You are on page 1of 37

ASSOt IAl I O N

Concrete Floors
on Ground

Second Edition
PREFACE TO THE SECOND EDITION

This second edition of Concrete Floors on Ground con-


tinues Portland Cement Associations tradition of pro-
viding the concrete user with information on the latest
in concrete technology and its application at the jobsite.
Although the fundamentals of good floor design and
construction practice do not change, reader responses
and queries following publication of the first edition
called for clarification and additions to the text so that
new concrete floors continue to improve in serviceability
and economy. This second edition includes supplemental
information on-
Safety factors Joints and joint spacing
Effective contact areas Filling joints
Unjointed slabs Reinforcement
Uncommon storage Finishes for slabs
conditions
New sections have been added on-
Load transfer across Doweled control joints
joints
The publication is intended for owners, architects,
engineers, contractors, and any others who share the
responsibility for floor performance in industrial and
commercial buildings.
This publication is based on the facts, tests, and authorities
stated herein. It is intended for the use of professional personnel
competent to evaluate the significance and limitations of the
reported findings and who will accept responsibility for the
application of the material it contains. The Portland Cement
Association disclaims any and all responsibility for applica-
tion of the stated principles or for the accuracy of any of the
sources other than work performed or information developed
by the Association.
Caution: Avoid prolonged contact between unhardened (wet)
cement or concrete mixtures and skin surfaces. To prevent such
contact, it is advisable to wear protective clothing. Skin areas
that have been exposed to wet cement or concrete, either direct-
ly or through saturated clothing, should be thoroughly washed
with water.

Cover: Ride-on triple trowel. Photograph courtesy of


the Master Consolidated Corporation.
The author of this text is Ralph E. Spears, formerly man-
ager (now retired) of the Building Construction Section;
revisions were made by William C. Panarese, associate
manager, Building Construction Section, Building De-
sign and Construction Department, Portland Cement
Association.

@ Portland Cement Association 1983


First Edition 1978
Second Edition 1983
Printed in U.S.A.
CONTENTS

Introduction .*...a.**.......*.............. 3 Reinforcement for Floors


on Ground . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . ...21
Uniform Subgrade of Adequate
Bearing Capacity.. . . . . . . . . . . . . . . . . . . . . . . . . 3 unjointed Floors . . . . . . . . . . . . . . . . . . . . . . . . . . 22
Subgrades . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 3
Soil Properties, Density, Plasticity Index, Construction ............................... 22
Problem Soils, Site Preparation, Expansive Workmanship . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 22
Soils, Hard Spots and Soft Spots, Backfilling,
Modulus of Subgrade Reaction Subgrades . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 22
Subbases . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . ...*. 6 Expansive Soils, Hard Spots and Soft
Spots, Backfilling
Subbase or Cushion . . . . . . . . . . . . . . . . . . . . . . . . . . 23
Quality of the Concrete .................. 6
Vapor Barrier . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 24
Strength.. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 6 Insulation Under Slabs . . . . . . . . . . . . . . . . . . . . . . . 24
Minimum Cement Content . . . . . . . . . . . . . . . . . . . . 7 Slab Thickness Tolerances . . . . . . . . . . . . . . . . . . . .24
Maximum-Size Coarse Aggregate . . . . . . . . . . . . . . 7 Finishing Concrete Floors . . . . . . . . . . . . . . . . . . . . .24
Slump . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 7 Concreting Procedures. . . . . . . . . . . . . . . . . . . . . . . .25
Entrained Air . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 7 Edge Forms, Positioning Reinforcing
Tensile Strength of Concrete: Modulus of Steel, Placing and Spreading, Striking
Rupture . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 8 Off and Consolidating, Leveling, Edging,
Floating, Jointing, Troweling
Adequacy of Structural Capacity . . . . . . . . 8 Curing . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 29
Location and Frequency of Imposed Loads . . . . . 8 Acceptable Surface Tolerances. . . . . . . . . . . . . . . . .30
Flexural Stresses and Safety Factors . . . . . . . . . . . 8
Fatigue and Safety Factor, Shrinkage Special Finishes for Concrete
Stress, Impact, Flexural Stress Floor Slabs ................................ 30
Preliminary Design . . . . . . . . . . . . . . ..*.......... 9 Dry-Shake Finishes . . . . . . . . . . . . . . . . . . . . . . . . . . 30
Design Procedure . . . . * . . . . . . . . . . . . . . . . . . . . . . . 10 High-Strength-Concrete Toppings . . . . . . . . . . . . . .3 1
Vehicle Loads, Thickness Design Monolithic Toppings, Separate Bonded
Example-Single-Wheel Axle Loads, Toppings, Separate Unbonded Toppings
High-Rack-Storage-Leg Loads, Uniform Vacuum Dewatering . . . . . . . . . . . . . . . . . . . . . . . . . . 31
Loads, Uncommon Storage Conditions
Surface Grinding . . . . . . . . . . . . . . . . . . . . . . . . . . . . 31
Thickness Design Summary . . . . . . . . . . . . . . . . . . . 16
Sealing Concrete Floors . . . . . . . . . . . . . . . . . . . . . .31
Sodium Silicate (Water Glass), Silico-
Jointing Practice . . . . . . . . . . . . . . . . . . . . . . . . . . 16 fluorides, Linseed Oil
KindsofJoints . . . . . . . . . . . . . . . . . . . . . . . . . . . ...16 Floor Coatings . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 32
Isolation Joints, Control Joints, Seamless Floor Surfacings
Construction Joints
Filling Joints e............................... 17 Repairs and Overlays . . . . . . . . . . . . . . . . . . . . .32
Joint Layout . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .18 Evaluation of Damage.. . . . . . . . . . . . . . . . . . . . . . .32
Spacing of Joints Preparation of Old Concrete . . . . . . . . . . . . . . . . . .33
Load Transfer Across Joints . . . . . . . . . . . . . . . . . . 19 Cleaning Concrete Floors
Aggregate Interlock, Load Transfer
Effectiveness, Influence of Joint Opening, Concrete Overlays . . . . . . . . . . . . . . . . . . . . . . . . . . . 34
Influence of Slab Thickness, Influence Bonded Patching o/4 to 2 in. thick),
Thin Bonded Overlay, Unbonded Toppings
of Subgrade Support, Influence of Load
Magnitude, Influence of Aggregate Shape, Repair of Cracks and Joints.. . . . . . . . . . . . . . . . . .35
How to Improve Load Transfer Across Filling Cracks (Sealing), Refilling Joints
Joints (Resealing), Patching Spalls
Doweled Control Joints . . . . . . . . . . . . . . . . . . . . . .21
Dowels in Reinforced Slabs Metric Conversions . . . . . . . . . Inside back cover
Concrete Floors
on Ground
INTRODUCTION UNIFORM SUBGRADE OF
ADEQUATE BEARING CAPACITY
Large-area concrete floors for commercial and industrial
buildings must be designed and constructed with the To ensure that the concrete floor will continue to carry
greatest possible economy to give trouble-free service its design loading successfully, it is vital to design and
year after year. The building of a good concrete floor construct the subgrade as carefully as the floor itself. A
requires close communication between owner, architect, subbase, while not mandatory, can provide added bene-
engineer, and contractor-with a mutual understanding fits in construction and performance.
of the level of quality needed for its intended use.
Many erroneous notions have developed over the years
as to how the rules of good concrete practice affect the Subgrades
serviceability of floors on ground. They have brought
more complaints about poor performance of floors than The subgrade is the natural ground, graded and com-
any other part of a building. Advice is rarely sought be- pacted, on which the floor is built. The subgrade as found
fore design or construction begins, indicating that floors can be improved bydrainage,compaction(seeDensity),
receive little attention at any stage in the building process. or soil stabilization. (Site drainage is not discussed in
Before construction begins, careful attention must be this publication.) Because of the rigidity of concrete floor
given to a number of factors that influence performance: slabs, concentrated loads from forklift wheels or high-
rack legs are spread over large areas and pressures on the
1. Uniformity of the subgrade and subgrade are usually low. Thus, concrete floors do not
adequacy of its bearing capacity. necessarily require strong support from the subgrade.
2. Quality of the concrete Subgrade support must, however, be reasonably uniform
3. Adequacy of structural capacity without abrupt changes from hard to soft, and the upper
4. Type and spacing of joints portion of the subgrade must be of uniform material and
5. Workmanship density.
6. Special surface finishes
7. Future maintenance and repair Soil Properties
All these factors are covered in detail in this text. The Proper classification of the subgrade soil must be made
technology and details apply equally to the small-area to identify potential problem soils.* One soil classifica-
floor in a residence, light industry, or warehouse and to tion system in common use is Classification of Soils for
the large area covering many acres typified by the heavy Engineering Purposes, American Society for Testing and
industrial plant and its storage facilities. Major emphasis
is given to attaining the best possible balance between
service requirements and costs of construction and future *See PCA Soil Primer, Portland Cement Assoctation publication
maintenance. EBoo7S, 1973.
Materials (ASTM) Designation: D2487. Table 1, based structural properties of the soil. Density of a soil is meas-
on the ASTM system, shows the major divisions of soils ured in terms of its mass per unit volume.
with descriptive names and letter symbols indicating their Tests performed according to Moisture-Density Rela-
principal characteristics. When soil is a combination of tions of Soils, ASTM D698, will determine the maxi-
two types, it is described by combining both names. Thus, mum density and corresponding optimum-moisture con-
clayey sand is predominantly sand but contains an appre- tent of the soil.
ciable amount of clay. Reverse the name to sandy cla?
and the soil is predominantly clay with an appreciable
amount of sand.
Plasticity Index
Density When a soil can be rolled into thin threads, it is called
plastic. Most fine-grained soils containing clay minerals
The strength of the soil-its supporting capacity and are plastic. The degree of plasticity is expressed as the
resistance to movement or consolidation-is important plasticity index (PI). The PI is the numerical difference
to the performance of floors on ground, particularly between the liquid limit and plastic limit. Liquid limit
when the floor must support extremely heavy loads. Soil (LL) is the amount of moisture present when the soil
strength is affected by the degree of its compaction and
changes from a plastic to liquid state. Plastic limit (PL)
its moisture content.
Compaction is a method for purposely densifying or is the amount of moisture present when a soil changes
increasing the unit weight of a soil mass by rolling, tamp- from semisolid to plastic.
ing, or vibrating. It is the lowest-cost way to improve the PI = LL - PL

Table 1. ASTM Soil Classification System


Modulus of
Presumptive subgrade reaction, k,
Group Typical bearing capacity, pounds per square inch
symbols names tons per square foot per inch
Well-graded gravels and gravel-
GW 5 300 or more
sand mixtures, little or no fines
Poorly graded gravels and gravel-
GP 5 300 or more
sand mixtures, little or no fines
Silty gravels, gravel-sand-silt
G M 2.5 200 to 300 or more
mixtures
Clayey gravels, gravel-sand-clay
GC 2 200 to 300
mixtures
Well-graded sands and gravelly
SW 3.75 200 to 300
sands, little or no fines
Poorly graded sands and gravelly
SP 3 200 to 300
sands, little or no fines
S M Silty sands, sand-silt mixtures 2 200 to 300
SC Clayey sands, sand-clay mixtures 2 200 to 300
Inorganic silts, very fine sands,
ML rock flour, silty or clayey fine 1 100 to 200
sands
Inorganic clays of low to medium
CL plasticity, gravelly clays, sandy 1 100 to 200
clays, silty clays, lean clays
Organic silts and organic silty
OL 100 to 200
clays of low plasticity
Inorganic silts, micaceous or
MH diatomaceous fine sands or silts, 1 100 to 200
elastic silts
Inorganic clays of high plasticity,
CH 1 50 to 100
fat clays
Organic clays of medium to high
OH 50 to 100
plasticity
Peat, muck, and other highly
Highly organic soils PT
organic soils
Based on the malenal passlng the 3-1n (75.mm) sieve
Nattonal Bullding Code 1976 EdWon American Insurance Association
Soils with a high PI, greater than 20, may cause future ASTM D698) will minimize possible loss of support
problems by expanding under changes of moisture con- from any future increases in moisture content and give
tent in the subgrade due, for example, to a rising water the subgrade the uniform stability that is needed for good
table. performance.
For exceptionally heavy loadings or poor soil condi-
Problem Soils tions, a soils investigation should be made by a compe-
Soils are considered problem soils when they are highly tent soils engineer.
expansive, highly compressible, and do not provide rea-
sonably uniform support. Concrete-floor-on-ground de- Hard Spots and Soft Spots
sign is based on the assumption of uniform subgrade sup- If the subgrade is of nonuniform support, the slab when
port. The key word is uniform. Where problem soils loaded will tend to bridge over soft spots and ride on hard
create nonuniform conditions, correction is most eco- spots, all too often with the results illustrated in Fig. 1.
nomically and effectively achieved through subgrade Special care must be taken by excavating and backfilling
preparation methods. to prevent localized soft or hard spots. Uniform support,
however, cannot be obtained merely by dumping granu-
Site Preparation lar material on the soft spot. Moisture and density condi-
To construct a reasonably uniform subgrade, special care tions of the replacement soil should be as similar as pos-
must be taken to ensure that there are no variations of sible to the adjacent soil. At transition areas where soil
support within the floor area and that the following types or conditions change abruptly, the replacement soil
major causes of nonuniform support are controlled: should be mixed with the surrounding soil by crosshaul-
ing and blending to form a transition zone with uniform
Expansive soils support conditions.
Hard spots and soft spots
Backfilling
Expansive Soils
Most soils sufficiently expansive to cause floor distortion
are classified by the ASTM Soil Classification System
(Table 1) as clays of high plasticity (CH), silts of high
plasticity (MH), and organic clays (OH). Simple soil tests
provide indexes that serve as useful guides to identify the
approximate volume-change potential of soils. Follow-
ing are some of these tests:
Plasticity Index, ASTM D424
Volume Change of Soils, ASTM D1883
Shrinkage Factors of Soils, ASTM D427
Fig. 1. Soft spots and hard spots.
Soil Compaction Tests, ASTM D698
Liquid Limit of Soils, ASTM D423
The following table shows approximate expansion-
plasticity relationships:
Backfilling
Approximate Any fill material added to improve the subgrade or raise
Degree of I Percentage I ntasticitv
expansion of swell the existing grade should be a stable material that can be
Lex (Pi)
thoroughly compacted. Rubble from building or pave-
Nonexpansive 2 or less oto IO ment demolitions must first be passed through a crusher
Moderately expansive 2 to 4 IO to 20
Highly expansive more than 4 more than 20
because large pieces can cause compaction difficulties.
Underfloor pipeline and utility trenches should be
backfilled with soils like those surrounding the trench
Abnormal shrinkage and swelling of high-volume- and compacted in layers to duplicate moisture and den-
change soils in a subgrade will create nonuniform sup- sity conditions in the adjacent soils. Every attempt should
port. As a result, the concrete floor may become dis- be made to restore as much as possible the original uni-
torted. Compaction of highly expansive soils when the formity of the subgrade.
soils are too dry can contribute to deterimental expan- Poorly compacted subgrade fill can cause subsequent
sion and softening of the subgrade upon future wetting. settlement problems and premature failure of the slab.
When expansive soil subgrades are too wet prior to cast-
ing a floor slab, subsequent drying and shrinkage of the
soil may leave portions of the slab unsupported.
Modulus of Subgrade Reaction
Selective grading, crosshauling, and blending of sub-
grade soils make it possible to obtain uniformconditions The objective of design for thickness of concrete floors
in the upper part of the subgrade. Compaction of expan- (and pavements) is to control tensile stresses within the
sive soils to 95% optimum density at 1% to 3% above slab. The stresses are influenced by the amount of support
standard optimum moisture (Soil Compaction Tests, provided by the subgrade.
In thickness design, the subgrade support used for con- performance by densifying under vibration and repetitive
crete floors on ground is taken to be Westergaards mod- loads. To prevent densification, the subbase material
ulus of subgrade reaction, k, which is determined by load should be compacted to high density: a minimum of 98%
tests on the subgrade at the jobsite. The modulus of sub- maximum density at optimum moisture determined by
grade reaction, k, is the ratio of load in pounds per square Soil Compaction Tests, ASTM D698.
inch to a 0.05-in.* deflection of a 30-in.diameter bearing Granular material for the subbase can be sand, sand-
plate: gravel, crushed stone, or combinations of these materials.
load (psi) A satisfactory dense-graded material will meet the fol-
k =
deflection (at 0.05 in.) lowing requirements:
The probable range of values for k on various soils is
shown in Table 1 and in the following box. Maximum size: Not more than 1/3 the sub-
base thickness
Passing No. 200 sieve: 15% maximum
Plasticity index: 6 maximum
Liquid limit: 25 maximum

