PORTO ARABIA (7B - TOWER) BASELINE REV0-MEP Classic WBS Layout 13-Nov-17 08:29

Activity ID Activity Name Start Finish Original Total


Duration Float
27-May-17 31-Oct-18 444 0
PORTO ARABIA (7B - TOWER)
TOW BASELINE REV0-MEP PROGRAM
GENERAL 27-May-17 31-Oct-18 444 0
Mile Stones 27-May-17 31-Oct-18 444 0
PA07B-ML-001 Start of the Project 27-May-17 0 0
PA07B-ML-002 Engineering Phase Completion 31-Dec-17 0 89
PA07B-ML-003 Procurement Phase Completion 10-Apr-18 0 70
PA07B-ML-004 Construction Phase Completion 23-Aug-18 0 2
PA07B-ML-004. Permanent Power Supply for T&C 10-May-18 0 38
PA07B-ML-005 Testing & Commissioning Phase Completion 30-Oct-18 0 1
PA07B-ML-006 Project Completion 31-Oct-18 0 0
Design Activities 27-May-17 25-Sep-18 413 9
PA07B-IFC-DWG-011 Design Start of the Project 27-May-17 19-Jul-17 45 0
PA07B-IFC-DWG-012 Design Approval of the Project 13-Jun-17 06-Sep-17 70 0
PA07B-IFC-DWG-021 Design approval from UDC 25-Aug-18 09-Sep-18 14 2
PA07B-IFC-DWG-031 Design approval from Kahraama 10-Sep-18 25-Sep-18 14 9
PA07B-IFC-DWG-041 Design approval from QCDD 10-Sep-18 25-Sep-18 14 2
ENGINEERING 19-Jun-17 30-Jan-18 189 200
Shop Drawing Submission 19-Jun-17 14-Jan-18 175 184
Shop Drawing Approval 29-Jun-17 30-Jan-18 182 200
PROCUREMENT 27-May-17 10-Apr-18 269 114
Material Submittal 27-May-17 03-Dec-17 160 160
Material Approval 01-Jun-17 14-Dec-17 165 160
Material Ordering 13-Jun-17 16-Jan-18 182 147
Material Delivery 02-Jul-17 10-Apr-18 240 114
CONSTRUCTION 27-May-17 25-Sep-18 413 2
PARKING 01 02-Sep-17 23-Aug-18 305 0
PARKING 02- 04 13-Sep-17 24-Jul-18 269 44
Mezannine & Amenity Floor 22-Nov-17 16-Jul-18 202 51
Dry Area : Rooms 27-May-17 02-Aug-18 367 44
1st Floor 18-Feb-18 09-Jul-18 122 63
2nd Floor 27-May-17 29-Apr-18 285 52
3rd Floor 15-Jul-17 01-May-18 247 58
4th Floor 07-Aug-17 24-May-18 247 88
5th Floor 19-Aug-17 26-May-18 238 88
6th Floor 02-Sep-17 27-May-18 229 88
7th Floor 11-Sep-17 28-May-18 222 88
8th Floor 20-Sep-17 29-May-18 215 88
9th Floor 30-Sep-17 30-May-18 208 88
10th Floor 09-Oct-17 31-May-18 201 88
11th Floor 18-Oct-17 02-Jun-18 194 88
12th Floor 11-Nov-17 03-Jun-18 175 88
13th Floor 11-Nov-17 04-Jun-18 176 88
14th Floor 20-Nov-17 05-Jun-18 169 88

