ID Task Name Duration Start Finish Predecessors Resource Names Jun '17 Jul '17 Aug '17 Sep

rce Names Jun '17 Jul '17 Aug '17 Sep '17
28 4 11 18 25 2 9 16 23 30 6 13 20 27 3 10 17
1 A 20 days Mon 6/5/17 Fri 6/30/17
2 B 30 days Mon 7/3/17 Fri 8/11/17 1 TERLAMBAT TERLAMBAT
3 C 25 days Mon 8/14/17 Fri 9/15/17 2,4
4 D 40 days Mon 6/19/17 Fri 8/11/17 TERLAMBAT TERLAMBAT
5 E 30 days Mon 7/10/17 Fri 8/18/17 6 LEBIH CEPAT LEBIH CEPAT
6 F 20 days Mon 6/5/17 Fri 6/30/17 7SS TERLAMBAT TERLAMBAT
7 G 40 days Mon 6/5/17 Fri 7/28/17 LEBIH CEPAT LEBIH CEPAT

Task Milestone External Tasks


Project: Ari Nasrudin 3331141932.mpp
Split Summary External Milestone
Date: Tue 10/17/17
Progress Project Summary Deadline