Professional Documents
Culture Documents
Partnering,
Responsibility &
Authority, and On-Site
Responsibilities
BSCE 5-1 Group II
Prepared by:
Biblanias, Gericho S.
Cezar, Genalyn S.
Climacosa, Lucky Nichole
Concepcion, Jerbie
Cruz, Alleli P.
Figueroa, Benjamin E.
Francisco, Joseph A.
Oclarit, Mark Francis G.
San Juan, Apple J.
TABLE OF CONTENTS
I. Partnering
Implementation of partnering
The Client
Principal Designer
Designer
Principal Contractor
Contractor
Workers
1
I. PARTNERING
Black (1999, p. 423) elaborates on the partnering concept by stating that the
partnering procurement method aims to eliminate adversarial relationships between client
and contractor by encouraging the parties to work together towards shared objective and
achieve a win-win outcomeSuccessful partnering requires many factors, in particular
high level of commitment to shared goals, preferably including those of the client.
Lu and Yan have developed an applicability assessment model for partnering that
focuses on factors related to management tools, organizations and project parameters.
1. First thing is to identify the project parameters,
2. Secondly to compare the gains from partnering with the expectation of the project.
2
3. Thirdly the recommendation is to select partners carefully in order to understand
the partners potentials, capabilities and expectations of the project.
The implementation of partnering goes through different steps as can be seen here
below suggested by (Li, et al., 2000).
1. The introduction of partnering to organization
2. The identification of the needs for partnering
3. The selection of the partnering companions
4. The organization of the partnering workshop
5. The development of the partnering value/culture during the workshop
6. The mobilization of the internal work process
7. The execution of the project
8. The repetition of the cycle
IMPLEMENTATION OF PARTNERING
Partnering requires considerable time, effort, and commitment at all stages of a
project. The use of a partnering strategy is the voluntary decision to which all team
members agreed at the beginning of the project. Implementation steps for partnering could
proceed in the following manner:
All parties should express their desire to perform the project under a partnering
agreement at the beginning of the project. The owner 's intention of utilizing the concept
should be mentioned in the bid solicitation and specifications. Any prebid conference
should include a presentation on partnering.
There should be a meeting of top management of all firms involved in the project
in the early design stage. However, the executives at the CEO level should meet to discuss
the partnering approach to managing the project. A commitment from the top of each
organization is essential for partnering to work.
3
A partnering workshop/team building session should be held in the very early
stages of the project. Each member team should designate a partnering leader who would
intend to participate in the workshop. All of the participants of the partnering workshop
would develop and agree to a partnering charter which is a written list of the goals and
objectives for the project. The charter is a physical symbol of the project team members'
commitment to partnering. It is considered to be a road map for regular evaluation of the
project process. Specific benchmarking measurement goals as well as general goals can be
part of the partnering charter. The charter does not change the terms of the project
participants' contracts and is not a contract in itself. The charter is a guide for cooperation.
Each party to the project should sign the charter to show their commitment to the partnering
process. For periodic evaluation, a formal, regular evaluation of the progress of the project
should occur normally as a formal monthly or bimonthly meeting. At this review meeting,
there should be an open dialogue on any problem areas with the goal of maintaining all
parties' commitment to the partnering process and to make sure that an adversarial
relationship has not started to build.
The partnering charter should commit all of the team members to dispute resolution
without claims or litigation. The goal is that any disagreement is resolved at the project
level and that if a dispute is unable to be resolved at the project level, it should quickly
move up to the next level of management for resolution. Resolutions should be sought in a
win-win atmosphere of open communication and trust. The goal is to avoid claims and
any involvement by outside lawyers that could result in litigation. Alternate dispute
resolution (ADR) techniques can be an important part of the partnering process. If any
dispute is unable to be resolved at the lower level, the parties should agree to mediation or
some similar low-cost dispute resolution dispute resolution technique. The goal is to avoid
the time and expense of claims and litigation. Alternate dispute resolution techniques can
help maintain team spirit and friendly working relationships at the project.
