Professional Documents
Culture Documents
=
Rate per sft. = Tk. 24.82
Rate per sqm. = Tk. 267.16
1. Updating Implementation Schedule prepared in M.S. Project software 3 day 100000 month = Tk. 10,000.00
2. Printing : 3set 12.08 sft day Tk. 16.50 L.S. = Tk. 300.00
Total = Tk. 10,300.00
Profit 10.00% = Tk. 1,030.00
Overhead 3.50% = Tk. 360.50
Tk. 11,690.50
Add VAT with adjustment factor 1.0582 5.50% = Tk. 680.40
Grand total = Tk. 12,370.90
1. Logistic support to arrange and conducting progress meeting L.S. = Tk. 1,500.00
2. Incidental, sundries etc. L.S. = Tk. 225.00
Total = Tk. 1,725.00
Profit 10.00% = Tk. 172.50
Overhead 3.50% = Tk. 60.38
Tk. 1,957.88
Analysis of PWD SoR 2014 for Civil Works 60
Earth work in foundation trenches up to 1.5 m depth and maximum 10 m lead including
protecting and maintaining the trench: Very stiff (hard) claye soil / rubbish
Considering 1000 cft. work
1. Mason 0.25 No. @ Tk. 389.00 each = Tk. 97.25
2. Ordinary labour 10.00 Nos. @ Tk. 245.00 each = Tk. 2,450.00
3. Skilled labour 2.5 Nos. @ Tk. 303.00 each = Tk. 757.50
4. Tools and plant, protecting and maintaining trench dry L.S. = Tk. 102.08
Total = Tk. 3,406.83
Profit 10.00% = Tk. 340.68
Overhead 3.50% = Tk. 119.24
Tk. 3,866.75
Add VAT with adjustment factor 1.0582 5.50% = Tk. 225.05
Grand total = Tk. 4,091.80
Rate per cft. = Tk. 4.09
Rate per cum. = Tk. 144.44
in/c hire charge of monkey with driving arranement. L.S. = Tk. 183.75
Total = Tk. 3,621.75
Profit 10.00% = Tk. 362.18
Overhead 3.50% = Tk. 126.76
= Tk. 4,110.69
Add VAT with adjustment factor 1.0582 5.50% = Tk. 239.25
Grand total = Tk. 4,349.94
Rate per rft. = Tk. 217.50
Rate per rm. = Tk. 713.62
1. Fine Sand (F.M. 0.8) 100.00 cft. @ Tk. 900.00 Per % cft. = Tk. 900.00
2. Labour for mixing sand and cutting loose sludge
in/c spreading and stacking 12.00 Nos. @ Tk. 245.00 Each = Tk. 2,940.00
3. Labour cutting dried sludge in/c loading,
unloading and truck/cart etc. 7.00 Nos. @ Tk. 245.00 Each = Tk. 1,715.00
4. Hire charge of truck 7.00 Trip @ Tk. 1,300.00 Per trip = Tk. 9,100.00
5. Tools and plant, sundries, incidental etc. L.S. = Tk. 1,327.08
Total = Tk. 15,982.08
Profit 10.00% = Tk. 1,598.21
Overhead 3.50% = Tk. 559.37
Tk. 18,139.66
Add VAT with adjustment factor 1.0582 5.50% = Tk. 1,055.75
Grand total = Tk. 19,195.41
Rate per cft. = Tk. 19.20
Rate per cum. = Tk. 678.05
Analysis of PWD SoR 2014 for Civil Works 67
Item No.- 02.16.4 For other than Dhaka, Ctg., Sylhet, Rajshahi, Barishal, Khulna metropolitan area and N'ganj district
Mass concrete in foundation (1:3:6) with brick chips & 100% local sand of F.M. 1.2
Considering 100 cft. of work
1. Cost of concrete 100 cft. @ Tk. 13,272.10 Per % cft. = Tk. 13,272.10
2. Laying / placing concrete 100 cft. @ Tk. 950.46 Per % cft. = Tk. 950.46
3. Curing for 7 days L.S. = Tk. 102.08
4. Extra cost of wood for side shutter: for 100 cft
2 x 60'-0" x 4" x 1"= 3.33 cft.
2 x 5'-0" x 4" x 1"= 0.28 cft.
10 x 6" x 2" x 1" = 0.07 cft.
3.68 cft.
Add 5% wastage 0.18 cft.
3.86 cft. @ Tk. 470.00 Per cft.
Using 6 times = Tk. 302.37
5. Labour for side shutter
2 x 40'-0" x 6" = 40.00 sft.
2 x 5' - 0" x 6" = 5.00 sft.
45.00 sft. @ Tk. 6.00 Per sft. = Tk. 270.00
Total = Tk. 14,897.01
Profit 10.00% = Tk. 1,489.70
Overhead 3.50% = Tk. 521.40
Tk. 16,908.11
Add VAT with adjustment factor 1.0582 5.50% = Tk. 984.07
Grand total = Tk. 17,892.18
Rate per cft. = Tk. 178.92
Rate per cum. = Tk. 6,318.56
6.02 cft.
Add 5% wastage 0.30 cft.
= 6.32 cft. @ Tk. 470.00 Per cft.
Using 6 times = Tk. 495.07
4. Labour for side shutter:
2 x 120'-0" x 3" = 60.00 sft. @ Tk. 12.00 Per sft. = Tk. 720.00
Total = Tk. 7,753.39
Profit 10.00% = Tk. 775.34
Overhead 3.50% = Tk. 271.37
Tk. 8,800.10
Add VAT with adjustment factor 1.0582 5.50% = Tk. 512.17
Grand total = Tk. 9,312.27
Rate per sft. = Tk. 93.12
Rate per sqm. = Tk. 1,002.34
DIVISION 04 : BRICKWORKS, PATENT STONEF IN FLOOR AND FANCY SCREEN BLOCK WORKS
Brick work with 9.5" x 4.5" x 2.75" size 3 hole machine made reinforced klinker facing bricks (1:4)
Considering 100 cft. work
1. Bricks 1100 Nos. @ Tk. 20,000.00 Per % 0 Nos. = Tk. 22,000.00
Sand (F.M 2.5) in/c wastage 24 cft. @ Tk. 3,000.00 Per % cft. = Tk. 720.00
2. Sand (F.M 1.2) in/c wastage 40 cft. @ Tk. 1,700.00 Per % cft. = Tk. 680.00
3. Cement 6.5 bags @ Tk. 440.00 Per bag = Tk. 2,860.00
4. Head mason 0.25 No. @ Tk. 493.00 each = Tk. 123.25
5. Mason 2 No. @ Tk. 389.00 each = Tk. 778.00
6. Skilled labour 1.5 No. @ Tk. 303.00 each = Tk. 454.50
7. Ordinary labour 2 Nos. @ Tk. 245.00 each = Tk. 490.00
8. Labour for soaking
& cleaning bricks 1 Nos. @ Tk. 245.00 each = Tk. 245.00
9. Screening and washing sand 1/2 No. @ Tk. 245.00 each = Tk. 122.50
10. Labour for 7 days curing
@ 1/8 labour per day: 0.875 Nos. @ Tk. 245.00 each = Tk. 214.38
11. Scaffolding 25 sft. @ Tk. 7.20 Per sft. = Tk. 180.00
12. Local carriage, sundries, T & P etc. ( times of ordinary labour rate) L.S. = Tk. 122.50
Total = Tk. 28,990.13
Profit 10.00% = Tk. 2,899.01
Overhead 3.50% = Tk. 1,014.65
Tk. 32,903.79
Add VAT with adjustment factor 1.0582 5.50% = Tk. 1,915.03
Grand total = Tk. 34,818.82
(a) Ground floor Rate per cft. = Tk. 348.19
Rate per cum. = Tk. 12,296.33
04.21.1 Add for each addl. floor up to 5th floor (@ 0.75 No. lab per % sft.) Per sqm = Tk. 24.00
04.21.2 Add for each addl. floor for 6th floor to 9th floor (@ 1 No. lab per % sft.) Per sqm = Tk. 32.00
04.21.3 Add for each addl. floor 10th floor and above (@ 1.25 Nos. lab per % sft.) Per sqm = Tk. 40.00
B. Labour:
1. Head mason 1/4 No. @ Tk. 493.00 each = Tk. 123.25
2. Mason 1.5 Nos. @ Tk. 389.00 each = Tk. 583.50
3. Skilled labour 3 Nos. @ Tk. 303.00 each = Tk. 909.00
4. Ordinary labour 1.5 Nos. @ Tk. 245.00 each = Tk. 367.50
5. Labour for soaking &
cleaning bricks 1 No. @ Tk. 245.00 each = Tk. 245.00
6. Labour for 7 days curing
@ 1/8 labour per day. 0.875 Nos. @ Tk. 245.00 each = Tk. 214.38
7. Local carriage & storage, sundries etc. L.S. = Tk. 122.50
Total = Tk. 20,103.13
Profit 10.00% = Tk. 2,010.31
Overhead 3.50% = Tk. 703.61
Tk. 22,817.05
Add VAT with adjustment factor 1.0582 5.50% = Tk. 1,327.98
Grand total = Tk. 24,145.03
Rate per sft. = Tk. 241.45
Rate per sqm. = Tk. 2,598.97
1. Crushed stone chips 90 cft. @ Tk. 13,500.00 Per % cft. = Tk. 12,150.00
2. Sand (F.M. 1.2) 22.5 cft. @ Tk. 1,700.00 Per % cft. = Tk. 382.50
3. Sand (F.M. 2.5) 22.5 cft. @ Tk. 3,000.00 Per % cft. = Tk. 675.00
4. Cement 22 bags @ Tk. 440.00 Per bag = Tk. 9,680.00
5. Labour for 7 days curing
@ 1/8 labour per day. 0.875 Nos. @ Tk. 245.00 each = Tk. 214.38
6. Local carriage, sundries, T & P and washing of sand etc. L.S. = Tk. 367.50
Sub-total = Tk. 23,469.38
For 100 sft. of work = Tk. 2,933.67
7. Extra cement for finishing 1/2 bag @ Tk. 440.00 Per bag = Tk. 220.00
8. Labour cost:
(a) Head mason 1/5 No. @ Tk. 493.00 each = Tk. 98.60
(b) Mason 3/4 No. @ Tk. 389.00 each = Tk. 291.75
(c) Skilled labour 1 No. @ Tk. 303.00 each = Tk. 303.00
(d) Ordinary labour 1 No. @ Tk. 245.00 each = Tk. 245.00
10. Extra cost of Garjan batten for side shutter
2 x 4 x 5'-0" x 1.5" x 3/4" = 0.31 cft.
Add 5% wastage 0.02 cft.
0.33 cft. @ Tk. 2,000.00 Per cft.
