Professional Documents
Culture Documents
4 Concrete Floors On Ground PDF
4 Concrete Floors On Ground PDF
Concrete Floors
on Ground
Second Edition
PREFACE TO THE SECOND EDITION
Slump
635 0.45 0.55 0.65 Excessive slump and consequent bleeding and segrega-
WATER- CEMENT RATIO tion are a primary cause of poor performance in concrete
Non-air-entmined concrete floors. If the finished floor is to be level, uniform in
Cement : Type I appearance, and wear resistant, it is important that all
batches placed in the floor have very nearly the same
Fig. 2. Recommended minimum strengths for industrial slump.
and commercial floors on ground.
Placing low-slump (2- to 4-in.) concrete flatwork is
routine with the use of mechanical equipment such as a
vibratory screed that rides on the side forms. When such
Minimum Cement Content equipment is used on floor work, less water is added at
the jobsite and the wear resistance of the surface is im-
Floor work in particular needs sufficient cement mortar proved. Low-slump concrete will go a long way towards
matrix for proper finishability. This is assured by speci-
fying a minimum cement content. Speeding up placement and consolidation
With modern concrete technology, high-strength con- Reducing finishing time
crete can be obtained with less cement than before. Where Reducing cracking
strength alone is the decisive criteria, less cement means Eliminating surface defects
greater economy. Wear resistance, however, depends Recommended slumps for each AC1 class of floor are
upon the surface hardness of the concrete as well as its given in Table 5.2.1 of AC1 302. A 3-in. slump is suggest-
internal strength and requires more cement. A minimum ed for class 4 and 5 floors.
cement content should be specified that will ensure tin-
ishability for maximum wear resistance at the surface as
well as adequate internal strength. The amount of cement Entrained Air
should not be less than shown in Table 2. Use the largest
size of aggregate possible to keep the cement content to a A small amount of purposely entrained air is useful in
minimum. almost all concrete for floors for reducing bleeding and
increasing plasticity. A total air content of 2% to 3% is
suggested. Concrete that will be exposed to cycles of
Maximum-Size Coarse Aggregate freezing and thawing and the application of deicer chemi-
cals needs a total air content of 5.5% to 7.5%, depending
Freedom from random cracking is desired for all concrete upon maximum size of aggregate, to ensure resistance to
floors. The degree to which random shrinkage cracking scaling. See Table 5.2.7a of AC1 302.
Tensile Strength of Concrete where extensive data had already been assembled from
many years of laboratory and field research and testing.
Modulus of Rupture Acknowledging the obvious similaritiesand differences
between a road pavement and a floor slab, pavement
When a load is applied to a floor on ground, it causes theory was reduced to easily used thickness design charts
bending that produces both compressive and flexural for floors on ground. The design method is presented in
stresses in the concrete slab. Of the two types of stress, Slab Thickness Design for Industrial Concrete Floors on
flexural stress is more critical because it will approach Grade* and is applicable as well to slabs on ground for
the ultimate tensile strength of the concrete (modulus of outdoor storage and material-handling areas. As in pave-
rupture), while compressive stress remains small in pro- ment design, the factors involved in determining the re-
portion to the ultimate compressive strength of the con- quired floor slab thickness are
crete. Consequently, theflexural stress and thejlexural 1. Strength of subgrade and subbase
strength of the concrete are used in floor-slab design to 2. Strength of concrete
determine thickness. 3. Location and frequency of imposed loads
Flexural strength is determined by modulus of rupture
(MR) tests in accordance with ASTM C78, Flexural The following procedures for thickness design are de-
Strength of Concrete Using Simple Beam with Third- rived from Slab 7Eckness Designfor industrial Concrete
Point Loading. If the size of the job does not warrant the Floors on Grade.
extra cost of flexural strength tests, compressive strength
test results can be used to approximate probable flexural
strength. An approximate relationship between compres- Location and Frequency
sive and flexural strength is shown in Table 3. of Imposed Loads
Slab cracking due to excessive loads can occur in response
Table 3. Approximate Relationship to flexural overstress; too much deflection; settlement
Between Compressive and due to consolidation of subsoil; and for very concentrated
Flexural Strengths loads, excessive concrete bearing or shear stresses.
The strategy in designing for floor slab thickness is to
Compressive strength, psi Flexural strength, psi keep all responses within safe limits. The controlling de-
3500 445-590 sign consideration will differ for different sizes of load
4000 480-640 contact area. For example, for lift trucks with wheel con-
4500 500-670
5000 535-710
tact areas in the range of 20 to 100 sq in., flexural stress
6000 585-780 will control thickness design.
7000 630-840
6
40 50 60 70 60 90 100 II0
tll,,,,11 I I I I I I 1
2 4 6 8 IO I2 I4 I6 I8 20 30 40 50
RATED CAPACITY OF LIFT TRUCK, kipr
Fig. 3. Estimated slab ihicknesses for lift trucks (based on average truck data shown in Table 4 and conservative
design assumptions of k = 50 pci, concrete working stress = 250 psi).
Table 4. Lift Truck Characteristics (Composites Averaged
from Manufacturers Data)
Range of wheel spacings, in. (c to c)
Rated Load on Dual wheels
capacity,* drive axle,** Single wheels,
lb kips st Sdt st
2,000 6.4 26 to 30 - -
4,000 10.4 31 to 35 - -
6,000 14.6 32 to 38 - -
10,000 22.2 37 to 43 10 to 12tt 41 to 53j.t
15,000 32.5 37 to 45 10 to 12 47 to 60
20,000 42.0 40 to 50 12 to 14 54 to 65
30,000 63.3 - 14 57
45,000 100.6 - 18 73
60,000 132.0 - 21 70
Other data:
Load Contact Pressure
solid or cushion tires-l 80 to 250 psi
pneumatic tires-80 to 100 psi (inflation pressure)
Load Contact Area (per tire)
solid or cushion tires-3 or 4 times tire width
pneumatic tires-wheel load divided by contact pressure
Approximately 90% of total weight (truck + load) on drive axle at rated
capacity.
Maximum axle load for many lift trucks is slightly greater than twice the
rated capacity.
Design Procedure
Vehicle Loads
Design for industrial lift-truck loads requires knowledge
of several specifics:
Maximum axle loads
Number of load repetitions
Wheel contact area
Spacing between wheels on heaviest axles
Subgrade strength
Flexural strength of concrete
Traffic and load data for past and future operating
conditions for lift trucks (Fig. 4) can be gathered from
plant maintenance departments, planning and operations
departments, and truck manufacturers data. Then the
safety factor can be selected and used to determine an
allowable working stress with which to enter the design
charts.
