You are on page 1of 11

BORED PILE

DIAMETER
DESCRIPTION LOCATION (m) DEPTH (m) DRILLING REBAR CONCRETING

BP-1 GL 1/A 1.00 17

BP-1 GL 1/A 1.00 17

BP-1 GL 1/A 1.00 17

BP-1 GL 6/A 1.00 17

BP-1 GL 6/A 1.00 17

BP-1 GL 6/A 1.00 17

BP-2 GL 2-4/A'-B' 0.80 18

BP-2 GL 2-4/A'-B' 0.80 18

BP-2 GL 2-4/A'-B' 0.80 18

BP-2 GL 2-4/A'-B' 0.80 18

BP-2 GL 2-4/A'-B' 0.80 18

BP-2 GL 2-4/A'-B' 0.80 18

BP-2 GL 2-4/A'-B' 0.80 18

BP-2 GL 2-4/A'-B' 0.80 18

BP-2 GL 2-4/A'-B' 0.80 18

BP-2 GL 2-4/A'-B' 0.80 18

BP-2 GL 2-4/A'-B' 0.80 18

BP-2 GL 2-4/A'-B' 0.80 18

BP-2 GL 2-4/A'-B' 0.80 18

BP-2 GL 2-4/A'-B' 0.80 18

BP-3 GL 2/A 0.80 17

BP-3 GL 2/A 0.80 17

BP-3 GL 2/A 0.80 17

BP-3 GL 4/A 0.80 17

BP-3 GL 4/A 0.80 17

BP-3 GL 4/A 0.80 17

BP-3 GL 1'/B 0.80 17

BP-4 GL 1/B 0.80 15

BP-4 GL 1/B 0.80 15

BP-4 GL 1/B 0.80 15

BP-4 GL 2-4/A'-B' 0.80 15

BP-4 GL 2-4/A'-B' 0.80 15

BP-4 GL 2-4/A'-B' 0.80 15

BP-4 GL 2-4/A'-B' 0.80 15

BP-4 GL 2-4/A'-B' 0.80 15

BP-4 GL 2-4/A'-B' 0.80 15

BP-4 GL 2-4/A'-B' 0.80 15

BP-4 GL 2-4/A'-B' 0.80 15

BP-4 GL 2-4/A'-B' 0.80 15

BP-4 GL 2-4/A'-B' 0.80 15

BP-4 GL 2-4/A'-B' 0.80 15

BP-5 GL 6/B' 1.00 20

BP-5 GL 6/B' 1.00 20

BP-5 GL 6/B' 1.00 20

BP-5 GL 6/B' 1.00 20


PROJECT : FRABELLE SALCEDO
LOCATION : Tordesillas St., cor. Bautista St. Makati City
OWNER : Frabelle Fishing Corporation
SUBJECT : Bored pile
CONTRACTOR : Monocrete Construction Philippines Inc.