Substantial benefits in floor performance and slab-


thickness reduction can be derived from a cement-treated
A reliable correlation does not exist between subgrade subbase (CTSB) under a concrete floor slab that is to be
modulus and the bearing capacity of the soil used for subject to extremely heavy loading conditions. The high
foundation design. The k value used in floor design re- support value of CTSB will-
flects the subgrade under temporary (elastic) conditions Reduce permeability
and small deflections-O.05 in. or less. Soil bearingcapac- Eliminate subbase consolidation
ity values from field tests-used to predict and limit dif- Permit use of thinner concrete slabs
ferential settlement between footings or parts of a foun-
dation-reflect total, permanent (inelastic) subgrade More information on preparing the grade is described
deformations that may be 10, 20, or more times greater in Subgrades and Subbases for Concrete Pavements.**
than the small deflections of k values.
The k value does not reflect the effect of compressible
soil layers at a depth of more than the 3 to 5 ft below sub-
grade surface. For exceptionally heavy floor loads dis- QUALITY OF THE CONCRETE
tributed over large areas, the allowable bearing capacity
of the underlying soil and the anticipated settlement due The wear resistance of a concrete floor slab is directly
to soil consolidation should be determined. Long-term related to the strength of the concrete. Research has
settlement may cause cracking and misalignment of slabs. shown that resistance to wear improves with a reduction
in water content or an increase in cement content, or both,
either one of which will increase strength. It is the rich
Subbases quality of the mortar that is important; the hardness and
toughness of the coarse aggregate becomes significant
A subbase-the thin layer of granular material placed only after the surface-mortar matrix has worn away. To
on top of the prepared subgrade-is not mandatory for get the right quality concrete, the order given to the ready
floors on ground. However, when a uniform subgrade is mixed concrete supplier must be clear and contain all the
not produced by grading and compaction operations, a basic information stated in the job specifications.
granular subbase will provide a cushion for more uniform In flatwork, the placeability of the concrete and the
support by equalizing minor subgrade defects. The gran- finishability of the surface are equally if not more impor-
ular subbase can also provide a capillary break and a tant than strength, because they have a significant effect
stable working platform for construction equipment. on the quality of the top I% or /la in. of the wearing sur-
It is seldom necessary or economical to build up the face. The order for ready mixed concrete should contain
supporting capacity of the subgrade with a thick subbase. the following information: strength, minimum cement
Tests made by the Portland Cement Association show content, maximum size of coarse aggregate, slump, and a
that increasing subbase thickness beyond 4 in. results in small amount of purposely entrained air.
only minor increases in subgrade support, and these
minor increases allow no appreciable reduction in the
thickness of a concrete slab for given loading conditions. Strength
Since uniform support rather than strong support is
the most important function of the subgrade and sub- A minimum strength of 4000 psi at 28 days is advisable
base for a concrete floor, it follows that floor strength is for light industrial and commercial floor use. Specifica-
achieved most economically by building strength into the
concrete slab itself-with optimum use of low-cost mate-
rials under the slab.
*Use conversion table at the end of this book to convert to metric
Thus, when a subbase is used, a 4-in. thickness is sug- measurements.
gested. A thicker subbase could contribute to poor floor **Portland Cement Association publication ISO29P, 1971.
tions for a lower strength may be adequate for supporting Table 2. Minimum Cement
the loads on the floor but will be inadequate for satisfac- Requirements
tory wear resistance. It is also advisable to require 1800
Maximum Cement,
psi strength at 3 days to build in early protection for the size of lb per
slab from construction traffic. Satisfying this 3-day re- aggregate, in. cubic yard
quirement will produce 28-day strengths well above the 1 h 470
recommended minimum shown in Fig. 2. 1 520
Classification of floors on the basis of intended use is k 540
given in American Concrete Institute (ACI) 302, Guide % 590
for Concrete Floor and Slab Construction, Table 1.1. 56 610
Recommended strengths for each class of floor are given
in AC1 302, Table 5.2.1.

COMPRESSIVE can be reduced is improved by using concrete with a mini-


STRENGTH, PSI mum shrinkage potential that contains the correct grada-
1.000 psi = 7 MPa tion of aggregates, the maximum size of coarse aggregate,
and the maximum amount of coarse aggregate consistent
with placing and finishing methods. A larger aggregate
size permits a lower water content in the concrete and is
more effective in restraining the shrinkage of the cement
paste.
The maximum aggregate size shown in Table 2 should
be used if it is economically available and if it satisfies the
requirement that maximum aggregate size not exceed
three-fourths the clear space between reinforcing bars or
one-third the depth of the floor slab.

Slump
635 0.45 0.55 0.65 Excessive slump and consequent bleeding and segrega-
WATER- CEMENT RATIO tion are a primary cause of poor performance in concrete
Non-air-entmined concrete floors. If the finished floor is to be level, uniform in
Cement : Type I appearance, and wear resistant, it is important that all
batches placed in the floor have very nearly the same
Fig. 2. Recommended minimum strengths for industrial slump.
and commercial floors on ground.
Placing low-slump (2- to 4-in.) concrete flatwork is
routine with the use of mechanical equipment such as a
vibratory screed that rides on the side forms. When such
Minimum Cement Content equipment is used on floor work, less water is added at
the jobsite and the wear resistance of the surface is im-
Floor work in particular needs sufficient cement mortar proved. Low-slump concrete will go a long way towards
matrix for proper finishability. This is assured by speci-
fying a minimum cement content. Speeding up placement and consolidation
With modern concrete technology, high-strength con- Reducing finishing time
crete can be obtained with less cement than before. Where Reducing cracking
strength alone is the decisive criteria, less cement means Eliminating surface defects
greater economy. Wear resistance, however, depends Recommended slumps for each AC1 class of floor are
upon the surface hardness of the concrete as well as its given in Table 5.2.1 of AC1 302. A 3-in. slump is suggest-
internal strength and requires more cement. A minimum ed for class 4 and 5 floors.
cement content should be specified that will ensure tin-
ishability for maximum wear resistance at the surface as
well as adequate internal strength. The amount of cement Entrained Air
should not be less than shown in Table 2. Use the largest
size of aggregate possible to keep the cement content to a A small amount of purposely entrained air is useful in
minimum. almost all concrete for floors for reducing bleeding and
increasing plasticity. A total air content of 2% to 3% is
suggested. Concrete that will be exposed to cycles of
Maximum-Size Coarse Aggregate freezing and thawing and the application of deicer chemi-
cals needs a total air content of 5.5% to 7.5%, depending
Freedom from random cracking is desired for all concrete upon maximum size of aggregate, to ensure resistance to
floors. The degree to which random shrinkage cracking scaling. See Table 5.2.7a of AC1 302.
Tensile Strength of Concrete where extensive data had already been assembled from
many years of laboratory and field research and testing.
Modulus of Rupture Acknowledging the obvious similaritiesand differences
between a road pavement and a floor slab, pavement
When a load is applied to a floor on ground, it causes theory was reduced to easily used thickness design charts
bending that produces both compressive and flexural for floors on ground. The design method is presented in
stresses in the concrete slab. Of the two types of stress, Slab Thickness Design for Industrial Concrete Floors on
flexural stress is more critical because it will approach Grade* and is applicable as well to slabs on ground for
the ultimate tensile strength of the concrete (modulus of outdoor storage and material-handling areas. As in pave-
rupture), while compressive stress remains small in pro- ment design, the factors involved in determining the re-
portion to the ultimate compressive strength of the con- quired floor slab thickness are
crete. Consequently, theflexural stress and thejlexural 1. Strength of subgrade and subbase
strength of the concrete are used in floor-slab design to 2. Strength of concrete
determine thickness. 3. Location and frequency of imposed loads
Flexural strength is determined by modulus of rupture
(MR) tests in accordance with ASTM C78, Flexural The following procedures for thickness design are de-
Strength of Concrete Using Simple Beam with Third- rived from Slab 7Eckness Designfor industrial Concrete
Point Loading. If the size of the job does not warrant the Floors on Grade.
extra cost of flexural strength tests, compressive strength
test results can be used to approximate probable flexural
strength. An approximate relationship between compres- Location and Frequency
sive and flexural strength is shown in Table 3. of Imposed Loads
Slab cracking due to excessive loads can occur in response
Table 3. Approximate Relationship to flexural overstress; too much deflection; settlement
Between Compressive and due to consolidation of subsoil; and for very concentrated
Flexural Strengths loads, excessive concrete bearing or shear stresses.
The strategy in designing for floor slab thickness is to
Compressive strength, psi Flexural strength, psi keep all responses within safe limits. The controlling de-
3500 445-590 sign consideration will differ for different sizes of load
4000 480-640 contact area. For example, for lift trucks with wheel con-
4500 500-670
5000 535-710
tact areas in the range of 20 to 100 sq in., flexural stress
6000 585-780 will control thickness design.
7000 630-840

Flexural Stresses and Safety Factors


In the design procedure based on flexure, the allowable
ADEQUACYOFSTRUCTURAL working stresses are determined by dividing the concrete
CAPACITY flexural strength by an appropriate safety factor. Safety
factors for vehicle loads have been established from ex-
Many variables directly or indirectly influence the deter- perience gained in pavement performance and take into
mination of correct thickness for concrete floors on account several influences such as load repetitions,
ground. To include all of them in a design method would shrinkage factors, and impact.
be an unduly complex procedure and could lead to over-
confidence in the design as a guarantee of good floor per- Fatigue and Safety Factor
formance. All too frequently shortcomings of workman- Concrete is affected more by repetitive loads than by a
ship are the cause of unsatisfactory floor performance single load of the same magnitude. The effect is called
rather than inadequate design or specifications. Since it fatigue. A flexural fatigue failure occurs when the con-
is the top surface of the floor that is continually and criti- crete cracks under continued repetitions of loads that
cally appraised by the user, added attention to the con- cause flexural stress-strength ratios of less than one. Tests
struction of the top surface of the slab and to properjoint- of concrete slabs indicate that as the number of load repe-
ing may contribute more to user satisfaction than undue titions increases a higher safety factor must be used to
attention to the thickness of the slab itself. prevent failure. Fatigue effects are accommodated in the
Previous design information covered only a limited design procedure by a safety factor, as follows:
range of load magnitudes and wheel spacings of indus- 1. Select a conservative safety factor of 1.7 to 2.0 for
trial trucks operating on industrial and warehouse floors. moderate-to-heavy traffic. A safety factor of 2.0 per-
Design guides for plain concrete slabs were needed, be- mits unlimited repetitions of design load.
cause a plain slab-one without distributed steel or struc- 2. Select a safety factor of 1.5 to 1.7 for light traffic.
tural reinforcement-often has advantages of economy
and ease of construction.
To prepare a design guide, Portland Cement Associa-
tion turned to the field of highway pavement engineering, *Portland Cement Association publication ISl95D. 1976.
The safety factor can be selected by either of two ways. els, keyways, or aggregate interlock), it is assumed that
When the full-rated capacity of the forklift truck is select- the panel area acts as a portion of a continuous large-area
ed to determine slab thickness, a safety factor between 1.5 slab.
to 1.7 is suggested because forklift trucks are not always At free edges that lack adequate load transfer, concen-
operated at full-load capacity. When realistic-load data trated loads will produce stresses that are somewhat
are known and used, a safety factor of 2 is suggested. greater than those for the interior. Because of this, if lift
trucks will pass over an isolation joint (at a doorway for
Shrinkage Stress instance) the slab should be thickened by 25% gradually
over a distance of 5 ft. Thickened sections (edges) restrain
Shrinkage stresses are not considered to be significant. horizontal movement that may cause cracking in the inte-
For example, a shrinkage stress of 23 psi is computed for
rior of the slab. Mechanical devices (dowels) may be pref-
an 8-in. slab jointed at 20 ft using a subgrade friction fac- erable for load transfer.
tor of 1.5. Pavement research has shown, however, that
the actual stress developed will be much less-only one- The assumption of interior load placement, combined
with the choice of an appropriate safety factor and ade-
third or one-half of that predicted.
quate concrete strength, gives a reasonable basis for floor
thickness design.
Impact
Some procedures for pavement design increase the wheel
loads by a factor to accommodate the effect of wheel im- Preliminary Design
pact. A load-impact factor is not included in the PCA For preliminary design purposes, or when detailed design
floor design procedure (except in the safety factor) be-
data are not available, Fig. 3 can be used to select slab
cause this procedure is based on pavement research that thickness based on the rated capacity of the heaviest lift
shows slab stresses are less for moving loads than for trucks that will operate on the floor. The chart was pre-
static loads.
pared for typical lift trucks from manufacturers data
Flexural Stress shown in Table 4. It cannot be used for trucks with capac-
ity and wheel-spacing data that differ substantially from
The flexural stresses indicated on the design charts are the data in Table 4.
computed at the interior of a slab. When the slab edges at The combination of a low k value and a low working
all joints have adequate load transfer (by means of dow- stress in Fig. 3 results in a conservative slab thickness.

