Exercise: Precedence Diagram Method: Project Management
Exercise: Precedence Diagram Method: Project Management
8 14 12
A H I
16 13
C E
19
SS+10
F
1. Calculate the forward and backward passes
2. Identify the critical path
3. Calculate the float for each apth
8 14 12
0 8 37 51 51 63
A H I
16 13
8 24 24 37
C E
19
SS+10 18 37
F
1. Calculate the forward and backward passes
2. Identify the critical path
3. Calculate the float for each apth
8 14 12
0 8 37 51 51 63
0
A 8 37
H 51 51
I 63
16 13
8 24 24 37
8
C 24 24
E 37
19
SS+10 18 37
32
F 51
8 14 12
0 8 37 51 51 63
0
A 8 37
H 51 51
I 63
16 13
8 24 24 37
8
C 24 24
E 37
19
SS+10 18 37
32
F 51
8 14 12
0 8 37 51 51 63
0
A 8 37
H 51 51
I 63
Float=0 Float=0 Float=0
16 13
8 24 24 37
8
C 24 24
E 37
Float=0 Float=0
19
SS+10 18 37
32
F 51 Float=14