5.00 1.00 43.00

M2 8.60 5.86 1.00 50.40

ESCALERA

M2 6.40 3.95 1.00 25.28

M2 1.45 3.95 1.00 5.73

02.03.00 CIELORRASOS
02.03.01 CIELORRASOS CON MEZCLA CEMENTO ARENA 1:4 M2 630.71
AULA

1ER PISO

AULA 1 M2 7.57 4.19 1.00 31.72

M2 7.57 4.20 1.00 31.79

VEREDA M2 4.16 2.15 1.00 8.94

VEREDA M2 4.17 2.15 1.00 8.97

AULA 2 M2 7.57 4.20 1.00 31.79

M2 7.57 4.20 1.00 31.79

VEREDA M2 4.17 2.15 2.00 17.93

AULA 3 M2 7.57 4.20 1.00 31.79

M2 7.57 4.18 1.00 31.64

VEREDA M2 4.17 2.15 1.00 8.97

VEREDA M2 4.15 2.15 1.00 8.92

2DO PISO

AULA 1 M2 8.20 4.19 1.00 34.36

M2 8.20 4.20 1.00 34.44

VEREDA M2 4.16 2.20 1.00 9.15

VEREDA M2 4.17 2.20 1.00 9.17

AULA 2 M2 8.20 4.20 1.00 34.44

M2 8.20 4.20 1.00 34.44

VEREDA M2 4.17 2.20 2.00 18.35

AULA 3 M2 8.20 4.20 1.00 34.44

M2 8.20 4.18 1.00 34.28

VEREDA M2 4.17 2.20 1.00 9.17

VEREDA M2 4.15 2.20 1.00 9.13

SS.HH.

14/87
HOJA DE METRADO

PROYECTO : AMPLIACION DE INFRAESTRUCTURA DE LA INSTITUCION EDUCATIVA"SAN JORGE" EN EL CENTRO POBLADO SUPTE SAN JORGE

FECHA : SETIEMBRE DEL 2011 HECHO POR: DAMS

SUB FORMULA : ARQUITECTURA

CENTRO POBLADO : SUPTE SAN JORGE DISTRITO : RUPA RUPA PROVINCIA : LEONCIO PRADO

MEDIDAS N SUB TOTAL


N DESCRIPCION DE TOTAL
UND LARGO ANCHO ALTO VECES LONG. AREA VOL. KG.

M2 6.25 3.80 1.00 23.75

M2 5.04 3.80 1.00 19.15

AREA ADMINISTRATIVA Y SS.HH.

M2 3.90 5.00 2.00 39.00

M2 1.15 5.00 1.00 5.75

ESCALERA

M2 6.81 3.29 1.00 22.40

M2 1.35 3.29 1.00 4.44

02.04.00 PISOS Y VEREDAS


02.04.01 PISO DE CONCRETO

02.04.01.01 PISO DE CONCRETO E=4" Fc=140 kg/cm2 PULIDO ,BRUADO Y COLOREADO 607.40
AULAS M2

1ER PISO

AULA 1 M2 68.85

AULA 2 M2 68.63

AULA 3 M2 68.81

2DO PISO

AULA 1 M2 68.85

AULA 2 M2 68.63

AULA 3 M2 68.81

SS.HH.

M2 29.85

M2 29.85

AREA ADMINISTRATIVA Y SS.HH.

M2 41.39

ESCALERA

M2 16.45

02.04.02 VEREDAS

02.04.02.01 VEREDA DE CONCRETO BRUADO DE 4" M2 352.33


AULA

1ER PISO

VEREDA M2 27.30 2.25 1.00 61.43

VEREDA M2 29.10 1.00 1.00 29.10

VEREDA M2 8.30 0.90 1.00 7.47

VEREDA M2 3.35 0.90 1.00 3.02

2DO PISO

VEREDA M2 61.19

DESCUENTO DE PARAPETO M2 28.50 0.15 -1.00 -4.28

SS.HH.

M2 9.50 2.20 1.00 20.90

M2 10.40 1.00 1.00 10.40

M2 7.80 0.90 2.00 7.02

AREA ADMINISTRATIVA Y SS.HH.

M2 5.16 0.90 1.00 4.64

ESCALERA

M2 4.85 2.25 1.00 10.91

M2 5.85 0.90 1.00 5.27

M2 3.95 0.90 1.00 3.56

COMPLEMENTARIO DE CIRCULACION

15/87
HOJA DE METRADO

PROYECTO : AMPLIACION DE INFRAESTRUCTURA DE LA INSTITUCION EDUCATIVA"SAN JORGE" EN EL CENTRO POBLADO SUPTE SAN JORGE

FECHA : SETIEMBRE DEL 2011 HECHO POR: DAMS

SUB FORMULA : ARQUITECTURA

CENTRO POBLADO : SUPTE SAN JORGE DISTRITO : RUPA RUPA PROVINCIA : LEONCIO PRADO

MEDIDAS N SUB TOTAL


N DESCRIPCION DE TOTAL
UND LARGO ANCHO ALTO VECES LONG. AREA VOL. KG.

M2 43.00 2.25 1.00 96.75

M2 4.56 2.25 1.00 10.26

M2 4.81 2.15 1.00 10.34

M2 16.60 1.50 1.00 24.90

02.04.02.02 CONCRETO EN UAS DE VEREDA C:H - 1:8 M3 8.28


AULAS M3 68.05 0.15 0.40 1.00 4.08

SS.HH. M3 27.70 0.15 0.40 1.00 1.66

AREA ADMINISTRATIVA Y SS.HH. M3 5.16 0.15 0.40 1.00 0.31

ESCALERA M3 14.65 0.15 0.40 1.00 0.88

COMPLEMENTARIO DE CIRCULACION M3 68.97 0.15 0.40 1.00 4.14

02.04.02.03 JUNTAS DE CONSTRUCCION EN VEREDA E = 1" ML 58.95


ML 2.25 25.00

02.05.00 ZOCALOS Y CONTRAZOCALOS M2

02.05.01 ZOCALO DE CERAMICO 20x30 CM COLOR GRIS 131.18


SS.HH.

SS.HH. DE AREA ADMINISTRATIVA

02.05.02 CONTRAZOCALO CEMENTO S/COLOREAR H = 20 CM EXTERIORE ML 213.15


AULAS

1er piso ML 71.82 1.00 71.82

2do piso ML 57.91 1.00 57.91

ML 2.20 1.00 2.20

SS.HH.

ML 31.36 1.00 31.36

AREA ADMINISTRATIVA Y SS.HH.

ML 19.41 1.00 19.41

ESCALERA

ML 12.85 1.00 12.85

02.05.03 CONTRAZOCALO CEMENTO S/COLOREAR H = 20 CM INTERIORES ML 296.34


AULAS

1er piso ML 34.80 1.00 34.80

descuento puerta ML 1.10 -1.00 -1.10

ML 34.73 1.00 34.73

descuento puerta ML 1.10 -1.00 -1.10

ML 34.79 1.00 34.79

descuento puerta ML 1.10 -1.00 -1.10

2do piso ML 34.80 1.00 34.80

descuento puerta ML 1.10 -1.00 -1.10

ML 34.73 1.00 34.73

descuento puerta ML 1.10 -1.00 -1.10

ML 34.79 1.00 34.79

descuento puerta ML 1.10 -1.00 -1.10

SS.HH.

ML 23.46 2.00 46.92

descuento puerta ML 1.10 -2.00 -2.20

AREA ADMINISTRATIVA Y SS.HH.

ML 35.30 1.00 35.30

descuento puerta ML 1.10 -2.00 -2.20

ESCALERA

16/87
HOJA DE METRADO

PROYECTO : AMPLIACION DE INFRAESTRUCTURA DE LA INSTITUCION EDUCATIVA"SAN JORGE" EN EL CENTRO POBLADO SUPTE SAN JORGE

FECHA : SETIEMBRE DEL 2011 HECHO POR: DAMS

SUB FORMULA : ARQUITECTURA

CENTRO POBLADO : SUPTE SAN JORGE DISTRITO : RUPA RUPA PROVINCIA : LEONCIO PRADO

MEDIDAS N SUB TOTAL


N DESCRIPCION DE TOTAL
UND LARGO ANCHO ALTO VECES LONG. AREA VOL. KG.

ML 16.48 1.00 16.48

02.06.00 REVESTIMIENTO DE GRADAS Y ESCALERA


02.06.01 FORJADO Y REVESTIMIENTO DE GRADAS Y ESCALERAS DE CEMENTO PULIDO ML 1.65 44.00 72.60 72.60

02.06.02 FORJADO Y REVESTIMIENTO DE DESCANZO DE ESCALERA DE CEMENTO PULIDO M2 3.45 1.79 1.00 6.18 6.18

02.06.03 REVESTIMIENTO DE FONDO DE ESCALERA M2 26.44


M2 0.56 1.65 20.00 18.48

M2 3.45 1.79 1.00 6.18

02.06.04 REVESTIMIENTO DE PLACA ESCALERA C:A, 1:4 M2 51.91


M2 3.00 8.24 2.00 49.44

M2 0.15 8.24 2.00 2.47

02.06.05 CANTONERA DE ANGULO DE FIERRO DE 2"x2"x1/8" ML 1.65 22.00 36.30 36.30

02.07.00 CARPINTERIA DE MADERA


02.07.01 PUERTAS

02.07.01.01 PUERTA DE MADERA CEDRO TABLERO REBAJADO M2 52.47


AULAS

1er piso M2 1.10 2.30 3.00 7.59

2do piso M2 1.10 2.30 3.00 7.59

SS.HH.

M2 1.00 2.30 2.00 4.60

M2 0.90 2.00 2.00 3.60

M2 0.70 2.00 12.00 16.80

AREA ADMINISTRATIVA Y SS.HH.

M2 1.00 2.10 1.00 2.10

M2 0.90 2.10 1.00 1.89

02.07.01.02 COLOCACION DE PUERTAS UND 28.00


AULAS

1er piso UND 3.00

2do piso UND 3.00

SS.HH.

UND 16.00

AREA ADMINISTRATIVA Y SS.HH.

UND 2.00

02.07.01.03 TRABAZON DE PUERTAS CON BARROTES DE FIERRO LISO 1/2" M2 8.49


AULAS

1er piso M2 1.10 0.90 3.00 2.97

2do piso M2 1.10 0.90 3.00 2.97

SS.HH.

M2 1.00 0.90 2.00 1.80

AREA ADMINISTRATIVA Y SS.HH.

M2 1.00 0.90 1.00 0.90

M2 0.90 0.90 1.00 0.81

02.07.02 VENTANAS

17/87
HOJA DE METRADO

PROYECTO : AMPLIACION DE INFRAESTRUCTURA DE LA INSTITUCION EDUCATIVA"SAN JORGE" EN EL CENTRO POBLADO SUPTE SAN JORGE

FECHA : SETIEMBRE DEL 2011 HECHO POR: DAMS

SUB FORMULA : ARQUITECTURA

CENTRO POBLADO : SUPTE SAN JORGE DISTRITO : RUPA RUPA PROVINCIA : LEONCIO PRADO

MEDIDAS N SUB TOTAL


N DESCRIPCION DE TOTAL
UND LARGO ANCHO ALTO VECES LONG. AREA VOL. KG.

02.07.02.01 VENTANAS DE MADERA CON SEGURIDAD SEGN DISEO M2 140.60


AULAS

1er piso M2 1.10 2.30 3.00 7.59

2do piso M2 1.10 2.30 3.00 7.59

SS.HH.

M2 1.00 2.30 2.00 4.60

M2 0.90 2.00 2.00 3.60

M2 0.70 2.00 12.00 16.80

AREA ADMINISTRATIVA Y SS.HH.

M2 1.00 2.10 1.00 2.10

M2 0.90 2.10 1.00 1.89

02.07.02.02 COLOCACION DE VENTANAS 48.00


AULAS

1er piso UND 12.00

2do piso UND 12.00

SS.HH.

UND 4.00

AREA ADMINISTRATIVA Y SS.HH.

