ANALISA HARGA SATUAN (AHS) PEKERJAAN INSTALASI LISTRIK

Harga Sat. Jumlah Harga


No. Uraian Jenis pekerjaan Sat. Koeff. Bahan / Upah / Alat Bahan Upah Alat
Rp. Rp. Rp. Rp.
1 2 3 4 5 6 7 8
XI PEKERJAAN INSTALASI LISTRIK
XI.1 LAMPU PIJAR 20 S/D 100 WATT
Lampu pijar 25 s/d 100 watt bh 1.000 Rp6,000.00 Rp6,000.00 - -
Pekerja Oh 2.237 Rp38,000.00 Rp85,000.00
Mandor Oh 0.5 Rp60,000.00 Rp30,000.00
Jumlah Rp6,000.00 Rp115,000.00
XI.2 LAMPU SL PHILIP 20 WATT
Lampu Sl philip 25 watt bh 1.000 Rp32,000.00 Rp32,000.00 - -
Pekerja Oh 2.237 Rp38,000.00 Rp85,000.00
Mandor Oh 0.5 Rp60,000.00 Rp30,000.00
Jumlah Rp32,000.00 Rp115,000.00
XI.3 LAMPU DOWNLIGHT
Downlight + SL 25 watt philip bh 1.000 Rp33,500.00 Rp33,500.00 - -
Pekerja Oh 2.237 Rp38,000.00 Rp85,000.00
Mandor Oh 0.5 Rp60,000.00 Rp30,000.00
Jumlah Rp33,500.00 Rp115,000.00
XI.4 LAMPU TAMAN
Lampu taman + tiang + lampu 1 buah bh 1.000 Rp146,500.00 Rp146,500.00 - -
Pekerja Oh 2.237 Rp38,000.00 Rp85,000.00
Mandor Oh 0.5 Rp60,000.00 Rp30,000.00
Jumlah Rp146,500.00 Rp115,000.00
XI.5 STOP KONTAK
Stop kontak broko standard (1 phase) bh 1.000 Rp13,500.00 Rp13,500.00 - -
Pekerja Oh 2.237 Rp38,000.00 Rp85,000.00
Mandor Oh 0.5 Rp60,000.00 Rp30,000.00
Jumlah Rp13,500.00 Rp115,000.00
XI.6 SAKLAR
Saklar broko tunggal standard bh 1.000 Rp10,000.00 Rp10,000.00 - -
Pekerja Oh 2.237 Rp38,000.00 Rp85,000.00
Mandor Oh 0.5 Rp60,000.00 Rp30,000.00
Jumlah Rp10,000.00 Rp115,000.00
XI.7 KABEL NYM SUPREME 2 X 10
Saklar broko tunggal standard m' 1.000 Rp20,800.00 Rp20,800.00 - -
Pekerja Oh 2.237 Rp38,000.00 Rp85,000.00
Mandor Oh 0.5 Rp60,000.00 Rp30,000.00
Jumlah Rp20,800.00 Rp115,000.00
TABEL XI.1