Page 1 of 3 TASK filter: All Activities


Primavera Systems, Inc.
PORTO ARABIA (7B - TOWER) BASELINE REV0-MEP Classic WBS Layout 13-Nov-17 08:29
Activity ID Activity Name Start Finish Original Total
Duration Float
15th Floor 29-Nov-17 11-Jun-18 166 84
16th Floor 29-Nov-17 20-Jun-18 174 77
17th Floor 29-Nov-17 11-Jul-18 192 60
18th Floor 17-Dec-17 14-Jul-18 179 59
19 & 20th Floor 27-Dec-17 02-Aug-18 188 44
Dry Area : Corridors & Electrical
Electrica Rooms 07-Sep-17 21-Jun-18 246 82
1st Floor 08-Mar-18 06-Jun-18 78 92
2nd Floor 07-Sep-17 17-May-18 216 52
3rd Floor 17-Jan-18 20-May-18 106 62
4th Floor 20-Jan-18 21-May-18 105 62
5th Floor 22-Jan-18 22-May-18 104 62
6th Floor 24-Jan-18 23-May-18 103 62
7th Floor 27-Jan-18 24-May-18 102 62
8th Floor 29-Jan-18 26-May-18 101 62
9th Floor 31-Jan-18 27-May-18 100 62
10th Floor 03-Feb-18 28-May-18 99 62
11th Floor 05-Feb-18 29-May-18 98 62
12th Floor 07-Feb-18 30-May-18 97 92
13th Floor 10-Feb-18 31-May-18 96 92
14th Floor 12-Feb-18 02-Jun-18 95 92
15th Floor 14-Feb-18 03-Jun-18 94 92
16th Floor 17-Feb-18 04-Jun-18 93 92
17th Floor 19-Feb-18 05-Jun-18 92 92
18th Floor 21-Feb-18 07-Jun-18 92 92
19th & 20th Floor 24-Feb-18 21-Jun-18 102 82
Wet Area : Toilets & Kitchen 07-Jun-17 25-Sep-18 403 2
1st Floor 03-Mar-18 25-Aug-18 151 27
2nd Floor 07-Jun-17 20-May-18 293 82
3rd Floor 07-Jun-17 20-May-18 293 82
4th Floor 13-Jun-17 22-May-18 290 82
5th Floor 13-Sep-17 24-May-18 217 82
6th Floor 19-Sep-17 27-May-18 214 82
7th Floor 18-Oct-17 29-May-18 191 82
8th Floor 18-Oct-17 29-May-18 191 82
9th Floor 24-Oct-17 07-Jun-18 194 76
10th Floor 30-Oct-17 07-Jun-18 189 78
11th Floor 05-Nov-17 01-Jul-18 204 60
12th Floor 28-Nov-17 07-Jul-18 189 57
13th Floor 04-Dec-17 15-Jul-18 191 52
14th Floor 10-Dec-17 15-Jul-18 186 54
15th Floor 16-Dec-17 07-Aug-18 201 36
16th Floor 16-Dec-17 07-Aug-18 201 36
17th Floor 23-Dec-17 30-Aug-18 216 18
18th Floor 28-Dec-17 13-Sep-18 223 8
19th & 20th Floor 03-Jan-18 25-Sep-18 228 2
Riser Works 02-Oct-17 13-Aug-18 270 27
MECHANICAL ROOM 17-May-18 04-Jul-18 42 43

Page 2 of 3 TASK filter: All Activities


Primavera Systems, Inc.
PORTO ARABIA (7B - TOWER) BASELINE REV0-MEP Classic WBS Layout 13-Nov-17 08:29
Activity ID Activity Name Start Finish Original Total
Duration Float
TESTING & COMMISSIONING
COMMISSIONIN 19-Jul-18 30-Oct-18 89 0

AUTHORITY INSPECTIONS & APPROVALS 03-Jun-18 29-Oct-18 128 0


PA07B-AUTHINSP-01 Kahraama Sub-station inspection & approval 03-Jun-18 19-Jun-18 15 93
PA07B-AUTHINSP-11 Kahraama Building internal inspection & approval 03-Oct-18 25-Oct-18 20 3
PA07B-AUTHINSP-31 QCDD inspection & approval 29-Sep-18 29-Oct-18 27 0
PROJECT CLOSE OUTS & H
HANDING OVER 01-Oct-18 31-Oct-18 27 0
PA07B-HO-01 As-built drawings submission & approval 01-Oct-18 29-Oct-18 25 0
PA07B-HO-02 O&M Manual Submission & approval 01-Oct-18 29-Oct-18 25 0
PA07B-HO-12 Mainatainance Team training 03-Oct-18 20-Oct-18 15 8
PA07B-HO-22 Handing over 30-Oct-18 31-Oct-18 2 0