UND 5.00

02.08.00 CARPINTERIA METALICA Y CERRAJERIA


02.08.01 BARANDAS - PASAMANOS
02.08.01.01 BARANDA DE TUBERIA GALVANIZADO D = 2 1/2" INC/COLOCACIO ML 48.96
BARANDA AL BORDE DE PLACA 1er y 2do. TRAMO ML 4.10 18.00 73.80

BARANDA EN 1er TRAMO Y DESCANSO ML 3.52 3.00 10.56

BARANDA EN DESCANSO Y 2do. TRAMO ML 3.56 3.00 10.68

02.08.01.02 BARANDA DE TUBERIA FG D = 2 " EN PARAPETOS INCL./COLOC ML 78.12


ML 4.10 18.00 73.80

ML 3.52 3.00 10.56

02.08.02 SEPARADORES METALICOS P/URINARIOS


02.08.02.01 SEPARADOR P/URINARIO C/PLANCHA METALICA E=1/20" MARCO DE TUBO CUADRADO DE 1"x1.5MM S/DISEO INCL. FABRICACIN PINTURA Y COLOCACIN 1.74
En SS.HH. Varones

02.08.03 CERRAJERIA
02.08.03.01 CERRADURA DE 02 GOLPES TIPO FORTE PZA 13.00 13.00

02.08.03.02 CERRADURA DE PERILLA C/SEGURO INTERIOR PZA 14.00 14.00

02.08.03.03 BISAGRA DE 3 1/2"x3 1/2" PZA 88.00 88.00

02.08.03.04 MANIJA DE BRONCE DE 4" PARA PUERTAS PZA 14.00 14.00

02.09.00 VIDRIOS, CRISTALES Y SIMILARES


02.09.01 VIDRIOS SEMIDOBLES NACIONALES PIE2 551.43
METRADO DE VENTANAS X (FACTOR=11) 50.13 11.00

02.10.00 PINTURA
02.10.01 PINTURA EN INTERIORES

02.10.01.01 PINTURA LATEX EN MUROS INTERIORES M2 691.68

18/87
HOJA DE METRADO

PROYECTO : AMPLIACION DE INFRAESTRUCTURA DE LA INSTITUCION EDUCATIVA"SAN JORGE" EN EL CENTRO POBLADO SUPTE SAN JORGE

FECHA : SETIEMBRE DEL 2011 HECHO POR: DAMS

SUB FORMULA : ARQUITECTURA

CENTRO POBLADO : SUPTE SAN JORGE DISTRITO : RUPA RUPA PROVINCIA : LEONCIO PRADO

MEDIDAS N SUB TOTAL


N DESCRIPCION DE TOTAL
UND LARGO ANCHO ALTO VECES LONG. AREA VOL. KG.

AULAS

1ER PISO

EJE F-F ENTRE EJE 4-6 M2 0.85 2.95 1.00 2.51

M2 1.39 1.35 1.00 1.88

M2 3.75 1.35 1.00 5.06

EJE F-F ENTRE EJE 6-8 M2 0.85 2.95 1.00 2.51

M2 1.39 1.35 1.00 1.88

M2 3.75 1.35 1.00 5.06

EJE F-F ENTRE EJE 8-10 M2 0.75 2.95 1.00 2.21

M2 1.31 1.35 1.00 1.77

M2 3.75 1.35 1.00 5.06

EJE A-A ENTRE EJE 10-4 M2 3.74 2.00 2.00 14.96

M2 3.75 2.00 4.00 30.00

EJE 10-8-6-4 ENTRE EJE F-A M2 3.46 2.95 12.00 122.48

2DO PISO

EJE F-F ENTRE EJE 4-6 M2 0.85 2.90 1.00 2.47

M2 1.39 1.30 1.00 1.81

M2 3.75 1.30 1.00 4.88

EJE F-F ENTRE EJE 6-8 M2 0.85 2.90 1.00 2.47

M2 1.39 1.30 1.00 1.81

M2 3.75 1.30 1.00 4.88

EJE F-F ENTRE EJE 8-10 M2 0.75 2.90 1.00 2.18

M2 1.31 1.3 1.00 1.70

M2 3.75 1.30 1.00 4.88

EJE A-A ENTRE EJE 10-4 M2 3.74 1.95 2.00 14.59

M2 3.75 1.95 4.00 29.25

PARAPETO M2 2.00 1.54

PARAPETO M2 4.00 1.53

M2 3.46 3.00 8.00 83.04

M2 3.44 0.56 4.00 7.71

SS.HH.

EJE 1-1/B-F M2 2.95 1.80 2.00 10.62

EJE 2-2/B-F M2 2.95 2.70 4.00 31.86

EJE 3-3/B-F M2 2.95 1.80 2.00 10.62

EJE B-B/1-3 M2 3.36 2.70 2.00 18.14

EJE F-F/1-3 M2 2.38 2.70 2.00 12.85

EJE 1-3/B-F M2 2.16 2.12 8.00 36.63

M2 0.66 2.12 8.00 11.19

M2 0.78 2.12 8.00 13.23

M2 1.41 2.12 16.00 47.83

AREA ADMINISTRATIVA Y SS.HH.

EJE H-H/13-15 M2 3.45 2.70 1.00 9.32

EJE I-I/13-15 M2 3.45 2.70 1.00 9.32

EJE 13-13/H-I M2 3.07 0.80 1.00 2.46

EJE 14-14/H-I M2 3.17 2.70 1.00 8.56

EJE 15-15/H-I M2 4.05 2.70 1.00 10.94

ESCALERA

M2 2.84 1.53 1.00 4.35

M2 2.84 1.41 1.00 4.00

PARAPETO M2 1.96 1.05 1.00 2.06

M2 1.62 1.05 1.00 1.70

M2 1.00 1.31

19/87
HOJA DE METRADO

PROYECTO : AMPLIACION DE INFRAESTRUCTURA DE LA INSTITUCION EDUCATIVA"SAN JORGE" EN EL CENTRO POBLADO SUPTE SAN JORGE

FECHA : SETIEMBRE DEL 2011 HECHO POR: DAMS

SUB FORMULA : ARQUITECTURA

CENTRO POBLADO : SUPTE SAN JORGE DISTRITO : RUPA RUPA PROVINCIA : LEONCIO PRADO

MEDIDAS N SUB TOTAL


N DESCRIPCION DE TOTAL
UND LARGO ANCHO ALTO VECES LONG. AREA VOL. KG.

02.10.01.02 PINTURA LATEX EN INTERIORES COLUMNA Y VIGA M2 539.56


AULAS

COLUMNA

1ER PISO

EJE F-F Y 4-4 M2 0.45 2.88 1.00 1.30

EJE F-F Y 5-5 M2 1.04 2.88 1.00 3.00

EJE F-F Y 6-6 M2 0.82 2.88 1.00 2.36

EJE F-F Y 7-7 M2 1.04 2.88 1.00 3.00

EJE F-F Y 8-8 M2 0.82 2.88 1.00 2.36

EJE F-F Y 9-9 M2 1.04 2.88 1.00 3.00

EJE F-F Y 10-10 M2 0.45 2.88 1.00 1.30

EJE D-D Y 4-4 M2 0.25 2.74 1.00 0.69

EJE D-D Y 6-6 M2 0.25 2.88 2.00 1.44

EJE D-D Y 8-8 M2 0.25 2.88 2.00 1.44

EJE D-D Y 10-10 M2 0.25 2.88 1.00 0.72

EJE A-A Y 4-4 M2 0.45 2.88 1.00 1.30

EJE A-A Y 5-5 M2 1.04 2.88 1.00 3.00

EJE A-A Y 6-6 M2 0.82 2.88 1.00 2.36

EJE A-A Y 7-7 M2 1.04 2.88 1.00 3.00

EJE A-A Y 8-8 M2 0.82 2.88 1.00 2.36

EJE A-A Y 9-9 M2 1.04 2.88 1.00 3.00

EJE A-A Y 10-10 M2 0.45 2.88 1.00 1.30

2DO PISO

EJE F-F Y 4-4 M2 0.45 2.90 1.00 1.31

EJE F-F Y 5-5 M2 1.04 2.90 1.00 3.02

EJE F-F Y 6-6 M2 0.82 2.90 1.00 2.38

EJE F-F Y 7-7 M2 1.04 2.90 1.00 3.02

EJE F-F Y 8-8 M2 0.82 2.90 1.00 2.38

EJE F-F Y 9-9 M2 1.04 2.90 1.00 3.02

EJE F-F Y 10-10 M2 0.45 2.90 1.00 1.31

EJE D-D Y 4-4 M2 0.25 2.95 1.00 0.74

M2 0.25 1.12 1.00 0.28

EJE D-D Y 6-6 M2 0.25 2.95 2.00 1.48

M2 0.25 1.12 2.00 0.56

EJE D-D Y 8-8 M2 0.25 2.95 2.00 1.48

M2 0.25 1.12 2.00 0.56

EJE D-D Y 10-10 M2 0.25 2.95 1.00 0.74

M2 0.25 1.12 1.00 0.28

EJE A-A Y 4-4 M2 0.45 2.90 1.00 1.31

EJE A-A Y 5-5 M2 1.04 2.90 1.00 3.02

EJE A-A Y 6-6 M2 0.82 2.90 1.00 2.38

EJE A-A Y 7-7 M2 1.04 2.90 1.00 3.02

EJE A-A Y 8-8 M2 0.82 2.90 1.00 2.38

EJE A-A Y 9-9 M2 1.04 2.90 1.00 3.02

EJE A-A Y 10-10 M2 0.45 2.90 1.00 1.31

COLUMNETAS

EJE F-F ENTRE 4-5/6-7/8-9 M2 0.20 2.95 6.00 3.54

M2 0.13 2.95 3.00 1.15

EJE F-F ENTRE 10-4 M2 0.20 1.35 12.00 3.24

M2 0.13 1.35 6.00 1.05

EJE A-A ENTRE 10-4 M2 0.20 1.98 12.00 4.75

20/87
HOJA DE METRADO

PROYECTO : AMPLIACION DE INFRAESTRUCTURA DE LA INSTITUCION EDUCATIVA"SAN JORGE" EN EL CENTRO POBLADO SUPTE SAN JORGE

FECHA : SETIEMBRE DEL 2011 HECHO POR: DAMS

SUB FORMULA : ARQUITECTURA

CENTRO POBLADO : SUPTE SAN JORGE DISTRITO : RUPA RUPA PROVINCIA : LEONCIO PRADO

MEDIDAS N SUB TOTAL


N DESCRIPCION DE TOTAL
UND LARGO ANCHO ALTO VECES LONG. AREA VOL. KG.

M2 0.13 1.98 6.00 1.54

COLUMNETAS

EJE F-F ENTRE 4-5/6-7/8-9 M2 0.20 2.90 6.00 3.48

M2 0.13 2.90 3.00 1.13

EJE F-F ENTRE 10-4 M2 0.20 1.30 12.00 3.12

M2 0.13 1.30 6.00 1.01

EJE A-A ENTRE 10-4 M2 0.20 1.95 12.00 4.68

M2 0.13 1.95 6.00 1.52

SS.HH.

INTERIOR

EJE 1/B M2 0.24 3.87 1.00 0.93

EJE 1/E M2 0.60 4.88 1.00 2.93

EJE 1/F M2 0.45 3.87 1.00 1.74

EJE 2/B M2 0.32 3.87 1.00 1.24

EJE 2/E M2 0.90 4.88 1.00 4.39

EJE 2/F M2 0.32 3.87 1.00 1.24

EJE 3/B M2 0.24 3.87 1.00 0.93

EJE 3/E M2 0.60 4.88 1.00 2.93

EJE 3/F M2 0.45 3.87 1.00 1.74

COLUMNETAS

EJE 1-1 ENTRE B-F M2 0.20 2.00 4.00 1.60

EJE 2-2 ENTRE B-F M2 0.20 2.90 4.00 2.32

EJE 3-3 ENTRE B-F M2 0.20 2.00 4.00 1.60

EJE B-B ENTRE 1-3 M2 0.20 2.90 4.00 2.32

EJE F-F ENTRE 1-3 M2 0.20 2.90 4.00 2.32

ENTRE 2-2 / B-F M2 0.20 2.12 24.00 10.18

AREA ADMINISTRATIVA Y SS.HH.

INTERIOR

EJE 13/H M2 0.42 3.00 1.00 1.26

EJE 13/I M2 0.56 3.00 1.00 1.68

EJE 14/H M2 0.56 3.00 1.00 1.68

EJE 14/I M2 0.72 3.00 1.00 2.16

EJE 15/H M2 0.42 3.00 1.00 1.26

EJE 15/I M2 0.42 3.00 1.00 1.26

COLUMNETAS

EJE 13-13 ENTRE H-I M2 0.20 1.00 2.00 0.40

EJE 14-14 ENTRE H-I M2 0.20 2.90 4.00 2.32

EJE 15-15 ENTRE H-I M2 0.20 2.20 2.00 0.88

EJE H-H ENTRE 13-15 M2 0.20 2.90 4.00 2.32

EJE I-I ENTRE 13-15 M2 0.20 2.90 4.00 2.32

ESCALERA

INTERIOR

EJE 11/C M2 0.36 8.40 1.00 3.02

EJE 11/F M2 0.36 7.40 1.00 2.66

EJE 12/C M2 0.23 3.00 1.00 0.69

M2 0.36 5.40 1.00 1.94

EJE 12/F M2 0.23 3.00 1.00 0.69

M2 0.36 5.40 1.00 1.94

PLACA M2 0.30 8.24 2.00 4.94

PLACA M2 0.30 7.40 2.00 4.44

COLUMNETA

21/87
HOJA DE METRADO

PROYECTO : AMPLIACION DE INFRAESTRUCTURA DE LA INSTITUCION EDUCATIVA"SAN JORGE" EN EL CENTRO POBLADO SUPTE SAN JORGE

FECHA : SETIEMBRE DEL 2011 HECHO POR: DAMS

SUB FORMULA : ARQUITECTURA

CENTRO POBLADO : SUPTE SAN JORGE DISTRITO : RUPA RUPA PROVINCIA : LEONCIO PRADO

MEDIDAS N SUB TOTAL


N DESCRIPCION DE TOTAL
UND LARGO ANCHO ALTO VECES LONG. AREA VOL. KG.

