Design Detail To BS 8110 1997
Design Detail To BS 8110 1997
Project
LINDE ENGINEERING
Unit(s): ASU
PCWBS: Z
QATAR SHELL GTL PROJECT (PEARL)
C2 AIR SEPARATION UNITS CONSTRUCTION
Document Title:
T.4.234.582 &
Inspection for primer 100% Manufacturers QC Civil GAM-QCR-QAC-
3.4 Manufacturers
coat recommendation Inspector GTL-164 I S S
recommendation
T.4.234.582 &
100% QC Civil GAM-QCR-QAC-
3.5 Release to painting Manufacturers
Inspector GTL-164 I W S
recommendation
T.4.234.582 &
In process inspection 100% Manufacturers QC Civil GAM-QCR-QAC-
3.6 Manufacturers
of Painting system recommendation Inspector GTL-164
recommendation I S S
Inspection of a) Visual I W S
intermediate coats & T.4.234.582 &
Inspection Manufacturers Site Engineer & GAM-QCR-QAC-
3.7 minimum time between Manufacturers
d) Adhesion recommendation QCI GTL-164
the applications of recommendation
different coats. check
I W S
T.4.234.582 &
100% Manufacturers Manufacturers Site Engineer & GAM-QCR-QAC-
3.8 DFT Checking
recommendation recommendation QCI GTL-164
Final Coat inspection & Site Engineer & QC Linde Punch List
3.10 Punch Listing
100% ---- Visual confirmation
Civil Inspector
I W W
GAMA REP.
Accepted By
LINDE REP.
GAM-QCR-QAC-GTL-164, Rev-0
QSGTL-PEARL GTL PROJECT
C2-ASU-Construction Project
Inspection Form for Surface
Preparation(Buildings)
GAM-ITP-QAC-GTL- Rev.
GAM-QCR-QAC-GTL-166 Date :
Location Bldg/Area:
Drawing No:
Name
Signature
Date
GAM-QCR-QAC-GTL- 166