PT BERAU COAL

CHID Dept. - Site SMO

Reported b : Budi,Andre
Date : Thursday, October 12, 2017
Supervisi b : Budi,Andre

PEK. JALAN AKSES ke LOKASI JEMBATAN HD 785 via T3 - Swakelola PRO


A Activity Description A

1 Continue Pembuatan Jalan Akses Jembatan HD785/re-grading (sta 1+400 1


s/d sta 1+500)

2 Surfacing Scorea di sta 0+800 s/d sta 0+900 2

4
B Constraint B
1 Topografi eksisting cukup ekstrim 1

2 2

3
C Issue Safety C
1 1

2 2

D Equipment D
1 1 unit Dozer D85 -->Hujan, beroperasi ( 14.00 - 17.00 ) 1
2 1 unit Exca PC-200 --> Hujan, beroperasi ( 14.00 - 17.00 ) 2
3 1 Unit Bomag --> Hujan 3
4 1 unit Exca PC-200 (pinjam dari Mining) --> beroperasi ( 14.00 - 17.00 ) 4
5 2 unit DT-20T (pinjam dari Mining) --> beroperasi ( 14.00 - 17.00 )
E Others E
Man Power MIJ
1 Operator/Driver (MIJ) = 4 Orang 1
2 Pengawas CHID = 2 orang 2
3 Crew Leader CHID = 2 org 3
4 Foreman (MIJ) = 1 Orang 4
5 5
PHOTO's PHOTO's
Continue Pembuatan Jalan Akses Jembatan HD785/re-grading (sta 1+400 s/d sta Safety Recall dan Sosialisai Pro
1+500)

0
Surfacing Scorea di sta 0+800 s/d sta 0+900
PROYEK JEMBATAN HD B-EAST - PT. KRS PERBAIKAN JETTY COAL DA
Activity Description A

Safety Recall dan Sosialisai Prosedur Golden Rules 1

Constraint B
Topografi eksisting cukup ekstrim 1

3
Issue Safety C
1

Equipment D
Exca PC-200 = 1 unit beroperasi (preparasi area temporary facilities) 1
Crawler Crane 65 T = 1 unit (di lokasi) 2
Compactor= 1 unit (stand by) 3
Crawler Crane 35 T = 1 unit (stb di beaching point) 4
5
Others E
Man Power PT. KRS 1
Pengawas PT. KRS = 2 orang 1
Operator = 2 orang 2
Pekerja PT KRS = 6 orang 3
Pengawas CHID = 1 orang 4
Operator crane/crane truck = 1 orang 5
6

7
8

PHOTO's

ety Recall dan Sosialisai Prosedur Golden Rules Instalasi dan pengelasan lantai new dolphin

0
PERBAIKAN JETTY COAL DAN JETTY BBM - PT. BCN
Activity Description

Instalasi dan pengelasan lantai new dolphin

Constraint
Keterlambatan start operasional

Issue Safety
Pekerjaan di atas air

Pekerjaan dgn panas (welding/cutting metal)

Equipment
1 unit piling barge (Transworld 1)
1 unit crawler crane kap. 35 T
1 unit mesin las Miller
Peralatan welding

Others
Welder = 2 orang
Helper = 4 Orang
Crew pancang = 2 orang
Operator Crane = 1 orang
Rigger = 1 orang
Safetyman = 1 orang
Pengawas CHID = 1 orang

Crew Leader CHID = 1 org


nstalasi dan pengelasan lantai new dolphin
PROYEK : PEK. KONSTRUKSI JALAN AKSES KE LOKASI JEMBATAN HD B-EAST
DAILY REPORT UNIT LOKASI : SMO

Thursday, October 12, 2017

TENAGA KERJA DAN ALAT PRODUCTION PERFORMANCE


Jam Kerja Hour Meter Fuel
NO Jenis / Alat No Lambung Operator/Driver Pekerjaan Vol Sat Keterangan Lokasi Pekerjaan
In Out Awal Akhir Total Liter/HM
pengisian
I PT. MIJ
1 0.0 Liter Pemadatan badan jalan akses di T3 T2
2 Dozer D 85 219 Martinus 14:00 17:00 0.0 Liter dozing material soil di T2 Switch dengan dozer under Mining (MIJ 215) T2
3 PC 200 112 Tola 14:00 17:00 0.0 Liter Land clearing Start running 31/07/2017 13:00 T3
4 PC 200 122 Agus 14:00 17:00 0.0 Liter Loading Material Pinjam dari Mining per 28/09/2017 T3
5 DT CWB 325 Sugianto 14:00 17:00 0.0 Liter penimbunan di sta 1+400
6 DT CWB 343 Muklis 14:00 17:00 0.0 Liter penimbunan di sta 1+400
PT.BC
1 LV 209 7:30 17:00 0.0 Liter sarana support pengawasan pekerjaan di T3

SAFETY ISSUE LAPORAN CUACA CUACA OTHER ISSUE


1 07.30 - 08.00 Hujan
2 08.00 - 09.00 Hujan
09.00 - 10.00 Hujan
10.00 - 11.00 Hujan
11.00 - 12.00 Hujan Dibuat Diperiksa
Keterangan: 12.00 - 13.00 Hujan
13.00 - 14.00 Hujan
14.00 - 15.00 Cerah
15.00 - 16.00 Cerah
16.00 - 17.00 Cerah Budi
17.00 - 18.00 Berawan