6
40 50 60 70 60 90 100 II0

tll,,,,11 I I I I I I 1
2 4 6 8 IO I2 I4 I6 I8 20 30 40 50
RATED CAPACITY OF LIFT TRUCK, kipr

Fig. 3. Estimated slab ihicknesses for lift trucks (based on average truck data shown in Table 4 and conservative
design assumptions of k = 50 pci, concrete working stress = 250 psi).
Table 4. Lift Truck Characteristics (Composites Averaged
from Manufacturers Data)
Range of wheel spacings, in. (c to c)
Rated Load on Dual wheels
capacity,* drive axle,** Single wheels,
lb kips st Sdt st

2,000 6.4 26 to 30 - -
4,000 10.4 31 to 35 - -
6,000 14.6 32 to 38 - -
10,000 22.2 37 to 43 10 to 12tt 41 to 53j.t
15,000 32.5 37 to 45 10 to 12 47 to 60
20,000 42.0 40 to 50 12 to 14 54 to 65
30,000 63.3 - 14 57
45,000 100.6 - 18 73
60,000 132.0 - 21 70

Other data:
Load Contact Pressure
solid or cushion tires-l 80 to 250 psi
pneumatic tires-80 to 100 psi (inflation pressure)
Load Contact Area (per tire)
solid or cushion tires-3 or 4 times tire width
pneumatic tires-wheel load divided by contact pressure
Approximately 90% of total weight (truck + load) on drive axle at rated
capacity.
Maximum axle load for many lift trucks is slightly greater than twice the
rated capacity.

Load center 24 in. from fork face, mast vertical.


Varies by about 10% depending on manufacturer.
tSee insert drawings on Figs. 2 and 4.
ttValues shown are for pneumatic tires; limited data for 1 O,OOO-lb-capacity
trucks with solid or cushion tires show shorter spacings; for example, 8.5x29 in.

More accurate and more economical designs can be ob-


tained by the complete design method given in Slab irhick-
nesS Design for Industrial Concrete Floors on Grade. Use
of this publication is illustrated in the following design-
procedure examples.

Design Procedure
Vehicle Loads
Design for industrial lift-truck loads requires knowledge
of several specifics:
Maximum axle loads
Number of load repetitions
Wheel contact area
Spacing between wheels on heaviest axles
Subgrade strength
Flexural strength of concrete
Traffic and load data for past and future operating
conditions for lift trucks (Fig. 4) can be gathered from
plant maintenance departments, planning and operations
departments, and truck manufacturers data. Then the
safety factor can be selected and used to determine an
allowable working stress with which to enter the design
charts.
The safety factor (flexural strength divided by working Fig. 4. Traffic and load data are needed for design of
stress) reflects the expected frequency of loadings of the industrial concrete floors on ground.
heaviest vehicles. Safety factors in the range of 1.5 to 2.0 alent single-wheel axle load. Then Fig. 5 can be used to
are suggested for industrial and commercial floors. The determine the required thickness of the slab.
high number should be used where the heavy load traffic The effective contact area used in the charts is the cor-
is frequent and channelized. Where traffic is light and not rected area of tire in contact with the slab. If tire data are
channelized, lower safety factors of 1.5 to 1.7can be used. not available, the contact area can be estimated for pneu-
The design chart for industrial trucks with single-wheel matic tires by dividing wheel load by inflation pressure.
axles, Fig. 5, was taken from Slab Thickness Design for For solid or cushion tires, it can be approximated by mul-
Industrial Concrete Floors on Grade. This chart is entered tiplying tire width by three or four. Tire data can also be
with a calculated number for allowable working stress obtained from the tire manufacturers. When the tire con-
per 1000 lb of axle load. The number is obtained by divid- tact area is small, it must be corrected to an effective con-
ing the modulus of rupture of the concrete by the safety tact area because slab stresses for small-load contact areas
factor and then dividing the result by the axle load in kips. are overestimated using conventional theory. The same
The calculation makes it possible for one chart to cover a correction is used for the high-rack-storage-leg loads dis-
wide range of load magnitudes. cussed below. The correction is made with the design
For axles equipped with dual wheels, Slab Thickness chart for axles with dual wheels in Slab Thickness Design
Design for Industrial Concrete Floors on Grade includes for Industrial Concrete Floors on Grade. (The chart is
a chart for converting a dual-wheel axle load to an equiv- not included in this publication.)

\ 1 1 I/ I/ j/ I/ EFFECTIVE I II/l I/l0 i

/ - + - j SPnClNG t-+/+=

8 O-II I I I in. I I I

3
I I
50 100 21 00

Fig. 5. Design chart for axles with single wheels. SUBGRADE k, pci.
Thickness Design Example-
Single-Wheel-Axle Loads
Data for Lift tick
Axle load 25 kips (single-wheel axle)
Wheel spacing 37 in.
Number of wheels 2
Tire inflation pressure 110 psi
Tire contact area:
wheel load 114 sq in. (large
inflation pressure enough, correction
not required)

Subgrade and Concrete Data


Subgrade modulus, k 100 pci
Concrete flexural strength, MR 640 psi
Design Steps
1. Safety factor, SF:
For frequent operations of forklift trucks in channel-
ized aisle traffic, select a safety factor permitting un-
limited stress repetitions-2.0.
2. Concrete working stress, WS:
ws= MRuO-
SF=-320psi

3. Slab stress per 1000 lb of axle load:


ws = % = 12.8 psi per 1000 lb
axle load, kips
4. Enter Fig. 5 at left with stress of 12.8 psi, move right
to contact area of 114 sq in., down to wheel spacing
of 37 in., then right to read a slab thickness of 7.9 in.
on the line for subgrade k of 100 pci. Use 8-in.-thick
slab.

High-Rack-Storage-Leg Loads
Advancements in mechanized, computerized material-
handling equipment generated the high-rack configura-
tion now used for product storage in many warehouses.
In these buildings, permanent racks of fixed dimensions
rise to heights up to 60 ft. When loads on the rack legs (or
posts) exceed the wheel loads of vehicles operating in the
warehouse, leg loads will control the thickness design.
For leg loads, the design objective is to keep flexural Fig. 6. Loaded legs supporting high-rack storage must
stresses in the slab within safe limits. When flexural re- have base plates of adequate size to prevent bearing or
quirements are satisfied by adequate slab thickness, pres- shear failure in the slab.
sures on the soil will not be excessive; and when a correct-
size base plate is used (Fig. 6), concrete bearing and
punching shear stresses will remain within acceptable Fig. 7, taken from Slab Thickness Designfor Industrial
limits. Concrete Floors on Grade, is used to determine slab
The design factors for high-rack-leg loads are similar thickness requirements for rack configurations and loads.
to those used for vehicle loads except that a higher safety The x- and y-leg spacings used in Fig. 7 are the smallest
factor is selected. The specific design factors are dimension in the rack configuration (except the spacing
Maximum expected load on leg between legs on opposite sides of a joint).
Effective (corrected) load contact area The procedure is similar to that for wheel loads. In the
Spacing between legs grid at the left side of the chart, locate the point corre-
Subgrade strength sponding to stress per 100~lb-leg load and effective
Flexural strength of the concrete (corrected) contact area. Move right to the y-post spac-
6 0

6
IO

SUBGRAOE k= 5 O p c i

60 4 0 20 IO

EFFECTIVE CONTACT AREA,


sq. i n .

Fig. 7. Design chart for leg (post) loads, subgrade k = 50 pci.

ing (length or long axis dimension of the racks); then with Fig. 7 to establish a tentative slab thickness based
move up (or down) to the x-spacing and right to read the on flexure. Shear stress and concrete bearing stress should
slab thickness. also be computed to determine if these values are within
For loads on high racks, use high safety factors. High- safe limits.
rack loads require conservative safety considerations For exceptionally heavy rack loads on plain concrete
because the effects of differences in movement at the slabs, the thickness required may be so great that alter-
base of the rack are magnified at the top. In addition, nate design methods should be considered, such as:
if the rack layout and the slab joint layout are not co- Integral or separate footings under the leg lines
ordinated, it is possible that some rack legs could be Structural reinforced slabs
located near a joint. Unless the slab edges are intention- Use of cement-treated subbase under the concrete slab
ally thickened, this would result in higher floor slab The economic and construction practicality of these
stresses than those shown in Fig. 7, which are based on alternative designs should be considered along with the
loads at the slab interior. Safety factors should be chosen effects of thickness on stresses and deflections ofthefloor.
to include the possibility of rack loads being applied close
to slab edges or corners.
Since there is little available data on performance ex- Uniform Loads
perience with rack loads on slabs, safety factors cannot
be suggested with as much confidence as for vehicle loads. Uniform loads are defined as loads distributed over a
Safety factors in the range of 3.9 to 4.8 willsatisfy build- large area. For most warehouse and industrial floors,
ing code requirements when the rack leg is regarded as a concentrated loads are the controlling design factor since
supporting column and the slab is regarded as an unrein- distributed loads do not usually produce flexural stresses
forced spread footing. of the same magnitude. However, after an adequate slab
A safety factor in the range of 3.0 to 4.0 can be used thickness has been selected to support the heaviest vehi-
ties and storage racks, as previously described, the effects in these tables.
of uniform loads should also be examined. Storage Layout. The magnitudes of flexurai stresses and
Design for uniform (distributed) loads has two objec- deflections due to distributed loads vary with slab thick-
tives: (1) to prevent cracks in the aisleways or unloaded ness and subgrade strength. They also vary with aisle
areas due to excessive negative moment; and (2) to avoid width, dimensions of the loaded area, and the existence
objectionable settlements due to consolidation of the of joints or cracks in the aisleway. In Table 5 for fixed iay-
foundation soils. out, the critical aisle width and its allowable distributed
Cracking in an unjointed aisle can be controlled by load are identified and the loads for other aisle widths are
adequate slab thickness. Slab settlement, however, can- given. Table 5 is used when the storage layout is pre-
not be eliminated by making the slab thicker-this is a planned and will remain unchanged (Fig. 8).
foundation-soils-improvement problem. Normally, the The allowable loads shown in Table 6 for a variable
magnitude of distributed loads placed on floors with storage layout represent the most critical conditions and
properly prepared and compacted subgrades and sub- are suggested for practical design use when the aisle and
bases is not sufficient to cause excessive settlement; but storage layout is unknown at planning time(Fig. 9). There
for very heavy distributed loads on compressible sub- are no restrictions on where the load is placed or on the
grades, the possibility should be examined by a structural uniformity of loading for the allowable loads in Table 6.
foundation engineer. When there are joints in the aisleways or if cracks should
occur, the limit of load will depend on the tolerable set-
Allowable Uniform Loads to Prevent Cracking in Aisie- tlement of the slab.
way. In an unjointed aisieway between uniform load For wheel and rack loads, increased slab thickness ef-
areas, the maximum negative bending moment may be fectively reduces the unit pressure transmitted to the sub-
up to twice as great as the moment beneath the loaded grade soil. Under uniform distributed loads, however,
area. Hence, the thickness design should limit the resuit- soil pressure is not reduced by slab thickness, but is equal
ing stresses so that a crack will not occur in the aisleway. to the uniform load on the slab plus the slab weight plus
Allowable loads based on this consideration can be the weight of any fill material. Therefore, when the loads
found in Tables 5 and 6 for fixed and variable storage iay- are exceptionally heavy, as in Fig. 10, the amount of set-
outs. Note that the k value of the subgrade, rather than tlement should be estimated by methods used in founda-
the k value on top of the subbase (if there is one), is used tion engineering for spread footings or raft foundations.

Table 5. Allowable Distributed Loads, Unjointed Aisle


(Uniform Load, Fixed Layout)
Allowable load, psft
At other aisle widths
Slab Working Critical At critical
thickness, stress, aisle width, aisle 6-ft 8-ft 1 0-ft 12-ft 14-ft
in. psi ft" width aisle aisle aisle aisle aisle
Subgrade k=50 pci'
I 300 I 5.6 iI 610 1 615 1 670 1 615 1 1 , 0 5 0 1 1 . 2 1 5
4 I rvin I 58 II 710 I 715 I 785 I 950 I 1.225 I 1.420

i .0 II 900 I 935 I
900 I
8.0 11 1,025 1 1,070 1 1,025 1,065 1 1,175 1 1,350
9.4 II a45 I 930 855I 850 T 885 1 960
94 II
400 9.4 1,130 1.24
300 10.8 915 1.065 955 915 925 965
12 350 10.8 1,065 1.240 1,115 1,070 1,080 1,125
400 10.8 1.220 1.420 1,270 1,220 1,230 1,290
300 12.1 980 1,225 1,070 1,000 980 995
14 350 12.1 1,145 1.430 1,245 1,170 1,145 1,160
400 12.1 1,310 1.630 1,425 1,335 1,310 1,330

k of subgrade; disregard increase in k due to subbase.


Cntlcal aisle width equals 2.209 times radius of relative stiffness. Critical aisle width has maximum negative bending
moment (tenslon In top slab at aisle centerline due to loads on each side of aisle) For other aisle widths, bendmg
moments are not maxlmum
Assumed load width = 300 in.; allowable load vanes only slightly for other load widths. Allowable stress = one-half
flexural strength
tThere I S an explanation m Slab Thckness Des!gn for Industr!al Concrete Floors on Grade from which this table I S
reproduced, for what appear to be anomalous allowable loads
Table 6. Allowable Distrlbuted Loads,
Unjointed Aisle (Nonuniform
Loading, Variable Layout)

Concrete flexural strength, psi


thif$Ls, 1 "Te ~

5 100 760 830 900 965


200 1,075 1,175 1,270 1,370
50 585 640 695 750
6 100 830 905 980 1,055
200 1,175 1.280 1,390 1,495
50 680 740 800 865
8 100 960 1,045 1,135 1,220
200 1,355 1,480 1.603 1,725
50 760 830 895 965
10 100 1,070 1,170 1,265 1,365
200 1,515 1,655 1,790 1,930
50 830 905 980 I.055
12 100 1,175 1.280 1,390 1,495
200 1,660 1.810 1,965 2,115
50 895 980 1,060 1,140
14 100 1.270 1,385 1,500 1.615
Fig. 9. Variable storage area with no restrictions on where
200 1.795 1.960 2.120 2,285
load is placed or on uniformity of loading.
Reproduced from Slab Thickness for lnduslrml Concrete Floors on
Grade. Portland Cement Association publication IS1 950.

k of subgrade: disregard increase in k due to subbase.