SATUAN (AHS) PEKERJAAN INSTALASI LISTRIK

Jumlah Harga
Bahan + Upah
Rp.
9

121,000.00

147,000.00

148,500.00
261,500.00

128,500.00

125,000.00

135,800.00
TABEL XI.2

RAB BAHAN PEKERJAAN INSTALASI LISTRIK

HARGA SAT JUMLAH HARGA


NO URAIAN PEKERJAAN VOL SAT
BAHAN Biaya Bahan Bid Price Biaya Bahan Pelaksanaan
1 2 3 4 5 6 7
XI. PEKERJAAN INSTALASI LISTRIK
K.1 Lampu Pijar 25 Watt 2 bh Rp6,000 Rp12,000.00 Rp12,000.00
K.2 Lampu SL Philip 25 Watt 6 bh Rp32,000 Rp192,000.00 Rp192,000.00
K.3 Lampu Downlight 6 bh Rp33,500 Rp201,000.00 Rp201,000.00
K.4 Lampu Taman 2 bh Rp146,500 Rp293,000.00 Rp293,000.00
K.5 Stop Kontak 11 bh Rp13,500 Rp148,500.00 Rp148,500.00
K.6 Stop Kontak Dobel 4 bh Rp13,500 Rp54,000.00 Rp54,000.00
K.7 Saklar 8 bh Rp10,000 Rp80,000.00 Rp80,000.00
K.8 Kabel NYM supreme 2 x 10 100 m' Rp20,800 Rp2,080,000.00 Rp2,080,000.00
Jumlah Rp3,060,500 Rp3,060,500

RAB UPAH PEKERJAAN INSTALASI LISTRIK

HARGA SAT JUMLAH HARGA


NO URAIAN PEKERJAAN VOL SAT
UPAH Biaya Upah Bid Price Biaya Upah Pelaksanaan
1 2 3 4 5 6 7
XI. PEKERJAAN INSTALASI LISTRIK
K.1 Lampu Pijar 25 Watt 2 bh Rp115,000 Rp230,000.00 Rp207,000.00
K.2 Lampu SL Philip 25 Watt 6 bh Rp115,000 Rp690,000.00 Rp621,000.00
K.3 Lampu Downlight 6 bh Rp115,000 Rp690,000.00 Rp621,000.00
K.4 Lampu Taman 2 bh Rp115,000 Rp230,000.00 Rp207,000.00
K.5 Stop Kontak 11 bh Rp115,000 Rp1,265,000.00 Rp1,138,500.00
K.6 Stop Kontak Dobel 4 bh Rp115,000 Rp460,000.00 Rp414,000.00
K.7 Saklar 8 bh Rp115,000 Rp920,000.00 Rp828,000.00
K.8 Kabel NYM supreme 2 x 10 100 m' Rp115,000 Rp11,500,000.00 Rp10,350,000.00
Jumlah Rp15,985,000 Rp14,386,500
TABEL XI.3

KEBUTUHAN TENAGA KERJA

Koeff. Koeff.
No. Uraian Jenis pekerjaan Sat. Volume Sat Kebutuhan Tenaga Kerja
(Awal) (Akhir)

1 2 3 4 5 6 7 8=5x6
XI PEKERJAAN INSTALASI LISTRIK
XI.1 LAMPU PIJAR 25 WATT
Pekerja Oh 2.237 2.013 2.000 bh 4.026
Mandor Oh 0.500 0.450 2.000 bh 0.900
Jumlah 4.926
XI.2 LAMPU SL PHILIP 25 WATT
Pekerja Oh 2.237 2.013 6.000 bh 12.079
Mandor Oh 0.500 0.450 6.000 bh 2.700
Jumlah 14.779
XI.3 LAMPU DOWNLIGHT
Pekerja Oh 2.237 2.013 6.000 bh 12.079
Mandor Oh 0.500 0.450 6.000 bh 2.700
Jumlah 14.779
XI.4 LAMPU TAMAN
Pekerja Oh 2.237 2.013 2.000 bh 4.026
Mandor Oh 0.500 0.450 2.000 bh 0.900
Jumlah 4.926
XI.5 STOP KONTAK
Pekerja Oh 2.237 2.013 11.000 bh 22.145
Mandor Oh 0.500 0.450 11.000 bh 4.950
Jumlah 27.095
XI.6 STOP KONTAK DOBEL
Pekerja Oh 2.237 2.013 4.000 bh 8.053
Mandor Oh 0.500 0.450 4.000 bh 1.800
Jumlah 9.853
XI.7 SAKLAR
Pekerja Oh 2.237 2.013 8.000 bh 16.105
Mandor Oh 0.500 0.450 8.000 bh 3.600
Jumlah 19.705
XI.8 KABEL NYM SUPREME 2 X 10
Pekerja Oh 2.237 2.013 100.000 m' 201.316
Mandor Oh 0.500 0.450 100.000 m' 45.000
Jumlah 246.316
TABEL XI.4