Diameter Height Area Volume


Description Location (Grid Line)
(m) (m) ( m ) ( m )
BP-1 GL 1/A 1.00 10.150 0.785 7.972
BP-1 GL 1/A 1.00 10.150 0.785 7.972
BP-1 GL 1/A 1.00 10.150 0.785 7.972
BP-1 GL 6/A 1.00 10.150 0.785 7.972
BP-1 GL 6/A 1.00 10.150 0.785 7.972
BP-1 GL 6/A 1.00 10.150 0.785 7.972
BP-2 GL 2-4/A'-B' 0.80 11.650 0.503 5.856
BP-2 GL 2-4/A'-B' 0.80 11.650 0.503 5.856
BP-2 GL 2-4/A'-B' 0.80 11.650 0.503 5.856
BP-2 GL 2-4/A'-B' 0.80 11.650 0.503 5.856
BP-2 GL 2-4/A'-B' 0.80 11.650 0.503 5.856
BP-2 GL 2-4/A'-B' 0.80 11.650 0.503 5.856
BP-2 GL 2-4/A'-B' 0.80 11.650 0.503 5.856
BP-2 GL 2-4/A'-B' 0.80 11.650 0.503 5.856
BP-2 GL 2-4/A'-B' 0.80 11.650 0.503 5.856
BP-2 GL 2-4/A'-B' 0.80 11.650 0.503 5.856
BP-2 GL 2-4/A'-B' 0.80 11.650 0.503 5.856
BP-2 GL 2-4/A'-B' 0.80 11.650 0.503 5.856
BP-2 GL 2-4/A'-B' 0.80 11.650 0.503 5.856
BP-2 GL 2-4/A'-B' 0.80 11.650 0.503 5.856
BP-3 GL 2/A 0.80 10.150 0.503 5.102
BP-3 GL 2/A 0.80 10.150 0.503 5.102
BP-3 GL 2/A 0.80 10.150 0.503 5.102
BP-3 GL 4/A 0.80 14.500 0.503 7.289
BP-3 GL 4/A 0.80 14.500 0.503 7.289
BP-3 GL 4/A 0.80 14.500 0.503 7.289
BP-3 GL 1'/B 0.80 11.650 0.503 5.856
BP-4 GL 1/B 0.80 8.850 0.503 4.449
BP-4 GL 1/B 0.80 8.850 0.503 4.449
BP-4 GL 1/B 0.80 8.850 0.503 4.449
BP-4 GL 2-4/A'-B' 0.80 8.650 0.503 4.348
BP-4 GL 2-4/A'-B' 0.80 8.650 0.503 4.348
BP-4 GL 2-4/A'-B' 0.80 8.650 0.503 4.348
BP-4 GL 2-4/A'-B' 0.80 8.650 0.503 4.348
BP-4 GL 2-4/A'-B' 0.80 8.650 0.503 4.348
BP-4 GL 2-4/A'-B' 0.80 8.650 0.503 4.348
BP-4 GL 2-4/A'-B' 0.80 8.650 0.503 4.348
BP-4 GL 2-4/A'-B' 0.80 8.650 0.503 4.348
BP-4 GL 2-4/A'-B' 0.80 8.650 0.503 4.348
BP-4 GL 2-4/A'-B' 0.80 8.650 0.503 4.348
BP-4 GL 2-4/A'-B' 0.80 8.650 0.503 4.348
BP-5 GL 6/B' 1.00 13.650 0.785 10.721
BP-5 GL 6/B' 1.00 13.650 0.785 10.721
BP-5 GL 6/B' 1.00 13.650 0.785 10.721
BP-5 GL 6/B' 1.00 13.650 0.785 10.721

TOTAL 25.447 276.897

Prepared by:

Engr. Lean Christian V. Olores


Engr. In-Charge

Noted by:

Engr. Zandro P. Danes


Project In-Charge
PROJECT : FRABELLE SALCEDO
LOCATION : Tordesillas St., cor. Bautista St. Makati City
OWNER : Frabelle Fishing Corporation
SUBJECT : Gravel (G1) for Pile Cap
CONTRACTOR : Monocrete Construction Philippines Inc.

AREA 1 AREA 2 TOTAL AREA Height Volume


Description Location (Grid Line)
( m) ( m) ( m ) (m) ( m )
PILE CAP-1 GL 6/A 6.97 6.125 13.095 0.100 1.310
PILE CAP-2 GL 1/A 6.97 6.125 13.095 0.100 1.310
PILE CAP-3 GL 6/B' 20.16 0.000 20.160 0.100 2.016
PILE CAP-4 GL 1/B 5.10 4.725 9.825 0.100 0.983
PILE CAP-5 GL 1'/B 2.56 0.000 2.560 0.100 0.256
PILE CAP-6 GL 2-4/A'-B' 110.92 0.000 110.921 0.100 11.092
PILE CAP-7 GL 2/A 4.64 5.219 9.860 0.100 0.986
PILE CAP-7 GL 4/A 4.64 5.219 9.860 0.100 0.986

TOTAL 189.375 18.937

Prepared by:

Engr. Lean Christian V. Olores


Engr. In-Charge

Noted by:

Engr. Zandro P. Danes


Project In-Charge
PROJECT : FRABELLE SALCEDO
LOCATION : Tordesillas St., cor. Bautista St. Makati City
OWNER : Frabelle Fishing Corporation
SUBJECT : ESTIMATE FOR SOIL POISONING
CONTRACTOR : Monocrete Construction Philippines Inc.