The safety factor (flexural strength divided by working Fig. 4. Traffic and load data are needed for design of
stress) reflects the expected frequency of loadings of the industrial concrete floors on ground.
heaviest vehicles. Safety factors in the range of 1.5 to 2.0 alent single-wheel axle load. Then Fig. 5 can be used to
are suggested for industrial and commercial floors. The determine the required thickness of the slab.
high number should be used where the heavy load traffic The effective contact area used in the charts is the cor-
is frequent and channelized. Where traffic is light and not rected area of tire in contact with the slab. If tire data are
channelized, lower safety factors of 1.5 to 1.7can be used. not available, the contact area can be estimated for pneu-
The design chart for industrial trucks with single-wheel matic tires by dividing wheel load by inflation pressure.
axles, Fig. 5, was taken from Slab Thickness Design for For solid or cushion tires, it can be approximated by mul-
Industrial Concrete Floors on Grade. This chart is entered tiplying tire width by three or four. Tire data can also be
with a calculated number for allowable working stress obtained from the tire manufacturers. When the tire con-
per 1000 lb of axle load. The number is obtained by divid- tact area is small, it must be corrected to an effective con-
ing the modulus of rupture of the concrete by the safety tact area because slab stresses for small-load contact areas
factor and then dividing the result by the axle load in kips. are overestimated using conventional theory. The same
The calculation makes it possible for one chart to cover a correction is used for the high-rack-storage-leg loads dis-
wide range of load magnitudes. cussed below. The correction is made with the design
For axles equipped with dual wheels, Slab Thickness chart for axles with dual wheels in Slab Thickness Design
Design for Industrial Concrete Floors on Grade includes for Industrial Concrete Floors on Grade. (The chart is
a chart for converting a dual-wheel axle load to an equiv- not included in this publication.)
/ - + - j SPnClNG t-+/+=
8 O-II I I I in. I I I
3
I I
50 100 21 00
Fig. 5. Design chart for axles with single wheels. SUBGRADE k, pci.
Thickness Design Example-
Single-Wheel-Axle Loads
Data for Lift tick
Axle load 25 kips (single-wheel axle)
Wheel spacing 37 in.
Number of wheels 2
Tire inflation pressure 110 psi
Tire contact area:
wheel load 114 sq in. (large
inflation pressure enough, correction
not required)
High-Rack-Storage-Leg Loads
Advancements in mechanized, computerized material-
handling equipment generated the high-rack configura-
tion now used for product storage in many warehouses.
In these buildings, permanent racks of fixed dimensions
rise to heights up to 60 ft. When loads on the rack legs (or
posts) exceed the wheel loads of vehicles operating in the
warehouse, leg loads will control the thickness design.
For leg loads, the design objective is to keep flexural Fig. 6. Loaded legs supporting high-rack storage must
stresses in the slab within safe limits. When flexural re- have base plates of adequate size to prevent bearing or
quirements are satisfied by adequate slab thickness, pres- shear failure in the slab.
sures on the soil will not be excessive; and when a correct-
size base plate is used (Fig. 6), concrete bearing and
punching shear stresses will remain within acceptable Fig. 7, taken from Slab Thickness Designfor Industrial
limits. Concrete Floors on Grade, is used to determine slab
The design factors for high-rack-leg loads are similar thickness requirements for rack configurations and loads.
to those used for vehicle loads except that a higher safety The x- and y-leg spacings used in Fig. 7 are the smallest
factor is selected. The specific design factors are dimension in the rack configuration (except the spacing
Maximum expected load on leg between legs on opposite sides of a joint).
Effective (corrected) load contact area The procedure is similar to that for wheel loads. In the
Spacing between legs grid at the left side of the chart, locate the point corre-
Subgrade strength sponding to stress per 100~lb-leg load and effective
Flexural strength of the concrete (corrected) contact area. Move right to the y-post spac-
6 0
6
IO
SUBGRAOE k= 5 O p c i
60 4 0 20 IO
ing (length or long axis dimension of the racks); then with Fig. 7 to establish a tentative slab thickness based
move up (or down) to the x-spacing and right to read the on flexure. Shear stress and concrete bearing stress should
slab thickness. also be computed to determine if these values are within
For loads on high racks, use high safety factors. High- safe limits.
rack loads require conservative safety considerations For exceptionally heavy rack loads on plain concrete
because the effects of differences in movement at the slabs, the thickness required may be so great that alter-
base of the rack are magnified at the top. In addition, nate design methods should be considered, such as:
if the rack layout and the slab joint layout are not co- Integral or separate footings under the leg lines
ordinated, it is possible that some rack legs could be Structural reinforced slabs
located near a joint. Unless the slab edges are intention- Use of cement-treated subbase under the concrete slab
ally thickened, this would result in higher floor slab The economic and construction practicality of these
stresses than those shown in Fig. 7, which are based on alternative designs should be considered along with the
loads at the slab interior. Safety factors should be chosen effects of thickness on stresses and deflections ofthefloor.
to include the possibility of rack loads being applied close
to slab edges or corners.
Since there is little available data on performance ex- Uniform Loads
perience with rack loads on slabs, safety factors cannot
be suggested with as much confidence as for vehicle loads. Uniform loads are defined as loads distributed over a
Safety factors in the range of 3.9 to 4.8 willsatisfy build- large area. For most warehouse and industrial floors,
ing code requirements when the rack leg is regarded as a concentrated loads are the controlling design factor since
supporting column and the slab is regarded as an unrein- distributed loads do not usually produce flexural stresses
forced spread footing. of the same magnitude. However, after an adequate slab
A safety factor in the range of 3.0 to 4.0 can be used thickness has been selected to support the heaviest vehi-
ties and storage racks, as previously described, the effects in these tables.
of uniform loads should also be examined. Storage Layout. The magnitudes of flexurai stresses and
Design for uniform (distributed) loads has two objec- deflections due to distributed loads vary with slab thick-
tives: (1) to prevent cracks in the aisleways or unloaded ness and subgrade strength. They also vary with aisle
areas due to excessive negative moment; and (2) to avoid width, dimensions of the loaded area, and the existence
objectionable settlements due to consolidation of the of joints or cracks in the aisleway. In Table 5 for fixed iay-
foundation soils. out, the critical aisle width and its allowable distributed
Cracking in an unjointed aisle can be controlled by load are identified and the loads for other aisle widths are
adequate slab thickness. Slab settlement, however, can- given. Table 5 is used when the storage layout is pre-
not be eliminated by making the slab thicker-this is a planned and will remain unchanged (Fig. 8).