Using 10 times @ Tk. 200.00 Per cft. = Tk. 66.00
11. Labour for shuttering
2 x 4 x 5'-0" x 1.5" = 5 sft. @ Tk. 2.00 Per sft. = Tk. 10.00
Total = Tk. 4,168.02
Profit 10.00% = Tk. 416.80
Overhead 3.50% = Tk. 145.88
Tk. 4,730.70
Add VAT with adjustment factor 1.0582 5.50% = Tk. 275.33
Grand total = Tk. 5,006.03
(i) Ground floor Rate per sft. = Tk. 50.06
Rate per sqm. = Tk. 538.85
100% grey cement in/c 25 mm thick patent stone (1:2:4) with BRICK chips
Same as 05.1.1 100 sft. @ Tk. 3,013.50 Per % sft. = Tk. 3,013.50
Total = Tk. 9,536.22
Profit 10.00% = Tk. 953.62
Overhead 3.50% = Tk. 333.77
Tk. 10,823.61
Add VAT with adjustment factor 1.0582 5.50% = Tk. 629.94
Grand total = Tk. 11,453.55
(i) Ground floor Rate per sft. = Tk. 114.54
Rate per sqm. = Tk. 1,232.91
Same as 05.1.1 100 sft. @ Tk. 3,013.50 Per % sft. = Tk. 3,013.50
Total = Tk. 12,515.22
Profit 10.00% = Tk. 1,251.52
Overhead 3.50% = Tk. 438.03
Tk. 14,204.77
Add VAT with adjustment factor 1.0582 5.50% = Tk. 826.73
Grand total = Tk. 15,031.50
(i) Ground floor Rate per sft. = Tk. 150.32
Rate per sqm. = Tk. 1,618.04
in/c 25 mm thick patent stone with BRICK-CHIPS: (white cement : grey cement = 1:1)
Considering 100 sft. of work
A. Materials:
1. White cement 62.5 kg @ Tk. 25.00 Per kg = Tk. 1,562.50
2. Grey cement 1.25 bag @ Tk. 440.00 Per bag. = Tk. 550.00
3. India Deradun mosaic chips 125 kg @ Tk. 17.00 Per kg = Tk. 2,125.00
4. Minar stone 1/3 No. @ Tk. 400.00 each = Tk. 133.33
5. Cost of patent stone excluding cost of cement for neat
finish and 1/4 No. mason. 100 sft. @ Tk. 2,248.39 Per % sft. = Tk. 2,248.39
Sub-total = Tk. 6,619.22
B. Labour:
Same as item No.- 05.1.4 100 sft. @ Tk. 2,538.00 Per % sft. = Tk. 2,538.00
Total = Tk. 9,157.22
Profit 10.00% = Tk. 915.72
Overhead 3.50% = Tk. 320.50
Tk. 10,393.44
Add VAT with adjustment factor 1.0582 5.50% = Tk. 604.91
Grand total = Tk. 10,998.35
(i) Ground floor Rate per sft. = Tk. 109.98
Rate per sqm = Tk. 1,183.82
4. 1/2" thick plaster (1:4) 100 sft. @ Tk. 15.27 Per sft. = Tk. 1,527.00
Sub-total = Tk. 6,910.33
B. Labour:
(a) For mixing, laying, compacting and curing:
1. Head mason 1 No. @ Tk. 493.00 each = Tk. 493.00
2. Skilled labour 3/4 No. @ Tk. 303.00 each = Tk. 227.25
3. Ordinary labour 1 No. @ Tk. 245.00 each = Tk. 245.00
(b) For cutting mosaic mosaic wall surface with mumic stone:
1. Skilled labour 10 Nos. @ Tk. 303.00 each = Tk. 3,030.00
2. Pumic stone 2.5 Nos. @ Tk. 60.00 each = Tk. 150.00
(c) For spreading oxalic acid and washing:
1. Ordinary labour 1 No. @ Tk. 245.00 each = Tk. 245.00
Sub-total = Tk. 4,390.25
Total (A+B) = Tk. 11,300.58
Profit 10.00% = Tk. 1,130.06
Overhead 3.50% = Tk. 395.52
Tk. 12,826.16
Add VAT with adjustment factor 1.0582 5.50% = Tk. 746.50
Grand total = Tk. 13,572.66
(i) Ground floor Rate per sft. = Tk. 135.73
Rate per sqm = Tk. 1,461.00
Marble stone on walls with 12 mm thick Indian white / black marble stone
Considering 100 sft. of work
A. Cost of materials
1. 12 mm thick marble stone 100 sft. @ Tk. 315.00 Per sft. = Tk. 31,500.00
2. Grey cement 1.7 bag @ Tk. 440.00 Per bag = Tk. 748.00
3. Sand (F.M. 1.2) 2.08 cft. @ Tk. 1,700.00 Per % cft. = Tk. 35.36
4. Sand (F.M. 2.2) 2.08 cft. @ Tk. 3,000.00 Per % cft. = Tk. 62.40
5. White cement 4 kg @ Tk. 25.00 Per kg = Tk. 100.00
Sub-total = Tk. 32,445.76
B. Cost for cutting, shaping, tools and plants etc.
1. Hire charge of cutting and shaping
machine in/c cutting disc. 1 day @ Tk. 300.00 Per day = Tk. 300.00
2. Foreman 1 No. @ Tk. 567.00 each = Tk. 567.00
3. Machine operator 1 No. @ Tk. 423.00 each = Tk. 423.00
4. Helper 1 No. @ Tk. 304.00 each = Tk. 304.00
Sub-total = Tk. 1,594.00
C. Labour cost for laying
1. Mason 5.5 Nos. @ Tk. 389.00 each = Tk. 2,139.50
2. Helper 2 Nos. @ Tk. 304.00 each = Tk. 608.00
3. Scaffolding 100 sft. @ Tk. 7.20 Per sft. = Tk. 720.00
Sub-total = Tk. 3,467.50
D. Polishing
1. Hire charge of marble polishing
machine in/c polishing stone 2.5 days @ Tk. 400.00 Per day = Tk. 1,000.00
2. Machine operator 2.5 Nos. @ Tk. 423.00 each = Tk. 1,057.50
3. Helper 2.5 Nos. @ Tk. 304.00 each = Tk. 760.00
Sub-total = Tk. 2,817.50
Total (A+B+C+D) = Tk. 40,324.76
Profit 10.00% = Tk. 4,032.48
Overhead 3.50% = Tk. 1,411.37
Tk. 45,768.61
Add VAT with adjustment factor 1.0582 5.50% = Tk. 2,663.78
Grand total = Tk. 48,432.39
(i) Ground floor Rate per sft. = Tk. 484.32
Rate per sqm = Tk. 5,213.22
A. Cost of materials for base with 3/4'' (av.) thick cement mortar: (3:1):
1 Cement 1.87 bags @ Tk. 440.00 Per bag = Tk. 822.80
2. Sand (F.M. 1.2) 7.03 cft. @ Tk. 1,700.00 Per % cft. = Tk. 119.51
3. White cement 3.60 kg @ Tk. 25.00 Per kg = Tk. 90.00
B. Labour cost:
1. Head mason 2.00 Nos. @ Tk. 493.00 each = Tk. 986.00
2. Mason 2.00 Nos. @ Tk. 389.00 each = Tk. 778.00
3. Skilled labour 3.00 Nos. @ Tk. 303.00 each = Tk. 909.00
4. Ordinary labour 3.00 Nos. @ Tk. 245.00 each = Tk. 735.00
5. Local carriage, sundries, T & P & washing of sand etc. L.S. = Tk. 245.00
Total = Tk. 4,685.31
Laying cost per % sft. = Tk. 4,685.31
(i) Ground floor
(a) Wall tiles less than, equal or equivalent to 250mmx330mm in sizes
Considering 100 sft. of work
1. Cost of tiles 100 sft. @ Tk. 46.00 Per sft. = Tk. 4,600.00
Add wastage 5% = Tk. 230.00
2. Laying cost 100 sft. @ Tk. 4,685.31 Per % sft. = Tk. 4,685.31
Total = Tk. 9,515.31
Profit 10.00% = Tk. 951.53
Overhead 3.50% = Tk. 333.04
Tk. 10,799.88
Add VAT with adjustment factor 1.0582 5.50% = Tk. 628.56
Grand total = Tk. 11,428.44
Rate per sft. = Tk. 114.28
Rate per sqm = Tk. 1,230.11
Supplying, fitting and fixing unglazed homogeneous floor tiles on cement mortar base (4:1):
Cost for laying floor tiles: Same as item No. 6.7.1 Per % sft. = Tk. 4,530.50
(i) For ground floor
(a) GP (homogeneous) 300 x 300 mm floor tiles
Considering 100 sft. work
1. Cost of tiles 100 sft. @ Tk. 68.00 Per sft. = Tk. 6,800.00
Add wastage 5% = Tk. 340.00
2. Laying cost 100 sft. @ Tk. 4,530.50 Per % sft. = Tk. 4,530.50
Total = Tk. 11,670.50
Profit 10.00% = Tk. 1,167.05
Overhead 3.50% = Tk. 408.47
Tk. 13,246.02
Add VAT with adjustment factor 1.0582 5.50% = Tk. 770.93
Grand total = Tk. 14,016.95
Rate per sft. = Tk. 140.17
Rate per sqm = Tk. 1,508.79
Cost for laying floor tiles: Same as item No. 6.7.1 Per % sft. = Tk. 4,530.50
(i) For ground floor
06.9.1 GP (mirror polished) 300 x 300 mm floor tiles
Considering 100 sft. work
1. Cost of tiles 100 sft. @ Tk. 78.00 Per sft. = Tk. 7,800.00
Add wastage 5% = Tk. 390.00
2. Laying cost 100 sft. @ Tk. 4,530.50 Per % sft. = Tk. 4,530.50
Total = Tk. 12,720.50
Profit 10.00% = Tk. 1,272.05
Overhead 3.50% = Tk. 445.22
Tk. 14,437.77
Add VAT with adjustment factor 1.0582 5.50% = Tk. 840.29
Grand total = Tk. 15,278.06
Rate per sft. = Tk. 152.78
Rate per sqm = Tk. 1,644.52
a) Cost of materials
i) Pasting tiles adhesives 50.00 kg @ Tk. 16.00 Per kt = Tk. 800.00
ii) Tiles grout/Joint filler 1.00 kg @ Tk. 75.00 Per kt = Tk. 75.00
b) Labour cost:
i) Head mason 0.75 Nos. @ Tk. 493.00 each = Tk. 369.75
ii) Mason 1.50 Nos. @ Tk. 389.00 each = Tk. 583.50
iii) Skilled labour 1.50 Nos. @ Tk. 303.00 each = Tk. 454.50
iv) Ordinary labour 1.50 Nos. @ Tk. 245.00 each = Tk. 367.50
v) Local carriage, sundries, T & P & washing of sand etc. L.S. = Tk. 100.000
Sub-total (A) = Tk. 2,750.25
c) Cost of tiles
Homogenous tiles 100.00 sft. @ Tk. 75.00 Per sft. = Tk. 7,500.00
Size 400mm x 400 mm Add: Wastage 5% = Tk. 375.00
Sub-total (B) = Tk. 7,875.00
Sub-total (A+B) = Tk. 10,625.25
Profit 10.00% = Tk. 1,062.53
Overhead 3.50% = Tk. 371.88
Tk. 12,059.66
Add VAT with adjustment factor 1.0582 5.50% = Tk. 701.88
Grand total = Tk. 12,761.54
Rate per sft. = Tk. 127.62
Rate per sqm = Tk. 1,373.70
06.11.7.1
Extra Rate for each additional for Glazed Tiles and Marble Stone Works
06.12.1 Add for each addl. floor up to 5th floor (@ 0.25 No. lab per % sft.) Per sqm = Tk. 8.00
06.12.2 Add for each addl. floor for 6th floor to 9th floor (@ 0.5 No. lab per % sft.) Per sqm = Tk. 16.00
06.12.3 Add for each addl. floor for 10th floor and above (@ 0.75 No. lab per % sft.) Per sqm = Tk. 24.00
07.1.1.2 Formwork/shuttering, prop and necessary supports etc. (wooden) Per sqm. = 294.93
(From Secondary Input : Item C-1) Profit 10.00% = Tk. 29.49
Overhead 3.50% = Tk. 10.32
= Tk. 334.74
Add VAT with adjustment factor 1.0582 5.50% = Tk. 19.48
Grand total = Tk. 354.22
07.1.2.2 Formwork/shuttering, prop and necessary supports etc. (wooden) Per sqm. = 343.59
(From Secondary Input : Item C-2) Profit 10.00% = Tk. 34.36
Overhead 3.50% = Tk. 12.03
= Tk. 389.98
Add VAT with adjustment factor 1.0582 5.50% = Tk. 22.70
Grand total = Tk. 412.68
Ground floor and below plinth level Say, Tk. 413 .00 Per sqm..
