You are on page 1of 8

104

Luke Davies
Graduate Engineer
Lightweight backfill
Atkins materials in integral
bridge construction
Abstract
Analysis of integral bridge structures shows that lateral earth pressures
Tomasz Kucki on the end abutments have a dominant influence on the sizing of
Senior Engineer bridge components. Thermal cyclic movements induced by deck
expansion cause densification of backfill material, leading to the build
Atkins
up of high pressures behind the abutments.
Measures to reduce these pressures by the use of alternative backfill
materials can be highly beneficial to the structure as a whole, with extra
expenditure on the backfill material being offset, and in some cases
exceeded, by savings in material quantities in the rest of the structure
and build time.
Chris Fry This paper examines three contrasting backfill options that were
Head of Technology considered during the design of Cottington Road Overbridge in
Atkins Kent: 6N granular backfill; lightweight expanded clay; and expanded
polystyrene (EPS) blocks. Although more expensive than the other
options investigated, the EPS block option was selected as the most
economical solution for this particular structure due to material savings
elsewhere in the structure.
Although it did not form part of the decision making process, this
paper also shows a significant saving in transport-related carbon dioxide
Jamie Bull emissions through preferring EPS blocks to expanded clay.
Senior Sustainability
Consultant
oCo Carbon
Introduction Case study: Cottington
Maintenance issues with articulated Road Overbridge
bridge structures typically generate Kent County Council is currently
whole life costs due to the need to constructing Phase 2 of the major arterial
replace bearings and expansion joints, highway corridor East Kent Access (EKA).
and provide for safe/adequate inspection
access. Severe durability problems can Phase 2 involves upgrading two lengths
also arise from the ingress of de-icing salts of highway (the A299 and the A256),
Nomenclature
d Thermal displacement at top of wall into the bridge deck and substructure. together with the provision of a new link
H Retained height between these two strategic highways.
In accordance with Highways Agency
K* Earth pressure coefficient in accordance
design procedure BA 42/966, bridge See Figure 1: Cottington Road Overbridge
with BA 42/96
K0 At rest earth pressure coefficient decks up to 60m span with skews not location plan.
Kp Passive earth pressure coefficient exceeding 30 degrees are generally The existing single carriageway of the
L Length of EPS layer required to be continuous over A299 fronting Kent International Airport
Q EPS grade intermediate supports and integral with between Minster Roundabout and Cliffsend
q Pressure abutments to address such issues.
Strain Roundabout will be replaced with a new
Effective internal friction angle dual carriageway, and the existing A256
Geotechnical

between Richborough Roundabout and


Ebbsfleet Roundabout will be improved to
two-lane dual carriageway standard. The
new link will be provided between Cliffsend
Roundabout and Ebbsfleet Roundabout,
with a new roundabout at Sevenscore with
an exit towards Lord of the Manor.