4
II. RESPONSIBILITY AND AUTHORITY
Planning is an art and the art of planning exist only among human beings. This
power to be able to distinguishes man from other members of the animal kingdom.
The environmental development through planning is a natural field for Architects
as they are in better position because of their training and experience. However, for a good
planning intelligence are necessary. And for a plan to be successful, it must be prepared by
those who trained and qualified.
The pre-planning stage, establishes and determine the direction and success of any
construction project. Unfortunately, it seems that some engineers and constructors have not
given the pre-planning special emphasis despite they are on direction of going there.
Past experience has proven that there is no shortcuts to sound construction pre-
planning. There is no new procedure to replace the following four basic rules for any job.
1. The construction superintendent should be included in the consultation at very start of
the planning stage. Do not just present him later the finished plan and say: here is the plan
for you to implement.
2. Make a job breakdown into components. This will simplify the whole program.
3. Prepare a construction plan that will be consulted constantly. Do not just file it in a
drawer only to accumulate dust.
4. Take advantage of new tools, which have demonstrated in saving time, money or
confusion. For instance, a computer can be used to layout one sheet a detailed schedule
according to number of days, crafts, man-hours, costs, procurement and completion of
process.
5
Responsibilities:
The construction manager will have many responsibilities and these include the following:
A. Planning - From the outset, it is the responsibility of the Construction PM to plan the
build process, this means producing a critical path and understanding the timing of each
stage. Following each phase of the project is essential to ensuring that the project is
completed on time.
B. Resource Allocation - Any building project will need resources from bricks and mortar
to tools and basic amenities. It is the responsibility of the Project Manager to have an
understanding of what these are and ensure they are available.
C. Staff Management - The Project Manager will be responsible for recruiting a team and
allocating tasks to relevant managers. It may mean identifying suitable contractors who can
complete the work. The important thing for the Construction Project Manager is
understanding at which stage of the process each trade will need to be recruited.
D. Setting Benchmarks - An integral aspect of the ongoing monitoring of a project is
setting benchmarks to monitor progress, this allows the project manager to identify whether
or not the project is on target to finish on time and within budget.
E. Budget Management The Project Manager is responsible for the financial planning
and monitoring of the project. To avoid going over budget a PM should consider
continually forecasting, keeping the team informed of forecasts and changes and managing
the scope meticulously, so knowing the costs for unplanned construction work or resources
and keeping that set-aside.
Other:
1. Worksheet. Prepare a graph and plotting the anticipated date of delivery of all major
equipment at the site. The optimum time for each construction activities could be analyzed.
Severe peaks and uneconomical use of equipment will appear on the projected graph,
which could then be adjusted to prevent future conflicts in the field.
2. Timetable. The project manager should conduct one or more informal sessions with key
personnel assigned to the project such as: construction superintendent; job buyer, drafting
room coordinator; job expediter.
During the session, the preliminary construction program or worksheet is reviewed
to determine whether engineering work and procurement of materials can be accomplished
at the rate and in sequence as programmed in the schedule. The sequence of construction
activities, which are related to optional early and late starts, will serve as running list of
individual job components with notations to work activities with greater importance and
priority over the others. Specifications for equipment and materials which are in the
development should be possessed according to their importance or urgency in the overall
project. One important function of the construction planner is the preparation of an accurate
manpower estimates assigned to each function.
6
What Skills Do You Need To Be A Construction Project Manager?
General skills for project management are used in a construction project manager role. This
include:
Planning and Time Management to ensure that projects are completed within set
timeframes.
Resource Management ensuring that equipment is available throughout the building
project.
Financial and Budget Management making sure that the project is completed within a
financial budget.
Communication arranging meetings and ensuring that all stakeholders are aware of the
projects progress.
Delegation and Motivation the Project Manager, will be responsible for ensuring that
tasks are delegated effectively and staffs remain motivated to complete the project to a high
standard.