Item No. - 07.1.3
R.C.C. work (1:2:4) complete excluding the cost of reinforcement and its fabrication in foundation beam
with BRICK chips using WOODEN shutter
07.1.3.2 Formwork/shuttering, prop and necessary supports etc. (wooden) Per sqm. = 295.15
(From Secondary Input : Item C-3) Profit 10.00% = Tk. 29.52
Overhead 3.50% = Tk. 10.33
= Tk. 335.00
Add VAT with adjustment factor 1.0582 5.50% = Tk. 19.50
Grand total = Tk. 354.50
07.1.4.2 Formwork/shuttering, prop and necessary supports etc. (wooden) Per sqm. = 343.16
(From Secondary Input : Item C-4) Profit 10.00% = Tk. 34.32
Overhead 3.50% = Tk. 12.01
= Tk. 389.49
Add VAT with adjustment factor 1.0582 5.50% = Tk. 22.67
Grand total = Tk. 412.16
07.1.5.2 Formwork/shuttering, prop and necessary supports etc. (wooden) Per sqm. = 327.98
(From Secondary Input : Item C-5) Profit 10.00% = Tk. 32.80
Overhead 3.50% = Tk. 11.48
= Tk. 372.26
Add VAT with adjustment factor 1.0582 5.50% = Tk. 21.67
Grand total = Tk. 393.93
07.1.6.2 Formwork/shuttering, prop and necessary supports etc. (wooden) Per sqm. = 403.97
(From Secondary Input : Item C-6) Profit 10.00% = Tk. 40.40
Overhead 3.50% = Tk. 14.14
= Tk. 458.51
Add VAT with adjustment factor 1.0582 5.50% = Tk. 26.69
Grand total = Tk. 485.20
07.1.7.2 Formwork/shuttering, prop and necessary supports etc. (wooden) Per sqm. = 381.91
(From Secondary Input : Item C-7) Profit 10.00% = Tk. 38.19
Overhead 3.50% = Tk. 13.37
= Tk. 433.47
Add VAT with adjustment factor 1.0582 5.50% = Tk. 25.23
Grand total = Tk. 458.70
07.1.8.2 Formwork/shuttering, prop and necessary supports etc. (wooden) Per sqm. = 286.11
(From Secondary Input : Item C-9) Profit 10.00% = Tk. 28.61
Overhead 3.50% = Tk. 10.01
= Tk. 324.73
Add VAT with adjustment factor 1.0582 5.50% = Tk. 18.90
Grand total = Tk. 343.63
07.1.9.2 Formwork/shuttering, prop and necessary supports etc. (wooden) Per sqm. = 328.73
(From Secondary Input : Item C-10) Profit 10.00% = Tk. 32.87
Overhead 3.50% = Tk. 11.51
= Tk. 373.11
Add VAT with adjustment factor 1.0582 5.50% = Tk. 21.72
Grand total = Tk. 394.83
07.1.10.2 Formwork/shuttering, prop and necessary supports etc. (wooden) Per sqm. = 317.54
(From Secondary Input : Item C-11) Profit 10.00% = Tk. 31.75
Overhead 3.50% = Tk. 11.11
= Tk. 360.40
Add VAT with adjustment factor 1.0582 5.50% = Tk. 20.98
Grand total = Tk. 381.38
07.1.11.2 Formwork/shuttering, prop and necessary supports etc. (wooden) Per sqm. = 485.89
(From Secondary Input : Item C-8) Profit 10.00% = Tk. 48.59
Overhead 3.50% = Tk. 17.01
= Tk. 551.49
Add VAT with adjustment factor 1.0582 5.50% = Tk. 32.10
Grand total = Tk. 583.59
07.2.1.2 Formwork/shuttering, prop and necessary supports etc. (steel) Per sqm. = Tk. 317.86
(From Secondary Input : Item C-12) Profit 10.00% = Tk. 31.79
Overhead 3.50% = Tk. 11.13
= Tk. 360.78
Add VAT with adjustment factor 1.0582 5.50% = Tk. 21.00
Grand total = Tk. 381.78
07.2.2.2 Formwork/shuttering, prop and necessary supports etc. (steel) Per sqm. = Tk. 325.50
(From Secondary Input : Item C-13) Profit 10.00% = Tk. 32.55
Overhead 3.50% = Tk. 11.39
= Tk. 369.44
Add VAT with adjustment factor 1.0582 5.50% = Tk. 21.50
Grand total = Tk. 390.94
07.2.3.2 Formwork/shuttering, prop and necessary supports etc. (steel) Per sqm. = Tk. 268.67
(From Secondary Input : Item C-14) Profit 10.00% = Tk. 26.87
Overhead 3.50% = Tk. 9.40
= Tk. 304.94
Add VAT with adjustment factor 1.0582 5.50% = Tk. 17.75
Grand total = Tk. 322.69
07.2.4.2 Formwork/shuttering, prop and necessary supports etc. (steel) Per sqm. = Tk. 310.65
(From Secondary Input : Item C-15) Profit 10.00% = Tk. 31.07
Overhead 3.50% = Tk. 10.87
= Tk. 352.59
Add VAT with adjustment factor 1.0582 5.50% = Tk. 20.52
Grand total = Tk. 373.11
07.2.5.2 Formwork/shuttering, prop and necessary supports etc. (steel) Per sqm. = Tk. 316.25
(From Secondary Input : Item C-16) Profit 10.00% = Tk. 31.63
Overhead 3.50% = Tk. 11.07
= Tk. 358.95
Add VAT with adjustment factor 1.0582 5.50% = Tk. 20.89
Grand total = Tk. 379.84
07.2.6.2 Formwork/shuttering, prop and necessary supports etc. (steel) Per sqm. = Tk. 345.20
Analysis of PWD SoR 2014 for Civil Works 135
07.2.7.2 Formwork/shuttering, prop and necessary supports etc. (steel) Per sqm. = Tk. 414.95
(From Secondary Input : Item C-18) Profit 10.00% = Tk. 41.50
Overhead 3.50% = Tk. 14.52
= Tk. 470.97
Add VAT with adjustment factor 1.0582 5.50% = Tk. 27.41
Grand total = Tk. 498.38
07.2.8.2 Formwork/shuttering, prop and necessary supports etc. (steel) Per sqm. = Tk. 286.43
(From Secondary Input : Item C-19) Profit 10.00% = Tk. 28.64
Analysis of PWD SoR 2014 for Civil Works 136
07.2.9.2 Formwork/shuttering, prop and necessary supports etc. (steel) Per sqm. = Tk. 341.22
(From Secondary Input : Item C-20) Profit 10.00% = Tk. 34.12
Overhead 3.50% = Tk. 11.94
= Tk. 387.28
Add VAT with adjustment factor 1.0582 5.50% = Tk. 22.54
Grand total = Tk. 409.82
07.2.10.2 Formwork/shuttering, prop and necessary supports etc. (steel) Per sqm. = Tk. 335.94
(From Secondary Input : Item C-21) Profit 10.00% = Tk. 33.59
Overhead 3.50% = Tk. 11.76
Analysis of PWD SoR 2014 for Civil Works 137
= Tk. 381.29
Add VAT with adjustment factor 1.0582 5.50% = Tk. 22.19
Grand total = Tk. 403.48
07.2.11.2 Formwork/shuttering, prop and necessary supports etc. (steel) Per sqm. = Tk. 485.89
(From Secondary Input : Item C-8) Profit 10.00% = Tk. 48.59
Overhead 3.50% = Tk. 17.01
= Tk. 551.49
Add VAT with adjustment factor 1.0582 5.50% = Tk. 32.10
Grand total = Tk. 583.59
07.3.1.2 Formwork/shuttering, prop and necessary supports etc. (WOODEN) Per sqm. = Tk. 294.93
(From Secondary Input : Item C-1) Profit 10.00% = Tk. 29.49
Overhead 3.50% = Tk. 10.32
= Tk. 334.74
Analysis of PWD SoR 2014 for Civil Works 138
07.3.2.2 Formwork/shuttering, prop and necessary supports etc. (WOODEN) Per sqm. = Tk. 343.59
(From Secondary Input : Item C-2) Profit 10.00% = Tk. 34.36
Overhead 3.50% = Tk. 12.03
= Tk. 389.98
Add VAT with adjustment factor 1.0582 5.50% = Tk. 22.70
Grand total = Tk. 412.68
07.3.3.2 Formwork/shuttering, prop and necessary supports etc. (WOODEN) Per sqm. = Tk. 295.15
(From Secondary Input : Item C-3) Profit 10.00% = Tk. 29.52
Overhead 3.50% = Tk. 10.33
= Tk. 335.00
Add VAT with adjustment factor 1.0582 5.50% = Tk. 19.50
Analysis of PWD SoR 2014 for Civil Works 139
07.3.4.2 Formwork/shuttering, prop and necessary supports etc. (WOODEN) Per sqm. = Tk. 343.16
(From Secondary Input : Item C-4) Profit 10.00% = Tk. 34.32
Overhead 3.50% = Tk. 12.01
= Tk. 389.49
Add VAT with adjustment factor 1.0582 5.50% = Tk. 22.67
Grand total = Tk. 412.16
07.3.5.2 Formwork/shuttering, prop and necessary supports etc. (WOODEN) Per sqm. = Tk. 327.98
(From Secondary Input : Item C-5) Profit 10.00% = Tk. 32.80
Overhead 3.50% = Tk. 11.48
= Tk. 372.26
Add VAT with adjustment factor 1.0582 5.50% = Tk. 21.67
Grand total = Tk. 393.93
Analysis of PWD SoR 2014 for Civil Works 140
07.3.6.2 Formwork/shuttering, prop and necessary supports etc. (WOODEN) Per sqm. = Tk. 403.97
(From Secondary Input : Item C-6) Profit 10.00% = Tk. 40.40
Overhead 3.50% = Tk. 14.14
= Tk. 458.51
Add VAT with adjustment factor 1.0582 5.50% = Tk. 26.69
Grand total = Tk. 485.20
07.3.7.2 Formwork/shuttering, prop and necessary supports etc. (WOODEN) Per sqm. = Tk. 381.91
(From Secondary Input : Item C-7) Profit 10.00% = Tk. 38.19
Overhead 3.50% = Tk. 13.37
= Tk. 433.47
Add VAT with adjustment factor 1.0582 5.50% = Tk. 25.23
Grand total = Tk. 458.70
Analysis of PWD SoR 2014 for Civil Works 141
07.3.8.2 Formwork/shuttering, prop and necessary supports etc. (WOODEN) Per sqm. = Tk. 286.11
(From Secondary Input : Item C-9) Profit 10.00% = Tk. 28.61
Overhead 3.50% = Tk. 10.01
= Tk. 324.73
Add VAT with adjustment factor 1.0582 5.50% = Tk. 18.90
Grand total = Tk. 343.63
07.3.9.2 Formwork/shuttering, prop and necessary supports etc. (WOODEN) Per sqm. = Tk. 328.73
(From Secondary Input : Item C-10) Profit 10.00% = Tk. 32.87
Overhead 3.50% = Tk. 11.51
= Tk. 373.11
Add VAT with adjustment factor 1.0582 5.50% = Tk. 21.72
Grand total = Tk. 394.83
07.3.10.2 Formwork/shuttering, prop and necessary supports etc. (WOODEN) Per sqm. = Tk. 317.54
(From Secondary Input : Item C-11) Profit 10.00% = Tk. 31.75
Overhead 3.50% = Tk. 11.11
= Tk. 360.40
Add VAT with adjustment factor 1.0582 5.50% = Tk. 20.98
Grand total = Tk. 381.38
07.3.11.2 Formwork/shuttering, prop and necessary supports etc. (WOODEN) Per sqm. = Tk. 485.89
(From Secondary Input : Item C-8) Profit 10.00% = Tk. 48.59
Overhead 3.50% = Tk. 17.01
= Tk. 551.49
Add VAT with adjustment factor 1.0582 5.50% = Tk. 32.10
Grand total = Tk. 583.59
07.4.1.2 Formwork/shuttering, prop and necessary supports etc. (STEEL) Per sqm. = Tk. 317.86
(From Secondary Input : Item C-12) Profit 10.00% = Tk. 31.79
Overhead 3.50% = Tk. 11.13
= Tk. 360.78
Add VAT with adjustment factor 1.0582 5.50% = Tk. 21.00
Grand total = Tk. 381.78
07.4.2.2 Formwork/shuttering, prop and necessary supports etc. (STEEL) Per sqm. = Tk. 325.50
(From Secondary Input : Item C-13) Profit 10.00% = Tk. 32.55
Overhead 3.50% = Tk. 11.39
= Tk. 369.44
Add VAT with adjustment factor 1.0582 5.50% = Tk. 21.50
Grand total = Tk. 390.94
R.C.C work (1:2:4) complete excluding the cost of reinforcement and its fabrication in foundation beam
with STONE chips using STEEL shutter.