47
large hogging moments experienced at
the deck/abutment interface. Resisting
moments of this magnitude would
require 28 no. 1200mm diameter RC
piles with a two-layer cage of T40
reinforcement per abutment wall.
Additionally, there would be a need to
provide two rows of 900mm diameter
piles spaced at 2m centres to support
the wing walls, the design being dictated
by the need to control lateral deflection
at the top of the wall. This option was
evidently a costly solution and alternative
lightweight-backfill options were
then considered.
Expanded clay
Expanded clay was first used in the
1950s to provide insulation to roads,
railways and ditches. It is formed by
heating and firing natural marine clay
in a rotary kiln at temperatures up to
1150 degrees centigrade. The process
transforms the clay into various-sized
lightweight ceramic granules, which
have a hard ceramic shell and a porous
2010 Google Map data core. In this form, the material has
2010 Tele Atlas excellent insulating properties and is also
extremely lightweight with a unit weight
of approximately 4 kN/m3 (compared to
Figure 1. Cottington Road Overbridge location plan 19kN/m3 for 6N), greatly reducing lateral
pressures on bridge abutments and
This work involves two highway crossings overlying Head, Thanet Sand and Chalk. retaining walls1.
of the Ramsgate to Minster railway line, This ground strata dictates the use of deep
requiring an underpass at Cliffsend and piled (rather than spread foot) foundations. Expanded clay is much less dense than
an overbridge at Cottington. regular backfill material. However, the
Backfill options internal angle of friction () is greater and
The structure Three abutment backfill options were leads to increased passive earth pressure.
The structure proposed at Cottington is considered at design stage and a solution This coupled with the requirement to
a two-span integral, steel and concrete was chosen predominantly in terms of provide a 6N granular backfill capping
composite deck, with a 30 degree end structure capital expenditure. layer, means that the initially realised
skew and a 32 degree intermediate pier savings are diminished.
skew. Each span is 30.7m long skew 6N granular backfill
Usually, a granular backfill material There are a number of design
(26.6m square) measured along the EKA
is provided behind abutments. This considerations to take into account if
principal road centreline.
limits selection to 6N or 6P material as specifying expanded clay backfill:
See Figure 2: Cottington Road described in Table 6/1 of the Manual The porous particles will absorb
Overbridge elevation. of Contract Documents for Highway moisture after placement, increasing
The end abutments will comprise 1.5m Works - Volume 1 Specification - Series unit weight;
thick, 10m high, reinforced concrete 6005. As one of the most widely used Expanded clay should not be placed
(RC) walls on 900mm diameter RC bored and well understood backfill materials, below the water table or in areas
piles with independent RC wing walls. this was first considered as it is a standard prone to flooding as the particles may
The intermediate pier will comprise 6 no. design solution. become buoyant;
750mm diameter RC columns at 7.5m Unfortunately, the high density of The particles have a lower crushing
spacing, with each column founded on a the backfill material coupled with the strength compared to natural soils,
900mm diameter RC mono-pile. substantial height of retained material and so ordinary test methods such as
Ground conditions at this site are fairly resulted in large moments being applied the California Bearing Ratio test are
uniform and comprise Made Ground to the abutment wall piles, and equally not suitable;

Figure 2. Cottington Road Overbridge elevation


48
104 Lightweight backfill materials in integral
bridge construction

Material 6N Granular backfill Expanded Clay EPS blocks

Eliminates
settlement period
Placed by hand
Free draining
Well understood material No compaction required
1m compaction layers
Cheap and readily available Inhibited water absorption
Chemically inert
Advantages Ability to use normal Immune to attack from
Resistant to fire and frost bacteria and mould
compaction plant and
testing methods Re-usable, no special Minimises settlement issues
requirements for disposal
Can be recycled
Placed using same
methods as normal backfill

Heavy winds can blow the


High unit weight finer material increasing
0.25m compaction layers dust levels Susceptible to attack
Susceptible to Aggregate dust containing from hydrocarbons
Disadvantages
settlement issues quartz can constitute a long Expensive
Susceptible to frost heave term health risk
issues No accepted test for
measuring density in-situ

Unit weight, d (kN/m3) 19 4 0.5

Angle of friction,
35 37 N/A
(degrees)

