CODE OF PRACTIGE
FOR THE
STRUCTURAL USE
2011
410 he Ire»
Zao Mate OB
adi GA Yh ot
BUILDINGS
‘DEPARTNENT14.2.9
14.2.9.1
142.92
143
14.3.4
14.3.2
14321
14.3.3
14.3.3.1
1433.2
14.333
Storage
Stacking
Febricated components, which are stored prior o being transported or erected, shall be
stacked clear ofthe ground and arranged, so thet water cannot accumulate. They shall
be kept clean and supported in such a manner as to avoid permanent distortion.
Visible markings
Individual components shall be stacked and marked in such a way as to ensure that they
can be Kdentifed.
WORKMANSHIP — WELDING
General
‘Allwelding operations shall be consistent to one set of standard as given in Annex A1.4.1
‘and shall be applied stictly throughout the whole course of development. Welding shall
'bo a metal arc process in accordance with other clauses given in this section and the
requirements as given in Annex A141. In case of ambiguity, the more stringent
requirements shall apply
Joints shall be prepared in accordance with the requirements as given in Annex At.4
Precautions shall be taken to ensure cleanliness ofthe connection prior to welding,
Welding of higher strength stee! is covered by this socion but account should be taken of
the difference in procedures that will be requied for these materials and possible defects,
€.g, weld metal hydrogen cracking,
Welder qualification
Contifcation of welder tost
‘Welder test shall be witnessed by a qualified welding inspector and certificates endorsed
by an independent testing body. Welders shall be tested to meet the requirements as
‘ven in Annex 1.4.
Welding procedure specifications
Preparation of procedure specifications
Welding procedure specifications (WPS) shall be prepared in accordance with the
requirements as given in Annex A1.4.2 and made available to the Responsible Engineer.
They shall comply wih the guidance to avoid hydrogen cracking and to provide adequate
toughness in the heal affected zone.
‘Table 14.2a - Requirements for submission of welding procedure specifications
[Weld Typo |Wold Size [Approval of Welding Procedure rie
IButt Weld [s-4 mm INot necessary
a mm [By a qualified welding inspector.
Fillet Weld I<-4 mm INot necessary
[> am [By a qualified welding inspector.
Approval of procedure specifications and procedure tests
‘All welding procedure tesis shall be witnessed by a qualified welding inspector and al
‘Welding Procedure Approval Records (WPAR) shall be endorsed by a qualified wel
Personnel. WPAR shail record all relevant information, including original mats
certtiicates (showing the carbon equivalent value), mechanical tests data and non-
destructive test results.
Avellebilty of welding procedure specifications
WPS shall be submitted for the approval of the Responsible Engineer prior to the
commencement of the works.
208143.34
143.3.
143.4
143.44
14.3.4,2
1434.3
143.44
143.45
14.3.4.6
WPS shall be provided for the welders prior to the commencement of the works and shall
‘be made available to the concerned parties on request,
Avoidance of lamellar tearing: requirement for through thickness properties
‘The welding procedures should be chosen so as to minimise the risk of lamellar tearing.
If necessary, material with through-thickness properties shall be used, Guidance on the
‘choice of procedures and through-thickness grade Is glven in Annex At.4.1
Controtine segregation
Ceniteline segregation is @ material deficiency that may exist within the centre of plate
(concast) products and some sections. It can lead to local reductions in toughness and
\weldabty that can cause cracking in tee butt and cruciform weld configurations.
‘The use of good welding practice and details may avoid this phenomenon, for example,
+ Avoiding tee, butt or cruciform welds in which the attachment plate is thicker than
the through plate;
* Minimising through-thickness tension especially al the edges of plates;
* Dressing any cut edges to remove any areas of increased hardness;
+ Using smaller weld volumes;
+ Developing weld details and processes that minimise the restraint to welds;
+ Following the guidance on the avoidance of hydrogen cracking,
Where itis essential to avoid this phenomenon, either adcitional tests shall be carried out
or the continuous casting route shail not be used to produce the material
Assembly
Fitup
Joints shail be ited up tothe dimensional accuracy required by the welding procedure to
ensure thatthe qualty in clause 14.3.6.7 is achieved
Jigs
Fabrications assembled in jigs may be completely welded in the jig, or may be removed
‘ror the jig after tack welding.