For allowable stress equal to one-half flexural strength.
Based on aisle and load widths giving maximum stress

Fig. 10. Exceptionally heavy loads require special


consideration in slab design.

Uncommon Storage Conditions


Unusual and exceptionally heavy loadings require struc-
tural analysis of the slab to determine adequate thickness.
A wide range of unusual design conditions can be fitted
into computer programs that analyze and design founda-
tion mats and combined footings as plates on elastic
foundations or programs that determine flexural stresses
in concrete pavement slabs supported by dense liquid
Fig. 8. Preplanned storage area with uniform loads. subgrades.
Thickness Design Summary allow them to move independently without damage. Iso-
lation joints permit horizontal and vertical movement
The foregoing is a simple and concise approach to the between the abutting faces of the floor slab and other
thickness design of floor slabs supported directly on the parts of the building because there is no keyway, bond, or
ground. It is derived from the wealth ofinformationavaii- mechanical connection across the joint (Fig. I I).
able in highway and airport concrete pavement design Columns on separate footings are isolated from the
practice. Normal design situations can be conservatively floor slab either with a circular- or square-shape isoia-
resolved by this method. Unusual conditions can be anai- tion joint. The square shape should be rotated to align its
yzed by more advanced techniques including the use of comers with control and construction joints, as shown in
computer programs, influence charts, and structural engi- Fig. 12.
neering. But in most situations the method presented here Where traffic will cross isolation joints, provision
can serve as a guideline that has been proved through should be made for adequate load transfer.
practice and the measured observation of results in actual
floors.

JOINTING PRACTICE
Good jointing practice is one way of ensuring crack-free
floors. Most cracks in concrete floors are the result of
three actions: volumetric change due principally to dry-
ing shrinkage, direct stress due to applied loads, and flex-
urai stress due to bending. Cracks can be the net result EXPANSION JOINT MATERIAL
of ail three. Cracks will appear at any time and any place
where the stress within the concrete to pull it apart ex- Fig. 11. Isolation joints are used between the floor slab
ceeds the strength of the concrete to hold itself together. and fixed parts of building such as walls, columns, and
The magnitude of drying shrinkage inconcrete isaffect- machinery bases.
ed by the water content of the mix. More coarse aggregate
and less water mean less shrinkage (thus, less cracking) in
the concrete. Type of cement and cement content have
very little effect on drying shrinkage. The use of an accei-
CONSTRUCTION JOINT
erator admixture containing calcium chloride can in-
crease drying shrinkage significantly. The rate of drying
is influenced by thickness of the slab, humidity and tem-
perature of the surrounding air, and duration of expo- ISOLATION JOINT
sure. Drying shrinkage is an unavoidable, inherent prop-
erty of concrete, so the possibility of cracking exists. Con-
trol measures are taken to induce concrete to crack in pre- CONTROL JOINT
dictable, straight lines by proper jointing.

Kinds of Joints
Building use dictates the joint design and spacing for a
concrete floor on ground. The designer is always con- Fig. 12. Isolation joints around columns are circular or
fronted with the need to eliminate random cracking, so square shaped.
crack control is an important aspect of floor perform-
ance to be included in the floor design. Three kinds of
joints are used: Control Joints
1. Isolation joints (also called expansion joints)-to
allow movement between the floor and other fixed Control joints act to relieve stress and with proper spac-
parts of the building such as columns, wails, and ing they eliminate the cause of uncontrolled random
machinery bases cracking. They allow horizontal movement of the slab.
2. Control joints (also called contraction joints)-to Control joints in industrial and commercial floors are
induce cracking at preselected locations usually cut with a saw. They should be constructed to a
depth of generally one-fourth the slab thickness. In thick
3. Construction joints-to provide stopping places slabs a crack inducer anchored to the subgrade immedi-
during construction ately below the joint can be added to reduce the section.
The objective is to form a plane of weakness in the slab
Isolation Joints
so that the crack will occur along that line and nowhere
Isolation joints are placed wherever complete separation else, as shown in Fig. 13. Load transfer across a control
between the floor and adjoining concrete is needed to joint is provided by the interlocking of the jagged face
formed at the crack. With long joint spacings or heavily
loaded slabs, dowel bars (coated to prevent bond with the
concrete) are used as load transfer devices. Dowel sizes
and spacings are shown in Table 7.

Table 7. Dowel and Tiebar Sizes


and Spacings
- INDUCED CRACK Dowels

SAWED CONTROL JOINT Slab Total


depth, Diameter, length, Spacing,
, PREMOLDED JOINT MATERIAL in. in. in. in. c to c
5 56 12 12
6 # 14 12
7 7% 14 12
6 1 14 12
9 1% 16 12
10 1% 16 12
Tiebars

TONGUE AND GROOVE CONTROL JOINT


1
SAWCUT OR PREMOLDED
INSERT, ALIGN WITH CRACK
CRACK INDUCER , IYDUCER ON SUBGRADE

Construction Joints
Construction joints usually form the edges of each days
work. They are located to conform to the floor jointing
pattern and detailed and constructed to function as and
align with control joints or isolation joints.
Where there is no control or isolation joint, a butt-type
construction joint is satisfactory for thin floors, as shown
A+B=1/4DMIN in Fig. 14. For thicker, more heavily loaded floors, a
CONTROL JOINT IN THICK FLOOR SLABS
tongue-and-groove joint is used or dowels are added to
the butt joint. Whenever continuous concrete placement
will be interrupted for 30 minutes or more, a bonded con-
r PLASTIC OR HARDBOARD
1 PREFORMED STRIP
struction joint should be inserted to avoid the formation
of a cold joint. A bonded construction joint in a plain slab
is a butt-type construction joint with tiebars as shown in
Fig. 14. Tiebar sizes and spacings are shown in Table 7.
Any reinforcement in the slab is conti,vuous through the
bonded construction joint.

Filling Joints
PREMOLDED INSERT CONTROL JOINT
The movement at control joints in a floor is generally very
SMOOTH DOWEL BAR COATED small. For some industrial and commercial uses, these
TO PREVENT BOND T , joints can be left unfilled. Where there are wet conditions,
hygienic and dustcontrol requirements, or considerable
traffic by small, hard-wheeled vehicles such as forklifts,
joint filling is necessary.
In many places, a resilient material such as an elasto-
meric sealant is satisfactory, but to provide support to
the edges and prevent spalling at the joints, a good quality
rigid or semirigid filler with a durometer Shore A-scale
hardness number of approximately 80 should be used.*
CONTROL JOINT WITH DOWELS

Fig. 13. Varieties of control joints. *ASTM Designation: 02240 and D676.
EDGE EACH SIDE EDGE EACH SIDE SMOOTH DOWEL BAR
WITH I 18 IN. RADIUS 7 / PREVENT BOND WITH 118 IN. RADIUS 1 ,COATED TO PREVENT BOND

PREVENT BOND
BUTT-TYPE CONSTRUCTION JOINT BUTT-TYPE CONSTRUCTION
JOINT WITH DOWELS

EDGE EACH SIDE EDGE EACH SIDE


WITH 118 IN. RADIUS PREVENT BOND

D
D

TONGUE AND GROOVE BUTT-TYPE CONSTRUCTION


CONSTRUCTION JOINT JOINT WITH TIE BARS
(NOT A CONTROL JOINT)

Fig. 14. Varieties of construction jolnts.

The A scale is used for measuring the indentation hard-


ness of rubber, soft plastics, and other elastomers. A
hardness number of 80 would be considered as medium
hard. A rubber automobile tire has a hardness of approx-
imately 65. The D scale is designed to measure the hard-
ness of plastics and other semihard or hard materials.
AC1 302, paragraph 4.10, requires a D-hardness number
of 50.
Extruded-lead strips embedded in control joints give
support to the edges and thereby reduce spalling. Lead
strips, where permitted, are highly successful for heavy-
duty concrete floors where trucking is severe, especially 80
of the steel-wheel type.
Isolation and expansion joints are intended to accom-
modate movement, thus a flexible, elastomeric sealant
should be used.

.Joint Layout
A joint layout is illustrated in Fig. 15. Isolation joints are
provided around the perimeter of the floor where itabuts
the walls and around all fixed elements that restrain
movement of the slab in a horizontal plane. This includes
columns and machinery bases that pierce the floor slab.
With the slab isolated from other building elements, the
remaining task is to locate and correctly space control
joints to eliminate random cracking. Construction joints Fig. 15. Typical joint layout for concrete floor on ground
can be located by the floor contractor to accommodate with no reinforcement.
work schedules with the restriction that they coincide (in inches) for concrete made with less than 3%~in.-top-
with the control-joint pattern. Pipe trenches under slabs size coarse aggregate or 21%slab thicknesses for concrete
on ground (Fig. 16) require control joints placed directly containing greater than 3%-in. coarse aggregate. For low-
above each side of the trench. slump concrete, less than 4-in. slump, 3 slab thicknesses
are suitable. Suggested joint spacings are given in Table 8.
CONTROL JOINT

Load Transfer Across Joints


The passage of heavy loads on vehicles with small, hard
wheels over improperly made joints in a warehouse floor
can lead to spalling of joint edges and progressive deteri-
oration of the concrete. The building owner will be faced
with the prospect of expensive repairs that could have
been avoided had more attention been given to joint fill-
ing and to the factors that influence load transfer atjoints.
Load transfer across joints in concrete pavements has
Fig. 16. Pipe trench jointing. been investigated in the laboratories of the Portland Ce-
ment Association (Fig. 17).* Following are summarized
observations from the investigation that are applicable
to industrial floors on ground.
Spacing of Joints Aggregate Interlock
Maximum spacing between joints depends primarily on Load transfer across control joints in slabs on-ground
Slab thickness takes place through the shear developed by interlocking
Shrinkage potential of the concrete aggregate particles, provided there are no dowel bars or
Subgrade friction reinforcing steel running through the joints. The effec-
Curing environment tiveness of load transfer depends on
Absence or presence of distributed reinforcement Joint opening
Slabs made of high-slump concrete improperly cured Slab thickness
in a dry environment, with or without reinforcement, will Subgrade support
shrink excessively and crack extensively. Slabs made of Load magnitude and number of repetitions
low-slump concrete properly cured in a moist environ- Aggregate angularity
ment, with or without reinforcement, will have minimum
shrinkage and few cracks. Jobsite practices are some-
where between these extremes. Local practice and mate-
rials may give satisfactory control of cracking at joint
spacings greater than shown in Table 8. Joint spacing to
eliminate cracking within the panel is not the same as
joint spacing to limit width of the opening at the joint.
The most economical floor construction is a plain (no
reinforcement) concrete slab with short joint spacing sup-
ported by a uniform subgrade. A rule of thumb for plain
slabs constructed with 4- to 6-in.-slump concrete is that
joint spacing (in feet) should not exceed 2 slab thicknesses

Table 8. Suggested Spacing of Control Joints


Slab Less than Larger than Slump
thickness, %-in. aggregate: %-in. aggregate: less than 4 in.:
in. spacing, ft spacing, ft spacing, ft
5 10 13 15 Fig. 17. Laboratory testing device developed to apply
6 12 15 18
repetitive loads of known magnitude in a manner closely
7 14 18 21
8 16 20 24
simulating the action of wheel loads passing over a joint.
9 18 23 27
10 20 25 30

Note Gwen spacings also apply lo the distance from control founts to parallel
lsolatlon founts or to parallel constructlon joints Refer to text for other factors that *B. E. Colley and H. A. Humphrey, Aggregate Inrerlock ar Joints in
may call for different spacmg Spawigs greater than 15 11 show a marked loss In Concrete Pavemenrs. Research Department Bulletin DXl24, Portland
effectweness of aggregate Interlock to prowde load transfer across the lolnt Cement Association, 1967.
Control joints are constructed in slabs on ground to Concrete in service exhibits less drying shrinkage than
relieve tensile stresses caused by drying shrinkage. When laboratory test prisms. Therefore, a reduced shrinkage
properly spaced, they control the location and direction coefficient can be used to calculate joint spacings that will
of cracks. At the plane of weakness produced by the joint, limit the width of joint openings. For example, if the re-
restrained shrinkage forces are relieved by the crack that duced coefficient is 275 millionths, control joints at 10.5
forms below the saw cut (Fig. 18). ft will limit joint openings to 0.035 in. and 7.5 ft will limit
Load transfer across the crack is developed either by openings to 0.025 in. Use a short spacing between joints
the interlocking action of the aggregate particles at the to limit opening width.
fractured faces of the crack (aggregate interlock) or by a
combination of aggregate interlock and mechanical de- influence of Slab Thickness
vices such as dowel bars. When load transfer is effective,
the stresses and deflections in the slab near the joint are Investigation of the effect of slab thickness on load trans-
low and forklift and industrial trucks move smoothly fer demonstrated that a thick slab with wider joint open-
across the joint without damaging it. ings can be equally as effective as a thin slab with narrow
openings. For an effectiveness of 60%, the openings in
joints of 7- and 9-in.-thick slabs were 0.025 and 0.035 in.,
respectively.

influence of Subgrade Support


While it is true that concrete floors on ground do not
necessarily require strong support from the subgrade to
successfully carry design loads, strong support from the
subgrade (as measured by k value) will increase joint ef-
fectiveness. Silts and clays have low support values, that
is, k = 50 to 100 pci, and hasten the loss of aggregate inter-
lock effectiveness afteronlya few repetitive loading cycles.
Sandy soils with midrange support values of k = 200 pci
can keep joint effectiveness at an acceptable percentage
limit of 50% through one million load cycles. Sand-gravel
and cement-treated subbases with high support values, k
= 300 pci and higher, keep aggregate interlock effective-
ness at high percentages through one million load cycles.