ANALISIS PRODUKTIVITAS KERJA

Kebutuhan Tenaga Harga Satuan Durasi Volume


No. Uraian Pekerja Sat Biaya Upah
Kerja Upah (Hari) Pekerjaan
1 2 3 4 5 6=4x5 7 8
XI. PEKERJAAN INSTALASI LISTRIK
XI.1 LAMPU PIJAR 25 WATT
Pekerja Oh 4.026 Rp38,000 Rp153,000
Mandor Oh 0.900 Rp60,000 Rp54,000 1 2.000
Jumlah Rp207,000
XI. 2 LAMPU SL PHILIP 25 WATT
Pekerja Oh 12.079 Rp38,000 Rp459,000
Mandor Oh 2.700 Rp60,000 Rp162,000 1 6
Jumlah Rp621,000
XI.3 LAMPU DOWNLIGHT
Pekerja Oh 12.079 Rp38,000 Rp459,000
Mandor Oh 2.700 Rp60,000 Rp162,000 1 6.000
Jumlah Rp621,000
XI.4 LAMPU TAMAN
Pekerja Oh 4.026 Rp38,000 Rp153,000
Mandor Oh 0.900 Rp60,000 Rp54,000 2 2.000
Jumlah Rp207,000
XI.5 STOP KONTAK
Pekerja Oh 22.145 Rp38,000 Rp841,500
Mandor Oh 4.950 Rp60,000 Rp297,000 2 11.000
2 11.000
Jumlah Rp1,138,500
XI.6 STOP KONTAK DOBEL
Pekerja Oh 8.053 Rp38,000 Rp306,000
Mandor Oh 1.800 Rp60,000 Rp108,000 2 4.000
Jumlah Rp414,000
XI.7 SAKLAR
Pekerja Oh 16.105 Rp38,000 Rp612,000
Mandor Oh 3.600 Rp60,000 Rp216,000 2 8.000
Jumlah Rp828,000
XI.8 KABEL NYM SUPREME 2 X 10
Pekerja Oh 201.316 Rp38,000 Rp7,650,000
Mandor Oh 45.000 Rp60,000 Rp2,700,000 2 100.000
Jumlah Rp10,350,000
TABEL XI.4

ISIS PRODUKTIVITAS KERJA

Sat Kebutuhan Tenaga Kerja Produktivitas Kerja Sat


(Per Hari) (Per Hari)
9 10 = 4 7 11 = 8 10 12

4.026
bh 0.900 2.000 bh

12.079
bh 2.700 6.000 bh

12.079
bh 2.700 6.000 bh

4.026
bh 0.900 2.000 bh

22.145
bh 4.950 11.000 bh
bh 11.000 bh

8.053
bh 1.800 4.000 bh

16.105
bh 3.600 8.000 bh

201.316
m' 45.000 100.000 m'
TABEL XI.5

ANALISIS BAHAN DAN KEBUTUHAN BAHAN

Harga Satuan
No. Uraian Jenis pekerjaan Sat. Koeff. Volume Sat Kebutuhan Bahan Sat RAB Bahan
Bahan

1 2 3 4 5 6 7=5x4 7 8 9
XI PEKERJAAN INSTALASI LISTRIK
XI.1 LAMPU PIJAR 25 WATT
Lampu pijar 25 s/d 100 watt bh 1.000 2.00 bh 2.000 bh Rp6,000 Rp12,000
Jumlah Rp12,000
XI.2 LAMPU SL PHILIP 25 WATT
Lampu Sl philip 25 watt bh 1.0000 6.00 bh 6.000 bh Rp32,000 Rp192,000
Jumlah Rp192,000
XI.3 LAMPU DOWNLIGHT
Downlight + SL 25 watt philip bh 1.0000 6.00 bh 6.000 bh Rp33,500 Rp201,000
Jumlah Rp201,000
XI.4 LAMPU TAMAN
Lampu taman + tiang + lampu 1 buah bh 1.0000 2.00 bh 2.000 bh Rp146,500 Rp293,000
Jumlah Rp293,000
XI.5 STOP KONTAK
Stop kontak broko standard (1 phase) bh 1.0000 11.00 bh 11.000 bh Rp13,500 Rp148,500
Jumlah Rp148,500
XI.6 STOP KONTAK DOBEL
Stop kontak broko standard (1 phase) bh 1.0000 4.00 bh 4.000 bh Rp13,500 Rp54,000
Jumlah Rp54,000
XI.7 SAKLAR
Saklar broko tunggal standard bh 1.0000 8.00 bh 8.000 bh Rp10,000 Rp80,000
Jumlah Rp80,000
XI.8 KABEL NYM SUPREME 2 X 10
Saklar broko tunggal standard m' 1.0000 100.00 m' 100.000 m' Rp20,800 Rp2,080,000
Jumlah Rp2,080,000
TABEL XI.5