Tack welds
‘Tack welds shall be made using the same procedure as the main weld (single run) or the
root run of multi-un welds. Alternatively, they may be made using a satisfactory welding
procedure test based on the proposed length of tack weld to be used. The minimum
length of the tack shall be the lesser of 4 times the thickness of the thicker part or 60 mrn,
Tack welds, which are made by a qualified welder and found satisfactory by visual
Inspection, may be Incorporated into main welds,
‘Where tack welds are made in circumstances other than those identified above, they
must be removed,
Distortion control
The sequence of welding a joint or a sequence of joints shall be such that distortion is
minimised.
Fabrication or erection attachments
‘Welding of attachments required for fabrication or erection purposes shall be made in
accordance with the requirements for a permanent weld.
When removal of attachments is necessary, they shall be flame cut or gouged at a point
not less than 9 mm from the surface of the perent material, The residual material shal be
‘round flush and the affected area visually inspected. When parent metal thickness is
greater than 20 mm it shall also be checked by magnetic particle inspection, Acceptance
Giitea are as set oul in clause 14.367. Attachments shall not be removed by
hammering,
Extonsion pieces
Where the profile of a weld Is maintained to the free end of a run by the use of extension
pisces, they shall be of material of a simitar composition, but not necessarily the same
209143.47
143.6
14.3.6
14.364
14.3.6.2
14.3.8.3
143.64
grade, as the component. They shall be arranged so as to provide continuity of
Preparation and shall be removed after completion of the weld and the end surface of the
veld ground smooth.
Production test plates
Where production test plates are required for testing purposes, they shall be clamped in
line with the joint. The grade of material, carbon equivalent value, and rolling direction
shail match the parent plate, but need not be cut from the same plates or cast.
Non-destructive testing of parent material
Unless agree with the Responsible Engineer, areas of material thicker than 25 mm in tee
‘and cruciform connections within 160 mm of the weld shall be ultrasonically inspected
prior to welding. The qualified welding inspector shall report any laminations or any
significant variations in attenuation,
Non-destructive testing of welds (NDT)
Scope and frequency of inspection
Visual Inspection shall be carried out at all welds by a qualifed welding inspector (see
clause 14.3.6.3).
‘The scope and frequency of inspection using non-destructive testing (NDT) shall be in
accordance with Table 14.3a. Inspection requirements may be reduced at the discretion
of the Responsible Engineer, based upon satisfactory performance in the initial
production demonstrated against the requirements. Conversely, where testing inci
‘that weld qualty problems have occurred (in simitar materia's, assembly methods or
welding procedures), non-destructive testing requirements should be increased and
should be extended to non-mandatory components.
Where the requirement for inspection I less than 100%, the joints for testing ehall cover
all the different joint types, material grades and weld equipment. Apart from this the
selection should be random.
Record of testing
Results of visual inspection, surface law detection and ultrasonic examination shall
include the minimum requirement stipulated by the relevant standard and shall be
available for inspections,
Visual inspection of welds
Visual inspection shall be made in accordance with guidance given in Annex 1.4.4 over
the full length of all welds. Such inspection shall be performed before any required NOT
inspection.
‘Any welds which will be rendered inaccessible by subsequent work shall be examined in
accordance with the Code prior to the loss of access.
A suitably qualified person for visual inspection of welds may be a welding inspector who
‘can provide evidence of having trained and assessed for competence in visual inspection
of the relevant types of welds.
Hold time before final NOT
‘Owing to the risk of delayed cracking, @ hold time period of at least 16 hours should
generally be allowed before the final inspection is made of as-welded fabrications. This
hold time should be reduced for thin materials whose yield strength is fess than
500 Nimm or should be increased for materials of combined thickness greater than
'50 mm or of a yield strength over 500 Nimm’. Typical hold times conforming with this
requirement are illustrated in Table 14.2b. The hold timo is the waiting time normally
required after completion of welding. In high restraint situations (e.g. cruciform welds),
the hold time might need to be increased; with evidence of continual satisfactory
production, hold times might be reduced. For material with a yield strength greator than
500 Nimm hold time should be decided by a welding engineer and Table 14.2b should
not be used.
200Table 14.2b - Itustrative hold times.
