TERBILANG : Satu Milyard Tiga Ratus Enam Puluh Tujuh Juta Dua Ratus Ribu Rupiah
ESTIMATE ENGGINER (EE)
HARGA
NO URAIAN PEKERJAAN VOLUME SAT TOTAL
SATUAN (Rp)
1 2 3 4 5 6
b) Pekerjaan Plafon
1 Pasang Plafond Gipsum 186.32 M2 74,943.78 13,963,524.16
2 Rangka Plafon 1.19 M3 175,944.25 209,373.66
3 List Profil Plafond Gipsum 271.26 M' 111,320.00 30,196,663.20
A.4.1.1.7. Membuat 1 m Beton Mutu f'c = 9,8 Mpa (K125), Slump (12 2 )cm, w/c = 0,78
SATUAN JUMLAH
No. URAIAN PEKERJAAN KODE SATUAN KOEFISIEN HARGA HARGA
(Rp) (Rp)
1 2 3 4 5 6 7
A Tenaga Kerja
Pekerja L.01 OH 1.650 110,000.00 181,500.00
Tukang Batu L.02 OH 0.275 120,000.00 33,000.00
Kepala Tukang L.03 OH 0.028 130,000.00 3,640.00
Mandor L.04 OH 0.083 140,000.00 11,620.00
Jumlah Tenaga Kerja 229,760.00
B Bahan
Semen Portland Kg 276.000 2,200.00 607,200.00
Pasir Beton Kg 828.000 220.71 182,751.43
Kerikil Kg 1012.000 361.70 366,044.15
Air Liter 215.000 200.00 43,000.00
Jumlah Harga Bahan 1,198,995.58
C Peralatan
Molen E.28.b Sewa- Hari 0.250 625,000.00 156,250.00
Jumlah Harga Alat 156,250.00
D Jumlah Harga tenaga, Bahan dan Peralatan (A+B+C) 1,585,005.58
E Overhead + Profit (15%) 15% x D 237,750.84
F Harga Satuan Pekerjaan (D+E) 1,822,756.41
A.3.3. Koefisien untuk analisa harga satuan pekerjaan pembesian beton
B.17 Pembesian 10 kg dengan besi polos atau ulir
SATUAN JUMLAH
No. URAIAN PEKERJAAN KODE SATUAN KOEFISIEN HARGA HARGA
(Rp) (Rp)
1 2 3 4 5 6 7
A Tenaga Kerja
Pekerja L.01 OH 0.070 110,000.00 7,700.00
Tukang Besi L.02 OH 0.070 120,000.00 8,400.00
Kepala Tukang L.03 OH 0.007 130,000.00 910.00
Mandor L.04 OH 0.004 140,000.00 560.00
Jumlah Tenaga Kerja 17,570.00
B Bahan
Besi Beton Polos Kg 10.500 19,000.00 199,500.00
Kawat Ikat Kg 0.150 25,700.00 3,855.00
Jumlah Harga Bahan 203,355.00
C Peralatan
Jumlah Harga Alat -
D Jumlah Harga tenaga, Bahan dan Peralatan (A+B+C) 220,925.00
E Overhead + Profit (15%) 15% x D 33,138.75
F Harga Satuan Pekerjaan (D+E) 254,063.75
Untuk 10 Kg Besi Polos 254,063.75
Untuk 1 Kg Besi Polos 25,406.38
A.4.6.1.1. Pembuatan dan Pemasangan 1 m Kusen Pintu dan Jendela, Kayu Kelas I
SATUAN JUMLAH
No. URAIAN PEKERJAAN KODE SATUAN KOEFISIEN HARGA HARGA
(Rp) (Rp)
1 2 3 4 5 6 7
A Tenaga Kerja
Pekerja L.01 OH 7.000 110,000.00 770,000.00
Tukang Kayu L.02 OH 21.000 120,000.00 2,520,000.00
Kepala Tukang L.03 OH 2.100 130,000.00 273,000.00
Mandor L.04 OH 0.350 140,000.00 49,000.00
Jumlah Tenaga Kerja 3,612,000.00
B Bahan
Balok Kayu Kelas I M 1.100 5,433,000.00 5,976,300.00
