2016)
Preheater
5. 4th floor cf silo side feed pipe fixing & flap damper
11.3rd floor cf silo side cyclone roof plate cutting & outside scaffolding
12.3rd floor ccr side cyclone brick lining demolition & lintel plate fixing job
1. Tip casting first blocks tightening to be done then shuttering then while curing, other 3 nos tip
casting blocks to be fixed
3. Cooler 1st drive above bull mouth plate patching & old bull mouth removal
5. Cooler 2nd drive fixed beam replacement then 3 rows grate plates fixing
6. Cooler 3rd drive fixed beam fixing & cross arm lifting to site
7. Clinker breaker discharge chute welding