Nominal Carbon
Equivalent Value | 2t®<30mm | xt somm
(cevy
$0.40 None B hours 46 hours 40 hours"
£0.45 8 hours 46 hours 40hours" | 40 hours
50.48 16 hours 40hours | 40hours® | 40 hours
> 0.48 aohours —[4ohours® | 4ohours | 40 hours
Toles
()- Where the figures ate in bot, generly, th stvice ofa welding engineer should be sought
(2) The Carbon equivalent valus fs tat oF the parent material fo the Intemational Insitute of welding (IW)
forma end is cablated ae fellows:
Sie, OreMoev, Noe
cev =.
6
5
(0) 3 bo conned eet x sauna Fee 4
abe
toed
Benet
(not appscatio to Class 1H stool)
(m4)
Beh teeh
Figure 14.1 - Combined thickness
Whatever hold-time poriod is to be used shall be stated in the inspection records.
14.3.6.5 Surface flaw detection
Where a closer examination of a weld surface is required in accordance with Table 14.32,
magnetic particle inspection (MPI) shall be used
equipment is impractical, dye penetrant inspection (OP!) may be used.
Final surface flaw detection of a welded joint shall be carried out after completion of the
weld in accordance with the hold time given in Table 14.2b,
Where welding procedure requires an inspection after intial weld runs before further
welding Is performed, such inspections may be carried out when the weld metal has
cooled to ambient temperature.
A suitably qualified person for surface flaw detection of welds may be a welding inspector
‘or a welder, who holds a valid certificate of competence in surface flaw detection of the
relevant types of welds, from BA or a nationally recognised authority.
301
Hf magnetic particle inspectionTable 14.3a - Scope anil frequi
\cy of inspection (NDT)
PARTA VISUAL INSPECTION Prior to Non-Destructive Testing (NDT)
all welds to be vieually Inspected by a suitably qualified person (See
clause 14.3.6.3)
PART B THICKNESS FOR MANDATORY NDT AND FREQUENCY OF
TESTING (all dimensior
WELD TYRE
FULL PENETRATION PARTIAL
PENETRATION
ee
Ra sl —
‘
‘MPI [Thickness All thickness — All thickness:
Frequency 700% zi “20%
US [Thickness ina 10 ‘p28
Frequency, 100% an 20%
WELD TYPE FILLET
MPI_[ “Thickness: ‘Allthickness
Frequency 10%
WIS | Thicknoss Leg length 15
Frequen: 10%
Notes:
Longitudinal wells are those made paral withthe member ans. All other welds ae vansverse.
‘Tho siz of ft weld e Kendo’ in he table by We leg erat
MBI” "Magnete Panicle Inspection (see clauso 14.2.8.)
LUIS Ultrasonic Examinaton (se cause 14.3.5.)
For steis with a yield siren greater than SOONImm* the frequency of testing should bo 100% unless agreed
cohnervise Ly the Response Engineer,
30214.3.6.6
143.6.7
Utirasonie examination
‘Where ultrasonic examination (UIS) is required, it shall be made in accordance with the
‘requirement 2s contained in Annex A1.4.4. Recotds of the inspection procedure shall be
kept, connection types and locations shall be clearly identified and shall be available for
inspection uniess otherwise agreed by the Responsible Engineer.
Uttrasonic examination of the welded joint shall be carried out after completion of the weld
in accordance with the hold time given in Table 14.26.