EJE C-C/11-12 M2 0.20 1.51 2.00 0.60

M2 0.20 1.25 2.00 0.50

M2 0.20 1.05 4.00 0.84

VIGA

VIGUETAS DE ARRIOSTRE 1ER PISO

EJE F-F ENTRE 4-5 M2 1.25 0.10 2.00 0.25

M2 1.79 0.10 2.00 0.36

EJE F-F ENTRE 5-6 M2 4.15 0.10 2.00 0.83

EJE F-F ENTRE 6-7 M2 1.25 0.10 2.00 0.25

M2 1.79 0.10 2.00 0.36

EJE F-F ENTRE 7-8 M2 4.15 0.10 1.00 0.42

EJE F-F ENTRE 8-9 M2 1.25 0.10 2.00 0.25

M2 1.81 0.10 2.00 0.36

EJE F-F ENTRE 9-10 M2 1.25 0.10 2.00 0.25

M2 1.79 0.10 2.00 0.36

EJE A-A ENTRE EJES 10-9-8-7-6-5-4- M2 4.15 0.10 12.00 4.98

VIGA 1ER PISO

EJE F-F / 4-5 LATERAL M2 4.19 0.30 1.00 1.26

BASE M2 4.19 0.50 2.00 4.19

EJE F-F/5-6-7-8-9 LATERAL M2 4.20 0.30 4.00 5.04

BASE. M2 4.20 0.50 8.00 16.80

EJE F-F /9-10 LATERAL M2 4.18 0.30 1.00 1.25

BASE M2 4.18 0.50 2.00 4.18

EJE A-A ENTRE EJES 4-5 M2 4.19 0.30 1.00 1.26

M2 4.19 0.50 2.00 4.19

EJE A-A/5-6-7-8-9 M2 4.20 0.30 4.00 5.04

M2 4.20 0.50 8.00 16.80

EJE A-A/10-9 M2 4.18 0.30 1.00 1.25

M2 4.18 0.50 2.00 4.18

EJE F-F ENTRE EJES 4 AL 10 M2 25.17 0.40 1.00 10.07

M2 25.17 0.15 1.00 3.78

M2 25.17 0.21 1.00 5.29

EJE 10-8-6-4 ENTRE EJES F-F Y A-A M2 7.91 0.30 6.00 14.24

M2 8.37 0.50 2.00 8.37

M2 7.17 0.08 4.00 2.29

EJE 9-7-5 ENTRE EJES F-F Y A-A M2 7.17 0.30 3.00 6.45

M2 7.91 0.50 6.00 23.73

EJE 10-9-8-7-6-5-4/F-F M2 1.01 1.00 7.00 7.07

2DO PISO

VIGUETA DE ARRIOSTRE

EJE F-F ENTRE 4-5 M2 1.25 0.10 2.00 0.25

M2 1.79 0.10 2.00 0.36

EJE F-F ENTRE 4-6 M2 4.15 0.10 2.00 0.83

EJE F-F ENTRE 6-7 M2 1.25 0.10 2.00 0.25

M2 1.79 0.10 2.00 0.36

EJE F-F ENTRE 7-8 M2 4.15 0.10 2.00 0.83

EJE F-F ENTRE 8-9 M2 1.25 0.10 2.00 0.25

M2 1.81 0.10 2.00 0.36

EJE F-F ENTRE 9-10 M2 1.25 0.10 2.00 0.25

M2 1.79 0.10 2.00 0.36

EJE A-A ENTRE EJES 10-9-8-7-6-5-4 M2 4.15 0.10 12.00 4.98

VIGA

22/87
HOJA DE METRADO

PROYECTO : AMPLIACION DE INFRAESTRUCTURA DE LA INSTITUCION EDUCATIVA"SAN JORGE" EN EL CENTRO POBLADO SUPTE SAN JORGE

FECHA : SETIEMBRE DEL 2011 HECHO POR: DAMS

SUB FORMULA : ARQUITECTURA

CENTRO POBLADO : SUPTE SAN JORGE DISTRITO : RUPA RUPA PROVINCIA : LEONCIO PRADO

MEDIDAS N SUB TOTAL


N DESCRIPCION DE TOTAL
UND LARGO ANCHO ALTO VECES LONG. AREA VOL. KG.

EJE F-F / 4-5 LATERAL M2 4.19 0.30 1.00 1.26

BASE M2 4.19 0.50 2.00 4.19

EJE F-F/5-6-7-8-9 LATERAL M2 4.20 0.30 4.00 5.04

BASE. M2 4.20 0.50 8.00 16.80

EJE F-F /9-10 LATERAL M2 4.18 0.30 1.00 1.25

BASE M2 4.18 0.50 2.00 4.18

EJE A-A ENTRE EJES 4-5 M2 4.19 0.30 1.00 1.26

M2 4.19 0.50 2.00 4.19

EJE A-A/5-6-7-8-9 M2 4.20 0.30 4.00 5.04

M2 4.20 0.50 8.00 16.80

EJE A-A ENTRE 10-9 M2 4.18 0.30 1.00 1.25

M2 4.18 0.50 2.00 4.18

VIGA VOLADO M3 2.05 14.00 28.70

M3 0.78 14.00 10.92

VIGA TECHO M3 4.26 0.30 14.00 17.89

M3 4.26 0.30 7.00 8.95

EJE 4-6-8-10 ENTRE F-F AL A-A ARRIOSTRE M2 7.91 0.40 8.00 25.31

M2 7.17 0.08 4.00 2.29

SS.HH.

VIGAS

INTERIOR

EJE 1-1/B-F M2 3.45 0.50 2.00 3.45

M2 3.45 0.30 2.00 2.07

M2 3.45 0.17 2.00 1.17

TRIANGULAR M2 6.25 0.47 1.00 2.94

TRIANGULAR M2 5.05 0.47 1.00 2.37

EJE 2-2/B-F M2 3.45 0.50 2.00 3.45

M2 3.45 0.16 2.00 1.10

TRIANGULAR M2 6.25 0.46 1.00 2.88

TRIANGULAR M2 5.05 0.46 1.00 2.32

EJE 3-3/B-F M2 3.45 0.50 2.00 3.45

M2 3.45 0.30 2.00 2.07

M2 3.45 0.17 2.00 1.17

TRIANGULAR M2 6.25 0.47 1.00 2.94

TRIANGULAR M2 5.05 0.47 1.00 2.37

EJE B-B/1-3 M2 3.84 0.50 2.00 3.84

M2 3.84 0.30 2.00 2.30

DESCUENTO MURO M2 2.82 0.16 2.00 -0.90

EJE F-F/1-3 M2 3.84 0.50 2.00 3.84

M2 3.84 0.30 2.00 2.30

DESCUENTO MURO M2 3.84 0.16 2.00 -1.23

VIGUETAS

EJE 1-1/B-F M2 3.36 0.10 2.00 0.67

EJE 2-2/B-F M2 3.36 0.10 2.00 0.67

M2 2.92 0.10 2.00 0.58

M2 2.82 0.10 2.00 0.56

M2 1.41 0.10 8.00 1.13

EJE 3-3/B-F M2 3.36 0.10 2.00 0.67

EJE B-B/1-3 M2 3.75 0.10 2.00 0.75

EJE F-F/1-3 M2 2.78 0.10 2.00 0.56

ADMINISTRATIVO

VIGAS

23/87
HOJA DE METRADO

PROYECTO : AMPLIACION DE INFRAESTRUCTURA DE LA INSTITUCION EDUCATIVA"SAN JORGE" EN EL CENTRO POBLADO SUPTE SAN JORGE

FECHA : SETIEMBRE DEL 2011 HECHO POR: DAMS

SUB FORMULA : ARQUITECTURA

CENTRO POBLADO : SUPTE SAN JORGE DISTRITO : RUPA RUPA PROVINCIA : LEONCIO PRADO

MEDIDAS N SUB TOTAL


N DESCRIPCION DE TOTAL
UND LARGO ANCHO ALTO VECES LONG. AREA VOL. KG.

INTERIOR

EJE 13-13/H-I M2 4.53 0.20 1.00 0.91

BASE M2 4.53 0.30 1.00 1.36

EJE 14-14/H-I M2 4.53 0.20 2.00 1.81

M2 4.53 0.30 1.00 1.36

DESCUENTO DE MURO M2 3.60 0.16 1.00 -0.58

EJE 15-15/H-I M2 4.53 0.20 1.00 0.91

M2 4.53 0.30 1.00 1.36

EJE H-H/13-14 M2 4.05 0.20 1.00 0.81

M2 3.93 0.17 1.00 0.67

EJE H-H/14-15 M2 4.05 0.20 1.00 0.81

M2 3.93 0.17 1.00 0.67

EJE I-I/13-14 M2 4.05 0.20 1.00 0.81

M2 3.93 0.17 1.00 0.67

EJE I-I/14-15 M2 4.05 0.20 1.00 0.81

M2 3.93 0.17 1.00 0.67

VIGUETAS

EJE 13-13/H-I M2 3.47 0.10 1.00 0.35

EJE 14-14/H-I M2 3.57 0.10 1.00 0.36

EJE 15-15/H-I M2 4.45 0.10 1.00 0.45

EJE H-H/13-14 M2 3.85 0.10 1.00 0.39

EJE H-H/14-15 M2 3.85 0.10 1.00 0.39

EJE I-I/13-14 M2 3.85 0.10 1.00 0.39

EJE I-I/14-15 M2 3.85 0.10 1.00 0.39

ESCALERA

VIGAS

INTERIOR

EJE 11-11/C-F M2 4.92 0.40 1.00 1.97

M2 4.32 0.08 1.00 0.35

ARRIOSTRE M2 4.32 0.40 1.00 1.73

ARRIOSTRE M2 4.32 0.16 1.00 0.69

M2 3.94 0.16 1.00 0.63

M2 0.52 0.16 1.00 0.08

EJE 12-12/C-F M2 4.92 0.40 1.00 1.97

M2 4.32 0.08 1.00 0.35

ARRIOSTRE M2 4.32 0.40 1.00 1.73

ARRIOSTRE M2 4.32 0.16 1.00 0.69

M2 3.94 0.16 1.00 0.63

M2 0.52 0.16 1.00 0.08

EJE C-C/11-12 M2 3.32 0.30 1.00 1.00

M2 3.32 0.40 1.00 1.33

ARRIOSTRE M2 3.32 0.40 1.00 1.33

ARRIOSTRE M2 3.32 0.60 1.00 1.99

EJE F-F/11-12 M2 3.32 0.30 1.00 1.00

M2 3.32 0.30 1.00 1.00

ARRIOSTRE M2 3.32 0.40 1.00 1.33

ARRIOSTRE M2 3.32 0.60 1.00 1.99

VIGUETAS

EJE C-C/11-12 M2 3.24 0.10 2.00 0.65

ENTRE EJE F-F/11-12 M2 3.92 0.10 1.00 0.39

M2 2.10 0.10 1.00 0.21

M2 1.82 0.10 1.00 0.18

24/87
HOJA DE METRADO

PROYECTO : AMPLIACION DE INFRAESTRUCTURA DE LA INSTITUCION EDUCATIVA"SAN JORGE" EN EL CENTRO POBLADO SUPTE SAN JORGE

FECHA : SETIEMBRE DEL 2011 HECHO POR: DAMS

SUB FORMULA : ARQUITECTURA

CENTRO POBLADO : SUPTE SAN JORGE DISTRITO : RUPA RUPA PROVINCIA : LEONCIO PRADO

MEDIDAS N SUB TOTAL


N DESCRIPCION DE TOTAL
UND LARGO ANCHO ALTO VECES LONG. AREA VOL. KG.

DESCANSO M2 3.45 0.47 1.00 1.62

02.10.01.03 PINTURA EN CONTRAZOCALO CON ESMALTE H = 0.20 ML 303.14


AULAS

1er piso ML 34.80 1.00 34.80

descuento puerta ML 1.10 -1.00 -1.10

ML 34.73 1.00 34.73

descuento puerta ML 1.10 -1.00 -1.10

ML 34.79 1.00 34.79

descuento puerta ML 1.10 -1.00 -1.10

2do piso ML 34.80 1.00 34.80

descuento puerta ML 1.10 -1.00 -1.10

ML 34.73 1.00 34.73

descuento puerta ML 1.10 -1.00 -1.10

ML 34.79 1.00 34.79

descuento puerta ML 1.10 -1.00 -1.10

SS.HH.

ML 23.46 2.00 46.92

descuento puerta ML 1.10 -2.00 -2.20

AREA ADMINISTRATIVA Y SS.HH.