AHAN DAN KEBUTUHAN BAHAN

Durasi Kebutuhan Produktivitas/


Sat Sat
(Hari) Bahan/Hari Hari

10 11 12 13 14

2.000 bh
1 2.00 m2

6.000 bh 6.00 m2
1

6.000 bh 6.00 m2
1

2.000 bh 1.00 m2
2
11.000 bh 5.50 m2
2

4.000 bh 2.00 m2
2

8.000 bh 4.00 m2
2

100.000 m' 50.00 m2


2
TABEL XI.6
REKAPITULASI

REKAPITULASI UPAH TENAGA KERJA PEKERJAAN LISTRIK

No. Jenis Pekerja Sat Jumlah Pekerja Sat Harga Satuan RAB Upah Jumlah
Upah Pekerja/Hari
1 Pekerja Oh 279.829 Oh Rp38,000 Rp10,633,500 39.976
2 Mandor Oh 62.550 Oh Rp60,000 Rp3,753,000 8.936
Jumlah Rp14,386,500 Jumlah

REKAPITULASI BAHAN PEKERJAAN LISTRIK

No. Jenis Bahan Sat Jumlah Bahan Sat Harga Satuan RAB Bahan Jumlah
Bahan Bahan/Hari
1 Lampu Pijar 25 Watt bh 2.000 bh Rp6,000 Rp12,000 0.286
2 Lampu SL Philip 25 Watt bh 6.000 bh Rp32,000 Rp192,000 0.857
3 Lampu Downlight bh 6.000 bh Rp33,500 Rp201,000 0.857
4 Lampu Taman bh 2.000 bh Rp146,500 Rp293,000 0.286
5 Stop Kontak bh 11.000 bh Rp13,500 Rp148,500 1.571
6 Stop Kontak Dobel bh 4.000 bh Rp13,500 Rp54,000 0.571
7 Saklar bh 8.000 bh Rp10,000 Rp80,000 1.143
8 Kabel NYM supreme 2 x 10 m' 100.000 m' Rp20,800 Rp2,080,000 14.286
Jumlah Rp3,060,500 Jumlah
Biaya
Upah/Hari
Rp1,519,071
Rp536,143
Rp2,055,214

Biaya
Bahan/Hari
Rp1,714
Rp27,429
Rp28,714
Rp41,857
Rp21,214
Rp7,714
Rp11,429
Rp297,143
Rp437,214
RAB BAHAN PEKERJAAN INSTALASI LISTRIK

HARGA SAT JUMLAH HARGA


NO URAIAN PEKERJAAN VOL SAT
BAHAN Biaya Bahan Bid Price Biaya Bahan Pelaksanaan
1 2 3 4 5 6 7
XI. PEKERJAAN INSTALASI LISTRIK
K.1 Lampu Pijar 25 Watt 13 bh Rp6,000 Rp78,000.00 Rp78,000.00
K.2 Lampu SL Philip 25 Watt 10 bh Rp32,000 Rp320,000.00 Rp320,000.00
K.3 Lampu Downlight 7 bh Rp33,500 Rp234,500.00 Rp234,500.00
K.4 Lampu Taman 5 bh Rp146,500 Rp732,500.00 Rp732,500.00
K.5 Stop Kontak 6 bh Rp13,500 Rp81,000.00 Rp81,000.00
K.6 Stop Kontak Dobel 9 bh Rp13,500 Rp121,500.00 Rp121,500.00
K.7 Saklar 10 bh Rp10,000 Rp100,000.00 Rp100,000.00
K.8 Kabel NYM supreme 2 x 10 100 m' Rp20,800 Rp2,080,000.00 Rp2,080,000.00
Jumlah Rp3,747,500 Rp3,747,500
RAB UPAH PEKERJAAN INSTALASI LISTRIK

