You are on page 1of 2

SHOTPATCH 20S

Premixed, high build, shotcrete mortar

DESCRIPTION APPLICATION
SHOTPATCH 20S is a ready to use, cementitious Substrate condition
powder, which on mixing with the specified quantity of The substrate must be clean and free from surface
water yields a sprayable high build mortar. contaminants such as moss and fungus growth, curing
The shotcrete mortar can be modified with Barra membrane, rust, sludge, dirt and loose particles. Use
Emulsion AC for increased impermeability and bond scabbling, wire brushing and water blasting with
strength. compressed air through the shotcrete nozzle, to clean
the surface.
RECOMMENDED FOR If the application is for replacing damaged concrete, first
saw cut the boundary of the damaged area,
SHOTPATCH 20S is recommended for situations perpendicular to the surface, to at least 10 mm depth
requiring spray application of mortar to a thickness of 10 and hack out the area to at least 40 mm depth, before
- 100 mm in a single layer, for repairs and protection. cleaning the surface.
Applications include; Where required, cut back concrete to at least 25 mm
repairs to the underside of bridge decks, piers, and behind the rebars. Remove all corrosion products from
beams, tunnels and culverts. the rebars by grit blasting or other suitable technique.
repairs to sewer pipes, drains, water towers, etc. Replace the affected part of rebar if the diameter after
slope stabilisation. grit blasting is found to be reduced by more than 20% of
Fireproofing and protection to steelworks. the original diameter.
Note : It is recommended that the decision on
FEATURES & BENEFITS replacement of rebars is taken based on the advice of
the structural engineer responsible for the works.
Higher build per Considerable savings in time In a chloride laden environment, the rebars are
pass and labour when building up recommended to be coated with Barrafer S or
thick sections. Barrazinc SP zinc rich primer.
Prepacked, pre- No batching errors. Consistency Saturate the surface thoroughly with clean water before
formulated in performance. applying the mortar.
Reduced rebound Minimised wastage. Faster build Mixing
up. Dry process : Introduce both the powder and water at
High strength Stronger repair. the nozzle for mixing.
Wet process : Premix the powder and water, then pump
TYPICAL PERFORMANCE DATA the mixture to the nozzle.
If polymer modification is required, pre-mix the water
Strength (N/mm2) with Barra Emulsion AC in the ratio 1:1 by volume.
1 Day 28 Days Water requirement (per 25 kg)
Compressive (ASTM C109) 20.0 50.0 Consistency Min. Max.
Flexural (ASTM C348) 2.0 6.0 Sprayable 10% (2.5 L) 15% (3.75 L)
Plain Polymer Priming
Mortar Modified * Normally priming is not required. However, if damaged
-13 -13
Permeability, m/sec 4.1x10 2.5x10 concrete is being replaced and the concrete is known to
(Taywood method) be contaminated with chlorides, prime the prepared
Volume of permeable 11.3 6.6 surface with Mastertop 2525 (see separate data sheet).
core space (voids), %
(ASTM C642) Placing
Water absorption, % 5.2 1.7 On primed surfaces start placing after the primer
(ASTM C642 reaches a tacky state.
procedure A) SHOTPATCH 20S has been formulated for placing by
* SHOTPATCH 20S modified by Barra Emulsion AC spray to thickness ranging from 10 mm to 100 mm in
diluted with equal volume of water. one pass of the nozzle, both by wet and dry processes.

Head Office Factories Representative Offices


Plaza GRI 10th & 11th Floor Jl. Daan Mogot Km.14 Jl. Jababeka V Blok I-1 Grand Residence Office Park, Komp. Pertokoan Royal Sunggal
Jl. HR Rasuna Said Blok X-2 No.1 Cengkareng, Cikarang Industrial Estate 1st Floor Jl. Gagak Hitam No. A-12
Jakarta 12950 Jakarta 11750 Bekasi 17530 Jl. Darmo Harapan Complex 1 Ring Road Sunggal
Tel.: (6221) 5262481, 5262505 Tel.: (6221) 6190007 Tel.: (6221) 8934339 Surabaya 60187 Medan, Sumatera Utara 20128
Fax: (6221) 5262493, 5262515 Fax: (6221) 6190741 Fax: (6221) 8934342 Tel.: (6231) 7326705 Tel.: (6261) 8447110
Fax: (6231) 7326730 Fax: (6261) 8444072
SHOTPATCH 20S
Spray the mortar using a Deguna 20 mixer cum sprayer ESTIMATING DATA
for wet spraying or a Piccola spray unit for dry spraying,
or similar machines available from BASF Construction A 25 kg bag of SHOTPATCH 20S mixed with 3.25 L of
Chemicals. For satisfactory results, an experienced water (or with 3.25 L of a 1:1 solution of Barra Emulsion
3
operator in sprayed concrete is essential. AC in water) yields 12.40 litres (0.0124 m ).
The maximum thickness per pass is also dependent on Therefore, material requirement on a smooth and flat
the surface conditions of the substrate, skill of the surface is 20.16 kg/m2 at 10 mm thickness excluding
nozzleman and the orientation of the treated surface - rebound losses and allowance for cut off.
vertical, inclined or overhead. Actual consumption depends up on the surface profile
and rebound loss. The loss from rebound depends on
Smooth the final surface by a wooden, plastic, or
the experience of the nozzle man, the orientation of the
synthetic sponge faced trowel. Start trowelling only after
surface and the surface texture. Excluding any
the mortar has set sufficiently hard to resist penetration
allowance for cut off, it is recommended that a minimum
by fingers.
of 10% allowance for rebound be made for vertical and
CURING inclined surfaces and 50% for overhead surfaces.

Immediately after final finishing, start (preferably) 3 - 5 PACKAGING


days of wet-curing, then cure with a uniform coat of a
25 kg, multi-ply paper sacks with polythene liner.
membrane curing compound such as Masterkure 181
(see separate data sheet). SHELF LIFE
Protective coating
In a high chloride or a high carbon dioxide laden SHOTPATCH 20S can be stored in unopened original
atmosphere, a flexible protective coating with low bags for 12 months, if kept dry and at even temperature.
permeability to chlorides and carbon dioxide such as,
Barracryl D or Barracryl Elastic is recommended. PRECAUTIONS
Refer to BASF Construction Chemicals for detailed
product selection advice. Health : SHOTPATCH 20S is alkaline like normal
cement and can cause skin irritations to persons with
EQUIPMENT sensitive skin. Wear gloves and masks while handling
the product. Take all precautions normally taken while
Wet process : Deguna 20 combined mixing & spraying handling cement.
unit or a similar equipment (see separate data sheet). Safety : Take adequate safety measures during
Dry process : Piccola (see separate data sheet) spraying. Consult the supplier of the spraying machine.
spraying machine or a similar equipment. Fire : SHOTPATCH 20S is not flammable.
SP20S/01/1205
CLEANING
Clean tools and equipment with water, before the mortar
hardens.

The technical information and application advice given in this BASF Construction Chemicals
publication are based on the present state of our best scientific and practical knowledge. As the
STATEMENT OF information herein is of a general nature, no assumption can be made as to a product's suitability for a
RESPONSIBILITY particular use or application and no warranty as to its accuracy, reliability or completeness either
expressed or implied is given other than those required by law. The user is responsible for checking the
suitability of products for their intended use.
Field service where provided does not constitute supervisory responsibility. Suggestions made by
BASF Construction Chemicals either orally or in writing may be followed, modified or rejected by the
NOTE owner, engineer or contractor since they, and not BASF Construction Chemicals, are responsible for
carrying out procedures appropriate to a specific application.

You might also like