ML 35.30 1.00 35.30

descuento puerta ML 1.10 -2.00 -2.20

ESCALERA

ML 16.48 1.00 16.48

02.10.02 PINTURA EN EXTERIORES


02.10.02.01 PINTURA LATEX EN MUROS EXTERIORES M2 330.99
AULAS

1ER PISO

EJE F-F ENTRE EJE 4-6 M2 0.85 2.95 1.00 2.51

M2 1.39 1.35 1.00 1.88

M2 3.75 1.35 1.00 5.06

EJE F-F ENTRE EJE 6-8 M2 0.85 2.95 1.00 2.51

M2 1.39 1.35 1.00 1.88

M2 3.75 1.35 1.00 5.06

EJE F-F ENTRE EJE 8-10 M2 0.75 2.95 1.00 2.21

M2 1.31 1.35 1.00 1.77

M2 3.75 1.35 1.00 5.06

EJE A-A ENTRE EJE 10-4 M2 3.74 2.00 2.00 14.96

M2 3.75 2.00 4.00 30.00

2DO PISO

EJE F-F ENTRE EJE 4-6 M2 0.85 2.90 1.00 2.47

M2 1.39 1.30 1.00 1.81

M2 3.75 1.30 1.00 4.88

EJE F-F ENTRE EJE 6-8 M2 0.85 2.90 1.00 2.47

M2 1.39 1.30 1.00 1.81

M2 3.75 1.30 1.00 4.88

EJE F-F ENTRE EJE 8-10 M2 0.75 2.90 1.00 2.18

M2 1.31 1.3 1.00 1.70

M2 3.75 1.30 1.00 4.88

EJE A-A ENTRE EJE 10-4 M2 3.74 1.95 2.00 14.59

25/87
HOJA DE METRADO

PROYECTO : AMPLIACION DE INFRAESTRUCTURA DE LA INSTITUCION EDUCATIVA"SAN JORGE" EN EL CENTRO POBLADO SUPTE SAN JORGE

FECHA : SETIEMBRE DEL 2011 HECHO POR: DAMS

SUB FORMULA : ARQUITECTURA

CENTRO POBLADO : SUPTE SAN JORGE DISTRITO : RUPA RUPA PROVINCIA : LEONCIO PRADO

MEDIDAS N SUB TOTAL


N DESCRIPCION DE TOTAL
UND LARGO ANCHO ALTO VECES LONG. AREA VOL. KG.

M2 3.75 1.95 4.00 29.25

PARAPETO M2 2.00 1.54

PARAPETO M2 4.00 1.53

M2 2.10 1.00 1.00 2.10

SS.HH.

EJE 1-1/B-F M2 2.95 1.80 2.00 10.62

EJE 3-3/B-F M2 2.95 1.80 2.00 10.62

EJE B-B/1-3 M2 3.36 2.70 2.00 18.14

EJE F-F/1-3 M2 2.38 2.70 2.00 12.85

AREA ADMINISTRATIVA Y SS.HH.

EJE H-H/13-15 M2 3.45 2.70 1.00 9.32

EJE 13-13/H-I M2 3.07 0.80 1.00 2.46

EJE 15-15/H-I M2 4.05 2.70 1.00 10.94

ESCALERA

M2 2.84 1.53 1.00 4.35

M2 2.84 1.41 1.00 4.00

PARAPETO M2 1.96 1.05 1.00 2.06

M2 1.62 1.05 1.00 1.70

M2 1.00 1.31

02.10.02.02 PINTURA LATEX EN EXT. VIGAS Y COLUMNAS M2 463.68


AULAS

1ER PISO COLUMNA EXTERIOR

EJE F-F Y 4-4 M2 1.00 2.88 1.00 2.88

EJE F-F Y 5-5 M2 0.50 2.88 1.00 1.44

EJE F-F Y 6-6 M2 0.50 2.88 1.00 1.44

EJE F-F Y 7-7 M2 0.50 2.88 1.00 1.44

EJE F-F Y 8-8 M2 0.50 2.88 1.00 1.44

EJE F-F Y 9-9 M2 0.50 2.88 1.00 1.44

EJE F-F Y 10-10 M2 1.00 2.88 1.00 2.88

EJE A-A Y 4-4 M2 1.00 2.88 1.00 2.88

EJE A-A Y 5-5 M2 0.50 2.88 1.00 1.44

EJE A-A Y 6-6 M2 0.50 2.88 1.00 1.44

EJE A-A Y 7-7 M2 0.50 2.88 1.00 1.44

EJE A-A Y 8-8 M2 0.50 2.88 1.00 1.44

EJE A-A Y 9-9 M2 0.50 2.88 1.00 1.44

EJE A-A Y 10-10 M2 1.00 2.88 1.00 2.88

COLUMNETAS

EJE F-F ENTRE 4-5/6-7/8-9 M2 0.20 2.95 6.00 3.54

M2 0.13 2.95 3.00 1.15

EJE F-F ENTRE 10-4 M2 0.20 1.35 12.00 3.24

M2 0.13 1.35 6.00 1.05

EJE A-A ENTRE 10-4 M2 0.20 1.98 12.00 4.75

M2 0.13 1.98 6.00 1.54

2DO PISO COLUMNA EXTERIOR

EJE F-F Y 4-4 M2 1.13 2.90 1.00 3.28

EJE F-F Y 5-5 M2 0.76 2.90 1.00 2.20

EJE F-F Y 6-6 M2 0.76 2.90 1.00 2.20

EJE F-F Y 7-7 M2 0.76 2.90 1.00 2.20

EJE F-F Y 8-8 M2 0.76 2.90 1.00 2.20

EJE F-F Y 9-9 M2 0.76 2.90 1.00 2.20

26/87
HOJA DE METRADO

PROYECTO : AMPLIACION DE INFRAESTRUCTURA DE LA INSTITUCION EDUCATIVA"SAN JORGE" EN EL CENTRO POBLADO SUPTE SAN JORGE

FECHA : SETIEMBRE DEL 2011 HECHO POR: DAMS

SUB FORMULA : ARQUITECTURA

CENTRO POBLADO : SUPTE SAN JORGE DISTRITO : RUPA RUPA PROVINCIA : LEONCIO PRADO

MEDIDAS N SUB TOTAL


N DESCRIPCION DE TOTAL
UND LARGO ANCHO ALTO VECES LONG. AREA VOL. KG.

EJE F-F Y 10-10 M2 1.13 2.90 1.00 3.28

EJE A-A Y 4-4 M2 1.13 2.90 1.00 3.28

EJE A-A Y 5-5 M2 0.76 2.90 1.00 2.20

EJE A-A Y 6-6 M2 0.76 2.90 1.00 2.20

EJE A-A Y 7-7 M2 0.76 2.90 1.00 2.20

EJE A-A Y 8-8 M2 0.76 2.90 1.00 2.20

EJE A-A Y 9-9 M2 0.76 2.90 1.00 2.20

EJE A-A Y 10-10 M2 1.13 2.90 1.00 3.28

COLUMNATES

EJE F-F ENTRE 4-5/6-7/8-9 M2 0.20 2.90 6.00 3.48

M2 0.13 2.90 3.00 1.13

EJE F-F ENTRE 10-4 M2 0.20 1.30 12.00 3.12

M2 0.13 1.30 6.00 1.01

EJE A-A ENTRE 10-4 M2 0.20 1.95 12.00 4.68

M2 0.13 1.95 6.00 1.52

SS.HH.

EXTERIOR

EJE 1/B M2 0.24 3.87 1.00 0.93

EJE 1/E M2 0.60 4.88 1.00 2.93

EJE 1/F M2 0.45 3.87 1.00 1.74

EJE 2/B M2 0.32 3.87 1.00 1.24

EJE 2/E M2 0.90 4.88 1.00 4.39

EJE 2/F M2 0.32 3.87 1.00 1.24

EJE 3/B M2 0.24 3.87 1.00 0.93

EJE 3/E M2 0.60 4.88 1.00 2.93

EJE 3/F M2 0.45 3.87 1.00 1.74

COLUMNETAS

EJE 1-1 ENTRE B-F M2 0.20 2.00 4.00 1.60

EJE 3-3 ENTRE B-F M2 0.20 2.00 4.00 1.60

EJE B-B ENTRE 1-3 M2 0.20 2.90 4.00 2.32

EJE F-F ENTRE 1-3 M2 0.20 2.90 4.00 2.32

AREA ADMINISTRATIVA Y SS.HH.

EXTERIOR

EJE 13/H M2 0.70 3.00 1.00 2.10

EJE 13/I M2 0.30 3.00 1.00 0.90

EJE 14/H M2 0.40 3.00 1.00 1.20

EJE 15/H M2 0.70 3.00 1.00 2.10

EJE 15/I M2 0.30 3.00 1.00 0.90

COLUMNETAS

EJE 13-13 ENTRE H-I M2 0.20 1.00 2.00 0.40

EJE 15-15 ENTRE H-I M2 0.20 2.20 2.00 0.88

EJE H-H ENTRE 13-15 M2 0.20 2.90 4.00 2.32

ESCALERA

EXTERIOR

EJE 11/C M2 0.30 8.40 1.00 2.52

EJE 11/F M2 0.30 7.40 1.00 2.22

EJE 12/C M2 0.60 8.40 1.00 5.04

EJE 12/F M2 7.40 7.40 1.00 54.76

COLUMNETA

EJE C-C/11-12 M2 0.20 1.51 2.00 0.60

M2 0.20 1.25 2.00 0.50

M2 0.20 1.05 3.00 0.63

27/87
HOJA DE METRADO

PROYECTO : AMPLIACION DE INFRAESTRUCTURA DE LA INSTITUCION EDUCATIVA"SAN JORGE" EN EL CENTRO POBLADO SUPTE SAN JORGE

FECHA : SETIEMBRE DEL 2011 HECHO POR: DAMS

SUB FORMULA : ARQUITECTURA

CENTRO POBLADO : SUPTE SAN JORGE DISTRITO : RUPA RUPA PROVINCIA : LEONCIO PRADO

MEDIDAS N SUB TOTAL


N DESCRIPCION DE TOTAL
UND LARGO ANCHO ALTO VECES LONG. AREA VOL. KG.

VIGUETAS DE ARRIOSTRE 1ER PISO

EJE F-F ENTRE EJE 4-5 M2 1.25 0.10 2.00 0.25

M2 1.79 0.10 2.00 0.36

EJE F-F ENTRE EJE 5-6 M2 4.15 0.10 2.00 0.83

EJE F-F ENTRE EJE 6-7 M2 1.25 0.10 2.00 0.25

M2 1.79 0.10 2.00 0.36

EJE F-F ENTRE EJE 7-8 M2 4.15 0.10 1.00 0.42

EJE F-F ENTRE EJE 8-9 M2 1.25 0.10 2.00 0.25

EJE F-F ENTRE EJE 9-10 M2 1.81 0.10 2.00 0.36

M2 1.25 0.10 2.00 0.25

M2 1.79 0.10 2.00 0.36

EJE A-A ENTRE EJE 10-4 M2 4.15 0.10 12.00 4.98

VIGA 1ER PISO

EJE F-F / 4-5 LATERAL M2 4.19 0.30 1.00 1.26

BASE M2 4.19 0.50 2.00 4.19

EJE F-F/5-6-7-8-9 LATERAL M2 4.20 0.30 4.00 5.04

BASE. M2 4.20 0.50 8.00 16.80

EJE F-F /9-10 LATERAL M2 4.18 0.30 1.00 1.25

BASE M2 4.18 0.50 2.00 4.18

EJE A-A ENTRE EJES 4-5 M2 4.19 0.30 1.00 1.26

M2 4.19 0.50 2.00 4.19

EJE A-A/5-6-7-8-9 M2 4.20 0.30 4.00 5.04

M2 4.20 0.50 8.00 16.80

EJE A-A/10-9 M2 4.18 0.30 1.00 1.25

M2 4.18 0.50 2.00 4.18

EJE F-F ENTRE EJES 4 AL 10 M2 25.17 0.40 1.00 10.07

M2 25.17 0.15 1.00 3.78

M2 25.17 0.21 1.00 5.29

EJE 10-8-6-4 ENTRE EJES F-F Y A-A M2 7.91 0.30 6.00 14.24

M2 8.37 0.50 2.00 8.37

M2 7.17 0.08 4.00 2.29

EJE 9-7-5 ENTRE EJES F-F Y A-A M2 7.17 0.30 3.00 6.45

M2 7.91 0.50 6.00 23.73

EJE 10-9-8-7-6-5-4/F-F M2 1.01 1.00 7.00 7.07

2DO PISO

VIGUETA DE ARRIOSTRE

EJE F-F ENTRE 4-5 M2 1.25 0.10 2.00 0.25

M2 1.79 0.10 2.00 0.36

EJE F-F ENTRE 5-6 M2 4.15 0.10 2.00 0.83

EJE F-F ENTRE 6-7 M2 1.25 0.10 2.00 0.25

M2 1.79 0.10 2.00 0.36

EJE F-F ENTRE 7-8 M2 4.15 0.10 2.00 0.83

EJE F-F ENTRE 8-9 M2 1.25 0.10 2.00 0.25

M2 1.81 0.10 2.00 0.36

EJE F-F ENTRE 9-10 M2 1.25 0.10 2.00 0.25

M2 1.79 0.10 2.00 0.36

EJE A-A ENTRE EJES 10-9-8-7-6-5-4 M2 4.15 0.10 12.00 4.98

VIGA

EJE F-F / 4-5 LATERAL M2 4.19 0.30 1.00 1.26

BASE M2 4.19 0.50 2.00 4.19

EJE F-F/5-6-7-8-9 LATERAL M2 4.20 0.30 4.00 5.04

28/87
HOJA DE METRADO

PROYECTO : AMPLIACION DE INFRAESTRUCTURA DE LA INSTITUCION EDUCATIVA"SAN JORGE" EN EL CENTRO POBLADO SUPTE SAN JORGE

FECHA : SETIEMBRE DEL 2011 HECHO POR: DAMS

SUB FORMULA : ARQUITECTURA

CENTRO POBLADO : SUPTE SAN JORGE DISTRITO : RUPA RUPA PROVINCIA : LEONCIO PRADO

MEDIDAS N SUB TOTAL


N DESCRIPCION DE TOTAL
UND LARGO ANCHO ALTO VECES LONG. AREA VOL. KG.