foundation-soils-improvement problem. Normally, the The allowable loads shown in Table 6 for a variable
magnitude of distributed loads placed on floors with storage layout represent the most critical conditions and
properly prepared and compacted subgrades and sub- are suggested for practical design use when the aisle and
bases is not sufficient to cause excessive settlement; but storage layout is unknown at planning time(Fig. 9). There
for very heavy distributed loads on compressible sub- are no restrictions on where the load is placed or on the
grades, the possibility should be examined by a structural uniformity of loading for the allowable loads in Table 6.
foundation engineer. When there are joints in the aisleways or if cracks should
occur, the limit of load will depend on the tolerable set-
Allowable Uniform Loads to Prevent Cracking in Aisie- tlement of the slab.
way. In an unjointed aisieway between uniform load For wheel and rack loads, increased slab thickness ef-
areas, the maximum negative bending moment may be fectively reduces the unit pressure transmitted to the sub-
up to twice as great as the moment beneath the loaded grade soil. Under uniform distributed loads, however,
area. Hence, the thickness design should limit the resuit- soil pressure is not reduced by slab thickness, but is equal
ing stresses so that a crack will not occur in the aisleway. to the uniform load on the slab plus the slab weight plus
Allowable loads based on this consideration can be the weight of any fill material. Therefore, when the loads
found in Tables 5 and 6 for fixed and variable storage iay- are exceptionally heavy, as in Fig. 10, the amount of set-
outs. Note that the k value of the subgrade, rather than tlement should be estimated by methods used in founda-
the k value on top of the subbase (if there is one), is used tion engineering for spread footings or raft foundations.
i .0 II 900 I 935 I
900 I
8.0 11 1,025 1 1,070 1 1,025 1,065 1 1,175 1 1,350
9.4 II a45 I 930 855I 850 T 885 1 960
94 II
400 9.4 1,130 1.24
300 10.8 915 1.065 955 915 925 965
12 350 10.8 1,065 1.240 1,115 1,070 1,080 1,125
400 10.8 1.220 1.420 1,270 1,220 1,230 1,290
300 12.1 980 1,225 1,070 1,000 980 995
14 350 12.1 1,145 1.430 1,245 1,170 1,145 1,160
400 12.1 1,310 1.630 1,425 1,335 1,310 1,330
JOINTING PRACTICE
Good jointing practice is one way of ensuring crack-free
floors. Most cracks in concrete floors are the result of
three actions: volumetric change due principally to dry-
ing shrinkage, direct stress due to applied loads, and flex-
urai stress due to bending. Cracks can be the net result EXPANSION JOINT MATERIAL
of ail three. Cracks will appear at any time and any place
where the stress within the concrete to pull it apart ex- Fig. 11. Isolation joints are used between the floor slab
ceeds the strength of the concrete to hold itself together. and fixed parts of building such as walls, columns, and
The magnitude of drying shrinkage inconcrete isaffect- machinery bases.
ed by the water content of the mix. More coarse aggregate
and less water mean less shrinkage (thus, less cracking) in
the concrete. Type of cement and cement content have
very little effect on drying shrinkage. The use of an accei-
CONSTRUCTION JOINT
erator admixture containing calcium chloride can in-
crease drying shrinkage significantly. The rate of drying
is influenced by thickness of the slab, humidity and tem-
perature of the surrounding air, and duration of expo- ISOLATION JOINT
sure. Drying shrinkage is an unavoidable, inherent prop-
erty of concrete, so the possibility of cracking exists. Con-
trol measures are taken to induce concrete to crack in pre- CONTROL JOINT
dictable, straight lines by proper jointing.
Kinds of Joints
Building use dictates the joint design and spacing for a
concrete floor on ground. The designer is always con- Fig. 12. Isolation joints around columns are circular or
fronted with the need to eliminate random cracking, so square shaped.
crack control is an important aspect of floor perform-
ance to be included in the floor design. Three kinds of
joints are used: Control Joints
1. Isolation joints (also called expansion joints)-to
allow movement between the floor and other fixed Control joints act to relieve stress and with proper spac-
parts of the building such as columns, wails, and ing they eliminate the cause of uncontrolled random
machinery bases cracking. They allow horizontal movement of the slab.
2. Control joints (also called contraction joints)-to Control joints in industrial and commercial floors are
induce cracking at preselected locations usually cut with a saw. They should be constructed to a
depth of generally one-fourth the slab thickness. In thick
3. Construction joints-to provide stopping places slabs a crack inducer anchored to the subgrade immedi-
during construction ately below the joint can be added to reduce the section.
The objective is to form a plane of weakness in the slab
Isolation Joints
so that the crack will occur along that line and nowhere
Isolation joints are placed wherever complete separation else, as shown in Fig. 13. Load transfer across a control
between the floor and adjoining concrete is needed to joint is provided by the interlocking of the jagged face
formed at the crack. With long joint spacings or heavily
loaded slabs, dowel bars (coated to prevent bond with the
concrete) are used as load transfer devices. Dowel sizes
and spacings are shown in Table 7.
Construction Joints
Construction joints usually form the edges of each days
work. They are located to conform to the floor jointing
pattern and detailed and constructed to function as and
align with control joints or isolation joints.
Where there is no control or isolation joint, a butt-type
construction joint is satisfactory for thin floors, as shown
A+B=1/4DMIN in Fig. 14. For thicker, more heavily loaded floors, a
CONTROL JOINT IN THICK FLOOR SLABS
tongue-and-groove joint is used or dowels are added to
the butt joint. Whenever continuous concrete placement
will be interrupted for 30 minutes or more, a bonded con-
r PLASTIC OR HARDBOARD
1 PREFORMED STRIP
struction joint should be inserted to avoid the formation
of a cold joint. A bonded construction joint in a plain slab
is a butt-type construction joint with tiebars as shown in
Fig. 14. Tiebar sizes and spacings are shown in Table 7.
Any reinforcement in the slab is conti,vuous through the
bonded construction joint.
Filling Joints
PREMOLDED INSERT CONTROL JOINT
The movement at control joints in a floor is generally very
SMOOTH DOWEL BAR COATED small. For some industrial and commercial uses, these
TO PREVENT BOND T , joints can be left unfilled. Where there are wet conditions,
hygienic and dustcontrol requirements, or considerable
traffic by small, hard-wheeled vehicles such as forklifts,
joint filling is necessary.