07.4.3.2 Formwork/shuttering, prop and necessary supports etc. (STEEL) Per sqm. = Tk. 268.67
(From Secondary Input : Item C-14) Profit 10.00% = Tk. 26.87
Overhead 3.50% = Tk. 9.40
= Tk. 304.94
Add VAT with adjustment factor 1.0582 5.50% = Tk. 17.75
Grand total = Tk. 322.69
07.4.4.2 Formwork/shuttering, prop and necessary supports etc. (STEEL) Per sqm. = Tk. 310.65
(From Secondary Input : Item C-15) Profit 10.00% = Tk. 31.07
Overhead 3.50% = Tk. 10.87
= Tk. 352.59
Add VAT with adjustment factor 1.0582 5.50% = Tk. 20.52
Grand total = Tk. 373.11
07.4.5.2 Formwork/shuttering, prop and necessary supports etc. (STEEL) Per sqm. = Tk. 316.25
(From Secondary Input : Item C-16) Profit 10.00% = Tk. 31.63
Overhead 3.50% = Tk. 11.07
= Tk. 358.95
Add VAT with adjustment factor 1.0582 5.50% = Tk. 20.89
Grand total = Tk. 379.84
07.4.6.2 Formwork/shuttering, prop and necessary supports etc. (STEEL) Per sqm. = Tk. 345.20
(From Secondary Input : Item C-17) Profit 10.00% = Tk. 34.52
Overhead 3.50% = Tk. 12.08
= Tk. 391.80
Add VAT with adjustment factor 1.0582 5.50% = Tk. 22.80
Grand total = Tk. 414.60
07.4.7.2 Formwork/shuttering, prop and necessary supports etc. (STEEL) Per sqm. = Tk. 414.95
(From Secondary Input : Item C-18) Profit 10.00% = Tk. 41.50
Overhead 3.50% = Tk. 14.52
= Tk. 470.97
Add VAT with adjustment factor 1.0582 5.50% = Tk. 27.41
Grand total = Tk. 498.38
07.4.8.2 Formwork/shuttering, prop and necessary supports etc. STEEL) Per sqm. = Tk. 286.43
(From Secondary Input : Item C-19) Profit 10.00% = Tk. 28.64
Overhead 3.50% = Tk. 10.03
= Tk. 325.10
Add VAT with adjustment factor 1.0582 5.50% = Tk. 18.92
Grand total = Tk. 344.02
07.4.9.2 Formwork/shuttering, prop and necessary supports etc. (STEEL) Per sqm. = Tk. 341.22
(From Secondary Input : Item C-20) Profit 10.00% = Tk. 34.12
Overhead 3.50% = Tk. 11.94
= Tk. 387.28
Add VAT with adjustment factor 1.0582 5.50% = Tk. 22.54
Grand total = Tk. 409.82
07.4.10.2 Formwork/shuttering, prop and necessary supports etc. (STEEL) Per sqm. = Tk. 335.94
(From Secondary Input : Item C-21) Profit 10.00% = Tk. 33.59
Overhead 3.50% = Tk. 11.76
= Tk. 381.29
Add VAT with adjustment factor 1.0582 5.50% = Tk. 22.19
Grand total = Tk. 403.48
07.4.11.1 Formwork/shuttering, prop and necessary supports etc. (STEEL) Per sqm. = Tk. 485.89
(From Secondary Input : Item C-8) Profit 10.00% = Tk. 48.59
Overhead 3.50% = Tk. 17.01
= Tk. 551.49
Add VAT with adjustment factor 1.0582 5.50% = Tk. 32.10
Grand total = Tk. 583.59
07.5.1.2 Formwork/shuttering, prop and necessary supports etc. (wooden) Per sqm. = 294.93
(From Secondary Input : Item C-1) Profit 10.00% = Tk. 29.49
Overhead 3.50% = Tk. 10.32
= Tk. 334.74
Add VAT with adjustment factor 1.0582 5.50% = Tk. 19.48
Grand total = Tk. 354.22
07.5.2.2 Formwork/shuttering, prop and necessary supports etc. (wooden) Per sqm. = 343.59
(From Secondary Input : Item C-2) Profit 10.00% = Tk. 34.36
Overhead 3.50% = Tk. 12.03
= Tk. 389.98
Add VAT with adjustment factor 1.0582 5.50% = Tk. 22.70
Grand total = Tk. 412.68
07.5.3.2 Formwork/shuttering, prop and necessary supports etc. (wooden) Per sqm. = 295.15
(From Secondary Input : Item C-3) Profit 10.00% = Tk. 29.52
Overhead 3.50% = Tk. 10.33
= Tk. 335.00
Add VAT with adjustment factor 1.0582 5.50% = Tk. 19.50
Grand total = Tk. 354.50
07.5.4.2 Formwork/shuttering, prop and necessary supports etc. (wooden) Per sqm. = 343.16
(From Secondary Input : Item C-4) Profit 10.00% = Tk. 34.32
Overhead 3.50% = Tk. 12.01
= Tk. 389.49
Add VAT with adjustment factor 1.0582 5.50% = Tk. 22.67
Grand total = Tk. 412.16
07.5.5.2 Formwork/shuttering, prop and necessary supports etc. (wooden) Per sqm. = 327.98
(From Secondary Input : Item C-5) Profit 10.00% = Tk. 32.80
Overhead 3.50% = Tk. 11.48
= Tk. 372.26
Add VAT with adjustment factor 1.0582 5.50% = Tk. 21.67
Grand total = Tk. 393.93
(ii) Laying/placing concrete (@ 1000 cft. concreting using 1 mixer machine in one day) = Tk. 950.46
(From Secondary Input : Item A-4) Tk. 18,817.48
Profit 10.00% = Tk. 1,881.75
Overhead 3.50% = Tk. 658.61
= Tk. 21,357.84
Add VAT with adjustment factor 1.0582 5.50% = Tk. 1,243.05
Grand total = Tk. 22,600.89
Rate per cft. = Tk. 226.01
Rate per cum. = Tk. 7,981.54
07.5.6.2 Formwork/shuttering, prop and necessary supports etc. (wooden) Per sqm. = 403.97
(From Secondary Input : Item C-5) Profit 10.00% = Tk. 40.40
Overhead 3.50% = Tk. 14.14
= Tk. 458.51
Add VAT with adjustment factor 1.0582 5.50% = Tk. 26.69
Grand total = Tk. 485.20
07.5.7.2 Formwork/shuttering, prop and necessary supports etc. (wooden) Per sqm. = 381.91
(From Secondary Input : Item C-6) Profit 10.00% = Tk. 38.19
Overhead 3.50% = Tk. 13.37
= Tk. 433.47
Add VAT with adjustment factor 1.0582 5.50% = Tk. 25.23
Grand total = Tk. 458.70
07.5.8.2 Formwork/shuttering, prop and necessary supports etc. (wooden) Per sqm. = 286.11
(From Secondary Input : Item C-9) Profit 10.00% = Tk. 28.61
Overhead 3.50% = Tk. 10.01
= Tk. 324.73
Add VAT with adjustment factor 1.0582 5.50% = Tk. 18.90
Grand total = Tk. 343.63
07.5.9.2 Formwork/shuttering, prop and necessary supports etc. (wooden) Per sqm. = 328.73
(From Secondary Input : Item C-10) Profit 10.00% = Tk. 32.87
Overhead 3.50% = Tk. 11.51
= Tk. 373.11
Add VAT with adjustment factor 1.0582 5.50% = Tk. 21.72
Grand total = Tk. 394.83
07.5.10.2 Formwork/shuttering, prop and necessary supports etc. (wooden) Per sqm. = 317.54
(From Secondary Input : Item C-11) Profit 10.00% = Tk. 31.75
Overhead 3.50% = Tk. 11.11
= Tk. 360.40
Add VAT with adjustment factor 1.0582 5.50% = Tk. 20.98
Grand total = Tk. 381.38
07.5.11.2 Formwork/shuttering, prop and necessary supports etc. (wooden) Per sqm. = 485.89
(From Secondary Input : Item C-8) Profit 10.00% = Tk. 48.59
Overhead 3.50% = Tk. 17.01
= Tk. 551.49
Add VAT with adjustment factor 1.0582 5.50% = Tk. 32.10
Grand total = Tk. 583.59
= Tk. 28,165.55
Add VAT with adjustment factor 1.0582 5.50% = Tk. 1,639.26
Grand total = Tk. 29,804.81
Rate per cft. = Tk. 298.05
Rate per cum = Tk. 10,525.64
07.6.1.2 Formwork/shuttering, prop and necessary supports etc. (steel) Per sqm. = Tk. 317.86
(From Secondary Input : Item C-12) Profit 10.00% = Tk. 31.79
Overhead 3.50% = Tk. 11.13
= Tk. 360.78
Add VAT with adjustment factor 1.0582 5.50% = Tk. 21.00
Grand total = Tk. 381.78
07.6.2.2 Formwork/shuttering, prop and necessary supports etc. (steel) Per sqm. = Tk. 325.50
(From Secondary Input : Item C-13) Profit 10.00% = Tk. 32.55
Overhead 3.50% = Tk. 11.39
= Tk. 369.44
Add VAT with adjustment factor 1.0582 5.50% = Tk. 21.50
Grand total = Tk. 390.94
07.6.3.2 Formwork/shuttering, prop and necessary supports etc. (steel) Per sqm. = Tk. 268.67
(From Secondary Input : Item C-14) Profit 10.00% = Tk. 26.87
Overhead 3.50% = Tk. 9.40
= Tk. 304.94
Add VAT with adjustment factor 1.0582 5.50% = Tk. 17.75
Grand total = Tk. 322.69