HARGA SAT JUMLAH HARGA


NO URAIAN PEKERJAAN VOL SAT
UPAH Biaya Upah Bid Price Biaya Upah Pelaksanaan
1 2 3 4 5 6 7
XI. PEKERJAAN INSTALASI LISTRIK
K.1 Lampu Pijar 25 Watt 13 bh Rp115,000 Rp1,495,000.00 Rp1,345,500.00
K.2 Lampu SL Philip 25 Watt 10 bh Rp115,000 Rp1,150,000.00 Rp1,035,000.00
K.3 Lampu Downlight 7 bh Rp115,000 Rp805,000.00 Rp724,500.00
K.4 Lampu Taman 5 bh Rp115,000 Rp575,000.00 Rp517,500.00
K.5 Stop Kontak 6 bh Rp115,000 Rp690,000.00 Rp621,000.00
K.6 Stop Kontak Dobel 9 bh Rp115,000 Rp1,035,000.00 Rp931,500.00
K.7 Saklar 10 bh Rp115,000 Rp1,150,000.00 Rp1,035,000.00
K.8 Kabel NYM supreme 2 x 10 100 m' Rp115,000 Rp11,500,000.00 Rp10,350,000.00
Jumlah Rp18,400,000 Rp16,560,000
REKAPITULASI UPAH TENAGA KERJA PEKERJAAN LANTAI

No. Jenis Pekerja Sat Jumlah Pekerja Sat Harga Satuan Upah RAB Upah

1 Lampu Pijar 25 Watt bh 11.700 ttk Rp115,000 Rp1,345,500


2 Lampu SL Philip 25 Watt bh 9.000 ttk Rp115,000 Rp1,035,000
3 Lampu Downlight bh 6.300 ttk Rp115,000 Rp724,500
4 Lampu Taman bh 4.500 ttk Rp115,000 Rp517,500
5 Stop Kontak bh 5.400 ttk Rp115,000 Rp621,000
6 Stop Kontak Dobel bh 8.100 ttk Rp115,000 Rp931,500
7 Saklar bh 9.000 ttk Rp115,000 Rp1,035,000
8 Kabel NYM supreme 2 x 10 m' 90.000 ttk Rp115,000 Rp10,350,000
Jumlah Rp16,560,000

REKAPITULASI BAHAN PEKERJAAN LANTAI

No. Jenis Bahan Sat Jumlah Bahan Sat Harga Satuan Bahan RAB Bahan

1 Lampu Pijar 25 Watt bh 13.000 bh Rp6,000 Rp6,000


2 Lampu SL Philip 25 Watt bh 10.000 bh Rp32,000 Rp320,000
3 Lampu Downlight bh 7.000 bh Rp33,500 Rp234,500
4 Lampu Taman bh 5.000 bh Rp146,500 Rp732,500
5 Stop Kontak bh 6.000 bh Rp13,500 Rp81,000
6 Stop Kontak Dobel bh 9.000 bh Rp13,500 Rp121,500
7 Saklar bh 10.000 bh Rp10,000 Rp100,000
8 Kabel NYM supreme 2 x 10 m' 100.000 m' Rp20,800 Rp2,080,000
Jumlah Rp3,675,500
KAPITULASI UPAH TENAGA KERJA PEKERJAAN LANTAI