BASE. M2 4.20 0.50 8.00 16.80

EJE F-F /9-10 LATERAL M2 4.18 0.30 1.00 1.25

BASE M2 4.18 0.50 2.00 4.18

EJE A-A ENTRE EJES 4-5 M2 4.19 0.30 1.00 1.26

M2 4.19 0.50 2.00 4.19

EJE A-A/5-6-7-8-9 M2 4.20 0.30 4.00 5.04

M2 4.20 0.50 8.00 16.80

EJE A-A ENTRE 10-9 M2 4.18 0.30 1.00 1.25

M2 4.18 0.50 2.00 4.18

VIGA VOLADO M3 2.05 14.00 28.70

M3 0.78 14.00 10.92

VIGA TECHO M3 4.26 0.30 14.00 17.89

M3 4.26 0.30 7.00 8.95

EJE 4-6-8-10 ENTRE F-F AL A-A ARRIOSTRE M2 7.91 0.40 8.00 25.31

M2 7.17 0.08 4.00 2.29

SS.HH.

VIGAS

EXTERIOR

EJE 1-1/B-F M2 3.88 0.50 2.00 3.88

TRIANGULAR M2 6.25 0.50 1.00 3.13

TRIANGULAR M2 5.05 0.50 1.00 2.53

TRIANGULAR M2 2.11 0.50 1.00 1.06

TRIANGULAR M2 0.95 0.50 1.00 0.48

EJE 2-2/B-FTRIANGULAR M2 2.11 0.50 1.00 1.06

TRIANGULAR M2 0.95 0.50 1.00 0.48

EJE 3-3/B-F M2 3.88 0.50 2.00 3.88

TRIANGULAR M2 6.25 0.50 1.00 3.13

TRIANGULAR M2 5.05 0.50 1.00 2.53

TRIANGULAR M2 2.11 0.50 1.00 1.06

TRIANGULAR M2 0.95 0.50 1.00 0.48

EJE B-B/1-3 M2 4.28 0.50 2.00 4.28

BORDE M2 8.60 0.78 1.00 6.71

EJE F-F/1-3 M2 4.28 0.50 2.00 4.28

BORDE M2 8.60 1.23 1.00 10.58

VIGUETAS

EJE 1-1/B-F M2 3.36 0.10 2.00 0.67

EJE 3-3/B-F M2 3.36 0.10 2.00 0.67

EJE B-B/1-3 M2 3.75 0.10 2.00 0.75

EJE F-F/1-3 M2 2.78 0.10 2.00 0.56

AREA ADMINISTRATIVA Y SS.HH.

VIGAS

EXTERIOR

EJE 13-13/H-I M2 5.13 0.40 1.00 2.05

EJE 15-15/H-I M2 5.13 0.40 1.00 2.05

EJE H-H/13-14 M2 4.53 0.40 1.00 1.81

VOLADO M2 1.15 1.10 1.00 1.27

EJE H-H/14-15 M2 4.53 0.40 1.00 1.81

EJE I-I/13-14 VOLADO M2 1.15 0.50 1.00 0.58

VIGUETAS

EJE 13-13/H-I M2 3.47 0.10 1.00 0.35

EJE 15-15/H-I M2 4.45 0.10 1.00 0.45

29/87
HOJA DE METRADO

PROYECTO : AMPLIACION DE INFRAESTRUCTURA DE LA INSTITUCION EDUCATIVA"SAN JORGE" EN EL CENTRO POBLADO SUPTE SAN JORGE

FECHA : SETIEMBRE DEL 2011 HECHO POR: DAMS

SUB FORMULA : ARQUITECTURA

CENTRO POBLADO : SUPTE SAN JORGE DISTRITO : RUPA RUPA PROVINCIA : LEONCIO PRADO

MEDIDAS N SUB TOTAL


N DESCRIPCION DE TOTAL
UND LARGO ANCHO ALTO VECES LONG. AREA VOL. KG.

EJE H-H/13-14 M2 3.85 0.10 1.00 0.39

EJE H-H/14-15 M2 3.85 0.10 1.00 0.39

ESCALERA

VIGAS

EXTERIOR

EJE 11-11/C-F M2 2.26 0.20 1.00 0.45

M2 2.26 0.30 1.00 0.68

M2 2.56 0.40 1.00 1.02

M2 0.48 0.40 1.00 0.19

EJE 12-12/C-F M2 7.19 0.40 1.00 2.88

M2 2.26 0.30 1.00 0.68

M2 2.26 0.20 1.00 0.45

ARRIOSTRE M2 4.92 0.40 1.00 1.97

M2 2.56 0.70 1.00 1.79

M2 0.48 0.70 1.00 0.34

EJE C-C/11-12 M2 3.92 0.40 1.00 1.57

ARRIOSTRE M2 3.92 0.40 1.00 1.57

M2 3.92 0.68 1.00 2.67

EJE F-F/11-12 M2 3.92 0.80 1.00 3.14

M2 3.32 0.30 1.00 1.00

ARRIOSTRE M2 3.32 0.40 1.00 1.33

ARRIOSTRE M2 3.32 0.60 1.00 1.99

M2 3.92 0.75 1.00 2.94

M2 3.92 0.98 1.00 3.84

VIGUETAS

EJE C-C/11-12 M2 3.24 0.10 2.00 0.65

ENTRE EJE F-F/11-12 M2 3.92 0.10 1.00 0.39

M2 2.10 0.10 1.00 0.21

M2 1.82 0.10 1.00 0.18

02.10.02.03 PINTURA LATEX EN EXTERIORES EN GARGOLAS M2 0.57


M2 0.20 0.20 12.00 0.48

M2 0.15 0.10 6.00 0.09

02.10.02.04 PINTURA EN ZOCALOS CON ESMALTE H = 0.20 ML 195.55


AULAS

1er piso ML 71.82 1.00 71.82

2do piso ML 57.91 1.00 57.91

ML 2.20 1.00 2.20

SS.HH.

ML 31.36 1.00 31.36

AREA ADMINISTRATIVA Y SS.HH.

ML 19.41 1.00 19.41

ESCALERA

ML 12.85 1.00 12.85

02.10.03 PINTURA EN CIELORRASO


02.10.03.01 PINTURA EN CIELORRASO SOBRE C:A M2 631.48
1ER PISO

AULA 1 M2 7.57 4.19 1.00 31.72

M2 7.57 4.20 1.00 31.79

VEREDA M2 4.16 2.15 1.00 8.94

30/87
HOJA DE METRADO

PROYECTO : AMPLIACION DE INFRAESTRUCTURA DE LA INSTITUCION EDUCATIVA"SAN JORGE" EN EL CENTRO POBLADO SUPTE SAN JORGE

FECHA : SETIEMBRE DEL 2011 HECHO POR: DAMS

SUB FORMULA : ARQUITECTURA

CENTRO POBLADO : SUPTE SAN JORGE DISTRITO : RUPA RUPA PROVINCIA : LEONCIO PRADO

MEDIDAS N SUB TOTAL


N DESCRIPCION DE TOTAL
UND LARGO ANCHO ALTO VECES LONG. AREA VOL. KG.

VEREDA M2 4.17 2.15 1.00 8.97

AULA 2 M2 7.57 4.20 1.00 31.79

M2 7.57 4.20 1.00 31.79

VEREDA M2 4.17 2.15 2.00 17.93

AULA 3 M2 7.57 4.20 1.00 31.79

M2 7.57 4.18 1.00 31.64

VEREDA M2 4.17 2.15 1.00 8.97

VEREDA M2 4.15 2.15 1.00 8.92

2DO PISO

AULA 1 M2 8.20 4.19 1.00 34.36

M2 8.20 4.20 1.00 34.44

VEREDA M2 4.16 2.20 1.00 9.15

VEREDA M2 4.17 2.20 1.00 9.17

AULA 2 M2 8.20 4.20 1.00 34.44

M2 8.20 4.20 1.00 34.44

VEREDA M2 4.17 2.20 2.00 18.35

AULA 3 M2 8.20 4.20 1.00 34.44

M2 8.20 4.18 1.00 34.28

VEREDA M2 4.17 2.20 1.00 9.17

VEREDA M2 4.15 2.20 1.00 9.13

SS.HH.

M2 6.25 3.80 1.00 23.75

M2 5.04 3.80 1.00 19.15

AREA ADMINISTRATIVA Y SS.HH.

M2 3.90 5.00 2.00 39.00

M2 1.15 5.00 1.00 5.75

ESCALERA

M2 6.81 3.29 1.00 22.40

M2 1.35 3.29 1.00 4.44

02.10.04 PINTURA EN ESTRUCTURA METALICA


02.10.04.01 PINTURA ESMALTE ANTICORROSIVO - TAPAJUNTAS METALICAS ML 12.80
ML 3.20 4.00 12.80

02.10.04.02 PINTURA ESMALTE ANTICORROSIVO EN BARANDAS ML 127.08


BARANDAS ML 4.10 18.00 73.80

02.11.00 OTROS
02.11.01 JUNTA DE CONSTRUCCION CON TEKNOPORT DE 1" M2 2.90 0.15 30.00 13.05 29.25

02.11.02 MALLA MOSQUETERO P/SUPER. VENTANAS DE NYLON M2 91.37 91.37

02.11.03 LIMPIEZA FINAL DE OBRA GLB 1.00 1.00 1.00

02.11.04 TAPA JUNTAS METALICAS DE 1/8" x 6" SEGN DISEO ML 3.20 12.80 40.96

02.11.05 DISEO DE MEZCLA 140, 175 Y 210 KG/CM2 GLB. 3.00 3.00

02.11.06 PRUEBA DE CALIDAD DEL CONCRETO (PRUEBA A COMPRESION) UND 40.00 40.00

02.11.07 PLACA RECORDATORIA UND 1.00 1.00

31/87
HOJA DE METRADO

PROYECTO : AMPLIACION DE INFRAESTRUCTURA DE LA INSTITUCION EDUCATIVA"SAN JORGE" EN EL CENTRO POBLADO SUPTE SAN JORGE

FECHA : SETIEMBRE DEL 2011 HECHO POR: DAMS

SUB FORMULA : ARQUITECTURA

CENTRO POBLADO : SUPTE SAN JORGE DISTRITO : RUPA RUPA PROVINCIA : LEONCIO PRADO

MEDIDAS N SUB TOTAL


N DESCRIPCION DE TOTAL
UND LARGO ANCHO ALTO VECES LONG. AREA VOL. KG.

32/87
HOJA DE METRADO

PROYECTO : AMPLIACION DE INFRAESTRUCTURA DE LA INSTITUCION EDUCATIVA"SAN JORGE" EN EL CENTRO POBLADO SUPTE SAN JORGE

FECHA : SETIEMBRE DEL 2011 HECHO POR: DAMS

SUB FORMULA : INSTALACIONES SANITARIAS

CENTRO POBLADO : SUPTE SAN JORGE DISTRITO : RUPA RUPA PROVINCIA : LEONCIO PRADO

MEDIDAS N SUB TOTAL


N DESCRIPCION DE TOTAL
UND LARGO ANCHO ALTO VECES LONG. AREA VOL. KG.