07.6.4.2 Formwork/shuttering, prop and necessary supports etc. (steel) Per sqm. = Tk. 310.65
(From Secondary Input : Item C-15) Profit 10.00% = Tk. 31.07
Overhead 3.50% = Tk. 10.87
= Tk. 352.59
Add VAT with adjustment factor 1.0582 5.50% = Tk. 20.52
Grand total = Tk. 373.11
07.6.5.2 Formwork/shuttering, prop and necessary supports etc. (STEEL) Per sqm. = Tk. 316.25
(From Secondary Input : Item C-16) Profit 10.00% = Tk. 31.63
Overhead 3.50% = Tk. 11.07
= Tk. 358.95
Add VAT with adjustment factor 1.0582 5.50% = Tk. 20.89
Grand total = Tk. 379.84
07.6.6.2 Formwork/shuttering, prop and necessary supports etc. (steel) Per sqm. = Tk. 345.20
(From Secondary Input : Item C-16) Profit 10.00% = Tk. 34.52
Overhead 3.50% = Tk. 12.08
= Tk. 391.80
Add VAT with adjustment factor 1.0582 5.50% = Tk. 22.80
Grand total = Tk. 414.60
07.6.7.2 Formwork/shuttering, prop and necessary supports etc. (steel) Per sqm. = Tk. 414.95
(From Secondary Input : Item C-17) Profit 10.00% = Tk. 41.50
Overhead 3.50% = Tk. 14.52
= Tk. 470.97
Add VAT with adjustment factor 1.0582 5.50% = Tk. 27.41
Grand total = Tk. 498.38
07.6.8.2 Formwork/shuttering, prop and necessary supports etc. (steel) Per sqm. = Tk. 286.43
(From Secondary Input : Item C-19) Profit 10.00% = Tk. 28.64
Overhead 3.50% = Tk. 10.03
= Tk. 325.10
Add VAT with adjustment factor 1.0582 5.50% = Tk. 18.92
Grand total = Tk. 344.02
07.6.9.2 Formwork/shuttering, prop and necessary supports etc. (STEEL) Per sqm. = Tk. 341.22
(From Secondary Input : Item C-20) Profit 10.00% = Tk. 34.12
Overhead 3.50% = Tk. 11.94
= Tk. 387.28
Add VAT with adjustment factor 1.0582 5.50% = Tk. 22.54
Grand total = Tk. 409.82
07.6.10.2 Formwork/shuttering, prop and necessary supports etc. (steel) Per sqm. = Tk. 335.94
(From Secondary Input : Item C-18) Profit 10.00% = Tk. 33.59
Overhead 3.50% = Tk. 11.76
= Tk. 381.29
Add VAT with adjustment factor 1.0582 5.50% = Tk. 22.19
Grand total = Tk. 403.48
07.6.11.2 Formwork/shuttering, prop and necessary supports etc. (steel) Per sqm. = Tk. 485.89
(From Secondary Input : Item C-19) Profit 10.00% = Tk. 48.59
Overhead 3.50% = Tk. 17.01
= Tk. 551.49
Add VAT with adjustment factor 1.0582 5.50% = Tk. 32.10
Grand total = Tk. 583.59
07.7.1.2 Formwork/shuttering, prop and necessary supports etc. (wooden) Per sqm. = Tk. 294.93
(From Secondary Input : Item C-1) Profit 10.00% = Tk. 29.49
Overhead 3.50% = Tk. 10.32
= Tk. 334.74
Add VAT with adjustment factor 1.0582 5.50% = Tk. 19.48
Grand total = Tk. 354.22
07.7.2.2 Formwork/shuttering, prop and necessary supports etc. (wooden) Per sqm. = Tk. 343.59
(From Secondary Input : Item C-2) Profit 10.00% = Tk. 34.36
Overhead 3.50% = Tk. 12.03
= Tk. 389.98
Add VAT with adjustment factor 1.0582 5.50% = Tk. 22.70
Grand total = Tk. 412.68
07.7.3.2 Formwork/shuttering, prop and necessary supports etc. (wooden) Per sqm. = Tk. 295.15
(From Secondary Input : Item C-3) Profit 10.00% = Tk. 29.52
Overhead 3.50% = Tk. 10.33
= Tk. 335.00
Add VAT with adjustment factor 1.0582 5.50% = Tk. 19.50
Grand total = Tk. 354.50
07.7.4.2 Formwork/shuttering, prop and necessary supports etc. (wooden) Per sqm. = Tk. 343.16
(From Secondary Input : Item C-4) Profit 10.00% = Tk. 34.32
Overhead 3.50% = Tk. 12.01
= Tk. 389.49
Add VAT with adjustment factor 1.0582 5.50% = Tk. 22.67
Grand total = Tk. 412.16
07.7.5.2 Formwork/shuttering, prop and necessary supports etc. (STEEL) Per sqm. = Tk. 327.98
(From Secondary Input : Item C-5) Profit 10.00% = Tk. 32.80
Overhead 3.50% = Tk. 11.48
= Tk. 372.26
Add VAT with adjustment factor 1.0582 5.50% = Tk. 21.67
Grand total = Tk. 393.93
07.7.6.2 Formwork/shuttering, prop and necessary supports etc. (wooden) Per sqm. = Tk. 403.97
(From Secondary Input : Item C-5) Profit 10.00% = Tk. 40.40
Overhead 3.50% = Tk. 14.14
= Tk. 458.51
Add VAT with adjustment factor 1.0582 5.50% = Tk. 26.69
Grand total = Tk. 485.20
07.7.7.2 Formwork/shuttering, prop and necessary supports etc. (wooden) Per sqm. = Tk. 381.91
(From Secondary Input : Item C-6) Profit 10.00% = Tk. 38.19
Overhead 3.50% = Tk. 13.37
= Tk. 433.47
Add VAT with adjustment factor 1.0582 5.50% = Tk. 25.23
Grand total = Tk. 458.70
07.7.8.2 Formwork/shuttering, prop and necessary supports etc. (steel) Per sqm. = Tk. 286.11
Analysis of PWD SoR 2014 for Civil Works 163
07.7.9.2 Formwork/shuttering, prop and necessary supports etc. (STEEL) Per sqm. = Tk. 328.73
(From Secondary Input : Item C-10) Profit 10.00% = Tk. 32.87
Overhead 3.50% = Tk. 11.51
= Tk. 373.11
Add VAT with adjustment factor 1.0582 5.50% = Tk. 21.72
Grand total = Tk. 394.83
07.7.10.2 Formwork/shuttering, prop and necessary supports etc. (wooden) Per sqm. = Tk. 317.54
(From Secondary Input : Item C-7) Profit 10.00% = Tk. 31.75
Overhead 3.50% = Tk. 11.11
= Tk. 360.40
Add VAT with adjustment factor 1.0582 5.50% = Tk. 20.98
Grand total = Tk. 381.38
07.7.11.2 Formwork/shuttering, prop and necessary supports etc. (wooden) Per sqm. = Tk. 485.89
(From Secondary Input : Item C-9) Profit 10.00% = Tk. 48.59
Overhead 3.50% = Tk. 17.01
= Tk. 551.49
Add VAT with adjustment factor 1.0582 5.50% = Tk. 32.10
Grand total = Tk. 583.59
07.8.1.2 Formwork/shuttering, prop and necessary supports etc. (steel) Per sqm. = Tk. 317.86
(From Secondary Input : Item C-12) Profit 10.00% = Tk. 31.79
Overhead 3.50% = Tk. 11.13
= Tk. 360.78
Add VAT with adjustment factor 1.0582 5.50% = Tk. 21.00
Grand total = Tk. 381.78
07.8.2.2 Formwork/shuttering, prop and necessary supports etc. (steel) Per sqm. = Tk. 325.50
(From Secondary Input : Item C-13) Profit 10.00% = Tk. 32.55
Overhead 3.50% = Tk. 11.39
= Tk. 369.44
Add VAT with adjustment factor 1.0582 5.50% = Tk. 21.50
Grand total = Tk. 390.94
07.8.3.2 Formwork/shuttering, prop and necessary supports etc. (steel) Per sqm. = Tk. 268.67
(From Secondary Input : Item C-14) Profit 10.00% = Tk. 26.87
Overhead 3.50% = Tk. 9.40
= Tk. 304.94
Add VAT with adjustment factor 1.0582 5.50% = Tk. 17.75
Grand total = Tk. 322.69
Analysis of PWD SoR 2014 for Civil Works 167
07.8.4.2 Formwork/shuttering, prop and necessary supports etc. (steel) Per sqm. = Tk. 310.65
(From Secondary Input : Item C-15) Profit 10.00% = Tk. 31.07
Overhead 3.50% = Tk. 10.87
= Tk. 352.59
Add VAT with adjustment factor 1.0582 5.50% = Tk. 20.52
Grand total = Tk. 373.11
07.8.5.2 Formwork/shuttering, prop and necessary supports etc. (STEEL) Per sqm. = Tk. 316.25
(From Secondary Input : Item C-16) Profit 10.00% = Tk. 31.63
Overhead 3.50% = Tk. 11.07
= Tk. 358.95
Add VAT with adjustment factor 1.0582 5.50% = Tk. 20.89
Grand total = Tk. 379.84
Analysis of PWD SoR 2014 for Civil Works 168
07.8.6.2 Formwork/shuttering, prop and necessary supports etc. (steel) Per sqm. = Tk. 345.20
(From Secondary Input : Item C-17) Profit 10.00% = Tk. 34.52
Overhead 3.50% = Tk. 12.08
= Tk. 391.80
Add VAT with adjustment factor 1.0582 5.50% = Tk. 22.80
Grand total = Tk. 414.60
Ground floor and below plinth level Say, Tk. 415 .00 Per sqm.