Description Location (Grid Line) Length Width AREA


(m) (m) ( m )
F-4 GL 1'/C 2.50 2.50 6.25
F-4 GL 3/C 2.50 2.50 6.25
F-6 GL 4-5'/D 4.00 3.30 13.2
F-4 GL 4/C 2.50 2.50 6.25
F-5 GL 2-3/D-D" 5.00 3.40 17
MF-1 GL 2-3/E 19.3
F-4 GL 5/B' 2.50 2.50 6.25
F-3 GL 1/C 3.60 3.60 12.96
F-2 GL 1/D' 3.60 3.60 12.96
F-1 GL 1/F 4.00 4.00 16
PILE CAP-1 GL 6/A 13.095
PILE CAP-2 GL 1/A 13.095
PILE CAP-3 GL 6/B' 20.16
PILE CAP-4 GL 1/B 9.825
PILE CAP-5 GL 1'/B 2.56
PILE CAP-6 GL 2-4/A'-B' 10.33 10.75 111.0045
PILE CAP-7 GL 2/A 9.86
PILE CAP-7 GL 4/A 9.86
TOTAL 305.88

Prepared by:

Engr. Lean Christian V. Olores


Engr. In-Charge

Noted by:

Engr. Zandro P. Danes


Project In-Charge
PROJECT : FRABELLE SALCEDO
LOCATION : Tordesillas St., cor. Bautista St. Makati City
OWNER : Frabelle Fishing Corporation
SUBJECT : ESTIMATE FOR SOIL POISONING
CONTRACTOR : Monocrete Construction Philippines Inc.

Description Location (Grid Line) AREA 1 ( m) AREA 2 ( m) TOTAL AREA


( m )
PILE CAP-1 GL 6/A 6.97 6.125 13.095
PILE CAP-2 GL 1/A 6.97 6.125 13.095
PILE CAP-3 GL 6/B' 20.16 0.000 20.160
PILE CAP-4 GL 1/B 5.10 4.725 9.825
PILE CAP-5 GL 1'/B 2.56 0.000 2.560
PILE CAP-6 GL 2-4/A'-B' 110.92 0.000 110.921
PILE CAP-7 GL 2/A 4.64 5.219 9.860
PILE CAP-7 GL 4/A 4.64 5.219 9.860
F-4 GL 1'/C 6.25 0.000 6.250
F-4 GL 3/C 6.25 0.000 6.250
F-6 GL 4-5'/D 13.20 0.000 13.200
F-4 GL 4/C 6.25 0.000 6.250
F-5 GL 2-3/D-D" 17.00 0.000 17.000
MF-1 GL 2-3/E 19.30 0.000 19.300
F-4 GL 5/B' 6.25 0.000 6.250
F-3 GL 1/C 12.96 0.000 12.960
F-2 GL 1/D' 12.96 0.000 12.960
F-1 GL 1/F 16.00 0.000 16.000
cistern 212.00 212.000
holding tank 36.00 36.000
fuel tank 25.29 25.290
grease trap 3.84 3.840
GROUND FLOOR GL A-C/1-7 & GL C-F'/1-7 515.35 381.470 896.820
TOTAL 1,479.74

Prepared by:

Engr. Lean Christian V. Olores


Engr. In-Charge

Noted by:

Engr. Zandro P. Danes


Project In-Charge
PROJECT : FRABELLE SALCEDO
LOCATION : Tordesillas St., cor. Bautista St. Makati City
OWNER : Frabelle Fishing Corporation
SUBJECT : Pile Cap
CONTRACTOR : Monocrete Construction Philippines Inc.