In many places, a resilient material such as an elasto-
meric sealant is satisfactory, but to provide support to
the edges and prevent spalling at the joints, a good quality
rigid or semirigid filler with a durometer Shore A-scale
hardness number of approximately 80 should be used.*
CONTROL JOINT WITH DOWELS
Fig. 13. Varieties of control joints. *ASTM Designation: 02240 and D676.
EDGE EACH SIDE EDGE EACH SIDE SMOOTH DOWEL BAR
WITH I 18 IN. RADIUS 7 / PREVENT BOND WITH 118 IN. RADIUS 1 ,COATED TO PREVENT BOND
PREVENT BOND
BUTT-TYPE CONSTRUCTION JOINT BUTT-TYPE CONSTRUCTION
JOINT WITH DOWELS
D
D
.Joint Layout
A joint layout is illustrated in Fig. 15. Isolation joints are
provided around the perimeter of the floor where itabuts
the walls and around all fixed elements that restrain
movement of the slab in a horizontal plane. This includes
columns and machinery bases that pierce the floor slab.
With the slab isolated from other building elements, the
remaining task is to locate and correctly space control
joints to eliminate random cracking. Construction joints Fig. 15. Typical joint layout for concrete floor on ground
can be located by the floor contractor to accommodate with no reinforcement.
work schedules with the restriction that they coincide (in inches) for concrete made with less than 3%~in.-top-
with the control-joint pattern. Pipe trenches under slabs size coarse aggregate or 21%slab thicknesses for concrete
on ground (Fig. 16) require control joints placed directly containing greater than 3%-in. coarse aggregate. For low-
above each side of the trench. slump concrete, less than 4-in. slump, 3 slab thicknesses
are suitable. Suggested joint spacings are given in Table 8.
CONTROL JOINT
Note Gwen spacings also apply lo the distance from control founts to parallel
lsolatlon founts or to parallel constructlon joints Refer to text for other factors that *B. E. Colley and H. A. Humphrey, Aggregate Inrerlock ar Joints in
may call for different spacmg Spawigs greater than 15 11 show a marked loss In Concrete Pavemenrs. Research Department Bulletin DXl24, Portland
effectweness of aggregate Interlock to prowde load transfer across the lolnt Cement Association, 1967.
Control joints are constructed in slabs on ground to Concrete in service exhibits less drying shrinkage than
relieve tensile stresses caused by drying shrinkage. When laboratory test prisms. Therefore, a reduced shrinkage
properly spaced, they control the location and direction coefficient can be used to calculate joint spacings that will
of cracks. At the plane of weakness produced by the joint, limit the width of joint openings. For example, if the re-
restrained shrinkage forces are relieved by the crack that duced coefficient is 275 millionths, control joints at 10.5
forms below the saw cut (Fig. 18). ft will limit joint openings to 0.035 in. and 7.5 ft will limit
Load transfer across the crack is developed either by openings to 0.025 in. Use a short spacing between joints
the interlocking action of the aggregate particles at the to limit opening width.
fractured faces of the crack (aggregate interlock) or by a
combination of aggregate interlock and mechanical de- influence of Slab Thickness
vices such as dowel bars. When load transfer is effective,
the stresses and deflections in the slab near the joint are Investigation of the effect of slab thickness on load trans-
low and forklift and industrial trucks move smoothly fer demonstrated that a thick slab with wider joint open-
across the joint without damaging it. ings can be equally as effective as a thin slab with narrow
openings. For an effectiveness of 60%, the openings in
joints of 7- and 9-in.-thick slabs were 0.025 and 0.035 in.,
respectively.
Subgrades
Good construction begins with a well-prepared subgrade.
Many floor problems can be traced to poor subgrade
preparation. A poorly compacted and prepared subgrade
006 ranks high as a cause of settlement cracking and failure
to carry the applied loads.
The subgrade should be uniform, firm, and free from
0.04 all sod, grass, humus, and other rich organic matter as
these materials will not compact to give good support to
0.02 the floor. Subgrade support should be reasonably uni-
form with no abrupt changes from hard to soft spots with-
01 in the floor area. To construct a reasonably uniform sub-
20 30 40 50 60 70
grade, special care must be taken to ensure that there is
DISTANCE IN FEET BETWEEN FREE ENDS control of the three major causes of nonuniform support:
(1) expansive soils, (2) hard spots and soft spots, and (3)
Fig. 20. Selection chart for distributed steel. backfilling.
The subgrade must be brought to within required toler-
ances at the specified grade and level. The use of laser
UNJOINTED FLOORS alignment tools to control grading operations will make
the surface as level as possible; or a scratch templet can
An unjointed floor can be constructed when joints are be used to reveal high and low spots. Occasionally a chok-
unacceptable. Three methods are suggested: er fill should be added to bind the surface before final
1. A prestressed floor can be built through use of post- compaction with a vibratory roller, heavy-plate vibrator,
tensioning, a method in which steel strandsarepulled or a tandem roller. A reasonably accurate, level subgrade
taut after the concrete hardens to put a compressive will ensure that the correct thickness of concrete is placed.
stress in the concrete. This will counteract the devel- If the surface is too uneven, concrete will be wasted and
opment of tensile stresses and provide a crack-free the potential for random cracking will be increased. The
surface. Large areas, 10,000 sq ft and more, can be subgrade should be moist when concrete placement be-
constructed in this manner without joints. gins (Fig. 21).
Fig. 21. Subgrade must be moist when concrete is placed.
Expansive Soils in the surrounding area. The moisture content and den-
sity of the replacement soil should be as similar as pos-
Excessive differential shrinkage and swelling of expan- sible to the adjacent soils. At the edges of the area, the re-
sive soils causes heaving in the subgrade and creates non- placement soil should be intermixed with in-place soil to
uniform support. As a result, the floor slab may become form a gradual transition zone.
distorted and crack. Compaction of highly expansive soil
when it is too dry can lead to detrimental expansion and Backfilling
softening of the subgrade as it takes on moisture with
time. If an expansive-soil subgrade is too wet when the Backfilling at footings, foundations, and utility trenches
slab is cast, subsequent drying and shrinkage of the soil should consist of soils like those surrounding the trench
can cause settlement and leave the slabedges unsupported and should be compacted or consolidated in moderate
and likely to crack under appiied loads. layers. Every attempt should be made to restore as much
Selective grading, crosshauling, and mixing of sub- as possible the original uniformity of the subgrade.
grade, soils make it possible to obtain uniform conditions
in the upper part of the subgrade. Compaction at 1% to
3% above standard optimum moisture* minimizes sub- Subbase or Cushion
grade weakening due to changes in moisture content and
gives it relatively uniform stability. Placement of a dense- A satisfactory floor on ground can be built without a sub-
ly graded blanketing layer (subbase or cushion) on the base, but a subbase is frequently used as a leveling course
subgrade will minimize changes in the moisture content for fine grading and a cushion that will equalize minor
of the subgrade and provide a stable working platform surface irregularities and contribute to uniform support.
for floor construction. It also serves as a capillary break between the floor slab
and a subgrade that is water soaked most of the time.
