Professional Documents
Culture Documents
104 - Lightweight Backfill Materials in Integral Bridge Construction PDF
104 - Lightweight Backfill Materials in Integral Bridge Construction PDF
Luke Davies
Graduate Engineer
Lightweight backfill
Atkins materials in integral
bridge construction
Abstract
Analysis of integral bridge structures shows that lateral earth pressures
Tomasz Kucki on the end abutments have a dominant influence on the sizing of
Senior Engineer bridge components. Thermal cyclic movements induced by deck
expansion cause densification of backfill material, leading to the build
Atkins
up of high pressures behind the abutments.
Measures to reduce these pressures by the use of alternative backfill
materials can be highly beneficial to the structure as a whole, with extra
expenditure on the backfill material being offset, and in some cases
exceeded, by savings in material quantities in the rest of the structure
and build time.
Chris Fry This paper examines three contrasting backfill options that were
Head of Technology considered during the design of Cottington Road Overbridge in
Atkins Kent: 6N granular backfill; lightweight expanded clay; and expanded
polystyrene (EPS) blocks. Although more expensive than the other
options investigated, the EPS block option was selected as the most
economical solution for this particular structure due to material savings
elsewhere in the structure.
Although it did not form part of the decision making process, this
paper also shows a significant saving in transport-related carbon dioxide
Jamie Bull emissions through preferring EPS blocks to expanded clay.
Senior Sustainability
Consultant
oCo Carbon
Introduction Case study: Cottington
Maintenance issues with articulated Road Overbridge
bridge structures typically generate Kent County Council is currently
whole life costs due to the need to constructing Phase 2 of the major arterial
replace bearings and expansion joints, highway corridor East Kent Access (EKA).
and provide for safe/adequate inspection
access. Severe durability problems can Phase 2 involves upgrading two lengths
also arise from the ingress of de-icing salts of highway (the A299 and the A256),
Nomenclature
d Thermal displacement at top of wall into the bridge deck and substructure. together with the provision of a new link
H Retained height between these two strategic highways.
In accordance with Highways Agency
K* Earth pressure coefficient in accordance
design procedure BA 42/966, bridge See Figure 1: Cottington Road Overbridge
with BA 42/96
K0 At rest earth pressure coefficient decks up to 60m span with skews not location plan.
Kp Passive earth pressure coefficient exceeding 30 degrees are generally The existing single carriageway of the
L Length of EPS layer required to be continuous over A299 fronting Kent International Airport
Q EPS grade intermediate supports and integral with between Minster Roundabout and Cliffsend
q Pressure abutments to address such issues.
Strain Roundabout will be replaced with a new
Effective internal friction angle dual carriageway, and the existing A256
Geotechnical
47
large hogging moments experienced at
the deck/abutment interface. Resisting
moments of this magnitude would
require 28 no. 1200mm diameter RC
piles with a two-layer cage of T40
reinforcement per abutment wall.
Additionally, there would be a need to
provide two rows of 900mm diameter
piles spaced at 2m centres to support
the wing walls, the design being dictated
by the need to control lateral deflection
at the top of the wall. This option was
evidently a costly solution and alternative
lightweight-backfill options were
then considered.
Expanded clay
Expanded clay was first used in the
1950s to provide insulation to roads,
railways and ditches. It is formed by
heating and firing natural marine clay
in a rotary kiln at temperatures up to
1150 degrees centigrade. The process
transforms the clay into various-sized
lightweight ceramic granules, which
have a hard ceramic shell and a porous
2010 Google Map data core. In this form, the material has
2010 Tele Atlas excellent insulating properties and is also
extremely lightweight with a unit weight
of approximately 4 kN/m3 (compared to
Figure 1. Cottington Road Overbridge location plan 19kN/m3 for 6N), greatly reducing lateral
pressures on bridge abutments and
This work involves two highway crossings overlying Head, Thanet Sand and Chalk. retaining walls1.
of the Ramsgate to Minster railway line, This ground strata dictates the use of deep
requiring an underpass at Cliffsend and piled (rather than spread foot) foundations. Expanded clay is much less dense than
an overbridge at Cottington. regular backfill material. However, the
Backfill options internal angle of friction () is greater and
The structure Three abutment backfill options were leads to increased passive earth pressure.