Description Location (Grid Line) AREA 1 AREA 2 TOTAL AREA Height Volume
( m) ( m) ( m ) (m) ( m )
PILE CAP-1 GL 6/A 6.97 6.125 13.095 2.500 32.738
PILE CAP-2 GL 1/A 6.97 6.125 13.095 2.500 32.738
PILE CAP-3 GL 6/B' 20.16 0.000 20.160 2.200 44.352
PILE CAP-4 GL 1/B 5.10 4.725 9.825 1.800 17.685
PILE CAP-5 GL 1'/B 2.56 0.000 2.560 1.000 2.560
PILE CAP-6 GL 2-4/A'-B' 110.92 0.000 110.921 2.000 221.841
PILE CAP-7 GL 2/A 4.64 5.219 9.860 2.500 24.649
PILE CAP-7 GL 4/A 4.64 5.219 9.860 2.500 24.649

TOTAL 189.375 401.211

Prepared by:

Engr. Lean Christian V. Olores


Engr. In-Charge

Noted by:

Engr. Zandro P. Danes


Project In-Charge
PROJECT : FRABELLE SALCEDO
LOCATION : Tordesillas St., cor. Bautista St. Makati City
OWNER : Frabelle Fishing Corporation
SUBJECT : Cistern
CONTRACTOR : Monocrete Construction Philippines Inc.

Length Width Height Area Volume


Description Location (Grid Line)
(m) (m) (m) ( m ) ( m )
RW-3 GL 2'/B-C 7.50 0.300 2.400 36.000 5.400
RW-1 GL 2/A'-B 4.40 0.300 4.500 39.600 5.940
RW-4 GL 2/B-B' 7.50 0.300 2.400 36.000 5.400
RW-1 GL 2/C-D' 7.77 0.300 4.500 69.966 10.495
RW-6 GL 1"/B-B' 7.50 0.300 2.800 42.000 6.300
RW-5 GL 1'/B-B' 6.90 0.300 5.200 71.760 10.764
RW-1 GL 1/B-B' 20.27 0.300 4.200 170.302 25.545
RW-1 GL A'/1-2 8.42 0.300 4.200 70.728 10.609
RW-3 GL B/2-2' 2.66 0.300 2.400 12.744 1.912
RW-1 GL B/1'-1'' 2.45 0.300 4.500 22.050 3.308
RW-2 GL B/1-1' 5.67 0.300 4.200 47.628 7.144
RW-3 GL C/2-2' 2.66 0.300 2.400 12.744 1.912
RW-1 GL C/1'-1'' 2.45 0.300 4.200 20.580 3.087
RW-2 GL C/1-1' 5.67 0.300 4.200 47.628 7.144
RW-1 GL D'/1-2 8.42 0.300 4.200 70.728 10.609

TOTAL 770.458 115.569

Description Location (Grid Line) Length Width Height Area Volume


(m) (m) (m) ( m ) ( m )
B-1 4.40 0.3 0.50 5.720 0.660
B-2 7.77 0.3 0.700 13.216 1.633
B-3 4.98 0.3 0.600 7.469 0.896
B-4 6.90 0.3 0.600 10.350 1.242
B-5 7.77 0.3 0.600 11.661 1.399
TOTAL 48.415 5.830

Description Location (Grid Line) Length Width Height Area Volume


(m) (m) (m) ( m ) ( m )
S-3 4.40 2.45 0.125 10.780 1.348
S-2 7.50 2.45 0.125 18.375 2.297
S-6 7.77 2.45 0.125 19.046 2.381
S-4 4.98 2.71 0.125 13.478 1.685
S-6 6.90 2.71 0.125 18.678 2.335
S-7 7.77 2.71 0.125 21.044 2.631
S-5 4.98 2.66 0.125 13.259 1.657
S-6 6.90 2.66 0.125 18.375 2.297
S-6 7.77 2.66 0.125 20.702 2.588
SOG 20.27 10.45 0.25 212.00 52.955
TOTAL 365.74 72.17

Prepared by:

Engr. Lean Christian V. Olores


Engr. In-Charge

Noted by:

Engr. Zandro P. Danes


Project In-Charge
PROJECT : FRABELLE SALCEDO
LOCATION : Tordesillas St., cor. Bautista St. Makati City
OWNER : Frabelle Fishing Corporation
SUBJECT : FUEL TANK
CONTRACTOR : Monocrete Construction Philippines Inc.