03.00.00 INSTALACIONES SANITARIAS


03.01.00 APARATOS SANITARIOS Y ACCESORIOS
03.01.01 INODORO TANQUE BAJO BLANCO CON ACCESORIOS PZA 15.00 15.00

03.01.02 LAVATORIO DE PARED BLANCO 1 LLAVE PZA 15.00 15.00

03.01.03 URINARIO DE LOSA DE PICO BLANCO ML 4.00 4.00

03.01.04 PAPELERA DE LOSA Y BARRA PLASTICA PZA 15.00 15.00

03.01.05 SUMINISTRO Y COLOC. KIDS DE ACCESORIOS DE SUJECIN EN SS.HH. MINUSVLIDOS, ACERO INOX. S/DISEO (02 RECTAS Y 01 OSCILANTE)

KIDS DE ACCESORIOS UND 2.00 2.00

03.01.06 COLOCACION DE APARATOS SANITARIOS UND 35.00 35.00

03.01.07 COLOCACION DE ACCESORIOS SANITARIOS UND 15.00 15.00

03.02.00 SALIDA DE DESAGUE


03.02.01 SALIDA DE DESAGUE EN PVC 2" PTO 20.00 20.00

03.02.02 SALIDA DE DESAGUE EN PVC DE 4" PTO 15.00 15.00

03.02.03 SALIDA DE VENTILACION 2" PTO 4.00 4.00

03.03.00 RED DE DISTRIBUCION


03.03.01 RED DE DISTRIBUCION DE DESAGUE TUBERIA PVC SAP DE 6" ML 105.27 105.27

03.03.02 RED DE DISTRIBUCION DE DESAGUE TUBERIA PVC SAP DE 4" ML 28.67 28.67

03.03.03 RED DE DISTRIBUCION TUBERIA DE DESAGUE PVC SAP DE 2" ML 46.67

03.04.00 ACCESORIOS DE REDES


03.04.01 CODO PVC SAP 2"X 90 PZA 19.00 19.00

03.04.02 CODO PVC SAP 2"X 45 PZA 8.00 8.00

03.04.03 CODO PVC SAP DE 4"X 90 PZA 2.00 2.00

03.04.04 YEE PVC SAP SANITARIA 4" A 2" PZA 10.00 10.00

03.04.05 YEE DE PVC SAP DE 2" UND 15.00 15.00

03.04.06 YEE PVC SAP 4"X4" PZA 3.00 3.00

03.04.07 TEE PVC SAP DE 4"x 4" PZA 12.00 12.00

03.04.08 REDUCCIN PVC SAP DE 4" A 2" PZA 8.00 8.00

03.05.00 ADITAMENTOS VARIOS


03.05.01 SUMIDEROS CROMADOS DE 2" EN PISO PZA 9.00 9.00

03.05.02 SOMBRERO DE VENTILACIN PVC DE 2" PZA 4.00 4.00

1/87
HOJA DE METRADO

PROYECTO : AMPLIACION DE INFRAESTRUCTURA DE LA INSTITUCION EDUCATIVA"SAN JORGE" EN EL CENTRO POBLADO SUPTE SAN JORGE

FECHA : SETIEMBRE DEL 2011 HECHO POR: DAMS

SUB FORMULA : INSTALACIONES SANITARIAS

CENTRO POBLADO : SUPTE SAN JORGE DISTRITO : RUPA RUPA PROVINCIA : LEONCIO PRADO

MEDIDAS N SUB TOTAL


N DESCRIPCION DE TOTAL
UND LARGO ANCHO ALTO VECES LONG. AREA VOL. KG.

03.05.03 REGISTRO DE BRONCE DE 4" PZA 5.00 5.00

03.06.00 CAMARA DE INSPECCION


03.06.01 CAJA DE REGISTRO DE DESAGUE 12" X 24" PZA 8.00 8.00

03.07.00 SISTEMA DE AGUA FRIA


03.07.01 SALIDA DE AGUA FRIA CON TUBERIA DE PVC SAP 1/2" PTO 38.00 38.00

03.08.00 RED DE DISTRIBUCION


03.08.01 RED DE DISTRIBUCION TUBERIA DE 3/4" PVC-SAP ML 150.30

03.09.00 ACCESORIOS DE REDES


03.09.01 CODO PVC SAP DE 1/2" AGUA FRIA UND 47.00 47.00
03.09.02 CODO PVC SAP DE 3/4" AGUA FRIA PZA 11.00 11.00
03.09.03 TEE PVC SAP DE 3/4" PARA AGUA PZA 5.00 5.00
03.09.04 TEE PVC SAP DE 1/2" PARA AGUA PZA 28.00 28.00

03.09.05 REDUCCIN PVC SAP DE 3/4" A 1/2" PZA 4.00 4.00

03.10.00 LLAVES Y VALVULAS


03.10.01 VALVULA COMPUERTA DE BRONCE ROSCADA DE 3/4" UND 2.00 2.00
03.10.02 VALVULAS DE INTERRUPCION GENERAL PZA 1.00 1.00
03.10.03 LLAVES DE PASO UND 5.00 5.00

03.11.00 PIEZAS VARIAS


03.11.01 CAJA METALICA PARA VALVULAS DE 12" X 12" PZA 5.00 5.00

2/87
HOJA DE METRADO

PROYECTO : AMPLIACION DE INFRAESTRUCTURA DE LA INSTITUCION EDUCATIVA"SAN JORGE" EN EL CENTRO POBLADO SUPTE SAN JORGE

FECHA : SETIEMBRE DEL 2011 HECHO POR: DAMS

SUB FORMULA : INSTALACIONES ELECTRICAS

CENTRO POBLADO : SUPTE SAN JORGE DISTRITO : RUPA RUPA PROVINCIA : LEONCIO PRADO

MEDIDAS N SUB TOTAL


N DESCRIPCION DE TOTAL
UND LARGO ANCHO ALTO VECES LONG. AREA VOL. KG.

04.00.00 INSTALACIONES ELECTRICAS


04.01.00 SALIDAS ELECTRICAS
04.01.01 SALIDA PARA CENTROS DE LUZ PTO 55.00 55.00
04.01.02 SALIDA PARA TOMACORRIENTE BIPOLAR DOBLE PTO 51.00 51.00
04.01.03 SALIDA EN LA PARED PARA INTERRUPTOR PTO 18.00 18.00

04.02.00 CANALIZACION Y / O TUBERIAS


04.02.01 TUBERIA PVC SAP P/INST. ELECTRICAS 20mm ML 285.92
ML 3.96 1.00 3.96

ML 4.73 1.00 4.73

ML 3.98 1.00 3.98

ML 4.24 1.00 4.24

ML 2.03 1.00 2.03

ML 1.86 1.00 1.86

ML 1.16 1.00 1.16

ML 0.94 1.00 0.94

ML 1.66 1.00 1.66

ML 3.98 2.00 7.96

ML 4.31 2.00 8.62

ML 3.98 2.00 7.96

ML 2.01 2.00 4.02

ML 4.42 2.00 8.84

ML 3.97 2.00 7.94

ML 4.17 2.00 8.34

ML 2.01 2.00 4.02

ML 3.98 2.00 7.96

ML 4.42 2.00 8.84

ML 3.98 2.00 7.96

ML 1.90 2.00 3.80

ML 4.19 2.00 8.38

ML 3.98 2.00 7.96

ML 3.15 2.00 6.30

ML 4.41 2.00 8.82

ML 4.05 2.00 8.10

ML 4.39 2.00 8.78

ML 1.94 2.00 3.88

ML 4.06 2.00 8.12

ML 4.22 2.00 8.44

ML 4.26 2.00 8.52

ML 2.90 2.00 5.80

ML 2.24 2.00 4.48

ML 1.50 2.00 3.00

ML 8.00 1.00 8.00

ML 3.92 1.00 3.92

ML 2.76 1.00 2.76

ML 3.60 1.00 3.60

ML 2.19 1.00 2.19

04.02.02 TUBERIA PVC SAP P/INST. ELECTRICAS 20mm (Toma Corrientes) ML 157.69
ML 2.89 2.00 5.78

1/87
HOJA DE METRADO

PROYECTO : AMPLIACION DE INFRAESTRUCTURA DE LA INSTITUCION EDUCATIVA"SAN JORGE" EN EL CENTRO POBLADO SUPTE SAN JORGE

FECHA : SETIEMBRE DEL 2011 HECHO POR: DAMS

SUB FORMULA : INSTALACIONES ELECTRICAS

CENTRO POBLADO : SUPTE SAN JORGE DISTRITO : RUPA RUPA PROVINCIA : LEONCIO PRADO

MEDIDAS N SUB TOTAL


N DESCRIPCION DE TOTAL
UND LARGO ANCHO ALTO VECES LONG. AREA VOL. KG.

ML 4.45 2.00 8.90

ML 3.08 2.00 6.16

ML 2.63 2.00 5.26

ML 4.71 2.00 9.42

ML 3.06 2.00 6.12

ML 2.83 2.00 5.66

ML 5.24 2.00 10.48

ML 6.42 2.00 12.84

ML 4.02 2.00 8.04

ML 3.93 2.00 7.86

ML 2.73 2.00 5.46

ML 3.55 2.00 7.10

ML 3.41 2.00 6.82

ML 2.90 2.00 5.80

ML 3.72 2.00 7.44

ML 3.68 2.00 7.36

ML 2.93 2.00 5.86

ML 1.24 2.00 2.48

ML 3.38 1.00 3.38

ML 3.04 1.00 3.04

ML 2.94 1.00 2.94

ML 3.19 1.00 3.19

04.02.03 TUBERIA PVC SAP P/INST. ELECTRICAS 40mm (Sub-Terraneo) ML 111.40


ML 10.00 1.00 10.00

ML 7.50 1.00 7.50

ML 45.00 1.00 45.00

ML 35.60 1.00 35.60

ML 7.50 1.00 7.50

04.02.04 TUBERIA PVC SAP P/INST. ELECTRICAS 25mm (Sub-Terraneo) ML 88.40


ML 0.81 1.00 0.81

ML 7.02 1.00 7.02

ML 7.24 1.00 7.24

ML 44.60 1.00 44.60

ML 35.85 1.00 35.85

04.03.00 CONDUCTORES Y/O CABLES


04.03.01 CONDUCTOR DE COBRE LSOH 4 MM2 ML 442.17
ML 2.89 6.00 17.34

ML 4.45 6.00 26.70

ML 3.08 6.00 18.48

ML 2.63 6.00 15.78

ML 4.71 6.00 28.26

ML 3.06 6.00 18.36

ML 2.83 6.00 16.98

ML 5.24 6.00 31.44

ML 6.42 6.00 38.52

ML 4.02 6.00 24.12

ML 3.93 6.00 23.58

ML 2.73 6.00 16.38

ML 3.55 6.00 21.30

2/87
HOJA DE METRADO

PROYECTO : AMPLIACION DE INFRAESTRUCTURA DE LA INSTITUCION EDUCATIVA"SAN JORGE" EN EL CENTRO POBLADO SUPTE SAN JORGE

FECHA : SETIEMBRE DEL 2011 HECHO POR: DAMS

SUB FORMULA : INSTALACIONES ELECTRICAS

CENTRO POBLADO : SUPTE SAN JORGE DISTRITO : RUPA RUPA PROVINCIA : LEONCIO PRADO

MEDIDAS N SUB TOTAL


N DESCRIPCION DE TOTAL
UND LARGO ANCHO ALTO VECES LONG. AREA VOL. KG.

ML 3.41 6.00 20.46

ML 2.90 6.00 17.40

ML 3.72 6.00 22.32

ML 3.68 6.00 22.08

ML 2.93 6.00 17.58

ML 1.24 6.00 7.44

ML 3.38 3.00 10.14

ML 3.04 3.00 9.12

ML 2.94 3.00 8.82

ML 3.19 3.00 9.57

04.03.02 CONDUCTOR DE COBRE LSOH DE 2.5 MM2 ML 733.61


ML 3.96 3.00 11.88

ML 4.73 3.00 14.19

ML 3.98 3.00 11.94

ML 4.24 3.00 12.72

ML 2.03 3.00 6.09

ML 1.86 3.00 5.58

ML 1.16 3.00 3.48

ML 0.94 3.00 2.82

ML 1.66 3.00 4.98

ML 3.98 6.00 23.88

ML 4.31 6.00 25.86

ML 3.98 6.00 23.88

ML 2.01 6.00 12.06

ML 4.42 6.00 26.52

ML 3.97 6.00 23.82

ML 4.17 6.00 25.02

ML 2.01 6.00 12.06

ML 3.98 6.00 23.88

ML 4.42 6.00 26.52

ML 3.98 6.00 23.88

ML 1.90 6.00 11.40

ML 4.19 6.00 25.14

ML 3.98 6.00 23.88

ML 3.15 6.00 18.90

ML 4.41 6.00 26.46

ML 4.05 6.00 24.30

ML 4.39 6.00 26.34

ML 1.94 6.00 11.64

ML 4.06 6.00 24.36

ML 4.22 6.00 25.32

ML 4.26 6.00 25.56

ML 2.90 6.00 17.40

ML 2.24 6.00 13.44

ML 1.50 6.00 9.00

ML 8.00 3.00 24.00

ML 3.92 3.00 11.76

ML 2.76 3.00 8.28

ML 3.60 3.00 10.80

ML 2.19 3.00 6.57

3/87
HOJA DE METRADO

PROYECTO : AMPLIACION DE INFRAESTRUCTURA DE LA INSTITUCION EDUCATIVA"SAN JORGE" EN EL CENTRO POBLADO SUPTE SAN JORGE

FECHA : SETIEMBRE DEL 2011 HECHO POR: DAMS

SUB FORMULA : INSTALACIONES ELECTRICAS

CENTRO POBLADO : SUPTE SAN JORGE DISTRITO : RUPA RUPA PROVINCIA : LEONCIO PRADO

MEDIDAS N SUB TOTAL


N DESCRIPCION DE TOTAL
UND LARGO ANCHO ALTO VECES LONG. AREA VOL. KG.

