2 SITE CLEARANCE R 133 006.00 3 EARTHWORKS R 1 621 060.00 4 PIPE TRENCHES R 1 680 715.00 5 GABIONS AND PITCHING R 648 360.00 6 CONCRETE (STRUCTURAL) R 458 729.46 7 MEDIUM PRESSURE PIPELINES R 46 900.00 8 BEDDING R 541 050.00 9 SEWERS R 2 474 845.00 10 ANCILLARY ROADWORKS R 96 290.00 Sub-total R 11 673 724.43 Contingencies (10%) R 1 167 372.44 Sub-total R 12 841 096.87 Escalation (5%) R 642 054.84 Sub-total R 13 483 151.72 VAT (14%) R 1 887 641.24 Total Estimate R 15 370 792.96