07.8.7.2 Formwork/shuttering, prop and necessary supports etc. (steel) Per sqm. = Tk. 414.95
(From Secondary Input : Item C-18) Profit 10.00% = Tk. 41.50
Overhead 3.50% = Tk. 14.52
= Tk. 470.97
Add VAT with adjustment factor 1.0582 5.50% = Tk. 27.41
Grand total = Tk. 498.38
07.8.8.2 Formwork/shuttering, prop and necessary supports etc. (steel) Per sqm. = Tk. 286.43
(From Secondary Input : Item C-19) Profit 10.00% = Tk. 28.64
Overhead 3.50% = Tk. 10.03
= Tk. 325.10
1.0582 5.50% = Tk. 18.92
Grand total = Tk. 344.02
07.8.9.2 Formwork/shuttering, prop and necessary supports etc. (STEEL) Per sqm. = Tk. 341.22
Analysis of PWD SoR 2014 for Civil Works 170
07.8.10.2 Formwork/shuttering, prop and necessary supports etc. (steel) Per sqm. = Tk. 335.94
(From Secondary Input : Item C-21) Profit 10.00% = Tk. 33.59
Overhead 3.50% = Tk. 11.76
= Tk. 381.29
Add VAT with adjustment factor 1.0582 5.50% = Tk. 22.19
Grand total = Tk. 403.48
(a) Extra head mason 0.1 No. @ Tk. 493.00 each = Tk. 49.30
(b) Extra mason 0.2 No. @ Tk. 389.00 each = Tk. 77.80
(c) Extra skilled labour 0.2 No. @ Tk. 303.00 each = Tk. 60.60
(d) Extra ordinary labour 1 No. @ Tk. 245.00 each = Tk. 245.00
(e) Extra for local carriage, storage & sundries etc. L.S. = Tk. 24.50
Total = Tk. 457.20
Profit 10.00% = Tk. 45.72
Overhead 3.50% = Tk. 16.00
= Tk. 518.92
Add VAT with adjustment factor 1.0582 5.50% = Tk. 30.20
Grand total = Tk. 549.12
Rate per cft. = Tk. 5.49
Rate per cum. = Tk. 193.88
(a) Extra cost for shorted out shutter 100 sft. @ Tk. 16.04 Per sft. = Tk. 1,604.00
(b) Extra labour for placing shutter 100 sft. @ Tk. 4.80 Per sft. = Tk. 480.00
(c) Shutter releasing agent / form oil 1 liter @ Tk. 150.00 Per liter = Tk. 150.00
(d) Sundries, incidental and extra supervision L.S. = Tk. 150.00
Total = Tk. 2,384.00
Profit 10.00% = Tk. 238.40
Overhead 3.50% = Tk. 83.44
= Tk. 2,705.84
Add VAT with adjustment factor 1.0582 5.50% = Tk. 157.48
Grand total = Tk. 2,863.32
Analysis of PWD SoR 2014 for Civil Works 174
09.1.1.2 Considering executing 400 mm /16 inch dia 29 meter long pile in days. 29 m 1.07 day
1. Hire charge of rig set in/c fuel, lubricant, bentonite,
mobilization, demobilization, maintenance and
insurance coverage etc. 1.07 days @ Tk. 8,820.00 Per day = Tk. 9,437.40
2 Driving log recorder 1.07 Nos. @ Tk. 567.00 Per day = Tk. 606.69
3 Foreman/supervisor 1.07 Nos. @ Tk. 567.00 each = Tk. 606.69
4 Skilled labour 3.21 Nos. @ Tk. 303.00 each = Tk. 972.63
5 Ordinary labour 6.42 Nos. @ Tk. 245.00 each = Tk. 1,572.90
6 power ,bentonite ,water, clean & sundry 1.02 Total = Tk. 13,196.31
Profit 10.00% = Tk. 1,319.63
Overhead 3.50% = Tk. 461.87
= Tk. 14,977.81
Add VAT with adjustment factor 1.0582 5.50% = Tk. 871.72
Grand total = Tk. 15,849.53
Rate per meter = Tk. 546.54
So, extra cost for each addl. meter boring and length up to 30m = 1.5(B-A)/9 = Tk. 3.50
Say, Tk. 4 .00 Per meter
450 29
09.1.2.2 Considering executing 450 mm /18 inch dia & 29 meter long pile in days 1.36
1. Hire charge of rig set in/c fuel, lubricant, bentonite,
mobilization, demobilization, maintenance
and insurance coverage etc. 1.36 days @ Tk. 8,820.00 Per day = Tk. 11,995.20
2 Driving log recorder 1.36 days @ Tk. 567.00 Per day = Tk. 771.12
2. Foreman/supervisor 1.36 Nos. @ Tk. 567.00 each = Tk. 771.12
3. Skilled labour 4.08 Nos. @ Tk. 303.00 each = Tk. 1,236.24
4. Ordinary labour 8.16 Nos. @ Tk. 245.00 each = Tk. 1,999.20
6 power ,bentonite ,water, clean & sundry 1.02 Total = Tk. 16,772.88
Profit 10.00% = Tk. 1,677.29
Overhead 3.50% = Tk. 587.05
= Tk. 19,037.22
Add VAT with adjustment factor 1.0582 5.50% = Tk. 1,107.99
Grand total = Tk. 20,145.21
Rate per meter = Tk. 694.66
So, extra cost for each addl. meter boring and length up to 29 m= 1.5(B-A)/9 = Tk. 4.83
500 29 m 1.68
09.1.3.2 Considering executing 500 mm /20 inch dia & 29 meter long pile in days 1.68
1. Hire charge of rig set in/c fuel, lubricant, bentonite,
mobilization, demobilization, maintenance and
insurance coverage etc. 1.68 days @ Tk. 8,820.00 Per day = Tk. 14,817.60
2 Driving log recorder 1.68 days @ Tk. 567.00 Tk. 952.56
3 Foreman/supervisor 1.68 Nos. @ Tk. 567.00 each = Tk. 952.56
4 Skilled labour 5.04 Nos. @ Tk. 303.00 each = Tk. 1,527.12
5 Ordinary labour 10.08 Nos. @ Tk. 245.00 each = Tk. 2,469.60
Analysis of PWD SoR 2014 for Civil Works 185
6 power ,bentonite ,water, clean & sundry 1.02 Total = Tk. 20,719.44
Profit 10.00% = Tk. 2,071.94
Overhead 3.50% = Tk. 725.18
= Tk. 23,516.56
Add VAT with adjustment factor 1.0582 5.50% = Tk. 1,368.69
Grand total = Tk. 24,885.25
Rate per meter = Tk. 858.11
So, extra cost for each addl. meter boring and length up to 29 m=1.5 (B-A)/9 = Tk. 6.75
So, extra cost for each addl. meter boring and length up to 29 m=1.5 (B-A)/9 = Tk. 8.17
So, extra cost for each addl. 1 m boring up to 29 meter = 1.5(B-A)/9 = Tk. 8.67
1. Hire charge of 3HP mud pump 1/4 day @ Tk. 588.00 Per day = Tk. 147.00
2. Hire charge of MS steel tank (6'-6" x 10'-0" x 4'-0") 1 trip @ Tk. 350.00 Per trip = Tk. 350.00
3. Hire charge of truck 1 trip @ Tk. 975.00 Per trip = Tk. 975.00
4. Pump operator 1/4 Nos. @ Tk. 356.00 Per nos = Tk. 89.00
5. Ordinary labour 1/2 Nos. @ Tk. 245.00 Per nos = Tk. 122.50
6. Sundries and incidental cost L.S. = Tk. 100.00
Total (A+B) = Tk. 1,783.50
Profit 10.00% = Tk. 178.35
Overhead 3.50% = Tk. 62.42
= Tk. 2,024.27
Add VAT with adjustment factor 1.0582 5.50% = Tk. 117.81
Grand total = Tk. 2,142.08
Rate per cft. = Tk. 10.71
Rate per cum. = Tk. 378.22
Analysis of PWD SoR 2014 for Civil Works 187
charges, hydraulic fluid etc.) 1 test @ Tk. 10,642.00 Per test = Tk. 10,642.00
(d) Cost of empty gunny bags
(taking 2 times use) 1367.142857 bags. @ Tk. 4.50 Per bag = Tk. 6,152.14
(e) Cost of local sand as loading
materials (taking 2 times use) 1367.142857 cft @ Tk. 450.00 Per % cft. = Tk. 6,152.14
(f) Labour for bag filling,
stitching, loading & unloading: 2734.285714 bags @ Tk. 8.64 Per bag = Tk. 23,624.23
(h) Preparation of result in standard
form in triplicate 1 test @ Tk. 6,250.00 Per test = Tk. 6,250.00
(i) Other incidental charges L.S. = Tk. 735.00
Total = Tk. 83,972.51
Profit 10.00% = Tk. 8,397.25
Overhead 3.50% = Tk. 2,939.04
= Tk. 95,308.80
Add VAT with adjustment factor 1.0582 5.50% = Tk. 5,547.07
Grand total = Tk. 100,855.87
= 176.00 rft.
Add 5% wastage= 8.8 rft.
= 184.80 rft.
@ 0.956 Ibs Per rft.= 176.67 Ibs. @ Tk. 25.40 Per Ib. = Tk. 4,487.42
(iv) Cost of nuts & bolts: 20.0 kg. @ Tk. 133.00 Per kg. = Tk. 2,660.00
(v) Manufacturing, fitting and fixing frame in/c drilling holes,
welding & supplying of chemicals etc.:
12 x 40'-0" x 0'-10"= 400.00 sft. @ Tk. 69.17 Per sft. = Tk. 27,668.00
Total = Tk. 161,538.68
Using 16 times = Tk. 10,096.17
(vi) Labour for fitting & fixing steel shuttering
in position as required 400.00 sft. @ Tk. 8.00 Per sft. = Tk. 3,200.00
(vii) Hessian tap for making
shutter water-proof. 400.00 sft. @ Tk. 1.13 Per sft. = Tk. 452.00
(viii) Curing 400.00 sft. @ Tk. 2.04 Per sft. = Tk. 816.00
Total for 305.56 cft. = Tk. 14,564.17
Cost for 100 cft. = Tk. 4,766.39
D. Cost of bed preparation:
Area of bed: 1 x 45'-0" x 13'-2"= 592.65 sft.
(a) One layer brick flat soling: 592.65 sft. @ Tk. 27.44 Per sft. = Tk. 16,262.32
(b) 1/2" thick cement finishing with
neat cement finishing 592.65 sft. @ Tk. 19.06 Per sft. = Tk. 11,295.91
Total for 305.56 cft. = Tk. 27,558.23
Cost for 100 cft. of work = Tk. 9,018.93
Using 8 times = Tk. 1,127.37
E. Polythene as separator between pile layers
during casting concrete 592.65 sft. @ Tk. 262.19 Per % sft. = Tk. 1,553.87
Cost for 100 cft. of work = Tk. 353.15
Abstract of cosr for 100 cft. of work
A. Cost of concrete = Tk. 23,865.00
B. Labour, machinery, fuel and lubricant for casting = Tk. 950.46
C. Cost of shuttering = Tk. 4,766.39
D. Cost of bed preparation = Tk. 1,127.37
E. Polythene = Tk. 353.15
Total = Tk. 31,062.37
Profit 10.00% = Tk. 3,106.24
Overhead 3.50% = Tk. 1,087.18
= Tk. 35,255.79
Add VAT with adjustment factor 1.0582 5.50% = Tk. 2,051.92
Grand total = Tk. 37,307.71
Rate per cft. = Tk. 373.08
Rate per rft. = Tk. 259.08
Rate per rm. = Tk. 850.04
= 227.50 rft.
= 145.60 Ibs @ Tk. 25.40 Per Ib. = Tk. 3,698.24
(iv) Cost of nuts & bolts: @ 3.5 kg per % sft steel shuter
20.00 kg. @ Tk. 133.00 Per kg. = Tk. 2,660.00
(v) Manufacturing, fitting and fixing
frame in/c drilling holes, welding
& supplying of chemical etc. 670.00 sft @ Tk. 69.17 Per sft. = Tk. 46,343.90
Sub-Total = Tk. 230,049.33
Using 16 times = Tk. 14,378.08
(vi) Labour for fitting and fixing steel shuttering in
position as required.