Paku 10 cm Kg 1.250 21,300.00 26,625.00
Lem Kayu Kg 1.000 81,300.00 81,300.00
Jumlah Harga Bahan 6,084,225.00
C Peralatan
Jumlah Harga Alat -
D Jumlah Harga tenaga, Bahan dan Peralatan (A+B+C) 9,696,225.00
E Overhead + Profit (15%) 15% x D 1,454,433.75
F Harga Satuan Pekerjaan (D+E) 11,150,658.75
A.4.6.1.5. Pembuatan dan Pemasangan 1 m daun pintu panel, Kayu Kelas I
SATUAN JUMLAH
No. URAIAN PEKERJAAN KODE SATUAN KOEFISIEN HARGA HARGA
(Rp) (Rp)
1 2 3 4 5 6 7
A Tenaga Kerja
Pekerja L.01 OH 1.000 110,000.00 110,000.00
Tukang Kayu L.02 OH 3.000 120,000.00 360,000.00
Kepala Tukang L.03 OH 0.300 130,000.00 39,000.00
Mandor L.04 OH 0.050 140,000.00 7,000.00
Jumlah Tenaga Kerja 516,000.00
B Bahan
Papan Kayu Kelas I M 0.040 5,733,300.00 229,332.00
Lem Kayu Kg 0.500 81,300.00 40,650.00
Jumlah Harga Bahan 269,982.00
C Peralatan
Jumlah Harga Alat -
D Jumlah Harga tenaga, Bahan dan Peralatan (A+B+C) 785,982.00
E Overhead + Profit (15%) 15% x D 117,897.30
F Harga Satuan Pekerjaan (D+E) 903,879.30
A.6.6.2.3. Pemasangan 1 Titik Instalasi Stp Kontak Kabel NYM 3 x 2,5 mm2
SATUAN JUMLAH
No. URAIAN PEKERJAAN KODE SATUAN KOEFISIEN HARGA HARGA
(Rp) (Rp)
1 2 3 4 5 6 7
A Tenaga Kerja
Pekerja L.01 OH 0.400 110,000.00 44,000.00
Tukang Listrik L.02 OH 0.400 120,000.00 48,000.00
Kepala Tukang L.03 OH 0.004 130,000.00 520.00
Mandor L.04 OH 0.004 140,000.00 560.00
Jumlah Tenaga Kerja 93,080.00
B Bahan
Kabel NYM 3 x 2,5 mm2 M 15.000 30,000.00 450,000.00
Conduit PVC 20 mm2 Bh 15.000 6,000.00 90,000.00
Socket Pipa Btg 2.500 5,000.00 12,500.00
Tee Dos Bh 2.000 15,000.00 30,000.00
Klem Pipa Bh 5.000 1,000.00 5,000.00
Isolasi Ban Roll 0.300 6,000.00 1,800.00
Jumlah Harga Bahan 589,300.00
C Peralatan
Jumlah Harga Alat -
D Jumlah Harga tenaga, Bahan dan Peralatan (A+B+C) 682,380.00
E Overhead + Profit (15%) 15% x D 102,357.00
F Harga Satuan Pekerjaan (D+E) 784,737.00
A.6.6.2.3. Pemasangan 1 Buah Lampu SL 24 Watt
SATUAN JUMLAH
No. URAIAN PEKERJAAN KODE SATUAN KOEFISIEN HARGA HARGA
(Rp) (Rp)
1 2 3 4 5 6 7
A Tenaga Kerja
Pekerja L.01 OH 0.050 110,000.00 5,500.00
Tukang Listrik L.02 OH 0.080 120,000.00 9,600.00
Kepala Tukang L.03 OH 0.008 130,000.00 1,040.00
Mandor L.04 OH 0.001 140,000.00 112.00
Jumlah Tenaga Kerja 16,252.00
B Bahan
Fitting+Lampu SL 24 Watt Bh 1.000 54,300.00 54,300.00
Jumlah Harga Bahan 54,300.00
C Peralatan
Jumlah Harga Alat -
D Jumlah Harga tenaga, Bahan dan Peralatan (A+B+C) 70,552.00
E Overhead + Profit (15%) 15% x D 10,582.80
F Harga Satuan Pekerjaan (D+E) 81,134.80