Where a subbase is used, the floor contractor should
Hard Spots and Soft Spots place a 4-in.-thick layer of material. The subbase should
To prevent bending and cracking of the slab from sub-
grade settlement or riding on hard spotsand bridging over
soft pockets, special care must be taken to dig out hard
and soft spots and backfill them with soils similar to those *ASTM Designation: D698
be fine-graded and compacted to maximum density im- sulation is needed only at the perimeters of the slab. This
mediately before placing concrete. Unless the subbase is practice is recommended by Model Code for EnergyCon-
well compacted, it is better to leave the subgrade uncov- servation** and other major codes and standards.
ered and undisturbed. Subgrades and subbases can be
compacted with small portable vibrators and rollers.
Hand tampers can be used in confined places. On large Slab thickness Tolerances
floor projects, compaction equipment similar to that used
in highway or airport construction can be used. Acceptable thickness tolerances for slab-on-ground con-
struction as stated in AC1 117, Standard Tolerances for
Concrete Construction and Materials (Section 2.1.5), are
+3/8 in. and --i/4 in. for slabs with cross sections up to 12 in.
thick and +A in. and -% in. for slabs of more than 12-in.
Vapor Barrier thickness.
Many of the moisture problems associated with floors on
ground can be minimized or eliminated by proper prelim- Finishing Concrete Floors
inary grading, correct selection of fill or subbase mate-
rials, and installation of a vapor barrier. Finishing concrete floors never should be done by inex-
A vaporproof barrier should be placed under all con- perienced, unskilled workers. Finishing is a critical task
crete floors on ground that are likely to receive an imper- that for best results requires the work of skilled cement
meable floor finish or used for any purpose where the masons. Two stages are usually required in producing a
passage of water vapor through the floor is undesirable. finished surface: (1) placing, compaction, and truing (to
Good quality, well-consolidated concrete at least 4 in. a rather rough surface) of the struck-off or screeded sur-
thick is impermeable to the passage of liquid water from face by the use of a hand or power-driven float; and (2)
the ground unless the water is under considerable pres- the final compaction and smoothing (to a tine texture)
sure; but concrete several times that thick is not imper- by steel-troweling with a hand or power-driven trowel.
meable to the slow passage of water vapor. If a coarse texture is desired, the steel-troweling may be
Water vapor normally passes through the concrete and omitted. A very fine grained (nonslip) swirl finish can be
evaporates at the top surface if it is not sealed. Floor cov- attained by light troweling; a very smooth hard finish is
erings such as linoleum, felt- or fabric-backed composi- the result of repeated troweling.
tions, cork tile, carpet, wood, and synthetic surfacing There are three basic finishes for a concrete slab sur-
effectively seal the moisture within the slab where it even- face: screeded, floated, and troweled.
tually may cause problems with the covering. When fur- A screeded finish is the result obtained when the sur-
niture, boxes, pallets, and other objects are placed on a plus concrete is removed immediately after consolidation
floor lacking a vapor barrier, moisture can condense be- by striking off with a straightedge or templet across edge
neath them, causing dampness and mildew. forms or screeds set as guides. There are instances in
Vapor-barrier materials with a permeance of less than building where a screeded finish is all that is needed.
0.30 perms are suitable for floor-on-ground construction. A floated finish is normal for outdoor slab surfaces.
Acceptable materials are available in preformed sheets Floating follows screeding and should not be done until
or mastics that will resist deterioration and punctures some stiffening has taken place and the water sheen has
from subsequent construction operations. disappeared. Floating should work the concrete no more
Vapor-barrier material placed directly under the slab than necessary to produce a surface that is level, uniform
also functions as a slipsheet to reduce subgrade drag fric- in texture, and free of foot and screed marks. If a troweled
tion, permitting freer slab movement and reducingcrack- or broomed finish is to be applied, floating should leave
ing in the slab. It will prevent the loss of mixing water a small amount of mortar, without excess water, on the
down into the subgrade and, therefore, requires a com- surface to permit effective troweling or brooming.
pensating adjustment in the mix design. A troweled finish is used on inside floor slabs. Trowel-
A vapor barrier may contribute to the slabs upward ing should not be done until after the moisture film and
warping (curling). A layer of sand below the slab will al- sheen have disappeared from the floated surface and the
low some moisture loss at the bottom of the slab. When a concrete has hardened enough to prevent an excess of fine
vapor barrier is used, a 3-in-thick layer of sand should material and water from being worked to the surface.
be placed over the vapor barrier to prevent or minimize Steel-troweling is performed with a firm pressure that
warping. The sand layer also protects the vapor barrier will close the open, sandy surface left by floating into a
from puncture during construction operations. hard, dense, uniform surface free of blemishes, ripples,
and trowel marks.
A hard steel-troweled (burnished) finish is a special Iin-
Insulation Under Slabs ish that provides added resistance to abrasion and wear.
After the first troweling the surface is troweled again (and
Placing insulation under slabs on ground to conserve
energy cannot be justified. Tests by the National Bureau
of Standards* proved the temperature of the slab aver-
ages only 5O F to 6 F below room temperature to within *BMS Report 103, 1945.
24 in. of an outside wall. In cold climates, therefore, in- **U.S. Department of Energy, December 1977.
again) until it has a somewhat polished (glossy) look. function properly for crack control, some failproof way
A fine-textured, swirl finish that is not slick can be ob- must be used to hold it in that position. Reinforcement
tained by retroweling the surface with the trowel held flat can be supported on chairs, slab bolsters, or small con-
and moved in a circular motion immediately after the crete bricks and blocks. Support accessories for wire
first regular troweling. mesh must be more closely spaced than for reinforcing
A steel-troweled floor has increased strength near the bars. The practice of laying the mesh on the subbase or
surface and therefore greater wear resistance. Steel trow- subgrade before concrete is placed and hooking it up into
eling helps the cosmetic appearance and provides a sur- position after concrete has been placed is not recommend-
face that is easier to clean. ed because this gives no assurance that the mesh will stay
Industrial and commercial floor slabs should have a in the concrete in straight lengths or on a true plane at the
troweled finish. There are no compelling reasons to trow- correct distance below the surface.
el finish an outdoor slab. If a light broom finish is wanted, Flat-sheet mesh can be placed by the sandwich method
broom the surface after troweling it. If a rough broom in two-course work. This involves first placing a layer of
finish is desired, rough broom over a floated finish. concrete struck off 2 in. below the finished grade. The
mesh is laid on this layer and then the top 2-in. layer of
concrete is placed. Work must be completed quickly so
Concreting Procedures that the top layer is placed while the bottom is still plastic.