The structure proposed at Cottington is considered at design stage and a solution This coupled with the requirement to
a two-span integral, steel and concrete was chosen predominantly in terms of provide a 6N granular backfill capping
composite deck, with a 30 degree end structure capital expenditure. layer, means that the initially realised
skew and a 32 degree intermediate pier savings are diminished.
skew. Each span is 30.7m long skew 6N granular backfill
Usually, a granular backfill material There are a number of design
(26.6m square) measured along the EKA
is provided behind abutments. This considerations to take into account if
principal road centreline.
limits selection to 6N or 6P material as specifying expanded clay backfill:
See Figure 2: Cottington Road described in Table 6/1 of the Manual The porous particles will absorb
Overbridge elevation. of Contract Documents for Highway moisture after placement, increasing
The end abutments will comprise 1.5m Works - Volume 1 Specification - Series unit weight;
thick, 10m high, reinforced concrete 6005. As one of the most widely used Expanded clay should not be placed
(RC) walls on 900mm diameter RC bored and well understood backfill materials, below the water table or in areas
piles with independent RC wing walls. this was first considered as it is a standard prone to flooding as the particles may
The intermediate pier will comprise 6 no. design solution. become buoyant;
750mm diameter RC columns at 7.5m Unfortunately, the high density of The particles have a lower crushing
spacing, with each column founded on a the backfill material coupled with the strength compared to natural soils,
900mm diameter RC mono-pile. substantial height of retained material and so ordinary test methods such as
Ground conditions at this site are fairly resulted in large moments being applied the California Bearing Ratio test are
uniform and comprise Made Ground to the abutment wall piles, and equally not suitable;
Eliminates
settlement period
Placed by hand
Free draining
Well understood material No compaction required
1m compaction layers
Cheap and readily available Inhibited water absorption
Chemically inert
Advantages Ability to use normal Immune to attack from
Resistant to fire and frost bacteria and mould
compaction plant and
testing methods Re-usable, no special Minimises settlement issues
requirements for disposal
Can be recycled
Placed using same
methods as normal backfill
Angle of friction,
35 37 N/A
(degrees)
Cost (/m3) 35 40 - 50 60 - 80
A capping layer is required (see movements and braking forces Density: where higher load bearing
previous) to spread traffic loads introducing stresses with accompanying capacities are required, higher grade
sufficiently to ensure that the strains in the EPS blocks. EPS blocks are specified but these
particle (in its mass) crushing limit is have a higher density;
not exceeded. See Figure 3: Typical EPS stress
strain curve3. Localised damage: the use of HDPE
In the case of Cottington Road will also require a capping layer of
Overbridge, assessment showed that the There are a number of design granular backfill to spread applied loads
use of expanded clay backfill allowed the considerations to take into account when sufficiently to prevent localised damage
foundations to be reduced from 28 no. specifying EPS blocks: to the EPS blocks or HDPE membrane.
1200mm diameter piles (in the case of Chemical attack: EPS is vulnerable The use of EPS as an alternative backfill
6N granular backfill) to 21 no. 900 mm to attack from hydrocarbons. So, if material had significant economic benefits
diameter piles (per abutment), although it is to be used in highway or railway for the Cottington Road Overbridge
heavy reinforcement would still be required embankments, it must be protected by structure. The abutment foundations
and the wing walls would still require two concrete encasement, or by use of high were able to be reduced from the 28
rows of piles to control deflection. density polyethylene (HDPE) sheets; no. 1200 mm diameter piles of the
EPS blocks UV resistance; 6N backfill option to 21 no. 900mm
Fire protection; diameter piles using a single layer cage
Focus then turned to the use of EPS of T40 reinforcement, and the wing
blocks. EPS can almost eradicate lateral wall foundations could be reduced to a
pressures on civil engineering structures as single (rather than double) row of piles
surcharge loads are taken vertically to the eradicating the need for a pile cap.
ground beneath.
See Table 1: Backfill material comparison.
EPS has a proven track record as a
Geotechnical
49
Alternative backfill study
In order to provide a numeric comparison
of loads applied to an integral bridge
structure by the three backfill materials
discussed, and the varying effects that
this has on the structure, a simple integral
bridge structure will be analysed and the
results discussed below.
The integral bridge structure analysed
for the purpose of this study is an overall
60m, (equal) two span bridge, 25m wide
with no skew. Main girders are spaced
at 2.75m. Abutments are 1500mm thick
RC walls and founded on 18 no. 900mm
diameter RC piles each. The central pier
consists of 9 no. 750mm diameter RC
columns, each column being founded on a
single 900mm diameter RC pile.
SuperStress is used to model the structure
as a frame with fixed connections between
deck and supports, the piles are modelled Figure 4. Simplified study General Arrangements
using spring supports.
See Figure 4: Simplified study
General Arrangements.
For transparency, results are given for
lateral pressures on the abutments only, all
other dead and live loads being ignored.
It should be noted that pressures exerted
on the abutment walls by EPS blocks will
only be experienced in Combination 36
of BD37/01 Loads for Highway Bridges
as this is the only case where restraint to
movement temperature effects are taken
into account.