A.4.7.1.9. Pengecetan 1 M Tembok Baru (1 Lapis Plamur, 1 Lapis Cat Dasar, 2 Lapis Cat Penutup)
SATUAN JUMLAH
No. URAIAN PEKERJAAN KODE SATUAN KOEFISIEN HARGA HARGA
(Rp) (Rp)
1 2 3 4 5 6 7
A Tenaga Kerja
Pekerja L.01 OH 0.020 110,000.00 2,200.00
Tukang Cat L.02 OH 0.063 120,000.00 7,560.00
Kepala Tukang L.03 OH 0.006 130,000.00 819.00
Mandor L.04 OH 0.003 140,000.00 420.00
Jumlah Tenaga Kerja 10,999.00
B Bahan
Plamur Kg 0.100 19,700.00 1,970.00
Cat Dasar Kg 0.100 19,000.00 1,900.00
Cat Penutup Kg 0.260 48,500.00 12,610.00
Jumlah Harga Bahan 16,480.00
C Peralatan
Jumlah Harga Alat -
D Jumlah Harga tenaga, Bahan dan Peralatan (A+B+C) 27,479.00
E Overhead + Profit (15%) 15% x D 4,121.85
F Harga Satuan Pekerjaan (D+E) 31,600.85
A.4.7.1.5. Pengecetan 1 M Plafond (1 Lapis Plamur, 1 Lapis Cat Dasar, 2 Lapis Cat Penutup)
SATUAN JUMLAH
No. URAIAN PEKERJAAN KODE SATUAN KOEFISIEN HARGA HARGA
(Rp) (Rp)
1 2 3 4 5 6 7
A Tenaga Kerja
Pekerja L.01 OH 0.020 110,000.00 2,200.00
Tukang Cat L.02 OH 0.063 120,000.00 7,560.00
Kepala Tukang L.03 OH 0.006 130,000.00 819.00
Mandor L.04 OH 0.003 140,000.00 420.00
Jumlah Tenaga Kerja 10,999.00
B Bahan
Plamur Kg 0.100 19,700.00 1,970.00
Cat Dasar Kg 0.100 19,000.00 1,900.00
Cat Penutup Kg 0.260 48,500.00 12,610.00
Jumlah Harga Bahan 16,480.00
C Peralatan
Jumlah Harga Alat -
D Jumlah Harga tenaga, Bahan dan Peralatan (A+B+C) 27,479.00
E Overhead + Profit (15%) 15% x D 4,121.85
F Harga Satuan Pekerjaan (D+E) 31,600.85
A.4.7.1.4. Pengecetan 1 M Bidang Kayu (1 Lapis Plamur, 1 Lapis Cat Dasar, 2 Lapis Cat Penutup)
SATUAN JUMLAH
No. URAIAN PEKERJAAN KODE SATUAN KOEFISIEN HARGA HARGA
(Rp) (Rp)
1 2 3 4 5 6 7
A Tenaga Kerja
Pekerja L.01 OH 0.070 110,000.00 7,700.00
Tukang Cat L.02 OH 0.009 120,000.00 1,080.00
Kepala Tukang L.03 OH 0.006 130,000.00 819.00
Mandor L.04 OH 0.003 140,000.00 420.00
Jumlah Tenaga Kerja 10,019.00
B Bahan
Cat Menie Kg 0.200 33,300.00 6,660.00
Plamur Kg 0.150 33,300.00 4,995.00
Cat Dasar Kg 0.170 27,300.00 4,641.00
Cat Penutup Kg 0.260 44,300.00 11,518.00
Kuas Bh 0.010 20,300.00 203.00
Thinner Kg 0.030 30,000.00 900.00
Amplas Lbr 0.200 4,600.00 920.00
Jumlah Harga Bahan 29,837.00
C Peralatan
Jumlah Harga Alat -
D Jumlah Harga tenaga, Bahan dan Peralatan (A+B+C) 39,856.00
E Overhead + Profit (15%) 15% x D 5,978.40
F Harga Satuan Pekerjaan (D+E) 45,834.40
BAHAN
1 Batu Gunung m3 316,000.00
2 Batu Kali m3 316,000.00
3 Batu Pecah 2-3 m3 488,300.00
4 Batu Tela Bh 2,500.00
5 Pasir Urug m3 212,000.00
6 Pasir Pasang m3 245,000.00