40 x 25'-0" x 0'-8"= 670 sft @ Tk. 8.00 Per sft. = Tk. 5,360.00
(vii) Hessian tap for making shutter
water-proof 670 sft @ Tk. 1.13 Per sft. = Tk. 757.10
(viii) Curing 670 sft. @ Tk. 2.04 Per sft. = Tk. 1,366.80
Total = Tk. 21,861.98
Cost for 100 cft. = Tk. 4,994.97
D. Cost of bed preparation
Area: 33'-3" x 27'-0"= 897.75 sft.
Concrete: 39 x 8" x 8" x 25'-0= 437.68 cft.
(a) One layer brick flat soling: 897.75 sft. @ Tk. 27.44 Per sft. = Tk. 24,634.26
(b) 1/2 thick cement plaster
with neat cement finishing: 897.75 sft. @ Tk. 19.06 Per sft. = Tk. 17,111.12
Total = Tk. 41,745.38
Cost for 100 cft. of work = Tk. 9,537.88
Using 8 times = Tk. 1,192.24
E. Polythene as separator between pile layers
during casting concrete 897.75 sft. @ Tk. 262.19 Per % sft. = Tk. 2,353.81
Cost for 100 cft. of work = Tk. 537.79
Abstract of cost for 100 cft. of work
(a) Cost of concrete = Tk. 24,912.50
(b) Labour, machinery, fuel and lubricants for casting = Tk. 1,584.10
(c) Cost of shuttering = Tk. 4,994.97
(d) Cost of bed preparation = Tk. 1,192.24
(e) Cost of polythene = Tk. 537.79
Total = Tk. 33,221.60
Profit 10.00% = Tk. 3,322.16
Overhead 3.50% = Tk. 1,162.76
= Tk. 37,706.52
Add VAT with adjustment factor 1.0582 5.50% = Tk. 2,194.56
Grand total = Tk. 39,901.08
Rate per cft. = Tk. 399.01
Rate per rft. = Tk. 175.56
Rate per rm = Tk. 576.01
Mobilization & demobilization within 100km of dhaka in/c 1st 12 piles Tk. 20,000.00
= Tk. 16,335.75
Add VAT with adjustment factor 1.0582 5.50% = Tk. 950.76
Grand total = Tk. 17,286.51
Rate per sft = Tk. 115.24
Rate per sqm. = Tk. 1,240.44
B) Workshop charge:
(item i + ii = 1399.14 + 89.36 = 1488.50 kg)
Fabrication, welding, making charge etc. 1488.50 kg @ Tk. 32/- per kg Tk. 47,632.00
iii) Labour cost 125.42 sqm @ tk. 40/80 per sqm Tk. 5,117.14
Tk. 161,260.85
DIVISION 11. WOOD WORK IN DOOR AND WINDOW FRAME, ROOF TRUSS AND RAILINGS
Item No.- 11.1.1
Supply and making door and window frames with seasoned wood
Considering 1 No. door frame
Considering for door size: 3'-4" x 7'-0"
Wood reqd.: (2 x 7'-0" + 3'-4") x 0'-2.5" x 0'-5" =1.5 cft. (finished)
= (2 x 7'-0" + 3'-6") x 0'-2.75" x 0'-5.25" = 1.75 (gross)
Garjan/Jam wood
(a) Cost of wood 1.75 cft. @ Tk. 2,000.0 Per cft. = Tk. 3,500.00
(b) Coaltaring: 2 coats
1 x (2 x 7'-2.5" + 3'-4") x 0'-5"= 7.5 sft @ Tk. 6.00 Per sft. = Tk. 45.00
(c) Labour for making frame =
(i) Carpenter 0.75 No. @ Tk. 423.00 each = Tk. 317.25
(ii) Carpenter helper 1.0 No. @ Tk. 304.00 each = Tk. 304.00
(d) Labour for fitting, fixing in position L.S. = Tk. 151.50
Total = Tk. 4,317.75
Profit 10.00% = Tk. 431.78
Overhead 3.50% = Tk. 151.12
= Tk. 4,900.65
Add VAT with adjustment factor 1.0582 5.50% = Tk. 285.22
Grand total = Tk. 5,185.87
Rate per cft. = Tk. 3,457.25
Rate per cum. = Tk. 122,092.78
For Silkarai
(a) Cost of wood 1.75 cft. @ Tk. 2,800.0 Per cft. = Tk. 4,900.00
(b) Coaltaring: 2 coats 7.5 sft. @ Tk. 6.00 Per sft. = Tk. 45.00
(c) Labour for making
(i) Carpenter 0.75 No. @ Tk. 423.00 each = Tk. 317.25
(ii) Carpenter helper 1.0 No. @ Tk. 304.00 each = Tk. 304.00
(d) Labour for fitting fixing in position L.S. = Tk. 60.00
Total = Tk. 5,626.25
Profit 10.00% = Tk. 562.63
Overhead 3.50% = Tk. 196.92
= Tk. 6,385.80
Add VAT with adjustment factor 1.0582 5.50% = Tk. 371.66
Grand total = Tk. 6,757.46
Rate per cft. = Tk. 4,504.97
Rate per cum. = Tk. 159,093.02
= Tk. 9,762.42
Add VAT with adjustment factor 1.0582 5.50% = Tk. 568.18
Grand total = Tk. 10,330.60
Rate per cft. = Tk. 6,887.07
Rate per cum. = Tk. 243,216.88
2. Labour for fabrication: 50.43 Ibs @ Tk. 275.85 Per cwt. = Tk. 124.21
3. Cost of welding:
Frame: 2 x 4 x 1.5" = 12.00 inch
Clamp: 6 x 4 x 1.5" = 36.00 inch
Hinge: 6 x (2 x 2"+4") = 48.00 inch
= 96.00 inch @ Tk. 5.00 Per inch = Tk. 480.00
4. Labour for fitting fixing in position, making @ 6 Nos. of holes in
existing brick work or making special arrangement
for fixing with concrete work 1 No. @ Tk. 226.92 each = Tk. 226.92
5. Cost of C.C. (1:2:4) in/c mending good the damages:
6 x 5" x 5" x 6" = 0.52 cft. @ Tk. 176.37 Per cft. = Tk. 91.71
6. Local carriage & carriage from workshop to site LS = Tk. 73.50
Total = Tk. 2,569.53
Profit 10.00% = Tk. 256.95
Overhead 3.50% = Tk. 89.93
= Tk. 2,916.41
Add VAT with adjustment factor 1.0582 5.50% = Tk. 169.74
Grand total = Tk. 3,086.15
Rate per rft. = Tk. 171.45
Rate per rm. = Tk. 562.53
(ii) Carpenter helper 0.25 No. @ Tk. 304.00 each = Tk. 76.00
Total = Tk. 3,338.75
Profit 10.00% = Tk. 333.88
Overhead 3.50% = Tk. 116.86
= Tk. 3,789.49
Add VAT with adjustment factor 1.0582 5.50% = Tk. 220.55
Grand total = Tk. 4,010.04
Rate per cft. = Tk. 4,010.04
Rate per cum. = Tk. 141,614.56
(a) Fittings:
(i) 10" long iron tower bolt 1 No. @ Tk. 39.00 each = Tk. 39.00
(ii) 8" socket bolt 1 No. @ Tk. 28.00 each = Tk. 28.00
(iii) Hatch bolt 1 No. @ Tk. 354.00 each = Tk. 354.00
(iv) 4" long hinges 4 No. @ Tk. 73.00 each = Tk. 292.00
(v) Nickle plated handle 2 No. @ Tk. 48.00 each = Tk. 96.00
(vi) Iron screws 5 dzn. @ Tk. 16.00 Per dzn = Tk. 80.00
(vii) Hinged cleats & buffer block 1 set @ Tk. 58.00 Per set = Tk. 58.00
Total of (A) = Tk. 947.00
(b) Labour:
(i) Carpenter 3 Nos. @ Tk. 423.00 each = Tk. 1,269.00
(ii) Carpenter helper 5 Nos. @ Tk. 304.00 each = Tk. 1,520.00
Total of (B) = Tk. 2,789.00
(c) Cost of wood: Kathal
Solid wood:
7'-0" x 3'-0" x 1.75"= 3.06 cft.
Wood for joint:
4 x 7'-0" x 0'-1" x 0.5"= 0.1 cft.
3.16 cft. @ Tk. 2,250.0 Per cft. = Tk. 7,110.00
Total (A+B+C) = Tk. 10,846.00
Profit 10.00% = Tk. 1,084.60
Overhead 3.50% = Tk. 379.61
= Tk. 12,310.21
Add VAT with adjustment factor 1.0582 5.50% = Tk. 716.47
Grand total = Tk. 13,026.68
Rate per sft. = Tk. 635.45
Rate per sqm. = Tk. 6,839.98
A) Cost of materials
Ctg. Teak Wood
5 1/4" X 1 1/2" X 6'-10" X 2 nos = 0.87 cft
9 1/4" X 3 3/4" X 3'-0" X 1 no = 0.34 "
6 1/4" X 1 3/4" X 3'-0" X 2 nos = 0.46 "
For foreign 4 1/4" X 1 3/4" X 1'-0" X 1 no = 0.05 "
Panel 7 1/2" X 1 3/4" X 3'-0" X 4 nos = 1.09 "
7 1/2" X 1 3/4" X 2'-6" X 4 nos = 0.91 "
= 3.72 cft Tk. 4,500.00 Per cft = Tk. 16,740.00
B) Cost of labour
i) Carpenter 3 Nos @ Tk. 423.00 Per day = Tk. 1,269.00
ii) Carpenter helper 5 Nos @ Tk. 304.00 Per day = Tk. 1,520.00
Analysis of PWD SoR 2014 for Civil Works 219
(b) Labour:
(i) Carpenter 3 Nos. @ Tk. 423.00 each = Tk. 1,269.00
(ii) Carpenter helper 6.5 Nos. @ Tk. 304.00 each = Tk. 1,976.00
Total of (B) = Tk. 3,245.00
(c) Cost of wood:
4 x 6'-9" x 4.25" x 1.75"= 1.395 cft.
1 x 3'-9" x 9.25" x 1.75"= 0.422 cft.
1 x 3'-9" x 5.25" x 1.75"= 0.239 cft.
1 x 3'-9" x 4.25" x 1.75"= 0.194 cft.
panel: 1 x 5'-6" x 3'-0" x 1.25"= 1.719 cft.
= 3.969 cft. @ Tk. 2,250.0 Per cft. = Tk. 8,930.25
Total (A+B+C) = Tk. 13,414.25
Profit 10.00% = Tk. 1,341.43
Overhead 3.50% = Tk. 469.50
= Tk. 15,225.18
Add VAT with adjustment factor 1.0582 5.50% = Tk. 886.12
Grand total = Tk. 16,111.30
Rate per sft. = Tk. 666.31
Rate per sqm. = Tk. 7,172.16
= Tk. 433.57
Add VAT with adjustment factor 1.0582 5.50% = Tk. 25.23
Grand total = Tk. 458.80
Rate per cft. = Tk. 458.80
Rate per cum. = Tk. 16,202.52
24.48 sft.