Cost (/m3) 35 40 - 50 60 - 80

Table 1. Backfill materials comparison

A capping layer is required (see movements and braking forces Density: where higher load bearing
previous) to spread traffic loads introducing stresses with accompanying capacities are required, higher grade
sufficiently to ensure that the strains in the EPS blocks. EPS blocks are specified but these
particle (in its mass) crushing limit is have a higher density;
not exceeded. See Figure 3: Typical EPS stress
strain curve3. Localised damage: the use of HDPE
In the case of Cottington Road will also require a capping layer of
Overbridge, assessment showed that the There are a number of design granular backfill to spread applied loads
use of expanded clay backfill allowed the considerations to take into account when sufficiently to prevent localised damage
foundations to be reduced from 28 no. specifying EPS blocks: to the EPS blocks or HDPE membrane.
1200mm diameter piles (in the case of Chemical attack: EPS is vulnerable The use of EPS as an alternative backfill
6N granular backfill) to 21 no. 900 mm to attack from hydrocarbons. So, if material had significant economic benefits
diameter piles (per abutment), although it is to be used in highway or railway for the Cottington Road Overbridge
heavy reinforcement would still be required embankments, it must be protected by structure. The abutment foundations
and the wing walls would still require two concrete encasement, or by use of high were able to be reduced from the 28
rows of piles to control deflection. density polyethylene (HDPE) sheets; no. 1200 mm diameter piles of the
EPS blocks UV resistance; 6N backfill option to 21 no. 900mm
Fire protection; diameter piles using a single layer cage
Focus then turned to the use of EPS of T40 reinforcement, and the wing
blocks. EPS can almost eradicate lateral wall foundations could be reduced to a
pressures on civil engineering structures as single (rather than double) row of piles
surcharge loads are taken vertically to the eradicating the need for a pile cap.
ground beneath.
See Table 1: Backfill material comparison.
EPS has a proven track record as a
Geotechnical

fill material and has been used in the


construction of embankments since the
Stress

1970s offering the benefits of removing


specialised foundations, eliminating long
surcharge periods and reducing settlement
problems after construction2.
Lateral pressure is applied to the Strain (%)
abutment walls by the EPS blocks in Figure 3. Typical EPS stress strain curve
response to longitudinal temperature

49
Alternative backfill study
In order to provide a numeric comparison
of loads applied to an integral bridge
structure by the three backfill materials
discussed, and the varying effects that
this has on the structure, a simple integral
bridge structure will be analysed and the
results discussed below.
The integral bridge structure analysed
for the purpose of this study is an overall
60m, (equal) two span bridge, 25m wide
with no skew. Main girders are spaced
at 2.75m. Abutments are 1500mm thick
RC walls and founded on 18 no. 900mm
diameter RC piles each. The central pier
consists of 9 no. 750mm diameter RC
columns, each column being founded on a
single 900mm diameter RC pile.
SuperStress is used to model the structure
as a frame with fixed connections between
deck and supports, the piles are modelled Figure 4. Simplified study General Arrangements
using spring supports.
See Figure 4: Simplified study
General Arrangements.
For transparency, results are given for
lateral pressures on the abutments only, all
other dead and live loads being ignored.
It should be noted that pressures exerted
on the abutment walls by EPS blocks will
only be experienced in Combination 36
of BD37/01 Loads for Highway Bridges
as this is the only case where restraint to
movement temperature effects are taken
into account.
6N granular backfill
Earth pressures exerted on the abutment
Figure 5. Earth pressure distributions
walls are related to compression stresses
in the retained soil. However at the top
BA 42/96 gives an equation to calculate Lateral earth pressure at the top of the
of the wall, higher earth pressures will be
the relationship between K*, the height wall = 0 kN/m2
experienced because of wall friction.
(H) and thermal displacement at the top
of the abutment (d): Lateral earth pressure half way down the
BA42/96 - The Design of Integral Bridges'7
wall = K* soil z = 2.02 x 19 x 5 = 191.9kN/m2
suggests earth pressure distributions for
K* =K0 + (d/0.05 H)0.4 Kp
different structural forms. For the purposes This earth pressure then remains constant
of this study a full height frame abutment This equation uses Kp obtained using the to the base of the wall since it does
form is assumed. Clause 3.5.3 of BA 42/96 Eurocode 7 approach, for 6N granular backfill not fall below the earth pressure value
suggests a distribution comprising: with = 35o, K0 = 0.426 and Kp = 6.5. calculated using its K0 coefficient up to
this point.
A uniform value of K* over the top half BA 42/96 clause 2.10 states the
of the retained height of the wall, with; characteristic thermal strain for composite See Figure 5 (a): Earth pressure
Lateral earth pressure then remaining deck construction in the UK can be taken distribution - 6N granular backfill.
constant with depth as K* drops as 0.0005, therefore:
towards K0; d = 0.0005 x 30000 = 15 mm
If the lateral earth pressure falls to K0
then below that depth pressures are K* = 0.426 + (15/0.05 x 10000)0.4
applied in accordance with the in situ x 6.5 = 2.02
value of K0.

