Daily shift report

Date: 9/16/2016 Shift: A Shift start time: 9:30am Shift end time: 3:30pm
Day of week: Monday

Name: Yaseen Muhammad Position: Quality control and Body preparation manger

Shift responsibilities:
to buy a suitable sample for body preparition.

to minimize the working time of ball mill.

to standardize the dimmension of green and becket tile.

Control the moisture content in the powered between 7 to 8 percent.

Shift accomplishments:
50 tons of slip for the wall tile was prepare

2 tons of powder was supplied to the press zone. .

density and viscosity of down slip was brought to the standard rang.

Shift Notes:
the weather was cloudy which effect the moisture content.

no worker was absent due to this the assing work achieved succesfully on time.

Signature: yaseen Muhammad