04.03.03 CONDUCTOR DE COBRE TRIPLE N2XSH 3-1 x 35 MM2 ML 26.10


ML 4.96 3.00 14.88

ML 11.07 3.00 33.21

ML 13.10 3.00 39.30

ML 10.17 3.00 30.51

ML 10.17 3.00 30.51

ML 13.01 3.00 39.03

ML 12.45 3.00 37.35

ML 9.79 3.00 29.37

04.03.04 CONDUCTOR DE COBRE TRIPLE N2XSH 1x6MM2 ML 325.80


ML 8.00 3.00 24.00

ML 9.00 3.00 27.00

ML 6.00 3.00 18.00

ML 7.50 3.00 22.50

04.03.05 CONDUCTOR DE COBRE DUPLEX N2XSH 2-1 x 6 MM2 ML 402.00

04.04.00 ACCESORIOS
04.04.01 TOMACORRIENTE DE BAQUELITA DOBLE PTO 51.00 51.00
04.04.02 TUBERIA PVC SAP P/INST. ELECTRICAS 50mm ML 10.00 10.00
04.04.03 INTERRUPTOR DE BAQUELITA SIMPLE PTO 14.00 14.00
04.04.04 INTERRUPTOR DE BAQUELITA DOBLE PTO 9.00 9.00
04.04.05 INTERRUPTOR DE BAQUELITA TRIPLE PTO 2.00 2.00
04.04.06 INTERRUPTOR BAQUELITA DE CONMUTACION PTO 2.00 2.00
04.04.07 SALIDA PARA CAJA DE PASE 100 X 100 mm PTO 6.00 6.00

04.05.00 TABLERO Y SUB TABLEROS


04.05.01 TABLERO GENERAL UND 1.00 1.00
04.05.02 TABLERO DE DISTRIBUCIN (TD-1,3) UND 2.00 2.00

04.05.03 TABLERO DE DISTRIBUCIN (TD-2,4) UND 2.00 2.00

04.05.04 TABLERO DE DISTRIBUCIN (TD-5) UND 1.00 1.00

04.05.05 CONEXIN A RED EXTERNA Y MEDIDORES UND 1.00 1.00

04.06.00 ARTEFACTOS Y EQUIPOS DE ILUMINACION


04.06.01 FOCO AHORRADOR + ACCESORIOS UND 7.00 7.00
04.06.02 LUMINARIA DE 36 W X 3 UNIDADES + ACCESORIOS PTO 12.00 12.00
04.06.03 LUMINARIA DE 36 W X 2 UNIDADES + ACCESORIOS PTO 33.00 33.00
04.06.04 LUMINARIA DE 18 W X 2 UNIDADES MAS ACCESORIOS PTO 5.00 5.00
04.06.05 REFLECTORES DE ILUMINACION EN EXTERIORES 250 W UND 12.00 12.00

04.07.00 OTROS
04.07.01 POSTE DE SOPORTE DE CONCRETO CENTRIFUGADO UND 6.00 6.00
04.07.02 POZO DE TIERRA INCLUIDO INSTALACION GLB 3.00 3.00
04.07.03 BUZON DE REGISTRO DE C-A DE 400x 400mm UND 3.00 3.00
04.07.04 SUMINISTRO DE LUZ GLB 1.00 1.00

4/87
HOJA DE METRADO

PROYECTO : AMPLIACION DE INFRAESTRUCTURA DE LA INSTITUCION EDUCATIVA"SAN JORGE" EN EL CENTRO POBLADO SUPTE SAN JORGE

FECHA : SETIEMBRE DEL 2011 HECHO POR: DAMS

SUB FORMULA : LOSA MULTIDEPORTIVA

CENTRO POBLADO : SUPTE SAN JORGE DISTRITO : RUPA RUPA PROVINCIA : LEONCIO PRADO

MEDIDAS N SUB TOTAL


N DESCRIPCION DE TOTAL
UND LARGO ANCHO ALTO VECES LONG. AREA VOL. KG.

01.00 LOSA MULTIDEPORTIVA


01.01 TRABAJOS PRELIMINARES
01.01.01 TRAZO NIVELES Y REPLANTEO PRELIMINAR M2 28.00 15.00 1.00 420.00 504.00
01.01.02 DEMOLICION DE LOSA DEPORTIVA E=4" M3 32.65 21.24 0.30 1.00 208.05 138.70

01.01.03 TRANSPORTE DE MATERIALES DE HUANUCO A OBRA VER HOJA DE CALCULO DE FLETE

01.02.00 MOVIMIENTO DE TIERRAS


01.02.01 RELLENO CON MATERIAL DE PRESTAMO MANUAL M3 28.00 15.00 0.25 1.00 105.00 100.80
01.02.02 PERFILADO Y COMPACTACION A NIVEL DE RASANTE M2 28.00 15.00 1.00 420.00 504.00
01.02.03 COLOCACION DE RELLENO ESTRUCTURAL E=10CM M2 28.00 15.00 1.00 420.00 504.00
01.02.04 EXCAVACION DE ZANJAS PARA SARDINELES (UAS) M3 43.00 0.20 0.20 2.00 3.44 7.36
01.02.05 ELIMINACION DE MATERIAL EXCEDENTE C/MAQUINARIA DIST.=5 M3 1.25 260.06 146.06

01.03.00 OBRAS DE CONCRETO ARMADO


01.03.01 ENCOFRADO Y DESENCOFRADO PARA LOSA M2 49.00
Encofrado alternado intermedio long. M2 28 0.10 3.00 8.40

Encofrado alternado intermedio trans. M2 15 0.10 5.00 7.50

Encofrado alternado lateral long. M2 28 0.30 2.00 16.80

Encofrado alternado lateral trans. M2 15 0.30 2.00 9.00

losa en arcos M2 6 0.20 2.00 2.40

01.03.02 CONCRETO F'C=140 KG/CM2 LOSA MULTIDEPORTIVA M2 512.00


Concreto en losas M2 28 15.00 1.00 420.00

Concrto en losas de arcos M2 4 1.00 2.00 8.00

01.03.03 CONCRETO F'C= 140 KG/CM2 M3 7.61


Sardinel M3 56 0.20 0.20 2.00 4.48

Dados de anclaje M3 0.3 0.30 0.35 2.00 0.06

Dados de Parantes M3 0.3 0.45 0.35 4.00 0.19

01.03.04 ACERO FY =4200 KG/CM2 PARA LOSA DEPORTIVA KG 839.25

01.04.00 VARIOS
01.04.01 JUNTAS DE DILATACION EN LOSA DEPORTIVA E=1", H=0.10 M. ML 64.00
28.00 1.00 28.00

15.00 2.00 30.00

01.04.02 JUNTAS DE CONTRACCION EN LOSA DEPORTIVA E=3/4", H=0.05 M ML 110.00


28.00 2.00 56.00

15.00 3.00 45.00

01.04.03 EQUIPAMIENTO DEPORTIVO GLB 1.00


arco de fulbito 2.00

tablero para basket 2.00

soporte de net de voley 2.00

01.04.04 CURADO DE LOSA M2 504.00


Tendido de arrocera 28.00 15.00 1.00 420.00

Limpieza de arrocera 28.00 15.00 1.00 420.00

01.04.05 DEMARCACION DE LOSA DEPORTIVA ML 301.50

1/87
HOJA DE METRADO

PROYECTO : AMPLIACION DE INFRAESTRUCTURA DE LA INSTITUCION EDUCATIVA"SAN JORGE" EN EL CENTRO POBLADO SUPTE SAN JORGE

FECHA : SETIEMBRE DEL 2011 HECHO POR: DAMS

SUB FORMULA : LOSA MULTIDEPORTIVA

CENTRO POBLADO : SUPTE SAN JORGE DISTRITO : RUPA RUPA PROVINCIA : LEONCIO PRADO

MEDIDAS N SUB TOTAL


N DESCRIPCION DE TOTAL
UND LARGO ANCHO ALTO VECES LONG. AREA VOL. KG.

cancha de Basket color anaranjado 122.00 1.00 122.00

cancha de Voley color amarillo 58.50 1.00 58.50

Cancha de fulbito color blanco 121.00 1.00 121.00

02.00.00 TRIBUNAS Y COBERTURA


02.01 TRABAJOS PRELIMINARES
02.01.01 TRAZO NIVELES Y REPLANTEO PRELIMINAR M2 29.08 4.28 1.00 124.46 124.46

02.02.00 MOVIMIENTO DE TIERRAS


02.02.01 EXCAVACION MASIVA MANUAL M3 34.73
25.70 4.28 0.30 1.00 33.00

3.40 1.70 0.15 2.00 1.73

02.02.02 RELLENO COMPACTADO C/MATERIAL PROPIO M3 25.70 0.50 0.30 2.00 7.71 7.71

02.02.03 PERFILADO Y COMPACTACION A NIVEL DE RASANTE M2 25.70 4.28 1.00 110.00 110.00

02.02.04 ELIMINACION DE MATERIAL EXCEDENTE C/MAQUINARIA DIST.=5 M3 1.25 27.02 33.78 27.02

02.03.00 OBRAS DE CONCRETO SIMPLE


02.03.01 CONCRETO CICLOPEO FC=140 KG/CM2 + 70 % PM. EN GRADERI M3 80.17
EN GRADERIA AREA= 3.00 25.70 1.00 77.10

EN PELDAOS 1.83 0.35 0.15 6.00 0.58

1.83 0.35 0.19 4.00 0.47

1.83 0.35 0.23 2.00 0.29

RAMPA 3.40 1.70 0.15 2.00 1.73

02.03.02 ENCOFRADO Y DESENCOFRADO EN TRIBUNAS M2 64.29


EN GRADERIA 25.70 0.30 3.00 23.13

25.70 0.37 2.00 19.02

25.70 0.40 1.00 10.28

GRADERIA LATERAL AREA= 3.00 2.00 6.00

EN PELDAOS 1.83 0.15 6.00 1.65

1.83 0.19 4.00 1.35

1.83 0.23 2.00 0.82

RAMPA 1.70 0.15 4.00 1.02

RAMPA LATERAL 3.40 0.15 2.00 1.02

02.04.00 SOPORTE DE TIJERALES


02.04.01 TUBERIA DE SOPORTE DE COBERTURA 4" FG UND 11.00 11.00
Tubo Galvanizado 6" (2.20 M)

02.04.02 ANCLAJE DE TUBERIAS UND 11.00 11.00


PLANCHA de 12"x 12" x 1/4"

4 Pernos 3/4" x40cm gancho

2/87
HOJA DE METRADO

PROYECTO : AMPLIACION DE INFRAESTRUCTURA DE LA INSTITUCION EDUCATIVA"SAN JORGE" EN EL CENTRO POBLADO SUPTE SAN JORGE

FECHA : SETIEMBRE DEL 2011 HECHO POR: DAMS

SUB FORMULA : LOSA MULTIDEPORTIVA

CENTRO POBLADO : SUPTE SAN JORGE DISTRITO : RUPA RUPA PROVINCIA : LEONCIO PRADO

MEDIDAS N SUB TOTAL


N DESCRIPCION DE TOTAL
UND LARGO ANCHO ALTO VECES LONG. AREA VOL. KG.

02.05.00 TIJERAL
02.05.01 TIJERAL PRINCIPAL T-3 INCLUYE PINTURA UND 22.00 22.00
INSUMOS POR UND DE TIJERAL ML 7.20

ANGULO 1"X1"X1/8" 2.60 2.00 5.46

MONTANTES Y DIAGONALES KG KG/ML

Fierro grado 60 3/8" 3.00 1.00 0.58 1.74

1.25 1.00 0.58 0.73

2.75 1.00 0.58 1.60

ANCLAJE DE TIJERALES UND 22.00

02.05.02 MONTAJE DE TIJERALES UND 22.00 22.00

02.05.03 ARRIOSTRE TIJERAL ML 117.40


2.50 22.00 55.00

3.12 20.00 62.40

02.06.00 CORREAS
02.06.01 CORREAS ML 2.50 80.00 200.00 200.00

02.06.02 MONTAJE DE CORREAS UND 80.00 80.00

02.07.00 COBERTURAS
02.07.01 COBERTURA FIBRAFORTE TIPO FLEXIFORTE DE 1.83 x 1.10 M2 138.78
25.70 2.70 1.00 69.39

25.70 2.70 1.00 69.39

02.07.02 CANALETA DE CALAMINA GALVANIZADA N 30 ML 25.70 1.00 25.70 25.70

3/87
HOJA DE METRADO

PROYECTO : AMPLIACION DE INFRAESTRUCTURA DE LA INSTITUCION EDUCATIVA"SAN JORGE" EN EL CENTRO POBLADO SUPTE SAN JORGE

FECHA : SETIEMBRE DEL 2011 HECHO POR: DAMS

SUB FORMULA : CERCO PERIMETRICO Y DRENAJE PLUVIAL

CENTRO POBLADO : SUPTE SAN JORGE DISTRITO : RUPA RUPA PROVINCIA : LEONCIO PRADO

MEDIDAS N SUB TOTAL


N DESCRIPCION DE TOTAL
UND LARGO ANCHO ALTO VECES LONG. AREA VOL. KG.

