You are on page 1of 2

Tonights Jobs(29.12.

2016)

Preheater

1. 7th floor twin cyclone no 2 castable job

2. 7th floor twin cyclone no 1 lugs welding

3. 6th floor cf silo dummy & beam removal

4. 5th floor both cyclones beam removal...based on manpower availablity

5. 4th floor cf silo side feed pipe fixing & flap damper

6. 4th floor ccr side flap damper casing castable job

7. 4th floor cf silo side cyclone cone brick lining patching

8. 4th floor cf silo side immersion tube inspection

9. Immersion tube plates shifting to 4th floor

10. 3rd floor DDF neck lintel plate fixing

11.3rd floor cf silo side cyclone roof plate cutting & outside scaffolding

12.3rd floor ccr side cyclone brick lining demolition & lintel plate fixing job

13.3rd floor material removal from floor

14.2.5 floor Material removal from ccr side cyclone cone

15.Inlet cone drum castable and S-plate fixing

16.TAD brick lining and castable removal

Kiln & Cooler

1. Tip casting first blocks tightening to be done then shuttering then while curing, other 3 nos tip
casting blocks to be fixed

2. Cooler 1st drive cleaning

3. Cooler 1st drive above bull mouth plate patching & old bull mouth removal

4. Kiln brick lining then rotation

5. Cooler 2nd drive fixed beam replacement then 3 rows grate plates fixing

6. Cooler 3rd drive fixed beam fixing & cross arm lifting to site
7. Clinker breaker discharge chute welding

8. Cooler drag chain casing patching