General Construction at times of uncertainty the project manager may be relied upon for
his superior knowledge of the industry and specific problems. Managerial competence is a
function of a managers character, knowledge and experience. These three ingredients
interact to mold a particular style of management. Styles maybe altered or fashioned by
education gained from formal training and work seasoning. An advantage of studying
management techniques is the opportunity it allows to explore and develop managerial
skills without suffering the consequences of trial and error learning.
7
B.) The Owners Duties in Construction
The owner's failure to understand and perform his duties can seriously affect a project.
The following is a summary of the many tasks that must be performed by the owner during
the pre-construction phase.
1. Ensure that suitable management arrangements are made for the project
On all projects, the client must verify that adequate management arrangements
are in place to ensure that the roles, functions and responsibilities of all members
of the project team are clear and understood. The organizations and individuals
working on the project should know their roles, responsibilities and authorities
and their relationship with other members of the team.
2. Select & appoint a competent and resourced Principal Designer and Principal
Contractor
The principal designer will oversee the design and planning of a project and
assist the client in the performance of the client's duties. The principal contractor
is responsible for managing the health and safety aspects of the construction.
8
appointed as soon as the client knows enough about the project to select a
suitable contractor, so that they can make contributions to the health and safety
of the design. Only one principal designer and one principal contractor may be
appointed to the project at any one time, although the appointments may be
changed.
On non-notifiable projects, the client still has duties to perform under the
regulations. The client may well have formal arrangements in place with the
principal designer and principal contractor which state how the project is to be
managed and subsequent duties discharged.
3. Ensure sufficient time and resources are allowed for all stages of the project.
It is required that the client to allow sufficient time and other resources for all
parties involved to fulfil their health and safety responsibilities. The client still
needs to seek advice on the time and resources proposed to be allocated to the
different phases of a project.
The client must allow sufficient time for the design, design reviews, planning,
hazard identification, risk assessment, specification of risk control measures,
selection of contractors, mobilization, sequencing and scheduling of work, and
carrying out construction.
5. Verify the sufficiency of the construction phase plan (CPP) prior to construction
commencement.
A suitable CPP must contain the following areas:
9
a) A description of the project including key dates and important project team
members
They can also be principal contractors or specialist contractors, if they get actively
involved in design work for their project.
Regulation 5 of the CDM 2015 requires the client to appoint a principal designer if
there are more than one contractor on the project
Principal Designer a designer with control over the pre-construction phase. Require the
principal designer to manage health and safety at the pre-construction phase and produce a
health and safety file.
Designers must:
10
1. Make sure the client is aware of the client duties under CDM 2015 before starting any
design work
2. When preparing or modifying designs;
-take account of any pre-construction information provided by the client (and
principal designer, if one is involved)
-eliminate foreseeable health and safety risks to anyone affected by the project (if
possible)
-take steps to reduce or control any risks that cannot be eliminated
3. Provide design information to the client and principal contractor to help them comply
with their duties, such as ensuring a construction phase plan is prepares.
4. Communicate, cooperate and coordinate (3C)
- Any other designers (including the principal designer) so that all designs are
compatible and ensure health and safety, both during the project and beyond
-All contractors (including the principal contractor) to take account of their
knowledge and experience of building designs
DUTIES:
Make suitable arrangements for managing a project, including making sure:
Other duty holders are appointed as appropriate
Sufficient time and resources are allocated
Relevant information is prepared and provided to other duty holders
11
The principal designer and principal contractor carry out their duties
Welfare facilities are provided
DUTIES:
Plan, manage, monitor and coordinate health and safety in the preconstruction phase of a
project. This includes:
identifying, eliminating or controlling foreseeable risks
ensuring designers carry out their duties
Prepare and provide relevant information to other duty holders. Liaise with the
principal contractor to help in the planning, management, monitoring and
coordination of the construction phase.
DUTIES:
When preparing or modifying designs, eliminate, reduce or control foreseeable risks that
may arise during:
construction
maintenance and use once it is built
Provide information to other members of the project team to help them fulfill their duties.
