Detailed estimate for the construction of Anganwadi Centre at _______________________

under focus plan MGNREGA during year 2017-18 Block _____________________________

S.No Particulars of items Amount


1 Earthwork in excavation in foundation tranches/ drains including disposal of
excavated soil lead upto 50mt and lift 1.5mt all kinds of soil.
Centre to centre length
1x168-9"x2-0"x2-3"=759.37cft
Septic tank= 1x6-0"x5-0"=180cft
Soakage pit= 1x3.14x8x8x10-0"=2009.6cft
=2481.97cft = 83.45cum@.88lab/cum=73.48lab
Providing and laying of cement concrete of grade M7.5 excluding cost of material
2
with 40mm size of aggregate.
1x168-9"x2-0"x0-4=111.37cft
1x6-0"x6-0"x0-4=11.88cft
Steps 1x6-0"x3-0"x0-4= 5.94cft
Under flooring =1x(7'x7'+7'x6'+13-3"x9+11'x15'+2x6'x4')x0-4"=139.67cft
Total quantity= =268.90cft
7.660cum@2.33lab/cum=17.46lab

7.60cum@.10lab/cum=1lab
Lying of reinforced cement concrete of M15 grade with 40mm size of aggregate
3
curing etc. complate.