influence of Load Magnitude


Fig. 18. Irregular faces of crack that forms below sawed
control joint provide adequate aggregate interlock for Light loads of 5000 lb or less usually cause little or no
load transfer when short joint spacings are used. joint deterioration and probably do not need to be con-
sidered. Significant differences in aggregate interlock
effectiveness, however, develop under repetitive heavy
loads. Effectiveness decreases as the magnitude of load
increases. Joints that successfully provide load transfer
Load Transfer Effectiveness for one load condition may break down under a new,
Joint effectiveness is measured as a percentage of the heavier load condition.
ability of the joint to transfer load from the loaded slab
to the unloaded slab. If load transfer at a joint were per- influence of Aggregate Shape
fect, the deflections of the loaded and unloaded slabs Aggregate interlock is more effective in load transfer
would be equal and the effectiveness would be 100% If, when the aggregate is crushed gravel or crushed stone
however, there was no load transfer at a joint, only the rather than natural gravel. The higher effectiveness is
loaded slab would deflect and the effectiveness would be attributed to the angularity of the coarse crushed aggre-
zero. gate particles.
influence of Joint Opening
The opening of a control joint depends primarily on the How to improve Load Transfer Across Joints
environment and on the spacing between joints. Load The ability of a joint to effectively transfer repetitious
transfer effectiveness was determined in the PCA labora- loading will be improved by
tory for joint openings ranging from 0.015 to 0.085 in.
Effectiveness decreased as the joint opening became Keeping a small joint opening, 0.035 in.
wider. An opening of 0.035 in. or less showed good load Increasing the slab thickness
transfer effectiveness and endurance. Larger joint open- Strengthening the subgrade support
ings were less effective at transferring load. Joint open- Using an angular coarse aggregate
ings of 0.025 in. were almost 100% effective. Using dowel bars
Doweled Control Joints apart-more than 15 ft- to gain much benefit from ag-
gregate interlock. Load transfer at these joints can be
In most industrial and commercial floors on ground, two enhanced by using dowels (see Fig. 19).
mechanisms are used to help transfer moving loads across The integrity and serviceability of intermediate ran-
joints: keyways and dowels. dom cracks that may occur between control joints is en-
A keyed joint is made by attaching a beveled strip of sured by the distributed steel in reinforced slabs. But the
wood, or a preformed key, to the bulkhead against which distributed steel must be properly sized, located 2 in.
the slab is cast. The depression left in the edge of the slab below the slab surface, and discontinued at all control
after the bulkhead is stripped is coated with bondbreaker joints in order to keep intermediate cracks tightly closed
and then filled with concrete when the next slab is placed, and ensure aggregate interlock for effective load transfer
thus, in theory, keying the slabs together. But in practice at the cracks.
a keyed joint does not always remain tight. As the floor Since dowels are designed to slip, permitting slab move-
slabs shorten due to drying shrinkage, the key loses con- ment at the joints, they must be accurately aligned parallel
tact with its matching recess. Then as loads roll over the to the floor surface and the centerline of the slab.
joint, the slab edges deflect. This loss of load transfer is
an inherent weakness of keyed joints, especially in heavily
loaded floors.
The other method of load transfer-steel dowels- REINFORCEMENT FOR
seems to work better. The dowels continue to distribute FLOORS ON GROUND
the load after the slabs shrink and pull apart. As noted
previously, control joints that open wider than 0.035 in. Is reinforcement necessary?
are less than 100% effective at transferring wheel loads
across the joints in a concrete floor. However, dowels can . WITH UNIFORM SUPPORT AND SHORT
be used to supplement the load transfer produced by ag- NO JOINT SPACING
gregate interlock.
Placed at middepth in the slab, dowels resist shear as . WHEN LONG JOINT SPACING IS
loads cross the joint and thus help to reduce deflections YES REQUIRED
l WHEN JOINTS ARE UNACCEPTABLE IN
and stresses at the joint. Dowels should be smooth round FLOOR USE
steel bars conforming to ASTM A615. Recommended
dowel dimensions and spacing are in Table 7.
Dowels should be free to move longitudinally in their
slots to accommodate joint movements due to expansion When a long joint spacing is selected to minimize the
or contraction of the concrete slab. Accordingly, before number of joints (shrinkage cracks may occur within the
delivery to the jobsite, at least one-half of each dowel bar panel) or when joints are unacceptable in floor use, then
should be coated with a bondbreaking substance such as distributed-steel reinforcement is placed in the slab.
one coat of lead or tar paint. If this is not done, lubricants The primary purpose of reinforcement in a slab on
must be applied in the field to reduce friction. Plastic grade is to hold tightly closed any cracks that may occur
dowel sleeves may be used instead of coating. between the joints so that aggregate interlock can func-
tion. It does not prevent cracking nor does it increase sig-
Dowels in Relnforced Slabs nificantly the load-carrying capacity of the floor. Since
critical flexural stresses occur in the top as well as the bot-
In floor slabs reinforced with distributed steel for crack tom of concrete floors, the steel would have to be placed
control, the control joints are usually spaced too far in two layers to resist the stresses. To illustrate, if the rela-
tively small amount of reinforcement normally used in
floor slabs could be placed near both the top and bottom
of the slab, in a 6-in. slab the load-carryingcapacity would
be increased by approximately 3%.
INTERMEDIATE The amount of steel reinforcement needed can be de-
CRACKS
termined by the traditional subgradedrag method as in
pavement design. This method provides sufficient steel
area to resist the tensile stress carried by the steel across
, cracks that develop as a result of subgrade restraint to
slab movement. The formula to determine the amount of
SAW M TO /!a IN. steel per linear foot is
WIDE, D/4 DEEP
1
/, - FLw
I ?C

FILL JOINT WITH SEALANT HAVING MINIMUM


in which
SHORE A HARDNESS OF 80 (ASTM 02240) A, = cross-sectional area of steel, in square inches per
linear foot of slab.
F = coefficient of subgrade friction. (Designers use
1.5 or 2.0 for pavements; 1.5 is recommended for
Fig. 19. Reinforced (mesh-dowel design) floor slab. concrete floors on ground.)
L = s!ab length (or width if appropriate) between free 2. Concrete made, with expansive cement can be used
ends, in feet. (A free end is any joint free to move to offset the amount of drying shrinkage to be antici-
in a horizontal plane.) pated after curing. Control joints are not needed
w = weight.of slab, in pounds per square foot. (For when construction joints are used at intervals of 40
regular weight concrete, designers use 12.5 to 120 ft. Large areas, to 20,000 sq ft, have been cast
pounds per inch of floor thickness.) in this manner without joints.
fs = allowable working stress of reinforcement, in 3. Large areas can be cast without control joints when
pounds per square inch. (The working stress of the amount of distributed steel is about one-half of
steel is usually 0.67 or 0.75 times the yield strength 1% of the cross-sectional area of the slab. Special
of the steel in pounds per square inch.) effort should also be made to reduce subgrade fric-
The values shown in Fig. 20 were calculated by the sub- tion in floors without control joints.
grade-drag method. A value of 0.75 of the yield strength
was used because the consequences of a reinforcement
failure are much less important than in normal reinforced
concrete structural work.

Welded wire fabric


or
Steel bar mat CONSTRUCTION
with yield strength
of reinforcement Workmanship
exceeding 60,000 PSI
All parties-owner, designer, contractor-must agree
A, , SQ IN./FT when f, = 45,OOOPSI prior to bidding on the level of quality or class of work-
0.18 manship that will be necessary for the floorjob they want.
A good concrete floor on ground is the result of sensible
planning, careful design and detailing, complete specifi-
0.16
cations, proper inspection, good workmanship, and the
good intentions of each person sharing responsibility for
the end result.

Subgrades
Good construction begins with a well-prepared subgrade.
Many floor problems can be traced to poor subgrade
preparation. A poorly compacted and prepared subgrade
006 ranks high as a cause of settlement cracking and failure
to carry the applied loads.
The subgrade should be uniform, firm, and free from
0.04 all sod, grass, humus, and other rich organic matter as
these materials will not compact to give good support to
0.02 the floor. Subgrade support should be reasonably uni-
form with no abrupt changes from hard to soft spots with-
01 in the floor area. To construct a reasonably uniform sub-
20 30 40 50 60 70
grade, special care must be taken to ensure that there is
DISTANCE IN FEET BETWEEN FREE ENDS control of the three major causes of nonuniform support:
(1) expansive soils, (2) hard spots and soft spots, and (3)
Fig. 20. Selection chart for distributed steel. backfilling.
The subgrade must be brought to within required toler-
ances at the specified grade and level. The use of laser
UNJOINTED FLOORS alignment tools to control grading operations will make
the surface as level as possible; or a scratch templet can
An unjointed floor can be constructed when joints are be used to reveal high and low spots. Occasionally a chok-
unacceptable. Three methods are suggested: er fill should be added to bind the surface before final
1. A prestressed floor can be built through use of post- compaction with a vibratory roller, heavy-plate vibrator,
tensioning, a method in which steel strandsarepulled or a tandem roller. A reasonably accurate, level subgrade
taut after the concrete hardens to put a compressive will ensure that the correct thickness of concrete is placed.
stress in the concrete. This will counteract the devel- If the surface is too uneven, concrete will be wasted and
opment of tensile stresses and provide a crack-free the potential for random cracking will be increased. The
surface. Large areas, 10,000 sq ft and more, can be subgrade should be moist when concrete placement be-
constructed in this manner without joints. gins (Fig. 21).
Fig. 21. Subgrade must be moist when concrete is placed.

