EVENT ANALYSIS REPORT
_|
UNITNO :8 _ |TPS: Koradi ‘Unit Capacity : 660 MW
: Time 00:05|ate#- 06.08.2037 No
1. *HO Code: Station Code: T004 Tire [Of days from last synchronization: 10 Days
jand 6 Hours
‘Operating conditions at the time of Event :.
—_—toad MW ‘Coal_cycles In service ‘Oil Support
144 MW D wl
3. Nature of Event : Set withdrawn for attending various shutdown works.
Ia. Name of First Up, Main Protections & protection on which GCB tripped:
1) MFT operated (Loss of flame). 2) Turbine trip. 3) Gen.Protection trip alarm appeared. 4) Lock out relay 86 GA 1/2 operated.
IS A) Observations :- While withdrawing unit, only one coal cycle was in service without oll suppor and coal flow was 28}
|TPH CV was 4000. Due to high CV of coal , BID Lock at 150 MW due to ecostezming & load was not reduced to minimum .
Hence hand trip nat done due to high load and Boiler failed on loss of flame
[5 B) Remedial Action/Work done :- Work done by BM section: As per the attached sheet.
[6. Root Cause Analysis :- Set withdrawn (planned outage) for attending various shutdown works.
7. Preventive action suggested (Short Term) = As per the atiacne
8. Preventive action suggested (Long Term!
19. Similar event occurred last tim
10. Boiler lighted up Time- 12:39 Hrs Date — 12.08.2017
111. T-A Set Synchronized Time - 21:08 Hrs Date ~ 12.08.2017
[12. Remarks : Work done by EMT section: 06.08.2017. Ai & (iz are covered with polythene for Boiler
washing activity.
107.08.2017:- ID Fan outlet damper control box mounted end trial take
IMOBFP,
108.08.2017:- # P/M of FD fan-A&B, GT R,Y,B & UT 182, common
IC.w.182. # C&r TPS panel 220v OC source 182 checking, con
supply voltage is observed and contactor deenergised. Therefore to avoid tripping both sources are kept on source 1. # H.P.
heater 6A & 7A MOV actuator replaced, L.P. cleanup blow down MOV attended. # ESP pass A,B,D & E FRP rod inspection
carried out, 6 Nos. rod found damage & is replaced by new. # P/M of Gene: p rings, 4 Nos. brushes replaced.
J09.08.2017:- # P/M of soot blowers 207, 243 & 264. # 220v battery bi lis are replaced. # Boller feed pump
I/L MOV attended. # 220v battery charger P/M done. # P/M of ‘Seal air fan A & B done. # Seal air fen A
lf 1D fan 8A found abnormal sound in motor replaced with spa Slip ring polarity interchanged.
10.08,2017:- # Ventilator V/v was replaced with modified MOV & trial taken. # P/M of TDBFP A&B, A.CAOP 1 & 2, AC. EOP
Jdone, L.P. & H.P. Vacuur pump done.
11.08,2017:- # ECP panel 220V D.C. supervision relay 80 A & 80 B found fauity replaced by new. # ESP pass F field no, 3 HT
side insulator is changed. # All LRSB tral is taken. # P/M of 220v DC charge” & settings checked.
32.08.2017:- # P/M of RAPH A & B done, # Two Lc
ISG/TG charger and settings checked.
|Work done by TM section: 1) Condenser fil test for vacuur
preventive maintenance done. 4) TD- B governing done. 5) All CEP preventive
leakage attended. 7) 24 mtr clean up MIV gland leakage attended. 8) DMC\\
replacement done. 10) Ventilator V/v shaft replacement done. 11)
leakage attended. 13) HPH orifice modification done (Vent line).
intenance of CEP-A&C, ID fan A&B,
trol panel, P.R.V & Buckholz relay, A.C.W. 1,
During changeover interruption in
tenance done. 6) CRH pegging MOV gland
np overhaul done. 9) SCCW fitter
2 PM cone, 12) Clean up line safety V/V‘Surpjam 4q papuany|
‘Surpjom £q papuany|
aiquoridde yoy pasejdas 1ayse9|
aiqeandde oN -panejdas
io}
wio] 3u0y
SuonepuoUTUOIoy
‘uop {yom SuIysHY apts 49}BA YC 494009 a
‘uop 30M juouDse} dau pnp A/a a
‘uop om Bupsou aeyeay
‘uop 0m auEeda NENW = FOP AIA HSL
2uop pow wwDsej das puBID 1OF NA HSC
au0p 10M,