50
104 Lightweight backfill materials in integral
bridge construction

Expanded clay Layer


The calculation of build-up of lateral earth Depth Deflection Strain Pressure
Node length
pressures behind the abutment when (m) (mm) (%) (kN/m2)
(mm)
using expanded clay is identical to that
for normal granular fill, in accordance 1 0.00 - - - 0
with BA42/96.
2 1.00 - - - 38
The expanded clay backfill wedge abuts
the vertical rear face of the abutment wall 3 1.64 13.9 8540 0.16 20
and is set to a 1 in 1 incline in relation
to the normal embankment fill behind. 4 2.29 13.7 8540 0.16 19
A 1000mm capping layer of 6N granular
backfill is assumed to prevent crushing of 5 2.93 13.6 7320 0.19 22
the expanded clay by applied dead and
live loading. 6 3.57 13.4 7320 0.18 22

Lateral earth pressure at the top of the 7 4.21 13.2 6100 0.22 26
wall = 0 kN/m2
8 4.86 12.9 6100 0.21 25
Lateral earth pressure at capping layer
interface = K* soil z = 2.02 x 19 x 1 = 38 9 5.50 12.7 4880 0.26 31
kN/m2
10 6.14 12.4 4880 0.25 30
K* then increases to reflect the expanded
clay material properties with = 37o, K0 11 6.79 12 3660 0.33 39
= 0.398 and Kp = 7.0:
12 7.43 11.7 3660 0.32 38
K* =0.398 + (15 / 0.05 x 10000)0.4 x 7.0
= 2.12 13 8.07 11.3 2440 0.46 56
Lateral earth pressure half way down the 14 8.71 11 2440 0.45 54
wall =
15 9.36 10.6 1220 0.87 104
K* (exp_clay zexp_clay + soil zsoil) = 2.12
(4 x 4 + 19 x 1) = 74 kN/m2 16 10.00 10.2 1220 0.84 100
This earth pressure then remains constant
Table 2: EPS lateral earth pressures exerted on abutment wall
to the base of the wall (as per 6n
granular backfill).
Total applied load (per unit width)
See Figure 5 (b): Earth pressure 1410 kN 100%
distribution Expanded clay.
Maximum hogging moment
16324 kNm 100%
EPS blocks
14 layers of EPS blocks abut the end (a) 6N granular backfill
Total applied load (per unit width)
supports, each layer increasing in length 592 kN 42%
at 1 in 1 benching steps to the interface
Maximum hogging moment
with embankment backfill. Using 6449 kNm 40%
this slope gradient limits lateral earth
(b) Expanded clay
pressures exerted on the back of the
Total applied load (per unit width)
EPS blocks. 376 kN 27%
A 1000mm capping layer of 6N granular Maximum hogging moment
backfill is assumed to prevent localised 3579 kNm 22%
(c) EPS blocks
damage of the EPS blocks and HDPE
membrane by applied dead and live
Figure 7. Bending moment diagrams
loads. Lateral earth pressures exerted by
this layer will be identical to those in 3.1
and 3.2. Lateral earth pressure at the top of the depending on the grade of EPS selected.
wall = 0 kN/m2
See Figure 5 (c): Earth pressure
d
Geotechnical

Lateral earth pressure at capping layer distribution EPS blocks.