Expansive Soils in the surrounding area. The moisture content and den-
sity of the replacement soil should be as similar as pos-
Excessive differential shrinkage and swelling of expan- sible to the adjacent soils. At the edges of the area, the re-
sive soils causes heaving in the subgrade and creates non- placement soil should be intermixed with in-place soil to
uniform support. As a result, the floor slab may become form a gradual transition zone.
distorted and crack. Compaction of highly expansive soil
when it is too dry can lead to detrimental expansion and Backfilling
softening of the subgrade as it takes on moisture with
time. If an expansive-soil subgrade is too wet when the Backfilling at footings, foundations, and utility trenches
slab is cast, subsequent drying and shrinkage of the soil should consist of soils like those surrounding the trench
can cause settlement and leave the slabedges unsupported and should be compacted or consolidated in moderate
and likely to crack under appiied loads. layers. Every attempt should be made to restore as much
Selective grading, crosshauling, and mixing of sub- as possible the original uniformity of the subgrade.
grade, soils make it possible to obtain uniform conditions
in the upper part of the subgrade. Compaction at 1% to
3% above standard optimum moisture* minimizes sub- Subbase or Cushion
grade weakening due to changes in moisture content and
gives it relatively uniform stability. Placement of a dense- A satisfactory floor on ground can be built without a sub-
ly graded blanketing layer (subbase or cushion) on the base, but a subbase is frequently used as a leveling course
subgrade will minimize changes in the moisture content for fine grading and a cushion that will equalize minor
of the subgrade and provide a stable working platform surface irregularities and contribute to uniform support.
for floor construction. It also serves as a capillary break between the floor slab
and a subgrade that is water soaked most of the time.
Where a subbase is used, the floor contractor should
Hard Spots and Soft Spots place a 4-in.-thick layer of material. The subbase should
To prevent bending and cracking of the slab from sub-
grade settlement or riding on hard spotsand bridging over
soft pockets, special care must be taken to dig out hard
and soft spots and backfill them with soils similar to those *ASTM Designation: D698
be fine-graded and compacted to maximum density im- sulation is needed only at the perimeters of the slab. This
mediately before placing concrete. Unless the subbase is practice is recommended by Model Code for EnergyCon-
well compacted, it is better to leave the subgrade uncov- servation** and other major codes and standards.
ered and undisturbed. Subgrades and subbases can be
compacted with small portable vibrators and rollers.
Hand tampers can be used in confined places. On large Slab thickness Tolerances
floor projects, compaction equipment similar to that used
in highway or airport construction can be used. Acceptable thickness tolerances for slab-on-ground con-
struction as stated in AC1 117, Standard Tolerances for
Concrete Construction and Materials (Section 2.1.5), are
+3/8 in. and --i/4 in. for slabs with cross sections up to 12 in.
thick and +A in. and -% in. for slabs of more than 12-in.
Vapor Barrier thickness.
Many of the moisture problems associated with floors on
ground can be minimized or eliminated by proper prelim- Finishing Concrete Floors
inary grading, correct selection of fill or subbase mate-
rials, and installation of a vapor barrier. Finishing concrete floors never should be done by inex-
A vaporproof barrier should be placed under all con- perienced, unskilled workers. Finishing is a critical task
crete floors on ground that are likely to receive an imper- that for best results requires the work of skilled cement
meable floor finish or used for any purpose where the masons. Two stages are usually required in producing a
passage of water vapor through the floor is undesirable. finished surface: (1) placing, compaction, and truing (to
Good quality, well-consolidated concrete at least 4 in. a rather rough surface) of the struck-off or screeded sur-
thick is impermeable to the passage of liquid water from face by the use of a hand or power-driven float; and (2)
the ground unless the water is under considerable pres- the final compaction and smoothing (to a tine texture)
sure; but concrete several times that thick is not imper- by steel-troweling with a hand or power-driven trowel.
meable to the slow passage of water vapor. If a coarse texture is desired, the steel-troweling may be
Water vapor normally passes through the concrete and omitted. A very fine grained (nonslip) swirl finish can be
evaporates at the top surface if it is not sealed. Floor cov- attained by light troweling; a very smooth hard finish is
erings such as linoleum, felt- or fabric-backed composi- the result of repeated troweling.
tions, cork tile, carpet, wood, and synthetic surfacing There are three basic finishes for a concrete slab sur-
effectively seal the moisture within the slab where it even- face: screeded, floated, and troweled.
tually may cause problems with the covering. When fur- A screeded finish is the result obtained when the sur-
niture, boxes, pallets, and other objects are placed on a plus concrete is removed immediately after consolidation
floor lacking a vapor barrier, moisture can condense be- by striking off with a straightedge or templet across edge
neath them, causing dampness and mildew. forms or screeds set as guides. There are instances in
Vapor-barrier materials with a permeance of less than building where a screeded finish is all that is needed.
0.30 perms are suitable for floor-on-ground construction. A floated finish is normal for outdoor slab surfaces.
Acceptable materials are available in preformed sheets Floating follows screeding and should not be done until
or mastics that will resist deterioration and punctures some stiffening has taken place and the water sheen has
from subsequent construction operations. disappeared. Floating should work the concrete no more
Vapor-barrier material placed directly under the slab than necessary to produce a surface that is level, uniform
also functions as a slipsheet to reduce subgrade drag fric- in texture, and free of foot and screed marks. If a troweled
tion, permitting freer slab movement and reducingcrack- or broomed finish is to be applied, floating should leave
ing in the slab. It will prevent the loss of mixing water a small amount of mortar, without excess water, on the
down into the subgrade and, therefore, requires a com- surface to permit effective troweling or brooming.
pensating adjustment in the mix design. A troweled finish is used on inside floor slabs. Trowel-
A vapor barrier may contribute to the slabs upward ing should not be done until after the moisture film and
warping (curling). A layer of sand below the slab will al- sheen have disappeared from the floated surface and the
low some moisture loss at the bottom of the slab. When a concrete has hardened enough to prevent an excess of fine
vapor barrier is used, a 3-in-thick layer of sand should material and water from being worked to the surface.
be placed over the vapor barrier to prevent or minimize Steel-troweling is performed with a firm pressure that
warping. The sand layer also protects the vapor barrier will close the open, sandy surface left by floating into a
from puncture during construction operations. hard, dense, uniform surface free of blemishes, ripples,
and trowel marks.
A hard steel-troweled (burnished) finish is a special Iin-
Insulation Under Slabs ish that provides added resistance to abrasion and wear.
After the first troweling the surface is troweled again (and
Placing insulation under slabs on ground to conserve
energy cannot be justified. Tests by the National Bureau
of Standards* proved the temperature of the slab aver-
ages only 5O F to 6 F below room temperature to within *BMS Report 103, 1945.
24 in. of an outside wall. In cold climates, therefore, in- **U.S. Department of Energy, December 1977.
again) until it has a somewhat polished (glossy) look. function properly for crack control, some failproof way
A fine-textured, swirl finish that is not slick can be ob- must be used to hold it in that position. Reinforcement
tained by retroweling the surface with the trowel held flat can be supported on chairs, slab bolsters, or small con-
and moved in a circular motion immediately after the crete bricks and blocks. Support accessories for wire
first regular troweling. mesh must be more closely spaced than for reinforcing
A steel-troweled floor has increased strength near the bars. The practice of laying the mesh on the subbase or
surface and therefore greater wear resistance. Steel trow- subgrade before concrete is placed and hooking it up into
eling helps the cosmetic appearance and provides a sur- position after concrete has been placed is not recommend-
face that is easier to clean. ed because this gives no assurance that the mesh will stay
Industrial and commercial floor slabs should have a in the concrete in straight lengths or on a true plane at the
troweled finish. There are no compelling reasons to trow- correct distance below the surface.
el finish an outdoor slab. If a light broom finish is wanted, Flat-sheet mesh can be placed by the sandwich method
broom the surface after troweling it. If a rough broom in two-course work. This involves first placing a layer of
finish is desired, rough broom over a floated finish. concrete struck off 2 in. below the finished grade. The
mesh is laid on this layer and then the top 2-in. layer of
concrete is placed. Work must be completed quickly so
Concreting Procedures that the top layer is placed while the bottom is still plastic.
Flat-sheet fabric can be depressed into the slab by what
Floors cast under the protective cover of a tight roof with is termed walking in. The concrete is placed full depth
the building sidewalls in place are apt to be better con- and struck off. The flat sheet is then placed on the surface
structed than floors cast out of doors. Outside work can and the finishing crew carefully walks on it, forcing it into
be adversely affected by the weather (sun, heat, cold, the concrete. Accurate positioning of the steel fabric is
wind, and rain) and have a greater risk of future problems difficult with this method.
such as cracking, crazing, curling, and surface dusting. Wherever dowels or tiebars are placed in joints, they
The semimanual methods recommended here for plac- must be accurately aligned and spaced and held parallel
ing, consolidating, and finishing concrete floors require to the surface during concreting.
the use of mechanical equipment for striking off, com-
pacting, and finishing. Placing and Spreading
Rutted or marred subgrade or subbase surfaces must be
regraded and recompacted before placing concrete. There
Edge Forms are several ways to place fresh concrete where it is needed,
The surface-finish tolerance of the floor slab depends on including directly from a truck mixers chute, by buggy
careful setting of the edge forms and temporary inter- on wooden ramps, by crane with bucket, by conveyor
mediate screed guides with the use of a leveling device. belt, or by pump.* Concrete should be placed continu-
Edge forms and screed guides must be supported firmly ously as closely as possible to its final position and slightly
by wood or steel stakes driven solidly into the ground to above the top of the edge forms or screed guides. It is then
prevent any movement during mechanical strikeoff and spread with shovels, special concrete rakes, or come-
consolidation. Loose edge forms cause uneven floors. alongs. Air is trapped in the concrete during mixing and
Temporary screed guides that are not positively posi- placing, and this air must be removed by consolidation.
tioned can be displaced, causing uneven floors. All forms
should be straight, free from warping, and of sufficient Striking Off and Consolidating
strength to resist concrete pressure without bulging. Edge
forms should be full slab depth and continuously sup- Concrete is brought to its initial level and surface by the
ported on the compacted subgrade or subbase; for this first operations of strikeoff, consolidation, and darbying
reason steel road-type forms are preferred. Vibratory or bullfloating. Striking off is best done with mechanical
strikeoff and compaction equipment slides easily on a equipment riding on the side forms (Figs. 22,23, and 24).
steel surface. A form release agent must be applied to the Where surface tolerance is important, the strikeoff lane
forms before concreting for easier form removal. width should be limited to 20 to 24 ft. The limited width
When a continuous vapor barrier is required under the makes it possible to bullfloat and use a crossrod or
floor slab, special care is needed to place the barrier sheet straightedge more accurately.
correctly under the edge forms before the pins are driven. Surface vibration is recommended for slabs of up to 8-
in. thickness. When floors contain heavy reinforcement
and conduit or when they are thicker, internal spud vibra-
tors must also be used, or the slab should be placed in
Positioning Reinforcing Steel layers while the concrete remains plastic. When a thick
Reinforcing bars or welded-wire fabric (wire mesh) are slab has been compacted by internal vibrators, final com-
used in floor slabs for crack control. In order for rein- paction of the surface should be done with a beam- or
forcing bars or mesh to bond properly with the concrete,
they should be free of mud, oil, or other coatings that
would adversely affect the bonding capacity. The rein-
forcement should be placed at or above the center of the *See Transporring and Handling Concrete, Portland Cement Asso-
slab-2 in. below the surface is suggested-and if it is to ciation publication IS178T. 1974.
Fig. 22. Strikeoff can be done with a double-beam Fig. 24. After strikeoff with vibratory equipment, the
vibratory screed. surface may be ready for finishing without darbying or
bullfloating.

Crete, the surface will be ready for edging and finishing


with power floats and trowels with very little handwork
necessary.

Leveling
Bullfloating to bring the surface to the specified level
(Fig. 25) should immediately follow screeding and must
be completed before any bleed water is present on the sur-
face. Any finishing operation performed while there is
excess moisture or bleed water on the surface can cause
surface defects. This is the basic rule of concrete finishing
and it cannot be overemphasized. One of the purposes of
the bullfloat is to eliminate ridges and fill in surface voids
left by striking off and consolidating. In addition, it
should slightly embed the coarse aggregate. This prepares
the surface for subsequent edging, floating, jointing, and
troweling.
Darbying is done for the same reason as bullfloating,
that is, to correct small irregularities and smooth out
ridges left by striking off (Fig. 26). Because of its long
Fig. 23. A roller screed can be used to strike off and level handle, the bullfloat is easy to use on a large area, but the
the concrete. length of the handle detracts from the leverage, so that
close tolerances are difficult to achieve. The bullfloat may
slightly depress the surface near an edge form and a darby
truss-type surface vibrator. The initial strikeoff and con- must then be used to relevel the surface.
solidation of the concrete will have a greater effect on sur- Where close tolerancesare required, a scraping straight-
face tolerances and levels than subsequent operations of edge can be used to advantage. Minor surface irregulari-
floating and finishing. The secret of proper strikeoff and ties and excess laitance are removed by scraping with a
compaction is to maintain an adequate surcharge of con- IO-ft straightedge (Fig. 27). It should be used with a
crete at the screed face; a Gin.-thick slab needs a surcharge smooth, continuous action to float the surface; a jerky,
of about 1 in. cutting action is used only for removing high spots. Each
Strikeoff and consolidation must be completed before pass should overlap one-half the length of the previous
any excess water bleeds to the surface. If power-driven pass. Surface smoothness should be checked as late in the
equipment is used properly to strike off low-slump con- finishing operations as possible but while the concrete is
Fig. 25. Bullfloating corrects small irregularities and Fig. 27. A scraping straightedge removes minor surface
smooths out ridges. irregularities and excess laitance.

Fig. 26. Darbying brings the surface to the specified level.

still plastic enough to permit surface corrections. Testing


is done by lifting and lowering a checking straightedge in Fig. 26. Floating is begun when the water sheen has
successive positions. disappeared and the weight of a person leaves only a
A slight stiffening of the concrete is necessary before slight indentation on the concrete surface.
proceeding with finishing operations. Depending on job
conditions, it is usually necessary to wait for a time. No
operation should follow until the concrete will sustain
foot pressure with only about /4-m. indentation (Fig. 28). bleed water has left or been removed from the surface.
Before running the edger, the concrete should be cut away
Edging
from the forms with a pointed masons trowel or margin
Edging may be required along isolation and construction trowel (Fig. 29). An alternative to using an edging tool
joints. The purpose is to densify the concrete at the edge at construction joints is to lightly grind the edges with a
of the slab, making it more durable and less vulnerable to silicon carbide stone after the forms are stripped and be-
spalling and chipping. Edging should be done when all fore the adjacent slab is placed.
when the concrete will support the weight of a person
(leaving a footprint with only a slight indentation on the
surface), and when mortar is not thrown by the rotating
blades, the concrete is ready to be floated (Fig. 28). Float-
ing should start along walls and around columns and then
move systematically across the surface, leaving a matte
finish.
Marks left by the edger should be removed by floating.
During the interval between power-floating and the first
power-troweling, a steel hand trowel should be used along
the edges to give an improved surface and keep the con-
crete level with the side forms.

Jointing
While the edging is being done, or immediately after, the
control joints should be made unless they are to be sawed.
Jointing is a most important finishing step since proper
jointing can eliminate unsightly random cracks.
a Control joints can be made with a hand groover, a pre-
formed insert, or a power saw. The joint should extend
into the slab one-fourth of the slab thickness. A cut this
deep weakens the slab and induces a crack to form be-
neath the joint where it is inconspicuous.
There are few instances in industrial and commercial
floor work when a hand groover is used to make joints,
however when used its thin bit must be deep enough to
cut the slab one-fourth of the depth. An alternative is to
press a preformed insert into the fresh concrete until the
top is flush with the surface; finishing operations can then
continue.
On large floors it is more convenient to cut joints with
a power saw fitted with an abrasive or diamond blade
(Fig. 30). Again, saw cuts must be one-fourth the slab

Fig. 29. Edging densifies the concrete at the edge of the


slab: (a) cutting away with a margin trowel, (b) running
the edger.

Floating
Floating has four purposes: ( 1) to depress large aggregates
to just slightly beneath the surface; (2) to remove slight
imperfections and even out humps and voids for a level or
plane surface; (3) to compact the mortar at the surface in
preparation for later finishing operations; and (4) to keep
the surface open so excess moisture can escape.
Floating the stiffened concrete is done by machine.
Either a power float with rotating steel disc or a troweling
machine equipped with float blades is used almost flat on
the surface. Changes in concrete temperature, air temper-
ature, relative humidity, and wind make it difficult to set
a definite time to begin floating. In cold weather, it might Fig. 30. Control joints can be made by a power saw. These
be 3 hours; in hot weather, the concrete may stiffen very joints induce straight-line cracking at predetermined
rapidly. However, when the water sheen has disappeared, locations.
thickness. Sawing usually begins as soon as the surface of the wearing surface. When done correctly, curing re-
is firm enough so that it will not be tom or damaged by duces the risk of cracking, crazing, curling, and dusting.
the blade, usually within 4 to 12 hours after the concrete The purpose of curing is to maintain favorable condi-
hardens. tions under which concrete hardens and continues to gain
The method of constructing control joints must relate strength and wear-resistance by keeping it moist and
to the service use of the floor. Wide joints and inserts, for warm for a fixed period of time. A concrete floor slab has
example, may perform poorly under small hard wheels. a large exposed surface area in relation to its volume. This
means that water will evaporate very quickly from an un-
Troweling protected surface causing early drying and leavinga weak,
cracked, crazed, dusting floor. Prompt and adequate cur-
A power trowel is like a power float except that it is fitted ing, therefore, is mandatory. The slab should be continu-
with smaller, individual steel-trowel blades that can be ously moist-cured for at least 7 days. A longer period is
tilted slightly to exert pressure on the surface. Generally, desirable.
greater tilt will produce a smoother, more dense, bur-
nished slab surface. Three alternate methods of curing are suggested:
Power-troweling should start when the excess moisture 1. Wet-cure by fully covering the surface with wet bur-
brought to the surface by initial power-floating has evap- lap as soon as it can be placed without marking the
orated and the concrete is not sticky (Fig. 3 1). The wait- surface (Fig. 32). Keep the burlap continuously wet
ing time between floating and troweling depends upon and in place as long as possible.
the absence or presence of an admixture in the concrete
and the atmospheric condition at the surface.

Fig. 32. One method of wet-curing is to completely cover


Fig. 31. Power troweling is begun when excess moisture the surface with wet burlap, keeping it continuously wet
brought to the surface by floating has evaporated and the during the curing period.
concrete is not sticky. Two or more passes frequently are
required.