7 Pasir Plesteran m3 245,000.00
8 Pasir Beton m3 309,000.00
9 Tanah Biasa/Urug m3 178,750.00
10 Semen 50 Kg zak 95,000.00
11 Semen Kg 1,900.00
12 Kayu Kelas III (Balok) m3 2,667,000.00
13 Kayu Kelas III (Papan) m3 2,667,000.00
14 Kayu kelas II (Balok) m3 3,500,000.00
15 Kayu Kelas II (Papan) m3 3,556,700.00
16 Kayu kelas I (Balok) m3 5,433,000.00
17 Kayu Kelas I (Papan) m3 5,733,300.00
18 Kayu Dolken dia 8 - 10 Cm / 4 m Btg 25,000.00
19 Plywood tebal 9 mm Lbr 161,700.00
20 Besi Beton Polos Kg 19,000.00
21 Besi Beton Ulir Kg 40,000.00
22 Kawat Ikat / Beton Kg 25,700.00
23 Atap Spandek m2 125,000.00
24 Nok Bh 25,000.00
25 Besi Strip (Sambungan Kayu) Kg 22,500.00
26 Paku 5 - 12 cm kg 21,300.00
27 Paku Campur kg 23,000.00
28 Paku Tripleks Kg 16,300.00
29 Lem Kayu Kg 81,300.00
30 Kaca Tebal 5 mm m2 368,300.00
31 Gypsum board Lbr 102,000.00
32 Minyak Bekisting Ltr 35,000.00
33 List Plafond Gypsum m' 80,000.00
34 Granit 60 x 60 Bh 70,000.00
35 Keramik 20x20 Bh 3,500.00
36 Keramik 20x25 Bh 4,250.00
37 Semen Warna Kg 14,700.00
38 Kunci Tanam 2 Slaag Kw. I Bh 155,000.00
39 Kunci Tanam KM Kw .II Bh 130,000.00
40 Engsel Pintu Bh 40,000.00
41 Engsel Jendela Bh 25,000.00
42 Grendel Pintu Bh 33,000.00
43 Grendel Jendela Bh 26,000.00
44 Hak Angin Bh 35,000.00
45 Handle Biasa Bh 131,666.67
46 Kabel NYA 1 x 2,5 mm dan Assesories m' 20,500.00
47 Kabel NYA 1 x 3,5 mm dan Assesories m' 30,000.00
48 Lampu TL 24 Watt Bh 54,300.00
49 Lampu Pijar 18 Watt Bh 22,500.00
50 Saklar Tunggal Bh 17,000.00
51 Saklar Ganda Bh 22,500.00
52 Stop Kontak Bh 18,000.00
53 Closet Jongkok Bh 380,000.00
54 Bak Cuci Stainless Set 553,333.33
55 Water Drain Bh 32,500.00
56 Kran 1/2" Stenlessteel Bh 48,000.00
57 1 Set Pintu KM/WC (Aluminium) Bh 2,000,000.00
58 Pipa Galvanis 1/2" Btg 130,000.00
59 Pipa PVC 2" Btg 66,000.00
60 Pipa PVC 4" Btg 191,000.00
61 Plamur Tembok Kg 19,700.00
62 Plamur Kayu Kg 33,300.00
63 Cat Dasar Tembok Kg 19,000.00
64 Cat Penutup Tembok Kg 48,500.00
65 Cat Dasar Kayu Kg 27,300.00
66 Cat Penutup Kayu Kg 44,300.00
67 Cat Meni Kg 33,300.00
68 Kuas Bh 20,300.00
69 Thinner Kg 30,000.00
70 Amplas Lbr 4,600.00
71 Closet Duduk (Monoblok Komplit) Bh 2,183,300
71 Espangolet Bh 250,000.00
72 Down Light 1x18 Watt Bh 180,000.00
73 Down Light 1x14 Watt Bh 160,000.00
74 Jalusi Rooster Sedang Bh 41,700.00
75 Tangki Air Steenless 1100 Ltr Bh 5,000,000.00
76 Floor Drain Stenless Bh 70,000.00
UPAH KERJA
1 Mandor OH 140,000.00
2 Kepala Tukang OH 130,000.00
3 Tukang OH 120,000.00
4 Pekerja OH 110,000.00