interface = K* soil z = 2.02 x 19 x 1 =
38 kN/m2 Figure 6 shows a polystyrene block length
(L) being deformed by a distance (d).
q Pressure exerted on the abutment wall
by the EPS blocks occurs as described For example, assuming EPS grade (Q) of
previously. Abutment wall deflections due 90 kN/m2, deflection (d) of 10mm and
to thermal expansion of the deck (d) are layer length (L) of 6000mm:
L
used to calculate the strain () in each EPS = d / L = 10 / 6000 = 0.167%
layer, this then relates to a pressure (q) q = Q = 0.167 x 90 = 15 kN/m2
Figure 6. Development of EPS pressure

51
Figure 8: Embodied carbon footprint comparison Figure 10
Figure 8: Embodied carbon footprint comparison Figure 10
Embodied carbon of EPS and expanded clay backfill Tot
See Table 2: EPS lateral earth pressures 500 Embodied carbon of EPS and expanded clay backfill Tot
1200
exerted on abutment wall. 450
500 1200
1000
Results 400
450
Analysis of the effects of the three different 350 1000
800
400

saved

saved
backfill materials on the structure is carried 300
out using structure analysis software. 350 800
250 600
saved

saved
Figure 7 shows the bending moment 300
2


tCO tCO
tCO2tCO 200
diagrams produced when the various 250 600
400
backfill loads are applied to the structure. 150
200
100 400
200
Applying 6N granular backfill to 10m 150
high integral abutments produces huge 50
100 200
moments in the deck and at the top of 0 0
50
the wall. In this case there is a maximum Piling Piling rebar RC concrete RC rebar Backfill
hogging moment at the top of the wall 0 0
concrete
of over 16.3 MNm per metre width. Piling Piling rebar RC concrete RC rebar Backfill
In order to withstand moments of this concrete Expanded clay EPS
magnitude, very large heavily reinforced Expanded clay EPS
sections are required. Figure 11:
Figure 9: Transport carbon footprint comparison (note the logarithmic scale)
Using expanded clay backfill to abut the Figure 8. Embodied carbon footprint comparison
end supports reduces the applied load Figure 9: Transport carbon footprint comparison (note the logarithmic scale) FigureBre
11:
to 42% of that seen using 6N backfill, Transport carbon of EPS and expanded clay backfill
reducing the maximum hogging moment Bre
600
by 60% to 6.4 MNm per metre width. 1000 Transport carbon of EPS and expanded clay backfill
When EPS block loads are applied to 600
500
1000
the structure the bending moments
produced in the structure are significantly 100 500
400

saved
lower than those produced by either 6N
granular or expanded clay backfill. In this 100
saved