Flat-sheet fabric can be depressed into the slab by what
Floors cast under the protective cover of a tight roof with is termed walking in. The concrete is placed full depth
the building sidewalls in place are apt to be better con- and struck off. The flat sheet is then placed on the surface
structed than floors cast out of doors. Outside work can and the finishing crew carefully walks on it, forcing it into
be adversely affected by the weather (sun, heat, cold, the concrete. Accurate positioning of the steel fabric is
wind, and rain) and have a greater risk of future problems difficult with this method.
such as cracking, crazing, curling, and surface dusting. Wherever dowels or tiebars are placed in joints, they
The semimanual methods recommended here for plac- must be accurately aligned and spaced and held parallel
ing, consolidating, and finishing concrete floors require to the surface during concreting.
the use of mechanical equipment for striking off, com-
pacting, and finishing. Placing and Spreading
Rutted or marred subgrade or subbase surfaces must be
regraded and recompacted before placing concrete. There
Edge Forms are several ways to place fresh concrete where it is needed,
The surface-finish tolerance of the floor slab depends on including directly from a truck mixers chute, by buggy
careful setting of the edge forms and temporary inter- on wooden ramps, by crane with bucket, by conveyor
mediate screed guides with the use of a leveling device. belt, or by pump.* Concrete should be placed continu-
Edge forms and screed guides must be supported firmly ously as closely as possible to its final position and slightly
by wood or steel stakes driven solidly into the ground to above the top of the edge forms or screed guides. It is then
prevent any movement during mechanical strikeoff and spread with shovels, special concrete rakes, or come-
consolidation. Loose edge forms cause uneven floors. alongs. Air is trapped in the concrete during mixing and
Temporary screed guides that are not positively posi- placing, and this air must be removed by consolidation.
tioned can be displaced, causing uneven floors. All forms
should be straight, free from warping, and of sufficient Striking Off and Consolidating
strength to resist concrete pressure without bulging. Edge
forms should be full slab depth and continuously sup- Concrete is brought to its initial level and surface by the
ported on the compacted subgrade or subbase; for this first operations of strikeoff, consolidation, and darbying
reason steel road-type forms are preferred. Vibratory or bullfloating. Striking off is best done with mechanical
strikeoff and compaction equipment slides easily on a equipment riding on the side forms (Figs. 22,23, and 24).
steel surface. A form release agent must be applied to the Where surface tolerance is important, the strikeoff lane
forms before concreting for easier form removal. width should be limited to 20 to 24 ft. The limited width
When a continuous vapor barrier is required under the makes it possible to bullfloat and use a crossrod or
floor slab, special care is needed to place the barrier sheet straightedge more accurately.
correctly under the edge forms before the pins are driven. Surface vibration is recommended for slabs of up to 8-
in. thickness. When floors contain heavy reinforcement
and conduit or when they are thicker, internal spud vibra-
tors must also be used, or the slab should be placed in
Positioning Reinforcing Steel layers while the concrete remains plastic. When a thick
Reinforcing bars or welded-wire fabric (wire mesh) are slab has been compacted by internal vibrators, final com-
used in floor slabs for crack control. In order for rein- paction of the surface should be done with a beam- or
forcing bars or mesh to bond properly with the concrete,
they should be free of mud, oil, or other coatings that
would adversely affect the bonding capacity. The rein-
forcement should be placed at or above the center of the *See Transporring and Handling Concrete, Portland Cement Asso-
slab-2 in. below the surface is suggested-and if it is to ciation publication IS178T. 1974.
Fig. 22. Strikeoff can be done with a double-beam Fig. 24. After strikeoff with vibratory equipment, the
vibratory screed. surface may be ready for finishing without darbying or
bullfloating.
Leveling
Bullfloating to bring the surface to the specified level
(Fig. 25) should immediately follow screeding and must
be completed before any bleed water is present on the sur-
face. Any finishing operation performed while there is
excess moisture or bleed water on the surface can cause
surface defects. This is the basic rule of concrete finishing
and it cannot be overemphasized. One of the purposes of
the bullfloat is to eliminate ridges and fill in surface voids
left by striking off and consolidating. In addition, it
should slightly embed the coarse aggregate. This prepares
the surface for subsequent edging, floating, jointing, and
troweling.
Darbying is done for the same reason as bullfloating,
that is, to correct small irregularities and smooth out
ridges left by striking off (Fig. 26). Because of its long
Fig. 23. A roller screed can be used to strike off and level handle, the bullfloat is easy to use on a large area, but the
the concrete. length of the handle detracts from the leverage, so that
close tolerances are difficult to achieve. The bullfloat may
slightly depress the surface near an edge form and a darby
truss-type surface vibrator. The initial strikeoff and con- must then be used to relevel the surface.
solidation of the concrete will have a greater effect on sur- Where close tolerancesare required, a scraping straight-
face tolerances and levels than subsequent operations of edge can be used to advantage. Minor surface irregulari-
floating and finishing. The secret of proper strikeoff and ties and excess laitance are removed by scraping with a
compaction is to maintain an adequate surcharge of con- IO-ft straightedge (Fig. 27). It should be used with a
crete at the screed face; a Gin.-thick slab needs a surcharge smooth, continuous action to float the surface; a jerky,
of about 1 in. cutting action is used only for removing high spots. Each
Strikeoff and consolidation must be completed before pass should overlap one-half the length of the previous
any excess water bleeds to the surface. If power-driven pass. Surface smoothness should be checked as late in the
equipment is used properly to strike off low-slump con- finishing operations as possible but while the concrete is
Fig. 25. Bullfloating corrects small irregularities and Fig. 27. A scraping straightedge removes minor surface
smooths out ridges. irregularities and excess laitance.
Jointing
While the edging is being done, or immediately after, the
control joints should be made unless they are to be sawed.
Jointing is a most important finishing step since proper
jointing can eliminate unsightly random cracks.
a Control joints can be made with a hand groover, a pre-
formed insert, or a power saw. The joint should extend
into the slab one-fourth of the slab thickness. A cut this
deep weakens the slab and induces a crack to form be-
neath the joint where it is inconspicuous.