Power-troweling should be done in a systematic pat- 2. Wet-cure by fully covering the previously wetted
tern. Two or more passes frequently are required to in- surface with plastic sheeting or waterproof paper as
crease the compaction of fines at the surface and give soon as it can be placed without marking the surface
greater resistance to wear. Time must be allowed between (Fig. 33), and keep in place as long as possible.
each troweling for the concrete to stiffen and the water 3. Seal the slab surface and edges by spraying a liquid-
sheen to disappear. The tilt of the trowel blades should membrane-forming curing compound on the fin-
be increased with each pass to exert additional pressure ished surface. The curing compound should be a
as the concrete hardens. Each successive troweling should type that leaves no permanent discoloration on the
be made in a direction at right angles to the previous pass. surface and does not interfere with the application
of any subsequent surface treatment or overlay.
A combination of these methods can be used. For ex-
Curing ample, a cover of burlap, plastic, or paper can be kept on
for 5 days and then a liquid-membrane-forming curing
Curing the concrete has a significant influence on the compound can be applied so that the concrete will dry out
strength, wear resistance, final quality, and performance slowly and extend the period of curing.
large open areas, A in. from end to end and side to side
can be tolerated. In other words, the entire floor surface
would fall within a plane of + 1% in. from the datum floor
elevation shown on the building plans. The tolerance
across a joint should be A2 in. Surface irregularities can
be measured with a profilograph floorcontour-measur-
ing instrument. The instrument can be used to monitor
placing and finishing techniques on a day-today basis.
High-density industrial warehouses using high-rise-
storage racks and high-lift-turret trucks require especially
flat floor surfaces for efficient operation. Knownas super-
flat floors, the differences in elevation of the surface of
these slabs must be minimal over distances of from as
little as 12 in. to as much as 10 ft, often a maximum of %2
in. in the former and /8 in. in the latter. Since construction
of such closely toleranced floors can be expensive, the
exact requirements for a project must be established
through consultation between the handling equipment
manufacturer, owner, and specifier, and then clearly out-
lined in the job specifications along with the method of
measurement as well as corrective techniques (usually
grinding) to bring an out-of-tolerance area back to a sat-
Fig. 33. Wet-curing can also be done by covering the isfactory degree of flatness.
previously wetted surface with plastic sheeting for as long
a period as possible.

When moist-curing is completed, the concrete should


not be subjected to forced or rapid drying out. Drying out
should be a long, slow process. SPECIAL FINISHES FOR
The surface of a newly completed floor slab should be CONCRETE FLOOR SLABS
protected. Subsequent construction activities must not
be allowed to damage the surface through neglect and A variety of methods and proprietary products are avail-
carelessness. These rules should be followed: able that will, in specific instances, improve wear resist-
ance or chemical resistance, reduce dusting, or improve
1. Keep foot traffic off for 1 day. the appearance and ease of maintenance of concrete
2. Keep light, rubber-tired vehicles off for 7 days. floors.
3. Leave plastic or waterproof-paper curing sheets in The finish and the method of obtaining it depend largely
place as long as possible. on how the floor is to be used. Manufacturers directions
4. Protect the surface with sheets of hard board where should be closely followed, but first the floor surface
heavy traffic is expected. must be of good quality before treatment, otherwise the
benefits will be short lived.

Acceptable Surface Tolerances Dry-Shake Flnlshes


AC1 302, Guide for Concrete Floor and Slab Construc- Wear resistance can be improved for light-to-medium-
tion, gives four classes of surface finish tolerances: wear floors or heavy-wear floors by embedding into the
Class AA Surface Finish Tolerance. Depressions in concrete surface a selected natural or metallic aggregate,
floors between high spots shall not be greater than / in. usually blended with portland cement. The procedure
below a IO-ft-long straightedge. can be as follows. For light-to-medium wear, after float-
Class AX Swface Finish Tolerance. Depressions in ing the surface, apply half of the shake quantity and float
floors between high spots shall not be greater than 3/16 in. it in. Wait for the concrete to set hard enough to resist a
below a IO-ft-long straightedge. heel imprint, then apply the remainder of the shake and
Class BX Surface Finish Tolerance. Depressions in power steel trowel the surface.
floors between high spots shall not be greater than 716 in. For heavy-wear floors, apply one-third of the shake
below a IO-ft-long straightedge. quantity immediately after strikeoff. Wait for bleed water
Class CX Surface Finish Tolerance. Depressions in to disappear, then apply the second third of the shake and
floors between high spots shall not be greater than 1% in. float it in. Wait for theconcrete to partially harden enough
below a IO-ft-long straightedge. to resist a heel imprint, then apply the remaining shake
When an especially flat, smooth floor is required (at material and power steel trowel to a dense, hard surface.
increased cost), limits can be set for deviations from Shake finishes require special skills and should be en-
datum and tolerances across joints. For example, for trusted only to experienced craftsmen.
provided (if any). Isolation joints in the base slab, how-
High-Strength-Concrete Toppings ever, should be extended up through the topping.
Where close tolerances are needed or abrasive conditions
require concrete of exceptionally high strength, it be-
comes economic to apply a deferred concrete topping. Vacuum Dewatering
Toppings are put in place before the base slab hardens Vacuum dewatering of the floor slab immediately after
(monolithic) or after hardening (separate). placing and compaction is a method of reducing water
content in the concrete. The process quickly prepares the
Monolithic Toppings surface for final finishing and can reduce shrinkage of the
The thinnest topping can be used, between r/fi in. to 1 in., concrete, increase compressive strength, and improve the
consequently the base concrete slab should be placed and wear resistance of the slab surface.
compacted to leave the surface below the finished level by A vacuum system consists basically of a plastic-sheet
this amount. The topping concrete then is placed and top cover and a bottom filter cloth of nylon netting that
vibrated while the base remains plastic. In this way the are placed over the fresh concrete immediately after strik-
topping becomes part of the structural thickness of the ing off and leveling. The top sheet is fitted with suction
slab. Construction procedures, panel sizes, joints, and channels leading to a single vent connected to the vacuum
jointing arrangements are the same as those specified for generating unit. The system is claimed so effective that
the slab itself. water is drawn out of the concrete down to a depth of
about 10 in. at an extraction rate of about 21% minutes for
Separate Bonded Toppings* each 1 in. of slab thickness.

Separate bonded toppings 3/, to 1 $5 in. thick** are applied


after the base structural slab has hardened. A fully bond- Surface Grinding
ed topping is considered a part of the structural thickness
of the floor because the base slab and the topping act to- Surface grinding is a technique that claims to eliminate
gether as a monolithic slab. Thickness is based on the dusting of the floor surface due to laitance brought to the
flexural strength of the base slab. Being thin, these top- surface by the troweling. The concrete is placed, com-
pings have little load-carrying capacity of their own and pacted, and brought to as true a surface as possible by
their satisfactory performance depends upon their being bullfloating and a scraping straightedge. Instead of fur-
fully bonded to the base slab. The slab must be roughened ther finishing in the usual way, thesurface is immediately
with the coarse aggregate exposed, blown clean of dust covered with polyethylene sheets and cured for 36 to 48
and debris, and dampened. Immediately before the top- hours. The sheets are then removed and theentire surface
ping concrete is placed, a 1: 1 cement-sand slurry or a neat is ground with a special machine. The low-speed grinding
cement paste, each of a creamy consistency, should be action removes all laitance, leaving a smooth, hard, dur-
brushed into the surface. The topping must be placed be- able surface. For best results, highquality concrete must
fore the slurry dries out. be used.
High-strength-concrete-topping mixes (monolithic or
bonded) should be made with special aggregates selected
for hardness, surface texture, and particle shape that will Sealing Concrete Floors
produce concrete with a hard, wear-resistant finish.
These toppings should have high strength, low shrink- Floor sealing products are not floor finishes, but are men-
age, and finished surfaces that are resistant to abrasion tioned here since they are a means of upgrading a floors
and not slippery-properties achieved by limiting the wear resistance, reducing dusting, and improving chemi-
aggregate-cement ratio and the type of aggregateselected. cal resistance. Sealer products normally used are based
A water-cement ratio of 0.40 (by weight) or less, an aggre- on sodium silicate or a type of silicofluoride. It is impor-
gate-cement ratio of 3 (by weight), and goodquality tant to note that these products will not convert a poor-
coarse aggregate with a natural sand have proved to be quality floor into a goodquality floor.
suitable.

Separate Unbonded Toppings* Sodium Silicate (Water Glass)


Unbonded toppings are used when the existing floor slab The cement hydration reaction that takes place during
is cracked or otherwise not suitable to receive a fully curing produces hydrated lime [Ca(OH)z] within the
bonded topping. The base slab should be covered with a concrete that is converted to calcium carbonate after pro-
separation sheet of polyethylene or waterproof paper to longed exposure to air. When a dilute solution of sodium
ensure there is no bond between the existing and new con- metasilicate (NazSiOJ) soaks into the surface, the sili-
crete. A minimum thickness of 3 in. is recommended, but cate reacts with calcium compounds to form a hard,
for floors subject to very heavy moving loads or severe
impact, a 6-in. thickness is suggested for the topping.
Joints in the new topping can be laid out in panels to the *See also Resurfacing Concrete Floors, Portland Cement Associa-
most suitable size and shape, taking into account the tion publication IS144T. 1981.
thickness of the topping and the amount of reinforcement **Minimum and maximum recommended by AC1 3 0 2 .
glassy substance within the pores of the concrete. This Seamless Floor Surfacings
new substance fills the pores and after drying gives the
concrete a denser, harder surface. The degree of improve- Various types of plastic-reaction products (that is, two-
ment is dependent upon the depth of penetration by the part mixes that harden in place by chemical reaction) and
silicate solution. Therefore, the solution is diluted sig- plasticized synthetic resin are used as seamless surfacings
nificantly to allow adequate penetration. on concrete floors. The three principal systems used for
The treatment consists of three or four coats applied these products are polyesters, polyurethanes, and epoxies.
on successive days. On new concrete, a period of airdry- Resin suppliers can adjust their formulations to suit a
ing for 10 to 14 days after moist-curing ends gives a rea- particular application. Whatever the variations made,
sonably dry surface to gain maximum penetration. The each has been found to have its own limitations, peculi-
first coat should be a solution of 4 gal of water to 1 gal of arities, and special uses. A factor common to all three is
silicate. The second coat should be the same solution the need for a goodquality, well-constructed floor slab
applied after the first one has dried. The third coat should and for attention to detail in application.
be a 3-to-1 solution applied after the second coat has Polyesters have a high shrinkage factor that limits their
dried. The treatment is completed as soon as the concrete use to systems where this volume change can be easily
surface gains a glassy, reflective finish. Water-glass treat- controlled; They have good adhesion as well as good
ment will stop dusting, improve hardness, and increase wear resistance.
resistance to chemical attack, such as from organic acids. Polyurethunes are suitable for use in clear, decorative,
multicoat systems. They require a dry floor, which means
Silicofluorldes a considerable drying period must follow moist-curing
before these products are applied.
Zinc, sodium, and magnesium silicofluoride sealers are Epoxies are made from a wide range of resins and hard-
applied in the same manner as water glass. Each of the eners and are available in a wide variety of products. They
fluoride compounds can be used separately or in combi- possess hardness, high strength, good bonding strength,
nation, but a mixture of 20% zinc and 80% magnesium and chemical resistance. They are available as paints-
gives excellent results. For the first application, 1 lb of pout-able or flow applied-and as mortars.
the fluoride compound should be dissolved in 1 gal of
water. For subsequent coatings, the solution should be 2
lb to each gallon of water. The floor should be mopped
with clear water shortly after the preceding application
has dried to remove encrusted salts. Safety precautions
must be observed when applying fluorides owing to the
toxicity of the fluorine salts. Fluoridation of concrete
REPAIRS AND OVERLAYS
surfaces increases the chemical resistance and hardness Correct design, quality materials, and good construction
of the surface. should produce a floor that theoretically will be free of
major maintenance. In actual use, however, conditions
Linseed Oil arise that expose the concrete tochemicalattack, mechan-
One of the oldest proved techniques to protect exterior ical impact, and abrasive wear not anticipated in the
concrete slab surfaces from cycles of freeze-thaw and de- design. If good maintenance practices are neglected, the
icer chemicals is a linseed-oil treatment. The treatment floor may never provide the long-life serviceability for
consists of two or more applications of commercial-grade which it was intended.
boiled linseed oil mixed with a solvent such as mineral Normal maintenance cleaning will keep the floor at-
spirits. The first application should be a mixture of equal tractive, safe to work on, and free of harmful chemicals
parts of oil and solvent applied on a dry surface with a and abrasive objects. When a floor slab becomes badly
coverage of 400 sq ft per gallon. The second application worn with broken areas or utility cuts and spalling at
can be from one-half to full-strength oil applied to cover cracks and joints, countless materials and methods are
600 sq ft per gallon after the first treatment has been ab- available for repairs as well as a wide divergence of views
sorbed. Linseed oil-water emulsions also are available. on how the repairs should be made. In many instances,
expediency dictates that the work be done without adher-
ing to correct basic principles and the result is an unsatis-
Floor Coatings factory repair.
The basic principles of successful repairs include deter-
Numerous synthetic floor coatings are available such as mining the cause and extent of the damage, careful prepa-
epoxies, polymers, polyurethanes, chlorinated rubbers, ration of the old concrete, the placement and curing of
and phenolics. These products in appropriate circum- highquality replacement concrete, and rejointing where
stances offer good abrasion and chemical resistance and needed. The information and recommendations that fol-
also can be pigmented for attractive color.* The manu- low are a guide to obtaining satisfactory results.
facturers directions must be followed closely.

Evaluation of Damage
*For information on painting concrete, see fainring Concrere. Port- Evaluation of damage is necessary not only to determine
land Cement Association publication ISl34T. 1980. the method of repair to be used but also to ensure that the
repair will be permanent and the damage will not extend Drycleaning. Mechanical methods offer an efficient
into the concrete surrounding the repaired area. Follow- and economical way to dryclean a concrete surface.
ing are the principal factors to be considered before mak- Equipment is available for scabbling, scarifying, grind-
ing a final decision on repair: ing, shotblasting, planing, and flame cleaning. Some
1. The general condition of the floor slab,* that is, loss machines have a variety of interchangeable cutting and
of slab support, strength and thickness of the con- brushing heads.
crete, the extent of badly worn areas, joints, cracks, Scabbling uses an air-driven machine that has a vary-
and contamination of the surface by oil or grease, ing number of pistons mounted in a block. Each piston
paint, chemical attack,** and staining.? is fitted with a tungsten carbide bit. Operating much the
2. Intended use of the floor after repair-which may be same as a bushhammer or chipping hammer (Fig. 34), the
quite different from its previous or present use. striking action shatters away the surface contamination,
3. Limitations to raising the level of the finished floor. exposing a clean, sound concrete with a good mechanical
key for bonding.
4. Time allowed for repair work.