Jumlah Biaya
Pekerja/Hari Upah/Hari
1.671 Rp192,214
1.286 Rp147,857
0.900 Rp103,500
0.643 Rp73,929
0.771 Rp88,714
1.157 Rp133,071
1.286 Rp147,857
12.857 Rp1,478,571
Jumlah Rp2,365,714

REKAPITULASI BAHAN PEKERJAAN LANTAI

Jumlah Biaya
Bahan/Hari Bahan/Hari
1.857 Rp11,143
1.429 Rp45,714
1.000 Rp33,500
0.714 Rp104,643
0.857 Rp11,571
1.286 Rp17,357
1.429 Rp14,286
14.286 Rp297,143
Jumlah Rp535,357
KEBUTUHAN TENAGA KERJA

Koeff. Koeff. Kebutuhan No.


No. Uraian Jenis pekerjaan Sat. Volume Sat
(Awal) (Akhir) Tenaga Kerja
1
1 2 3 4 5 6 7 8=5x6 XI. PEKERJAAN INSTALASI LISTRI
XI PEKERJAAN INSTALASI LISTRIK XI.1 LAMPU PIJAR 25 WATT
XI.1 LAMPU PIJAR 25 WATT
Instalasi titik lampu/stop kontak (upah dan alat) ttk 1.0000 0.9000 13.000 bh 11.700
Jumlah 11.700 XI. 2 LAMPU SL PHILIP 25 WATT
XI.2 LAMPU SL PHILIP 25 WATT
Instalasi titik lampu/stop kontak (upah dan alat) ttk 1.0000 0.9000 10.000 bh 9.000
Jumlah 9.000 XI.3 LAMPU DOWNLIGHT
XI.3 LAMPU DOWNLIGHT
Instalasi titik lampu/stop kontak (upah dan alat) ttk 1.0000 0.9000 7.000 bh 6.300
Jumlah 6.300 XI.4 LAMPU TAMAN
XI.4 LAMPU TAMAN
Instalasi titik lampu/stop kontak (upah dan alat) ttk 1.0000 0.9000 5.000 bh 4.500
Jumlah 4.500 XI.5 STOP KONTAK
XI.5 STOP KONTAK
Instalasi titik lampu/stop kontak (upah dan alat) ttk 1.0000 0.9000 6.000 bh 5.400
Jumlah 5.400 XI.6 STOP KONTAK DOBEL
XI.6 STOP KONTAK DOBEL
Instalasi titik lampu/stop kontak (upah dan alat) ttk 1.0000 0.9000 9.000 bh 8.100
Jumlah 8.100 XI.7 SAKLAR
XI.7 SAKLAR
Instalasi titik lampu/stop kontak (upah dan alat) ttk 1.0000 0.9000 10.000 bh 9.000
Jumlah 9.000 XI.8 KABEL NYM SUPREME 2 X 1
XI.8 KABEL NYM SUPREME 2 X 10
Instalasi titik lampu/stop kontak (upah dan alat) ttk 1.0000 0.9000 100.000 m' 90.000
Jumlah 90.000

ANALISIS BAHAN DAN KEBUTUHAN BAHAN

Harga
No. Uraian Jenis pekerjaan Sat. Koeff. Volume SatKebutuhan Bahan Sat Satuan RAB Bahan
Bahan