There are few instances in industrial and commercial
floor work when a hand groover is used to make joints,
however when used its thin bit must be deep enough to
cut the slab one-fourth of the depth. An alternative is to
press a preformed insert into the fresh concrete until the
top is flush with the surface; finishing operations can then
continue.
On large floors it is more convenient to cut joints with
a power saw fitted with an abrasive or diamond blade
(Fig. 30). Again, saw cuts must be one-fourth the slab
Floating
Floating has four purposes: ( 1) to depress large aggregates
to just slightly beneath the surface; (2) to remove slight
imperfections and even out humps and voids for a level or
plane surface; (3) to compact the mortar at the surface in
preparation for later finishing operations; and (4) to keep
the surface open so excess moisture can escape.
Floating the stiffened concrete is done by machine.
Either a power float with rotating steel disc or a troweling
machine equipped with float blades is used almost flat on
the surface. Changes in concrete temperature, air temper-
ature, relative humidity, and wind make it difficult to set
a definite time to begin floating. In cold weather, it might Fig. 30. Control joints can be made by a power saw. These
be 3 hours; in hot weather, the concrete may stiffen very joints induce straight-line cracking at predetermined
rapidly. However, when the water sheen has disappeared, locations.
thickness. Sawing usually begins as soon as the surface of the wearing surface. When done correctly, curing re-
is firm enough so that it will not be tom or damaged by duces the risk of cracking, crazing, curling, and dusting.
the blade, usually within 4 to 12 hours after the concrete The purpose of curing is to maintain favorable condi-
hardens. tions under which concrete hardens and continues to gain
The method of constructing control joints must relate strength and wear-resistance by keeping it moist and
to the service use of the floor. Wide joints and inserts, for warm for a fixed period of time. A concrete floor slab has
example, may perform poorly under small hard wheels. a large exposed surface area in relation to its volume. This
means that water will evaporate very quickly from an un-
Troweling protected surface causing early drying and leavinga weak,
cracked, crazed, dusting floor. Prompt and adequate cur-
A power trowel is like a power float except that it is fitted ing, therefore, is mandatory. The slab should be continu-
with smaller, individual steel-trowel blades that can be ously moist-cured for at least 7 days. A longer period is
tilted slightly to exert pressure on the surface. Generally, desirable.
greater tilt will produce a smoother, more dense, bur-
nished slab surface. Three alternate methods of curing are suggested:
Power-troweling should start when the excess moisture 1. Wet-cure by fully covering the surface with wet bur-
brought to the surface by initial power-floating has evap- lap as soon as it can be placed without marking the
orated and the concrete is not sticky (Fig. 3 1). The wait- surface (Fig. 32). Keep the burlap continuously wet
ing time between floating and troweling depends upon and in place as long as possible.
the absence or presence of an admixture in the concrete
and the atmospheric condition at the surface.
Power-troweling should be done in a systematic pat- 2. Wet-cure by fully covering the previously wetted
tern. Two or more passes frequently are required to in- surface with plastic sheeting or waterproof paper as
crease the compaction of fines at the surface and give soon as it can be placed without marking the surface
greater resistance to wear. Time must be allowed between (Fig. 33), and keep in place as long as possible.
each troweling for the concrete to stiffen and the water 3. Seal the slab surface and edges by spraying a liquid-
sheen to disappear. The tilt of the trowel blades should membrane-forming curing compound on the fin-
be increased with each pass to exert additional pressure ished surface. The curing compound should be a
as the concrete hardens. Each successive troweling should type that leaves no permanent discoloration on the
be made in a direction at right angles to the previous pass. surface and does not interfere with the application
of any subsequent surface treatment or overlay.
A combination of these methods can be used. For ex-
Curing ample, a cover of burlap, plastic, or paper can be kept on
for 5 days and then a liquid-membrane-forming curing
Curing the concrete has a significant influence on the compound can be applied so that the concrete will dry out
strength, wear resistance, final quality, and performance slowly and extend the period of curing.
large open areas, A in. from end to end and side to side
can be tolerated. In other words, the entire floor surface
would fall within a plane of + 1% in. from the datum floor
elevation shown on the building plans. The tolerance
across a joint should be A2 in. Surface irregularities can
be measured with a profilograph floorcontour-measur-
ing instrument. The instrument can be used to monitor
placing and finishing techniques on a day-today basis.
High-density industrial warehouses using high-rise-
storage racks and high-lift-turret trucks require especially
flat floor surfaces for efficient operation. Knownas super-
flat floors, the differences in elevation of the surface of
these slabs must be minimal over distances of from as
little as 12 in. to as much as 10 ft, often a maximum of %2
in. in the former and /8 in. in the latter. Since construction
of such closely toleranced floors can be expensive, the
exact requirements for a project must be established
through consultation between the handling equipment
manufacturer, owner, and specifier, and then clearly out-
lined in the job specifications along with the method of
measurement as well as corrective techniques (usually
grinding) to bring an out-of-tolerance area back to a sat-
Fig. 33. Wet-curing can also be done by covering the isfactory degree of flatness.
previously wetted surface with plastic sheeting for as long
a period as possible.
Evaluation of Damage
*For information on painting concrete, see fainring Concrere. Port- Evaluation of damage is necessary not only to determine
land Cement Association publication ISl34T. 1980. the method of repair to be used but also to ensure that the
repair will be permanent and the damage will not extend Drycleaning. Mechanical methods offer an efficient
into the concrete surrounding the repaired area. Follow- and economical way to dryclean a concrete surface.
ing are the principal factors to be considered before mak- Equipment is available for scabbling, scarifying, grind-
ing a final decision on repair: ing, shotblasting, planing, and flame cleaning. Some
1. The general condition of the floor slab,* that is, loss machines have a variety of interchangeable cutting and
of slab support, strength and thickness of the con- brushing heads.
crete, the extent of badly worn areas, joints, cracks, Scabbling uses an air-driven machine that has a vary-
and contamination of the surface by oil or grease, ing number of pistons mounted in a block. Each piston
paint, chemical attack,** and staining.? is fitted with a tungsten carbide bit. Operating much the
2. Intended use of the floor after repair-which may be same as a bushhammer or chipping hammer (Fig. 34), the
quite different from its previous or present use. striking action shatters away the surface contamination,
3. Limitations to raising the level of the finished floor. exposing a clean, sound concrete with a good mechanical
key for bonding.