01.00 CERCO PERIMETRICO


01.01.00 OBRAS PRELIMINARES
01.01.01 LIMPIEZA DE TERRENO MANUAL M2 405.51 0.60 1.00 243.31 243.31

01.01.02 TRAZO, NIVELES Y REPLANTEO PRELIMINAR M2 405.51 0.60 1.00 243.31 243.31

01.01.03 TRANSPORTE DE MATERIALES DE HUANUCO A OBRA VER HOJA DE CALCULO DE FLETE

01.02.00 MOVIMIENTO DE TIERRAS


01.02.01 DEMOLICION SOBRECIMIENTO EXISTENTE M3 6.81
M3 34.42 0.16 0.40 1.00 2.20

M3 12.13 0.16 0.40 1.00 0.78

M3 49.93 0.16 0.40 1.00 3.20

01.02.02 DESMONTAJE DE CERCO PERIMETRICO METALICO M2 255.55


34.42 2.40 1.00 82.61

12.13 2.40 1.00 29.11

49.93 2.40 1.00 119.83

01.02.03 EXCAVACION PARA CIMIENTOS HASTA 1.00 MT TERRENO NORMAL M3 162.20


M3 29.23 0.40 1.00 1.00 11.69

M3 117.83 0.40 1.00 1.00 47.13

M3 71.70 0.40 1.00 1.00 28.68

M3 174.62 0.40 1.00 1.00 69.85

M3 12.13 0.40 1.00 1.00 4.85

01.02.04 REFINE, PERFILADO Y NIVELACION DE ZANJA M2 405.51 0.60 2.00 486.61 486.61

01.02.05 ELIMINACION MATERIAL EXCEDENTE C/MAQUINARIA DIST. = 5 KM M3

Excav. Para cimientos) - 202.76 162.20


(Relleno/ material propio)+25% de esponjamiento

01.03.00 OBRAS DE CONCRETO SIMPLE


01.03.01 CONCRETO 1:10 +30% P.G. PARA CIMIENTOS CORRIDOS M3 162.20
M3 29.23 0.40 1.00 1.00 11.69

M3 117.83 0.40 1.00 1.00 47.13

M3 71.70 0.40 1.00 1.00 28.68

M3 174.62 0.40 1.00 1.00 69.85

M3 12.13 0.40 1.00 1.00 4.85

01.04.00 OBRAS DE CONCRETO ARMADO


01.04.01 SOBRECIMIENTOS
01.04.01.01 CONCRETO 1:8+25% P.M. PARA SOBRECIMIENTOS M3 100.96

M3 29.23 0.40 0.30 1.00 3.51

M3 117.83 0.40 0.60 1.00 28.28

M3 71.70 0.40 0.90 1.00 25.81

M3 174.62 0.40 0.60 1.00 41.91

M3 12.13 0.40 0.30 1.00 1.46

01.04.01.02 ENCOFRADO Y DESENCOF. SOBRECIMIENTO DE 0.30 A 0.60 MT M2 504.82

1/87
HOJA DE METRADO

PROYECTO : AMPLIACION DE INFRAESTRUCTURA DE LA INSTITUCION EDUCATIVA"SAN JORGE" EN EL CENTRO POBLADO SUPTE SAN JORGE

FECHA : SETIEMBRE DEL 2011 HECHO POR: DAMS

SUB FORMULA : CERCO PERIMETRICO Y DRENAJE PLUVIAL

CENTRO POBLADO : SUPTE SAN JORGE DISTRITO : RUPA RUPA PROVINCIA : LEONCIO PRADO

MEDIDAS N SUB TOTAL


N DESCRIPCION DE TOTAL
UND LARGO ANCHO ALTO VECES LONG. AREA VOL. KG.

M2 29.23 0.30 2.00 17.54

M2 117.83 0.60 2.00 141.40

M2 71.70 0.90 2.00 129.06

M2 174.62 0.60 2.00 209.54

M2 12.13 0.30 2.00 7.28

01.04.01.03 ACERO FY= 4200 KG/CM2 EN SOBRECIMIENTOS KG 2131.31

01.04.02 COLUMNAS
01.04.02.01 CONCRETO EN COLUMNAS F'C=175 KG/CM2 M3 0.25 0.25 2.60 124.00 20.15 20.15

01.04.02.02 ENCOFRADO Y DESENCOFRADO NORMAL EN COLUMNAS M2 0.76 2.60 124.00 245.02 238.58

01.04.02.03 ACERO EN COLUMNAS FY = 4200 Kg/cm2 KG N ELEM KG/ML 2620.37


KG 3.75 124.00 1.02 4.00 1897.20

KG 1.15 124.00 0.25 18.00 641.70

01.04.03 VIGAS
01.04.03.01 CONCRETO EN VIGA COLLARIN F`C=175kG/CM2 M3 405.51 0.25 0.20 1.00 20.28 20.28

01.04.03.02 ENCOFRADO Y DESENCOFRADO EN VIGA COLLARIN M2 405.51 0.20 2.00 162.20 210.87
405.51 0.12 1.00 48.66

01.04.03.03 ACERO FY=4200 Kg/cm2 EN VIGA COLLARIN KG N ELEM KG/ML

1/2" KG 405.51 1.00 1.02 4.00 1654.48 2240.85


1/4" KG 0.85 2028.00 0.58 1.00 999.80

01.05.00 MUROS Y TABIQUES


01.05.01 MURO DE SOGA LADRILLO KK 18 HUECOS MEZCLA C-A 1:5 CARAVISTA 2 CARAS 724.76
M2 4.00 2.20 89.00 783.20

M2 3.01 2.20 1.00 6.62

M2 3.57 2.20 1.00 7.85

M2 1.14 2.20 1.00 2.51

M2 3.18 2.20 1.00 7.00

01.06.00 REVOQUES ENLUCIDOS Y MOLDURAS


01.06.01 TARRAJEO DE SUPERFICIE DE COLUMNAS M2 245.02 238.58

01.06.02 TARRAJEO DE SUPERFICIE DE VIGA COLLARIN M2 162.20 312.24


48.66

01.07.00 CARPINTERIA METALICA


01.07.01 PUERTA METAL. LAC 1/16" C/MARCO TUBO 2.5" Y REFUER. PLAT. 1/4 M2 2.38 2.20 1.00 5.24 5.24

01.08.00 CERRAJERIA
01.08.01 CANDADO DE 2", INC ALDABAS UND 1.00 1.00

01.09.00 PINTURA
01.09.01 PINTURA ESMALTE EN PUERTAS M2 2.38 2.20 1.00 5.24 10.47

01.09.02 PINTURA AL BARNIZ EN MURO CARAVISTA M2 2.00 724.76 1449.52

2/87
HOJA DE METRADO

PROYECTO : AMPLIACION DE INFRAESTRUCTURA DE LA INSTITUCION EDUCATIVA"SAN JORGE" EN EL CENTRO POBLADO SUPTE SAN JORGE

FECHA : SETIEMBRE DEL 2011 HECHO POR: DAMS

SUB FORMULA : CERCO PERIMETRICO Y DRENAJE PLUVIAL

CENTRO POBLADO : SUPTE SAN JORGE DISTRITO : RUPA RUPA PROVINCIA : LEONCIO PRADO

MEDIDAS N SUB TOTAL


N DESCRIPCION DE TOTAL
UND LARGO ANCHO ALTO VECES LONG. AREA VOL. KG.

01.10.00 VARIOS, LIMPIEZA


017.10.01 JUNTA DE CONSTRUCCION CON TEKNOPORT DE 1" M2 0.25 2.60 17.00 11.05 11.05

01.10.02 LIMPIEZA FINAL DE OBRA GLB 405.51 0.60 1.00 243.31 243.31

02.00 CANAL PLUVIAL DE CONCRETO


02.01 TRABAJOS PRELIMINARES
02.01.01 TRAZO NIVELES Y REPLANTEO PRELIMINAR M2 131.75
M2 4.16 0.40 1.00 1.66

M2 40.34 0.40 1.00 16.14

M2 8.40 0.40 1.00 3.36

M2 3.65 0.40 1.00 1.46

M2 3.85 0.40 1.00 1.54

M2 46.65 0.50 1.00 23.33

M2 48.18 0.40 1.00 19.27

M2 27.75 0.50 1.00 13.88

M2 103.81 0.50 1.00 51.91

02.02.00 MOVIMIENTO DE TIERRAS


02.02.01 EXCAVACION EN MATERIAL SUELTO MANUAL M3 79.05
M3 4.16 0.40 0.60 1.00 1.00

M3 40.34 0.40 0.60 1.00 9.68

M3 8.40 0.40 0.60 1.00 2.02

M3 3.65 0.40 0.60 1.00 0.88

M3 3.85 0.40 0.60 1.00 0.92

M3 46.65 0.50 0.60 1.00 14.00

M3 48.18 0.40 0.60 1.00 11.56

M3 27.75 0.50 0.60 1.00 8.33

M3 103.81 0.50 0.60 1.00 31.14

02.02.02 RELLENO CON MATERIAL PROPIO M3 13.17


M3 4.16 0.40 0.10 1.00 0.17

M3 40.34 0.40 0.10 1.00 1.61

M3 8.40 0.40 0.10 1.00 0.34

M3 3.65 0.40 0.10 1.00 0.15

M3 3.85 0.40 0.10 1.00 0.15

M3 46.65 0.50 0.10 1.00 2.33

M3 48.18 0.40 0.10 1.00 1.93

M3 27.75 0.50 0.10 1.00 1.39

M3 103.81 0.50 0.10 1.00 5.19

02.02.03 ELIMINACION DE MATERIAL EXCEDENTE C/MAQUINARIA DIST.=5 KM. M3 1.00 82.35 65.87

02.03.00 OBRAS DE CONCRETO ARMADO


02.03.01 CONCRETO F'C=175 KGC/M2 CANAL PLUVIAL M3 46.50
M3 4.16 0.10 0.50 2.00 0.42

M3 40.34 0.10 0.50 2.00 4.03

M3 8.40 0.10 0.50 2.00 0.84

M3 3.65 0.10 0.50 2.00 0.37

M3 3.85 0.10 0.50 2.00 0.39

M3 46.65 0.10 0.50 2.00 4.67

3/87
HOJA DE METRADO

PROYECTO : AMPLIACION DE INFRAESTRUCTURA DE LA INSTITUCION EDUCATIVA"SAN JORGE" EN EL CENTRO POBLADO SUPTE SAN JORGE

FECHA : SETIEMBRE DEL 2011 HECHO POR: DAMS

SUB FORMULA : CERCO PERIMETRICO Y DRENAJE PLUVIAL

CENTRO POBLADO : SUPTE SAN JORGE DISTRITO : RUPA RUPA PROVINCIA : LEONCIO PRADO

MEDIDAS N SUB TOTAL


N DESCRIPCION DE TOTAL
UND LARGO ANCHO ALTO VECES LONG. AREA VOL. KG.

M3 48.18 0.10 0.50 2.00 4.82

M3 27.75 0.10 0.50 2.00 2.78

M3 103.81 0.10 0.50 2.00 10.38

02.03.02 ENCOFRADO Y DESENCOFRADO CANALES M2 290.77


M2 4.16 0.50 4.00 8.32

M2 40.34 0.50 4.00 80.68

M2 8.40 0.50 4.00 16.80

M2 3.65 0.50 4.00 7.30

M2 3.85 0.50 4.00 7.70

M2 46.65 0.50 4.00 93.30

M2 48.18 0.50 4.00 96.36

M2 27.75 0.50 4.00 55.50

M2 103.81 0.50 4.00 207.62

02.03.03 ACERO FY=4200 KG/CM2 GRADO 60 EN CANAL PLUVIAL KG 1633.56


KG KG/ML

KG 1.10 0.58 659.00 420.44

KG 0.45 0.25 659.00 74.14

02.04.00 VARIOS
02.04.01 JUNTA ASFALTICA E=1" EN CANAL PLUVIAL ML 94.40
ML 0.50 57.00 28.50

02.04.02 REJILLA SUMIDERO-PLAT 1 1/4"X1/4"@1/2" Y MARCO "L" 1 1/4" INC/COLOCACION 114.00


M2 4.16 0.40 1.00 1.66

M2 40.34 0.40 1.00 16.14

M2 8.40 0.40 1.00 3.36

M2 3.65 0.40 1.00 1.46

M2 3.85 0.40 1.00 1.54

M2 46.65 0.40 1.00 18.66

M2 48.18 0.40 1.00 19.27

M2 27.75 0.40 1.00 11.10

02.05.00 TUBERIA DE EVACUACION PLUVIAL Y MONTANTES


02.05.01 TUBERIA DE BAJADA PVC SAL DIAMETRO 4" ML

ML 11.55 2.00 23.10 23.10

02.05.02 CONCRETO F'C=175 KG/CM2. PARA MONTANTES M3

M3 0.30 0.30 4.50 2.00 0.81 0.81

02.05.03 ENCOFRADO Y DESENCOFRADO M2

M2 0.30 4.50 6.00 8.10 8.10

02.05.04 ACERO FY=4200 KG/CM2 GRADO 60 EN MONTANTES KG 34.23


KG/ML

KG 4.70 0.58 8.00 21.81

KG 1.08 0.25 46.00 12.42

4/87