‘Note: In addition to weld examination, through-thickness ultrasonic examination of the
parent material may be necessary for weld geometries susceptible to lamellar fe
Operators carrying out final ultrasonic examination of the weld shall hold a valid certiicate
‘of competence from BA or a nationally recognised authority,
Acceptance enteria and corrective action
Unless otherwise specitied, the acceptance criteria for welds shall mest the minimum
requirement as contained in Table 14.3b. Welds that do not comply with the requirement
shall be repaired,
‘The position of welds shall be within 10 mm of that shown on the drawings. The length of
Weld shall be not less than that shown on the drawings and should not exceed the
specified length by more than 10 mn
Any repairs shall be carried out in accordance with approved welding repair procedures,
‘Any corrected welds shall be inspected again with increased hold times and shall meet
the requirements of the original welds,
In cases where fatigue can occur, acceptance standards more stringent than these
minima shall be required. In such’ case, the Responsible Engineer shall specify the
‘additional acceptance requirements
303Table 14,3b - Acceptance criteria for wolds in stee! structures
Foskie | Paamsr | wed |Pamlaorconaaoss] iis | Aciinncs | — Rada
‘ie weserce| ‘cher, | clon tor
Tape | normal quay?* {rorconnnng
‘uae | (adamensons |" wade
lover wa oie — pg —f= =o IE
geometry [Weld type [Aa ee aa = 1D =
exe! fog) [AI_—F= paTo-0
ft ost JAF SEO Coy
tress Etcose [Bs
i a —. as
Hetero (al —lranevaze tw —oz en ose
tee ona [onotcne) lose sre
fea)
ceed [sat —ranevexs 7 ze is
a te a Es
freongce —JBut-~ffassrene ——- —Ths018}
lvoe fons: =f osoae E
lente oo i a
tes —gai— renee bat |v azo roar fe
faetgnmen |x" [tenes = w fagbeeat fe
Jenctenn
it yet wy _Ineovoar |e
Dnaseu?-—Jal—JTsseco usw — Thm 0087 —
retiop ring Pn R
rua rensese fy Iemsooe fe
sno Wie ie
ac lox feontutost Inv yen a
jeutace —rsararoar— ors fotvrse in 4
cline lpeneafon fect [logins da___ is
es [att —frneres Wo a 1
Sezrortoy |e
longutnss «= ws ik
ae20 00)
iaacarnsen far = a i
fea fa — pre kif =
uteri Ne A
ii bts i
ears [rola srs CaO Ie
accor ssn :
eusutace fistnot fee far sso lk
cones [penaveson, [OH eo fe brsaPr
ates Joe pi cA iE it
a i
nga eal — fat —— pear] —T tc?
len pea oistect
ce fe fm i
Hh NL Re or
Ineo | fine R edges «
on R
I sagas ra ke se ioons 1
lee |
" |
E f= =n i |
E Fares nr fe
ato!
04Table 14.3b - Acceptance criteria for wolds in steel structures (cont'd)
[Robestod eons
lo As epactod on eravings ls Fora of xno aoe Tate 1432
Ios Geese amoatay [> Tncinese apple tomnenimmanberthsints et olin
Ie Raterto engineer (esi. For mesnesses grater han 70 mn sae keno
I, Noten 3b Whar porter fa cucontuty orale
Ne Netpermateasopaesioascomunies nner | ine maiimurn peed va ellie ae fan O23 enn Sy
Imedetetate by NOY eehoshTabet43s) | cae
lk Rapat by eit te arroted procedure fe ihre nae than eo reguemeot given bot shal 9p.
|= Greatarthan areata Le. etiss tt) ‘ihore a opair acess an approved procadre tat te weed
fz ietmonerenitocavnctgearan) sang nerve taper, ae pn carorbncs
[fy Leratot weit overuhien measuenentmayte | estan a
‘eeaged on) |p Sitjecto any ober ioatenatroquronens.
ln Cenginorweitoverwncn te sreston's fF “Lap eno py ony fet aeded ascent hose length
trae ne). ‘hs lengnuia dct nce er
eaptparatet the wel ave [> Cemetar ers sy ony be scape Fi egal well fe
los Sige sea tut wis feat dos el acon ita for kun anave'se eh
JpP Paral penceaten but wot
Table 14.3c = Definition of zones and weld orientation
Talegerlee of fink pee ecoarding fo loealon ond orentaton in abuelure Frequency af teaing?
(oe figure belo)
Connection | Shop welds See table 14.38
“Swale See aie
"Transveres bats web and Tenge
plates btore assembly
Member | Buitup See abe 14.28
zones, mombers | Traneveree flat welds at ends of ap
joints
Cong wade ‘Saotabe (asa
‘Secondary [eq for fring puis, sae vl, BUC ‘Soe bie 143
tachment | sutfeners ee.
welds
‘ation af Zanes and weld onenaion
:
fc rete
1 130m “
BIR entries
(Sicha gist
NOTE: Allwalivin connacton zones tobe anlad as wanaverse
"whore only par inspecton is requre, he mts far esting sll bo Saad oh a random baw, but
‘ensuring tat sampling covers the follwing variables as widely as possbie: jet ype, mateal grade and
melding egulpment‘Table 14.34 - Characteristic defects of wolds in steo! structures
Figura Figwe
WUSz yy
£
‘iy ih ie ple the wel es
vey ex
Figure (i) Figur ip
308AL4
AL44
ALAA
A112
Welding
Welding Standards
Aimerican standards
AWS D1.1/D1.1M: 2010
AWS D1.3/D1.3M: 2008
Structural Welding Code - Steel
Siructural Welding Code - Sheet Stee!