6N granular backfill
Earth pressures exerted on the abutment
Figure 5. Earth pressure distributions
walls are related to compression stresses
in the retained soil. However at the top
BA 42/96 gives an equation to calculate Lateral earth pressure at the top of the
of the wall, higher earth pressures will be
the relationship between K*, the height wall = 0 kN/m2
experienced because of wall friction.
(H) and thermal displacement at the top
of the abutment (d): Lateral earth pressure half way down the
BA42/96 - The Design of Integral Bridges'7
wall = K* soil z = 2.02 x 19 x 5 = 191.9kN/m2
suggests earth pressure distributions for
K* =K0 + (d/0.05 H)0.4 Kp
different structural forms. For the purposes This earth pressure then remains constant
of this study a full height frame abutment This equation uses Kp obtained using the to the base of the wall since it does
form is assumed. Clause 3.5.3 of BA 42/96 Eurocode 7 approach, for 6N granular backfill not fall below the earth pressure value
suggests a distribution comprising: with = 35o, K0 = 0.426 and Kp = 6.5. calculated using its K0 coefficient up to
this point.
A uniform value of K* over the top half BA 42/96 clause 2.10 states the
of the retained height of the wall, with; characteristic thermal strain for composite See Figure 5 (a): Earth pressure
Lateral earth pressure then remaining deck construction in the UK can be taken distribution - 6N granular backfill.
constant with depth as K* drops as 0.0005, therefore:
towards K0; d = 0.0005 x 30000 = 15 mm
If the lateral earth pressure falls to K0
then below that depth pressures are K* = 0.426 + (15/0.05 x 10000)0.4
applied in accordance with the in situ x 6.5 = 2.02
value of K0.
50
104 Lightweight backfill materials in integral
bridge construction
Lateral earth pressure at the top of the 7 4.21 13.2 6100 0.22 26
wall = 0 kN/m2
8 4.86 12.9 6100 0.21 25
Lateral earth pressure at capping layer
interface = K* soil z = 2.02 x 19 x 1 = 38 9 5.50 12.7 4880 0.26 31
kN/m2
10 6.14 12.4 4880 0.25 30
K* then increases to reflect the expanded
clay material properties with = 37o, K0 11 6.79 12 3660 0.33 39
= 0.398 and Kp = 7.0:
12 7.43 11.7 3660 0.32 38
K* =0.398 + (15 / 0.05 x 10000)0.4 x 7.0
= 2.12 13 8.07 11.3 2440 0.46 56
Lateral earth pressure half way down the 14 8.71 11 2440 0.45 54
wall =
15 9.36 10.6 1220 0.87 104
K* (exp_clay zexp_clay + soil zsoil) = 2.12
(4 x 4 + 19 x 1) = 74 kN/m2 16 10.00 10.2 1220 0.84 100
This earth pressure then remains constant
Table 2: EPS lateral earth pressures exerted on abutment wall
to the base of the wall (as per 6n
granular backfill).
Total applied load (per unit width)
See Figure 5 (b): Earth pressure 1410 kN 100%
distribution Expanded clay.
Maximum hogging moment
16324 kNm 100%
EPS blocks
14 layers of EPS blocks abut the end (a) 6N granular backfill
Total applied load (per unit width)
supports, each layer increasing in length 592 kN 42%
at 1 in 1 benching steps to the interface
Maximum hogging moment
with embankment backfill. Using 6449 kNm 40%
this slope gradient limits lateral earth
(b) Expanded clay
pressures exerted on the back of the
Total applied load (per unit width)
EPS blocks. 376 kN 27%
A 1000mm capping layer of 6N granular Maximum hogging moment
backfill is assumed to prevent localised 3579 kNm 22%
(c) EPS blocks
damage of the EPS blocks and HDPE
membrane by applied dead and live
Figure 7. Bending moment diagrams
loads. Lateral earth pressures exerted by
this layer will be identical to those in 3.1
and 3.2. Lateral earth pressure at the top of the depending on the grade of EPS selected.