1 2 3 4 5 6 7=5x4 7 8 9
XI PEKERJAAN INSTALASI LISTRIK
XI.1 LAMPU PIJAR 25 WATT
Lampu pijar 25 s/d 100 watt bh 1.000 13.00 bh 13.000 bh Rp6,000 Rp78,000
Jumlah Rp78,000
XI.2 LAMPU SL PHILIP 25 WATT
Lampu Sl philip 25 watt bh 1.0000 10.00 bh 10.000 bh Rp32,000 Rp320,000
Jumlah Rp320,000
XI.3 LAMPU DOWNLIGHT
Downlight + SL 25 watt philip bh 1.0000 7.00 bh 7.000 bh Rp33,500 Rp234,500
Jumlah Rp234,500
XI.4 LAMPU TAMAN
Lampu taman + tiang + lampu 1 buah bh 1.0000 5.00 bh 5.000 bh Rp146,500 Rp732,500
Jumlah Rp732,500
XI.5 STOP KONTAK
Stop kontak broko standard (1 phase) bh 1.0000 6.00 bh 6.000 bh Rp13,500 Rp81,000
Jumlah Rp81,000
XI.6 STOP KONTAK DOBEL
Stop kontak broko standard (1 phase) bh 1.0000 9.00 bh 9.000 bh Rp13,500 Rp121,500
Jumlah Rp121,500
XI.7 SAKLAR
Saklar broko tunggal standard bh 1.0000 10.00 bh 10.000 bh Rp10,000 Rp100,000
Jumlah Rp100,000
XI.8 KABEL NYM SUPREME 2 X 10
Saklar broko tunggal standard m' 1.0000 100.00 m' 100.000 m' Rp20,800 Rp2,080,000
Jumlah Rp2,080,000
ANALISIS PRODUKTIVITAS KERJA

Kebutuhan Harga Satuan Durasi Volume


Uraian Pekerja Sat Biaya Upah Sat
Tenaga Kerja Upah (Hari) Pekerjaan
2 3 4 5 6=4x5 7 8 9
XI. PEKERJAAN INSTALASI LISTRIK
XI.1 LAMPU PIJAR 25 WATT
Instalasi titik lampu/stop kontak (upah dan alat) ttk 11.700 Rp115,000 Rp1,345,500
2 13.000 bh
Jumlah Rp1,345,500
XI. 2 LAMPU SL PHILIP 25 WATT
Instalasi titik lampu/stop kontak (upah dan alat) ttk 9.000 Rp115,000 Rp1,035,000
2 10 bh
Jumlah Rp1,035,000
XI.3 LAMPU DOWNLIGHT
Instalasi titik lampu/stop kontak (upah dan alat) ttk 6.300 Rp115,000 Rp724,500 2 7.000 bh
Jumlah Rp724,500
XI.4 LAMPU TAMAN
Instalasi titik lampu/stop kontak (upah dan alat) ttk 4.500 Rp115,000 Rp517,500
2 5.000 bh
Jumlah Rp517,500
XI.5 STOP KONTAK
Instalasi titik lampu/stop kontak (upah dan alat) ttk 5.400 Rp115,000 Rp621,000
2 6.000 bh
Jumlah Rp621,000
XI.6 STOP KONTAK DOBEL
Instalasi titik lampu/stop kontak (upah dan alat) ttk 8.100 Rp115,000 Rp931,500
2 9.000 bh
Jumlah Rp931,500
XI.7 SAKLAR
Instalasi titik lampu/stop kontak (upah dan alat) ttk 9.000 Rp115,000 Rp1,035,000
2 10.000 bh
Jumlah Rp1,035,000
XI.8 KABEL NYM SUPREME 2 X 10
Instalasi titik lampu/stop kontak (upah dan alat) ttk 90.000 Rp115,000 Rp10,350,000
2 100.000 m'
Jumlah Rp10,350,000

N KEBUTUHAN BAHAN

Kebutuhan Produktivitas/
Durasi (Hari) Sat Sat
Bahan/Hari Hari

10 11 12 13 14

6.500 bh
2 6.50 m2

5.000 bh 5.00 m2
2

3.500 bh 3.50 m2
2

2.500 bh 2.50 m2
2

3.000 bh 3.00 m2
2
2

4.500 bh 4.50 m2
2

5.000 bh 5.00 m2
2

50.000 m' 50.00 m2


2
S PRODUKTIVITAS KERJA

Kebutuhan
Tenaga Kerja Produktivitas Sat
(Per Hari) Kerja (Per Hari)
10 = 4 7 11 = 8 10 12

5.850
6.500 bh

4.500
5.000 bh

3.150 3.500 bh

2.250 2.500 bh

2.700 3.000 bh

4.050 4.500 bh
4.500 5.000 bh

45.000 50.000 m'