UK European and ISO standards
BS EN 440: 1995,
BS ENISO 14341: 2011
BS EN 499: 1995,
BS EN ISO 2560: 2009
BS EN 719: 1994
BS EN ISO 14731: 2006
BS EN 729-2: 1995
BS EN ISO 3834-2: 2005
BS EN 729-3: 1995
BS EN ISO 3834-3: 2005
BS EN 729-4:1995
BS EN ISO 3834-4: 2005
BS EN 756: 2004
BS EN 14171: 2010
Welding consumables. Wire electrodes and deposits for
G28 shielded metal arc welding of non alloy and fine
Grain sets. Classification (Withdrawn in the UK,
replaced by BS EN ISO 14341: 2011)
Welding consumables. Wire electrodes and weld
deposits for gas shielded metal arc welding of non alloy
and fine grain steels. Classification
Welding consumables. Covered electrodes for manual
metal arc welding of non alloy and fine grain steels.
Classification (Withdrawn in the UK, replaced by
BS EN ISO 2560: 2009)
Welding consumables. Covered electrodes for manual
metal arc welding of non aloy and fine grain steets
Classification
Welding coordination. Tasks and responsibiliies
{Withdrawn in the UK, replaced by BS EN ISO 14731
2008)
Welding coordination. Tasks and responsibilities
ually requirements for welding. Fusion welding of
metalic materials. Part 2: Comprehensive quality
Feguitements (Withdrawn inthe UK, replaced by BS EN
1SO 3834-2: 2005)
‘Qualty requirements for fusion welding of metalic
tmeterials. Part 2: Comprehensive qualily requirements
Quality requirements for welding. Fusion welding of
metalic materials Part 3: Standard qualty requirements
(Wndrawn in the UK, replaced by BS EN ISO 3834-3:
2005)
Quality requirements for fusion welding of metallic.
‘materials, Part 3: Standard quality requirements
‘Quality requirements for welding. Fusion welding of
‘metalic materia. Part 4: Elementary quality
requirements (Withdraw in the UK, replaced by BS EN
180 3834-4: 2008)
Quality requirements for fuston welding of metal
materials. Pert 4: Elementary quality requirements
Welding consumabies. Solid wites, solid wire-flux and
tubular cored electrode-fux combinations for submerged
are welding of non alloy and fine grain steels.
Classification (Withdrawn in the UK, replaced by
BS EN 14171: 2010)
Welding consumables. Solid wire electrodes, tubular
cored electtodes and electrodefiux combinations for
submerged arc welding of non alloy and fine grain steels.