wall = 0 kN/m2
See Figure 5 (c): Earth pressure
d
Geotechnical
51
Figure 8: Embodied carbon footprint comparison Figure 10
Figure 8: Embodied carbon footprint comparison Figure 10
Embodied carbon of EPS and expanded clay backfill Tot
See Table 2: EPS lateral earth pressures 500 Embodied carbon of EPS and expanded clay backfill Tot
1200
exerted on abutment wall. 450
500 1200
1000
Results 400
450
Analysis of the effects of the three different 350 1000
800
400
saved
saved
backfill materials on the structure is carried 300
out using structure analysis software. 350 800
250 600
saved
saved
Figure 7 shows the bending moment 300
2
tCO tCO
tCO2tCO 200
diagrams produced when the various 250 600
400
backfill loads are applied to the structure. 150
200
100 400
200
Applying 6N granular backfill to 10m 150
high integral abutments produces huge 50
100 200
moments in the deck and at the top of 0 0
50
the wall. In this case there is a maximum Piling Piling rebar RC concrete RC rebar Backfill
hogging moment at the top of the wall 0 0
concrete
of over 16.3 MNm per metre width. Piling Piling rebar RC concrete RC rebar Backfill
In order to withstand moments of this concrete Expanded clay EPS
magnitude, very large heavily reinforced Expanded clay EPS
sections are required. Figure 11:
Figure 9: Transport carbon footprint comparison (note the logarithmic scale)
Using expanded clay backfill to abut the Figure 8. Embodied carbon footprint comparison
end supports reduces the applied load Figure 9: Transport carbon footprint comparison (note the logarithmic scale) FigureBre
11:
to 42% of that seen using 6N backfill, Transport carbon of EPS and expanded clay backfill
reducing the maximum hogging moment Bre
600
by 60% to 6.4 MNm per metre width. 1000 Transport carbon of EPS and expanded clay backfill
When EPS block loads are applied to 600
500
1000
the structure the bending moments
produced in the structure are significantly 100 500
400
saved
lower than those produced by either 6N
granular or expanded clay backfill. In this 100
saved
400
300
saved
case the maximum hogging moment is
2
10
tCO2tCO
saved
200
tCO2tCO
metre width. 10
200
100
Environmental impacts 1
saved
800
saved
embodied CO2 per kg is over 10 times
that of the expanded clay at 2.5kgCO2/ 600
tCO 600
kg. This might be expected to make
tCO
See Figure
otprint comparison (note8: the
Embodied carbonscale)
logarithmic Figure
Figure 11
: Breakdown
10. of comparison
Carbon footprint carbon footprint savings
otprint comparison
footprint(note the logarithmic scale)
comparison. Figure 11: Breakdown of carbon footprint savings
Transport carbon emissions Breakdown of embodied carbon savings when specifying
Breakdown of embodied carbon savings when specifying
n of EPS and expanded
Construction clay can
materials backfill
also be heavy EPS in place of expanded clay backfill
n of EPS and expanded clay backfill EPS in place of expanded clay backfill
which leads to a lot of transport related 600
carbon emissions. In the case of bridge 600
structures, the two materials which make 500
up the majority of transport emissions are 500
reinforced concrete and backfill as they 400
are the major components by weight.
saved
400
saved
53
the EPS option is significantly lower than Road, the EPS block and expanded favour of EPS in cases where the cost
the expanded clay option due to its clay solutions had very similar cost argument is marginal, or policy measures
lower density. implications on the project; however, EPS may be introduced which give the
blocks were selected because of problems embodied and transport carbon saved a
See Figure 11: Breakdown of carbon experienced in controlling deflection of greater financial value.
footprint savings. the independent wing walls.
Acting as a counter to this, the issues
EPS blocks provide a good solution that arise with the need to protect the
Conclusions to design problems such as retaining material from hydrocarbons and the huge
Although the results show the use of EPS wall deflection or restraints of bearing effort required to rectify problems should
blocks abutting the end supports of an pressure; however, in the absence of the protection fail will make Technical
integral bridge structure greatly reduces these issues the use of EPS blocks is Approval Authorities very reluctant to
pressures exerted on the walls and unlikely to be financially worthwhile. authorise this as a design solution. A
design loads experienced by the bridge robust technical solution to this problem
The recent increased emphasis on making would allow large reductions in the
components as a result, it is often less structures more sustainable is likely to
economical to use this as a solution than transport carbon footprint of backfill.
encourage the use of EPS blocks due to
expanded clay backfill material. Regarding the major reduction in transport-related
the integral bridge at Cottington emissions. This may tip the balance in
References
1. Maxit. (2004). Maxit LWA Lightweight fill for civil engineering [Brochure].
2. S+B. (2010). Product Handbook Civil Engineering [Brochure].
3. Jablite. (2010). Technical Information Civil Engineering using Fillmaster EPS [Brochure].
4. Hammond, G.P. and Jones, C.I. (2008), Inventory of Carbon and Energy V1.6a [University of Bath]
5. Department of Transport, Manual of Contract Documents for Highway Works, Vol 1, Specification of Highway Works,
Series 600, 2009.
6. BD 37(0) Loads for Highway Bridges, Highways Agency, UK
7. BD 42/96 The Design of Internal Bridges, Highways Agency, UK
54