Preparation of Old Concrete


Surface preparation is vital to production of a satisfac-
tory concrete repair. Irrespective of materials, method,
system, or thickness to be used, the keystone of success
is a clean, strong bonding surface with a suitable mechan-
ical key that is free of contamination, laitance, and dust.
Selection of a suitable method of surface preparationcan
be made from the following:

Cleaning Concrete Floors


Wet Cleaning. A floor can be brought to an acceptably
clean standard by wet cleaning. Two materials, one acid
based and the other alkali based, are commonly used in
three separate operations: (1) degreasing, (2) acid treat-
ment, and (3) neutralizing. Cleaning operations should / .
* I
be performed only under conditions where appropriate
safety precautions are taken. Fig. 34. Weak, defective concrete can be removed with a
Degreasing is accomplished by a mixture of a cleaner chipping hammer.
and curing-compound remover (a chlorinated, emulsifi-
able solvent), an industrial grease remover (a highly alka-
line, low-phosphate, biodegradable detergent), and lib- Scarifying uses a power-driven tool with a rotary head
eral amounts of water. The mixture is used to scrub the that can be fitted with a wide variety of scrubbing brushes,
surface-repeatedly if necessary-for added cleaning cutting wheels, scouring brushes, and steel scarifying
effect. The surface finally is rinsed and scrubbed withclear brushes.
water, vacuumed damp-dry, and then allowed to air-dry. Grinders can be used to remove weak, friable laitance;
Acid treatment of the surface is accomplished byapply- improve levels; and remove high spots and trowel and
ing an etching solution (a mild organic acid combined other marks. Grinding also can be used to produce a
with detergents, emulsifiers, and solvent) to the dry floor. smoother, more wear-resistant floor.
The solution is scrubbed over the floor, followed by a Shotblasting is done by closed-cycle steel-particle bom-
vacuum machine to pick up residual material. Thesurface bardment that is virtually dust-free to remove any sur-
is then rinsed, scrubbed clean of acid solution, and dried. face contaminants.
Neutralization of the surface for any residual acid is Planing machines can remove laitance, paint marks,
necessary. This is done by wetting the surface with clear pitch adhesives, and thermoplastic adhesives and can re-
water, sprinkling on a detergent cleaner (highly alkaline, duce the level of the concrete. Other uses includegrooving
high-phosphate, nonresidue detergent), scrubbing, rins- the concrete and making nonskid surfaces. The machines
ing with water, and vacuuming damp-dry. The surface is have hardened-steel cutting wheels for hammering off
then rinsed again with clear water, vacuumed damp-dry, the surface.
and allowed to airdry before applying the new surface
finish.
An acid treatment is recommended only for cleaning *How lo Prevent Concrete Slab Surface Deficts, Portland Cement
Association publication IS177T. 1977.
floor surfaces that are to receive a new surface finish.
** Effecrs of Subsrances on Concrete and Guide TO i+otective Treat-
Other wet cleaning methods include high-pressure ments, Portland Cement Association publication ISOOIT, 1981.
water-jet blasting and steam cleaning. Selection of meth- t Removing Stains and Cleaning Concrete Surfaces, Portland Ce-
od depends on the type and severity of contamination. ment Association publication IS214T. 1982.
Flame treatment involves moving a multiflame blow- maximum size) and portland cement mixed with water to
pipe with an oxygen-acetylene flame over a floor surface give a creamy consistency.** Neat cement grout (without
at a uniform speed. Oils, paints, and other organic sub- sand) also may be used. The grout should be applied at
stances are burned away, moisture in the surface of the a rate that will keep it from drying out before it is cov-
concrete is evaporated, and the surface layer is melted or ered with new concrete.
spalled off. The treatment removes laitance to a depth of Mix Proportions for Patching Concrete. When normal
0.04 to 0.08 in. or high-early-strength portland cement is used for the
After drycleaning a concrete surface, all residue must repair, the mix proportions for concrete and mortar
be removed. Various industrial vacuum machines are should be as follows:
available to remove microdust particles from the pre- Mortar (for patches less than 1 in. thick):
pared surface. I part portland cement
2!4 to 3 parts sand
Concrete (for deeper patches):
Concrete Overlays 1 part portland cement
2% parts sand
When surface wear has reached a point considered detri- 2% parts coarse aggregate-maximum size about
mental to building operations, action is required to re- one-half the patch depth
build and restore the original surface. The choice of repair The materials are proportioned to make a low-slump
method depends on cost, volume of the repair area, ac- mix using not more than 5 gal of water per bag of cement
ceptable downtime, required strength, required chemical (a water-cement ratio not to exceed 0.44 by weight). Ex-
and abrasion resistance, and ambient conditions while terior concrete subjected to freeze-thaw cycles and deicer
repair is under way. The resurfacing methods available chemicals needs an adequate system of air entrainment
can be classified as those using- with a 5% to 7% total air content (9% for mortar). Where
1. Normal or highearly-strength portland cement con- rapid reuse of the patched area is needed, calcium chlo-
cretes and mortars ride, not to exceed 2% by weight of cement (added to the
2. Polymer- and resin-modified portland cement con- mixing water at the jobsite), can be used to accelerate
cretes, that is, PVA- and latex-modified concrete. hardening and early-strength gain of the concrete.
3. High-alumina-cement concrete and mortar CAUTION: Calcium chloride should not be used when
4. Plastic concretes, that is, resin-bound mortars- dissimilar metals or electrical conduit are encased in the
usually epoxy or polyester based in two-component concrete.
systems Placing and Finishing the Concrete. Some type of
Following are basic recommendations for repairing surface vibration is mandatory for compacting surface
concrete floors with normal or high-early-strength port- patches. A hand-operated vibratory screed or strikeoff
land cement concretes and mortars. is effective as is a portable plate vibrator or compactor
float. Hand tampers can be used when power equipment
Bonded Patching+ (% to 2 in. Thick) is not available.
New concrete should be placed and struck off slightly
Surface preparation is the key to producing a well-bond- above the final grade and then mechanically vibrated,
ed, shallow concrete patch. Failure of a patch to tightly screeded, and floated to final grade. When a stiff, low-
bond usually is due to a lack of preparation so that bond slump mix is used, there will be no water gain on the sur-
is prevented by laitance, dust, and contamination on the face and troweling can begin immediately. Troweling
floor surface. should not be done when there is free water on the surface
All weak and defective concrete must be removed, pref- and should not be done to the extent that free water will
erably by saw-cutting 3/4 in. deep around the perimeter of be brought to the surface. When the surface has become
the patch, followed by removal of defective concrete with quite hard, it should be given a second and third trowel-
a jackhammer not heavier than the nominal 30-lb class. ing to produce a very hard, dense finish.
Chipping hammers not heavier than the nominal 15-lb Curing. Evaporation of water from thin-concrete
class can be used to remove concrete surrounding any patches is rapid and if not prevented immediately after
reinforcing bars. Handtools such as hammers and chisels the concrete is finished, rapid evaporation may cause
should be used to remove all final particles of unsound surface crazing, cracking, and curling. Rapid drying can
concrete. Sandblasting or water-jet blasting should be be prevented by covering the patch with wet burlap. The
used to clean the exposed reinforcement of all visible rust
and clinging concrete and clean all surfaces against which
new patch concrete will be placed, Prior to placing new
concrete, the surface should be blown clean by airblast
and then flushed with water. Puddles of free water must *Bonded patching applies to relatively small areas on the concrete
be removed before placing the patch. surface. The basic principles are the same for large areas, but large areas
Just before the new concrete is placed, the cleaned sur- can be reoaired more efficiently with customary mechanical finishing

equipment supported on guide rails. Such construction is called thin-


face should be brushed with a thin (I/s-in.) coat of freshly bonded resurfacing rather than patching.
mixed grout consisting of sand, cement, and water. This **Bonding Concrete or Plaster to Concrete, Portland Cement Associ-
bonding grout should have equal parts of fine sand (No. 8 ation publication IS139T. 1976.
surface should be kept continuously wet for 24 hours, and equal or slightly greater width. Duplicating joints can be
then covered with polyethylene film or waterproof paper done without difficulty by placing inserts in the new con-
for an additional 48 hours. Ambient conditions (hot or crete after screeding the surface. Saw cuts must be timed
cold, dry or humid, calm or windy) dictate the choice of to avoid reflective cracking from the joint in the old slab
a satisfactory curing method. below.

Unbonded Toppings
Thin Bonded Overlay* The minimum thickness of an unbonded topping is 3 in.
with 6 in. suggested for floors carrying heavy moving
A fully bonded concrete topping can be % in. or more loads and subjected to severe impact. The amount of
thick, while for unbonded construction the minimum is work required to prepare the old slab is negligible, con-
3 in. The thickness of overlays limits where they can be sisting only of sweeping clean and filling in badly worn
used because they raise the level of the floor. areas and holes with a cement and sand mortar.
The best surface preparation for a bonded overlay is A separation layer should be used to ensure that there
obtained with one of the drycleaning methods described will be no bond between the old and new concrete. A4-mil
previously. If contamination is present after drycleaning, polyethylene sheet is adequate for this purpose. The sepa-
then wetcleaning methods should be used to further ration layer prevents cracks in the old floor from being
cleanse the surface. An effective check for contamination reflected through into the new topping. It also reduces
is to sprinkle water on the concrete: if the water forms friction at the interface so that the new topping can move
little globules, contaminants are present that will inter- (from drying shrinkage and thermal changes) indepen-
fere with bond. If the water is immediately absorbed, it dently of the floor below.
can be assumed that the concrete is clean. The concrete mix proportions should be the same as
Mix Preparation for Bonded Overlays. Volume pro- those suggested for bonded toppings or for new floor
portions are suitable for small patches; but for large re- construction.
surfacing jobs, weight batching should be used to elimi- Placing and finishing operations are similar to those
nate variations in quality. The mix design varies, depend- used to construct a new concrete floor. An unbonded
ing upon the depth of concrete to be placed. The water- overlay permits control and construction joints in the old
cement ratio can range from 0.45 to 0.33, using 6 to 9 or slab to be ignored. The new topping can have a jointing
10 bags of portland cement per cubic yard, and producing arrangement designed for the most convenient panel size
concrete strengths at 28 days from 4500 psi to 9000 psi. and shape, taking into account the thickness of the top-
Aggregates can be selected for their hard-wearing and ping and the amount of reinforcement provided (if any).
abrasion-resisting qualities. A low-slump concrete, 2 in. However, isolation joints in the old slab must be repeated
to 4 in., generally works well. Adjustments in consistency in the new topping.
depend on thickness of topping, temperature, and equip-
ment available to do the work. A water-reducing admix-
ture can improve workability of low-slump concrete, and Repair of Cracks and Joints
a superplasticizer can produce high-strength concrete at
normal consistencies. Although joints are placed in concrete floors to provide
Formwork. The same principles that apply to edge crack control, sometimes problems arise from heavy
forms in general apply to topping forms. The method of usage, improper joint design or location, and careless
installing and anchoring varies greatly depending on the construction methods. The greatest portion offloor main-
job conditions. The forms and intermediate screeds must tenance is for crack and joint repair.** The principal
be set to grade and positively anchored in position to causes of distress are
maintain a true level. Poor subgrade support
Laying the Topping. The topping should be placed in Inadequate load transfer
small panels. The rate at which this work is completed Floor overloads
should not be overestimated. The topping must be well Excessive joint spacing
compacted to ensure bond, strength, and durability. On Joint filler failures
large projects, a self-propelled finishing machine with When a problem develops, its cause should be found
vibrating screed should be used. On smallerjobs, a manu-
ally operated vibratory screed or tamper can give satis- and corrected before any repair is undertaken.
factory results. Filling Cracks (Sealing)
Various methods of finishing floor slabs have already
been discussed. The new surface must be cured for at Only those cracks that are open wide enough to permit
least 3 days. One practical and satisfactory method is to the entry of a pourable joint filler or a mechanical routing
cover the surface with polyethylene sheets, with laps
sealed and all edges held down. After removing thesheets,
an application of curing compound will extend the curing
*Resurfacing Concrere Floors. Portland Cement Association publi-
period. cation IShUT, 1981.
All joints in the original floor must be duplicated **For repair of outdoor paving, storage yards, driveways, etc., see
exactly in the new topping; that is, they must be located Maintenance of Joints and Cracks in Concrete Pavement, Portland
directly over the joints in the original slab and must be of Cement Association publication ISl88P, 1976.
tool should be filled. Tightly closed cracks subject only
to light industrial traffic should be left alone, but kept
under observation and filled only if they open up or show
signs of spalling.
Each side of the open crack must be refaced so that the
surfaces are cc mpletely free of dust, dirt, debris, and any-
thing else that might prevent bonding of the new filler
material. Special tools such as random<ut saws or crack
grindersand vertical-bit routers should be used. The
crack should be refaced to a l-in. minimum depth or its
full depth without deepening, whichever is less, and then
blown out with compressed air ahead of refilling.

Fig. 35. Spalled concrete at a joint can be removed by


cutting with a saw.

Patching S~dls
Spalling is the dislodging of fragments of concrete from
Fig. 35. Joints and cracks that move can be refilled with the slab at the joint edges, usually from the repeated im-
flexible sealant. pact of hard wheels moving across the joint.
The procedures for bonded patching should be used to
repair spalls. The spalled concrete should be removed
to at least a Zin.-minimum depth and the area blown
clean (Fig. 36). A coating of bonding grout should then
be applied and the patching mortar compacted into place,
High-strength epoxy resin adhesives should not beused finished, and wet-cured. The joint can be reformed by
to rebond and seal cracks where subsequent appreciable placing in the joint groove a thin strip of wood, metal, or
movement is expected, since this could lead to cracking
plastic that has been coated orcovered with a bond-break-
elsewhere in the floor. A flexible epoxy or an elastomeric ing material. The patching mix should then be compacted
filler should be used in cracks that move (Fig. 35). from one or both sides against the form.
If further movement is unlikely, a rigid mortar such as Individual spalls that occur on both sides of ajoint can
cement and sand; cement, sand, and latex; or epoxy and also be repaired by patching the entire cavity and reform-
sand should be used. The crack should first be cut out ing the joint with a saw cut as soon as possible after the
with a special tool and thoroughly cleaned, as described patch is placed. The joint in the patch must be equal in
for patching, before the mortar is put in place. The mor- width to the old opening or slightly wider and it must be
tar must be thoroughly compacted and cured in a manner to the full depth of the patch to avoid subsequent spalling.
suitable to the particular material used. There is a lesson to be learned from the patching and
repair of concrete floors: At the time a new building is
Refilling Joints (Resealing)
constructed, it is essential that the concrete work be prop-
Where joint filler has failed, the old filler must be removed erly designed and executed and that the quality of the
to a depth that will accommodate the new sealant. The concrete work be correct for the intended use. If the les-
same procedures and sealant materials for filling cracks son is ignored, great annoyance and expense can arise
are used for refilling joints. from the resultant repairs.

You might also like