Giassification
345AL42
AIA2A
A122
A143
ALAA
AIAB.2
ALAA
ALAA
BS EN 758: 1997 Welding consumables. Tubular cored electrodes for
‘metal arc welding with and without a gas shield of non-
alloy and fine grain steels. Classification (Withdrawn in
the UK, replaced by BS EN 1S0 17632; 2008)
BS EN ISO 17632: 2008 Welding consumables, Tubular cored electrodes for gas
shielded and non-gas shielded metal arc welding of non-
alloy and fine grain steel. Classification
BS EN 1011-1: 2009 \Wolding - Recommendations for welding of metalic
materials. Part: General guidance for ae welding
BS EN 1011-2: 2001 Welding - Recommendations for welding of metallic
materials. Part 2: Are welding offerte steels
BS EN 22853: 1995 Welded, brazed and soldered joints - Symbolic
representation an drawings
Welding Procedure Specification (WPS)
American standards
AWS D1.1/01.1M: 2010 Structural Welding Code - Steel
UK European and ISO standords
BS EN 286-3: 1992 ‘Specification and approval of welding procedures for
‘metallic materials. Part 3: Welding procedure tests for
the arc welding of steels (Withdrawn in the UK, replaced
by BS EN ISO 1614-1: 2004+A1: 2008)
BS EN ISO 15614-1: 2004 Specification and qualification of welding procedure for
4A1: 2008 metallic materials. Welding procedure test. Part 4: Arc
and gas welding of steels and arc welding of nickel and
nickel alloys
BS EN ISO 1614-8:2002 Specification and qualification of welding procedures for
‘metallic materials — welding procedure test. Part 8
Welding of tubes to tube-plate joints
eee eee eee
Welder Qualification Tests
American standards
AWS D1.4/D1.1M: 2010 Structural Welding Code - Steel
UK European and ISO standards
BS EN 287-1: 2004 Qualification test of welders. Fusion welding. Part 1
Steels
Iso 9606-1: 1994 Approval testing of welders. Fusion welding. Part 4:
Steels
BS EN 1418:1998 Welding personnel. Approved testing of welding
operators for fusion welding and resistance weld setters
for fully mechanized and automatic welding of metallic
materials
BS 4871-3:1985 ‘Specification for approval testing of welders to approved
welding procedure. Part 3: Arc welding of tube to tube-
plate joints in metallic materials
Bs 4872-1:1982 ‘Specification for approval testing of welders to welding
procedure approval is not required. Part 1: Fusion
welding of stee!
Non-Destructive Test Methods
Amorican standards
AWS D1.1/01.1M: 2010 Structural Welding Code - Steet
346A144.2 UK European and ISO standards
BS 3023: Part 1: 1988 Methods for ultrasonic examination of welds. Part 1
Methods for manual examination of fusion welds in
feritic steels (Withdrawn in the UK, replaced by
BS EN 1714: 1998)
BS EN 1714: 1998 Non-destructive testing of welded joints. Ultrasonic
‘examination of welded joints (Withdrawn in the UK,
replaced by BS EN ISO 17840; 2010)
=> BS EN ISO 17840: 2010 Non-destructive testing of welds, Ultrasonic testing,
‘Techniques, testing levels and assessment
BS EN 571-1: 1997 Non-destructive testing. Penetrant testing, Part 1:
General principles
BS EN 970: 1997 Non-destructive examination of fusion welds. Visual
‘examination (Withdrawn in the UK, replaced by BS EN
180 17637: 2011)
SS BS EN ISO 17637; 2014 Non-destructive testing of welds. Visual testing of fusion
‘welded joints
BS EN 1290: 1998 Non-destructive examination of welds. Magnetic particle
‘examination of welds (Withdrawn in the UK, replaced by
BS EN ISO 17638: 2008)
—5>- BS EN ISO 17638: 2008 Non-destructive testing of welds. Magnetic particle
testing
BS EN 1435: 1997 Non-destructive examination of welds. Radiographic
examination of welded joints
BS EN ISO 9924-1: 2001 V Nondestructive testing. Magnetic particle testing. Part
1: General Principles
‘The abstracted essentials for typically used welding symbols are given in Annex C.
A145 — Destructive test methods for welds
BS EN 875:1995 Destructive tests on welds in metallic materials. Impact
tests. Test specimen location, notch orientation and.
‘examination (Withdrawn in the UK, replaced by BS EN
: a 1S 9016: 2011)
BS EN ISQ.9016: 2011" Destructive tests on welds in metallic materials. Impact
tests. Test specimen location, notch orientation and
examination
BS EN 876:1995 Destructive tests on welds in metalic materials.
Longitudinal tensile tests on weld metal in fusion welded
Joints (Withdrawn in the UK, replaced by BS EN ISO.
5178: 2011)
BSENISO 5178: 2017) Destructive tts on welds in metalic materials,
- Longitudinal tensile tests on weld metal in fusion welded
joints
BS EN 896:1995 Destructive tests on welds in melatc materials,
Transverse tensile test (Withdrawn inthe UK, replaced
- by BS EN ISO 4196: 2011)
BS EN 180 4196:2011 __Daatetv tests on weld n metic materia
Pape Transverse tensile test
BS EN 910:1996 Destructive tests on welds in metalic materials. Bend
———~.. teste (Witndrawn in the UK, replaced by BS EN ISO
> 8173: 2010)
BS EN 180 5173: 2010 Destructive tests on welds in melalic materials. Bend
tests
sar