Description Location (Grid Line) Length Width Height Area Volume


(m) (m) (m) ( m ) ( m )
RW-1 3.60 0.250 4.000 28.800 3.600
RW-1 3.60 0.250 4.000 28.800 3.600
RW-1 7.63 0.250 4.000 61.040 7.630
RW-1 7.63 0.250 4.000 61.040 7.630
B-2 6.68 0.300 0.700 11.356 1.403

TOTAL 191.036 23.863

Description Location (Grid Line) Length Width Height Area Volume


(m) (m) (m) ( m ) ( m )
S-8 1.65 6.68 0.125 11.022 1.378
S-8 1.65 6.68 0.125 11.022 1.378
SOG 3.60 7.03 0.250 25.294 6.323
TOTAL 47.34 9.08

Prepared by:

Engr. Lean Christian V. Olores


Engr. In-Charge

Noted by:

Engr. Zandro P. Danes


Project In-Charge
PROJECT : FRABELLE SALCEDO
LOCATION : Tordesillas St., cor. Bautista St. Makati City
OWNER : Frabelle Fishing Corporation
SUBJECT : HOLDING TANK
CONTRACTOR : Monocrete Construction Philippines Inc.

Description Location (Grid Line) Length Width Height Area Volume


(m) (m) (m) ( m ) ( m )
HTW-1 8.00 0.250 3.900 62.400 7.800
HTW-2 3.30 0.250 3.700 24.420 3.053
HTW-1 8.00 0.250 3.900 62.400 7.800
HTW-1 4.50 0.250 3.530 31.770 3.971
HTW-2 4.00 0.250 3.700 29.600 3.700
HTW-1 4.50 0.250 3.900 35.100 4.388
B-1 4.45 0.300 0.500 5.785 0.668

TOTAL 251.475 31.379

Description Location (Grid Line) Length Width Height Area Volume


(m) (m) (m) ( m ) ( m )
S-1 3.30 1.87 0.125 6.171 0.771
S-2 4.45 1.87 0.125 8.322 1.040
S-1 3.30 1.87 0.125 6.171 0.771
S-2 4.45 1.87 0.125 8.322 1.040
SOG 8.00 4.50 0.250 36.00 9.00
TOTAL 64.99 12.62

Prepared by:

Engr. Lean Christian V. Olores


Engr. In-Charge

Noted by:

Engr. Zandro P. Danes


Project In-Charge
PROJECT : FRABELLE SALCEDO
LOCATION : Tordesillas St., cor. Bautista St. Makati City
OWNER : Frabelle Fishing Corporation
SUBJECT : GREASE TRAP
CONTRACTOR : Monocrete Construction Philippines Inc.

Description Location (Grid Line) Length Width Height Area Volume


(m) (m) (m) ( m ) ( m )
RW-4 3.20 0.250 4.000 25.600 3.200
RW-4 3.20 0.250 4.000 25.600 3.200
RW-4 1.60 0.250 4.000 12.800 1.600
RW-4 1.60 0.250 4.000 12.800 1.600
GCW-2 1.20 0.150 0.800 2.100 0.144
GCW-2 1.20 0.150 1.000 2.580 0.180

TOTAL 81.480 9.924

Description Location (Grid Line) Length Width Height Area Volume


(m) (m) (m) ( m ) ( m )
S 3.20 1.20 0.125 3.840 0.480
SOG 3.20 1.20 0.250 3.840 0.960
TOTAL 7.68 1.44

Prepared by:

Engr. Lean Christian V. Olores


Engr. In-Charge

Noted by:

Engr. Zandro P. Danes


Project In-Charge