400
300

saved
case the maximum hogging moment is

2
10

tCO2tCO
saved

22% of the 6N value at 3.6 MNm per 300


2

200
tCO2tCO

metre width. 10
200
100
Environmental impacts 1

1 Piling Piling rebar RC concrete RC rebar Backfill 100


0
As well as final structure cost, there are concrete
other factors that need to be considered 0 Piling Piling rebar RC concrete RC rebar Backfill
concrete 0
when selecting an appropriate backfill
material. Over the past decade, initiatives 0 Expanded clay EPS
to curb global warming, and make
new construction more sustainable, Figure 9. Transport carbon footprint Expanded
comparison clay EPS scale)
(note the logarithmic
have led to an increased interest in the
environmental impacts of new structures. those materials. Emissions during the EPS case due to the reduced structural
This section looks primarily at the carbon construction process are expected to be requirements and also the lower density
emissions associated with the two similar for the two options, and there of the backfill material.
lightweight fill options. are methodological issues with end of
life costs such as the impossibility of Embodied carbon emissions
Carbon footprint
predicting how materials such as EPS will Many of the materials used in
The carbon footprint of a construction be recycled in the future, especially given construction are highly processed and
project includes all sources of emissions the long service life of a road bridge. so contribute to carbon emissions by
including those associated with: the energy required to process them.
In a carbon footprint assessment it is The figures used are sourced from the
Production, processing and transport important to define the functional unit to
of materials; Inventory of Carbon and Energy4. Average
be assessed. As there are several factors values are used for the embodied carbon
The process of construction itself; affecting the amount of materials used of materials rather than assessing the
Any maintenance required; in the Cottington Road Overbridge, individual raw materials extraction and
the only suitable functional unit is the manufacturing processes of the products
Disposal of materials at the end of
bridge structure taken as a whole. Both specified. This means that the results and
their service life.
options are assumed to have the same recommendations can be more easily
Scope and functional unit service life (the risk of failure due to generalised to other situations.
This study looks at the carbon footprint hydrocarbon ingress has been assumed to
be designed out). The raw material used in the protection
of the two lightweight backfill options
of expanded clay is quarried but further
expanded clay and EPS. The scope The main change between the two cases energy-intensive processing is needed
is limited to the carbon footprint of is that less material is required in the for expanded clay to achieve its final
the materials used and transport of
52
104 Lightweight backfill materials in integral
bridge construction

otprint comparison Figure 10: Carbonfootprint comparison


otprint comparison Figure 10: Carbonfootprint comparison
of EPS andstate.
expanded clay backfill Total embodied carbon of EPS and expanded clay backfill
of EPS and expanded clay
Due to lack backfill
of specific data, the Total embodied carbon of EPS and expanded clay backfill
embodied CO2 of expanded clay has been 1200
taken as that of General simple baked 1200
clay products at 0.22kgCO2/kg. 1000
1000
Conversely, the production of plastics
is an energy intensive process. The 800

saved
800
saved
embodied CO2 per kg is over 10 times
that of the expanded clay at 2.5kgCO2/ 600

tCO 600
kg. This might be expected to make
tCO

EPS blocks the least sustainable option 400


400
in terms of backfill material, however it
neglects the difference in weight. 200
200
As with cost the footprint should be 0
measured per m3 which makes the two 0
rebar RC concrete RC rebar
options much Backfill
closer. On this metric the Piling Piling rebar RC concrete RC rebar Backfill
rebar RC concrete RC rebar Backfill Piling
concrete Piling rebar RC concrete RC rebar Backfill
expanded clay gives 88kgCO2/m3 and the concrete
Expanded clayEPS gives 75
EPS 100kgCO2/m3 depending Expanded clay EPS
Expanded clayon the density
EPS of EPS specified. Expanded clay EPS

See Figure
otprint comparison (note8: the
Embodied carbonscale)
logarithmic Figure
Figure 11
: Breakdown
10. of comparison
Carbon footprint carbon footprint savings
otprint comparison
footprint(note the logarithmic scale)
comparison. Figure 11: Breakdown of carbon footprint savings
Transport carbon emissions Breakdown of embodied carbon savings when specifying
Breakdown of embodied carbon savings when specifying
n of EPS and expanded
Construction clay can
materials backfill
also be heavy EPS in place of expanded clay backfill
n of EPS and expanded clay backfill EPS in place of expanded clay backfill
which leads to a lot of transport related 600
carbon emissions. In the case of bridge 600
structures, the two materials which make 500
up the majority of transport emissions are 500
reinforced concrete and backfill as they 400
are the major components by weight.
saved