DUTIES:
Plan, manage, monitor and coordinate health and safety in the construction phase of a
project. This includes:
Liaising with the client and principal designer
preparing the construction phase plan
organizing cooperation between contractors and coordinating their work
12
Make sure:
suitable site inductions are provided
reasonable steps are taken to prevent unauthorized access
workers are consulted and engaged in securing their health and safety
welfare facilities are provided
5. Contractors Those who carry out the actual construction work, contractors can
be an individual or a company
DUTIES:
Plan, manage and monitor construction work under their control so it is carried out
without risks to health and safety.
For projects involving more than one contractor, coordinate their activities with
others in the project team in particular, comply with directions given to them by
the principal designer or principal contractor.
For single contractor projects, prepare a construction phase plan.
DUTIES:
Workers must:
be consulted about matters which affect their health, safety and welfare
take care of their own health and safety, and of others who might be affected
by their actions
report anything they see which is likely to endanger either their own or others
health and safety
cooperate with their employer, fellow workers, contractors and other duty
holders
On-site Responsibilities
The construction phase usually takes up the longest time in the whole project
period. In the construction phase, a lot of things happen, even unexpected things happen.
When these things happen, it is important to know your stand in the situation because
knowing so clearly defines your involvement and authority in the project, and having
defined so shows that you are responsible with your role in construction.
13
The Client
The client is whom the project is for, who plays a major role in the project
conception. During the actual construction phase, what has been planned in the pre-
construction might not apply to the site anymore. There comes the responsibility of the
client to coordinate once again with those in the pre-construction phase. The client may not
involve him/herself in the scenario, but it could become a problem when the modifications
done havent met his/her expectations, so it is right and just for the client to know whats
going on. If the/she does not, it would be easy for the contractor/s or workers to modify the
project in such way that they will profit more.
The client must occasionally be present in the site because in fact, the client is
protected by laws. The client is a consumer of services, and the Consumer Act of the
Philippines provides them protection against deceptive, unfair and unconscionable acts and
practices. It is stated in the Article 2 of R.A. 7394 and reiterated in the G.R. No. 189655.
Somehow, these laws provide the clients legal authority in inspecting the work done by the
party involved in building the project.
The Designer
Theres not much responsibility for a designer to do in the actual construction
process, unless such modification shall be done which will involve remodeling of the
printed plan.
The Workers
The workers play a crucial role in the site: bringing the plans into reality. No matter
how accurately calculated the design is, a single error by the workers in the execution of
plans may lead to a loss in the future. That is why the primary responsibility of a worker at
the site is to execute his work according to plan. Other than that, a worker, as a laborer,
shall know that he is protected by the Labor Code. Neglecting such provisions by the
Department of Labor and Employment, it would be easy for the superior to obtain what
they must not that the workers must.
The Contractor and Construction Supervisor
There is a saying that goes With great power comes with great responsibility. The
contractor may just stand as a single entity in the contract, but it is undeniable that he/she
has the most power and authority over anyone else in the party opposite to the clients.
First and foremost, providing all the resources necessary for the construction of the project
is the responsibility of the contractor. Overseeing his/her staffs is another thing. All of these
tasks might already be tedious to the contractor, but that is just half of the job. Another
important role is to oversee those staffs present in the site. There must be an assurance that
all of the resources provided by the contractor will be put into right place. This tedious task
requires another person, which is the supervisor.
14
Supervision varies with levels from foreman to site engineer; but general to them
all, it is their responsibility to heed the safety of his/her staffs as they do their work at the
site. As the site supervisor, its your job to both assess and manage safety hazards in the
workplace. Responsibilities may also include managing and instructing the site workers,
setting goals for the team, and seeing projects through to completion. While your main
priority is safety, it may also be your responsibility to motivate and, in some cases, even
discipline staff. You may be asked to mentor and encourage members of the team, which
is why many companies look for a qualified supervisor with years of experience working
as part of a team. It certainly isnt considered an entry level job. You need industry
experience and, in some cases, training.
Each role in the site bears its own duties. Accomplishing these duties is the key to
accomplish the project effectively; however, doing more than your duty to the extent of
your responsibility makes it possible for the effective to be efficient.
15