4. Time allowed for repair work.
Unbonded Toppings
Thin Bonded Overlay* The minimum thickness of an unbonded topping is 3 in.
with 6 in. suggested for floors carrying heavy moving
A fully bonded concrete topping can be % in. or more loads and subjected to severe impact. The amount of
thick, while for unbonded construction the minimum is work required to prepare the old slab is negligible, con-
3 in. The thickness of overlays limits where they can be sisting only of sweeping clean and filling in badly worn
used because they raise the level of the floor. areas and holes with a cement and sand mortar.
The best surface preparation for a bonded overlay is A separation layer should be used to ensure that there
obtained with one of the drycleaning methods described will be no bond between the old and new concrete. A4-mil
previously. If contamination is present after drycleaning, polyethylene sheet is adequate for this purpose. The sepa-
then wetcleaning methods should be used to further ration layer prevents cracks in the old floor from being
cleanse the surface. An effective check for contamination reflected through into the new topping. It also reduces
is to sprinkle water on the concrete: if the water forms friction at the interface so that the new topping can move
little globules, contaminants are present that will inter- (from drying shrinkage and thermal changes) indepen-
fere with bond. If the water is immediately absorbed, it dently of the floor below.
can be assumed that the concrete is clean. The concrete mix proportions should be the same as
Mix Preparation for Bonded Overlays. Volume pro- those suggested for bonded toppings or for new floor
portions are suitable for small patches; but for large re- construction.
surfacing jobs, weight batching should be used to elimi- Placing and finishing operations are similar to those
nate variations in quality. The mix design varies, depend- used to construct a new concrete floor. An unbonded
ing upon the depth of concrete to be placed. The water- overlay permits control and construction joints in the old
cement ratio can range from 0.45 to 0.33, using 6 to 9 or slab to be ignored. The new topping can have a jointing
10 bags of portland cement per cubic yard, and producing arrangement designed for the most convenient panel size
concrete strengths at 28 days from 4500 psi to 9000 psi. and shape, taking into account the thickness of the top-
Aggregates can be selected for their hard-wearing and ping and the amount of reinforcement provided (if any).
abrasion-resisting qualities. A low-slump concrete, 2 in. However, isolation joints in the old slab must be repeated
to 4 in., generally works well. Adjustments in consistency in the new topping.
depend on thickness of topping, temperature, and equip-
ment available to do the work. A water-reducing admix-
ture can improve workability of low-slump concrete, and Repair of Cracks and Joints
a superplasticizer can produce high-strength concrete at
normal consistencies. Although joints are placed in concrete floors to provide
Formwork. The same principles that apply to edge crack control, sometimes problems arise from heavy
forms in general apply to topping forms. The method of usage, improper joint design or location, and careless
installing and anchoring varies greatly depending on the construction methods. The greatest portion offloor main-
job conditions. The forms and intermediate screeds must tenance is for crack and joint repair.** The principal
be set to grade and positively anchored in position to causes of distress are
maintain a true level. Poor subgrade support
Laying the Topping. The topping should be placed in Inadequate load transfer
small panels. The rate at which this work is completed Floor overloads
should not be overestimated. The topping must be well Excessive joint spacing
compacted to ensure bond, strength, and durability. On Joint filler failures
large projects, a self-propelled finishing machine with When a problem develops, its cause should be found
vibrating screed should be used. On smallerjobs, a manu-
ally operated vibratory screed or tamper can give satis- and corrected before any repair is undertaken.
factory results. Filling Cracks (Sealing)
Various methods of finishing floor slabs have already
been discussed. The new surface must be cured for at Only those cracks that are open wide enough to permit
least 3 days. One practical and satisfactory method is to the entry of a pourable joint filler or a mechanical routing
cover the surface with polyethylene sheets, with laps
sealed and all edges held down. After removing thesheets,
an application of curing compound will extend the curing
*Resurfacing Concrere Floors. Portland Cement Association publi-
period. cation IShUT, 1981.
All joints in the original floor must be duplicated **For repair of outdoor paving, storage yards, driveways, etc., see
exactly in the new topping; that is, they must be located Maintenance of Joints and Cracks in Concrete Pavement, Portland
directly over the joints in the original slab and must be of Cement Association publication ISl88P, 1976.
tool should be filled. Tightly closed cracks subject only
to light industrial traffic should be left alone, but kept
under observation and filled only if they open up or show
signs of spalling.
Each side of the open crack must be refaced so that the
surfaces are cc mpletely free of dust, dirt, debris, and any-
thing else that might prevent bonding of the new filler
material. Special tools such as random<ut saws or crack
grindersand vertical-bit routers should be used. The
crack should be refaced to a l-in. minimum depth or its
full depth without deepening, whichever is less, and then
blown out with compressed air ahead of refilling.
Patching S~dls
Spalling is the dislodging of fragments of concrete from
Fig. 35. Joints and cracks that move can be refilled with the slab at the joint edges, usually from the repeated im-
flexible sealant. pact of hard wheels moving across the joint.
The procedures for bonded patching should be used to
repair spalls. The spalled concrete should be removed
to at least a Zin.-minimum depth and the area blown
clean (Fig. 36). A coating of bonding grout should then
be applied and the patching mortar compacted into place,
High-strength epoxy resin adhesives should not beused finished, and wet-cured. The joint can be reformed by
to rebond and seal cracks where subsequent appreciable placing in the joint groove a thin strip of wood, metal, or
movement is expected, since this could lead to cracking
plastic that has been coated orcovered with a bond-break-
elsewhere in the floor. A flexible epoxy or an elastomeric ing material. The patching mix should then be compacted
filler should be used in cracks that move (Fig. 35). from one or both sides against the form.
If further movement is unlikely, a rigid mortar such as Individual spalls that occur on both sides of ajoint can
cement and sand; cement, sand, and latex; or epoxy and also be repaired by patching the entire cavity and reform-
sand should be used. The crack should first be cut out ing the joint with a saw cut as soon as possible after the
with a special tool and thoroughly cleaned, as described patch is placed. The joint in the patch must be equal in
for patching, before the mortar is put in place. The mor- width to the old opening or slightly wider and it must be
tar must be thoroughly compacted and cured in a manner to the full depth of the patch to avoid subsequent spalling.
suitable to the particular material used. There is a lesson to be learned from the patching and
repair of concrete floors: At the time a new building is
Refilling Joints (Resealing)
constructed, it is essential that the concrete work be prop-
Where joint filler has failed, the old filler must be removed erly designed and executed and that the quality of the
to a depth that will accommodate the new sealant. The concrete work be correct for the intended use. If the les-
same procedures and sealant materials for filling cracks son is ignored, great annoyance and expense can arise
are used for refilling joints. from the resultant repairs.