400
saved

Unprocessed aggregates, despite their 300


300
2 2

low embodied carbon per tonne, are


tCO
tCO

heavy materials and so the carbon 200


footprint of transporting them can be 200
quite high. This also means that the 100
total emissions are very sensitive to the 100
rebar distance they
RC concrete are transported.
RC rebar For the
Backfill
rebar RC concrete RC rebar Backfill far 0
most part they are not transported 0
from the place they are produced. Piling Piling rebar RC concrete RC rebar Backfill Total
Piling
concrete Piling rebar RC concrete RC rebar Backfill Total
concrete
Expanded clay6N granular
EPSfill is a quarried material, with
Expanded claya number EPS
of source locations scattered Embodied CO2 Transport CO2
over the UK meaning that transport Embodied CO2 Transport CO2
distances are kept to a minimum. Figure 11. Breakdown of carbon footprint savings
Of the processed materials, there are a
number of concrete plants in the East
6N granular fill and expanded clay are Results
easy to reuse or dispose of while EPS The expanded clay option has a carbon
Kent area and so this does not require
blocks are not easy to reuse, and would footprint of 1,880 tonnes while the EPS
much transport. EPS and expanded clay
need to be disposed of correctly or option has a carbon footprint of 1,083
have to be transported greater distances
recycled. This could include incineration tonnes. Relative to the expanded clay,
to site.
with energy capture which would offset the EPS design saves approximately 800
See Figure 9: Transport carbon its carbon footprint to some extent. tonnes of carbon dioxide emissions.
footprint comparison.
Other environmental impacts See Figure 10: Carbon
Resource use There are a number of other impacts footprint comparison.
The use of non-renewable materials has which are beyond the scope of this
paper. These include toxicity of materials The vast majority of the savings
Geotechnical

impacts beyond embodied carbon and


used, emissions to air other than carbon comes from avoided transport of
emissions associated with transport. All
dioxide (such as sulphur dioxide, nitrous heavy materials. In fact the savings on
materials must be disposed of at the end
oxides, etc). Without carrying out a more transportation of fill material to site
of their service life. None of the materials
in depth life cycle analysis it is impossible has the greatest impacts on the carbon
used are renewable, although they can all
to say which of the options will have the footprint of the finished structure. Fill and
be re-used or recycled to some extent.
lowest impact in these other categories. expanded clay are both heavy materials,
relative to EPS. Embodied carbon is
proportional to the weight of material
used and so the embodied carbon of

53
the EPS option is significantly lower than Road, the EPS block and expanded favour of EPS in cases where the cost
the expanded clay option due to its clay solutions had very similar cost argument is marginal, or policy measures
lower density. implications on the project; however, EPS may be introduced which give the
blocks were selected because of problems embodied and transport carbon saved a
See Figure 11: Breakdown of carbon experienced in controlling deflection of greater financial value.
footprint savings. the independent wing walls.
Acting as a counter to this, the issues
EPS blocks provide a good solution that arise with the need to protect the
Conclusions to design problems such as retaining material from hydrocarbons and the huge
Although the results show the use of EPS wall deflection or restraints of bearing effort required to rectify problems should
blocks abutting the end supports of an pressure; however, in the absence of the protection fail will make Technical
integral bridge structure greatly reduces these issues the use of EPS blocks is Approval Authorities very reluctant to
pressures exerted on the walls and unlikely to be financially worthwhile. authorise this as a design solution. A
design loads experienced by the bridge robust technical solution to this problem
The recent increased emphasis on making would allow large reductions in the
components as a result, it is often less structures more sustainable is likely to
economical to use this as a solution than transport carbon footprint of backfill.
encourage the use of EPS blocks due to
expanded clay backfill material. Regarding the major reduction in transport-related
the integral bridge at Cottington emissions. This may tip the balance in

References
1. Maxit. (2004). Maxit LWA Lightweight fill for civil engineering [Brochure].
2. S+B. (2010). Product Handbook Civil Engineering [Brochure].
3. Jablite. (2010). Technical Information Civil Engineering using Fillmaster EPS [Brochure].
4. Hammond, G.P. and Jones, C.I. (2008), Inventory of Carbon and Energy V1.6a [University of Bath]
5. Department of Transport, Manual of Contract Documents for Highway Works, Vol 1, Specification of Highway Works,
Series 600, 2009.
6. BD 37(0) Loads for Highway Bridges, Highways Agency, UK
7. BD 42/96 The Design of Internal Bridges, Highways Agency, UK

54

You might also like