= 49.95 Ibs. @ Tk. 38.55 Per Ib. = Tk. 1,925.57
(b) Fittings, hardwares and consumables:
(i) Locking arrangement 2.00 Nos. @ Tk. 229.00 each = Tk. 458.00
(ii) 3" long hinge 4.00 Nos. @ Tk. 5.00 each = Tk. 20.00
(iii) Electrodes 80.00 Nos. @ Tk. 10.00 each = Tk. 800.00
c) Fabrication and making in work-shop
(i) Welder / fabricator 2.00 Nos. @ Tk. 423.00 each = Tk. 846.00
(ii) Welder helper 2.00 Nos. @ Tk. 304.00 each = Tk. 608.00
(iii) Ordinary labour 2.00 Nos. @ Tk. 245.00 each = Tk. 490.00
d) Carrying of materials to work-shop and fabricated materials to site: = Tk. 50.00
Sub-total = Tk. 8,902.62
e) Work-shop charges: 10% = Tk. 890.26
Total = Tk. 9,792.88
f) Ancillary works for fitting-fixing the door shutter
(i) Labour charge for cutting
2" x 2" x 6" size grooves 6 Nos @ Tk. 10.21 each = Tk. 61.26
(ii) CC (1:2:4):
6 x 3" x 3" x 6"= 0.19 cft. @ Tk. 17,637.01 Per % cft. = Tk. 33.51
g) Labour charge for fitting fixing the door shutter
(i) Mason 0.50 No. @ Tk. 389.00 each = Tk. 194.50
(ii) Mason helper 1.00 No. @ Tk. 304.00 each = Tk. 304.00
(iii) Ordinary labour 0.50 No. @ Tk. 245.00 each = Tk. 122.50
Grand total = Tk. 10,508.65
Profit 10.00% = Tk. 1,050.87
Overhead 3.50% = Tk. 367.80
= Tk. 11,927.32
Add VAT with adjustment factor 1.0582 5.50% = Tk. 694.18
Grand total = Tk. 12,621.50
Rate per sft. = Tk. 541.46
Rate per sqm. = Tk. 5,828.28
= 27.30 rft.
= 8.74 Ibs. @ Tk. 25.40 Per Ib. = Tk. 222.00
(iii) 1" x 1/8" F.I. bar (@ 0.423 Ib per rft.)
Chowkat: 1 x 4'-0"= 4 rft.
1 x 3'-0"= 3 rft.
= 7 rft.
Add wastage 5% = 0.35 rft.
= 7.35 rft.
= 3.11 Ibs. @ Tk. 25.40 Per Ib. = Tk. 78.99
(b) Fittings
(i) Stopper handle 2 Nos. @ Tk. 22.00 each = Tk. 44.00
(ii) 12" long iron cleats 3 Nos. @ Tk. 26.00 each = Tk. 78.00
(iii) 2" long pin hinges 6 Nos. @ Tk. 24.00 each = Tk. 144.00
(iv) 6" long clamp for chowkat 4 Nos. @ Tk. 28.00 each = Tk. 112.00
(c) Workshop charges:
Manufacturing including fabrication,
revetting, welding in/c supply of
all necessary incidental materials 15 sft. @ Tk. 58.00 Per sft. = Tk. 870.00
(d) Labour charges
Labour charges for fitting fixing in position finished window shutter and
frames in the building including embeding clamp
in CC (1:2:4) & making grooves and mending
good the damage etc. complete. 1 No. @ Tk. 171.64 Per sft. = Tk. 171.64
(e) Carriage charges:
Carriage charge for iron materials from market to
workshop & carrying the finished window
from workshop to building site. 1 No. @ Tk. 36.75 each = Tk. 36.75
(f) Glass panes:
(i) 3 mm glass panes in/c wastage etc. 15 sft. @ Tk. 41.00 Per sft. = Tk. 615.00
(ii) Fitting fixing of glass panes with necessary
iron pins & pucca putty 15 sft. @ Tk. 15.46 Per sft. = Tk. 231.90
Total = Tk. 4,118.20
Profit 10.00% = Tk. 411.82
Overhead 3.50% = Tk. 144.14
= Tk. 4,674.16
Add VAT with adjustment factor 1.0582 5.50% = Tk. 272.04
Grand total = Tk. 4,946.20
Rate per sft. = Tk. 329.75
Rate per sqm. = Tk. 3,549.43
Supplying, fitting & fixing of fixed glazed frame with outer member of 3/4" x 3/4" x 3/4" x 1/8" Z
& 3/4" x 3/4" x 1/8" T-section etc.
Considering 1 No. fixed glazed frame
For 5'-0" x 2'-0"= 10 sft. of work
(a) Steel materials:
(i) 3/4" x 3/4" x 3/4" x 1/8" Z-section (@0.96 Ib per rft.):-
2 x 5'-0" + 2 x 2'-0"= 14.00 rft.
Add wastage 5%= 0.70 rft.
= 14.70 rft.
= 14.11 Ibs. @ Tk. 28.34 Per Ib. = Tk. 399.88
(ii) 3/4" x 1/8" F.I. bar to make T-section
(@ 0.32 Ibs per rft.) for horizontal and vertical divider
2 x (1 x 5'-0") + 2 x (2 x 5 x 1'-0")= 30.00 rft.
Add wastage 5%= 1.50 rft.
= 31.50 rft.
= 20.48 Ibs. @ Tk. 25.40 Per Ib. = Tk. 520.19
(iii) 6" long clamp for chowkat: 6.00 Nos. @ Tk. 28.00 each = Tk. 168.00
(b) Workshop charges:
Manufacturing including fabrication,
revetting, welding in/c supply of all
necessary incidental materials 10 sft. @ Tk. 58.00 Per sft. = Tk. 580.00
(c) Labour charges
Labour charges for fitting fixing in position finished window frames in
the building shutter and including embeding clamp in
CC (1:2:4) & making grooves and mending
good the damage etc. complete. 1 No. @ Tk. 171.64 Per sft. = Tk. 171.64
(d) Carriage charges:
Carriage charge for iron materials from market to
workshop & carrying the finished window
from workshop to building site. 1 No. @ Tk. 36.75 each = Tk. 36.75
(f) Glass panes:
(i) 3 mm glass panes in/c wastage etc. 10 sft. @ Tk. 41.00 Per sft. = Tk. 410.00
(ii) Fitting fixing of glass panes with necessary
iron pins & pucca putty 10 sft. @ Tk. 15.46 Per sft. = Tk. 154.60
Total = Tk. 2,441.06
Profit 10.00% = Tk. 244.11
Overhead 3.50% = Tk. 85.44
= Tk. 2,770.61
Add VAT with adjustment factor 1.0582 5.50% = Tk. 161.25
Grand total = Tk. 2,931.86
Rate per sft. = Tk. 293.19
Rate per sqm. = Tk. 3,155.90
(ii) Carpenter helper 0.25 No. @ Tk. 304.00 each = Tk. 76.00
Total = Tk. 226.75
Profit 10.00% = Tk. 22.68
Overhead 3.50% = Tk. 7.94
= Tk. 257.37
Add VAT with adjustment factor 1.0582 5.50% = Tk. 14.98
Grand total = Tk. 272.35
Rate per No. = Tk. 272.35
b) workshope charge
labour cost for manufacturing, welding, welding 22.50 sft @ Tk. 45.71 per sft =Tk. 1,028.48
c) labour charges
labour charges for fitting fixing in position of grill
i) mason 0.50 No. @ Tk. 389.00 each Tk. 194.50
ii) skilled labour 0.50 No. @ Tk. 303.00 each Tk. 151.50
iii) cost of screws 3.00 dzn @ Tk. 16.00 per dznTk. 48.00
d) carriage charge for steel materials from market to
workshop and carrying the window grill from 1.00 No. @ Tk. 36.75 each = Tk. 36.75
workshop to building site
S Total = Tk. 2,689.58
Contractors profit 10.00% = Tk. 268.96
Overhead expenses 3.50% = Tk. 94.14
Tk. 3,052.67
Add VAT with adjustment factor 1.0582 5.50% = Tk. 177.67
Grand total = Tk. 3,230.34
Rate per sft. = Tk. 143.57
Rate per sqm = Tk. 1,544.82
ii) 1" x 1/4 F.I bars @ 0.850 lbs. per rft. For inner members
horizontal 6 x 5'-0" = 30.00 rft
horizontal short piece 6 x 4 x 1.22' = 29.33 rft
Analysis of PWD SoR 2014 for Civil Works 252
b) workshope charge
labour cost for manufacturing, welding, welding
including supply of necessary electrode, cutting steel to required size etc. complete 22.50 sft @ Tk. 45.71 per sft =Tk. 1,028.48
c) labour charges
labour charges for fitting fixing in position of grill
i) mason 0.50 No. @ Tk. 389.00 each = Tk. 194.50
ii) skilled labour 0.50 No. @ Tk. 303.00 each = Tk. 151.50
iii) cost of screws 3.00 dzn @ Tk. 16.00 per dznTk.
= 48.00
d) carriage charge for steel materials from market to 1.00 No. @ Tk. 36.75 each = Tk. 36.75
workshop and carrying the window grill from S. Total = Tk. 3,939.78
workshop to building site Profit 10.00% = Tk. 393.98
Overhead 3.50% = Tk. 137.89
= Tk. 4,471.65
Add VAT with adjustment factor 1.0582 5.50% = Tk. 260.25
Grand total = Tk. 4,731.90
Rate per sft. = Tk. 210.31
Rate per sqm. = Tk. 2,262.94
ii) 3/4" x 3/16" F.I bars @ 0.478 lbs. per rft. For inner members
horizontal 6 x 5'-0" = 30.00 rft
horizontal short piece 6 x 4 x 1.22' = 29.33 rft
vertical 6 x 4'-6" = 27.00 rft
F.I bars for clamps 4 x 2 x 0'-6" = 4.00 rft
90.33 rft
Add wastage 5% = 4.52 rft
94.85 rft
= 45.39 lbs @ Tk. 25.40 per lb =Tk. 1,152.84
b) workshope charge
labour cost for manufacturing, welding, welding
including supply of necessary electrode, cutting steel to required size etc. complete 22.50 sft @ Tk. 45.71 per sft =Tk. 1,028.48
c) labour charges
labour charges for fitting fixing in position of grill
i) mason 0.50 No. @ Tk. 389.00 each = Tk. 194.50
ii) skilled labour 0.50 No. @ Tk. 303.00 each = Tk. 151.50
iii) cost of screws 3.00 dzn @ Tk. 16.00 per dznTk.
= 48.00
d) carriage charge for steel materials from market to 1.00 No. @ Tk. 36.75 each = Tk. 36.75
S. Total = Tk. 3,043.14
Profit 10.00% = Tk. 304.31
Overhead 3.50% = Tk. 106.51
Tk. 3,453.96
Add VAT with adjustment factor 1.0582 5.50% = Tk. 201.02
Grand total = Tk. 3,654.98
Rate per sft. = Tk. 162.44
Rate per sqm. = Tk. 1,747.85
@ 1.28 per rft.= 41.66 Ibs @ Tk. 25.40 Per Ib. = Tk. 1,058.16
= Tk. 6,610.37
Add VAT with adjustment factor 1.0582 5.50% = Tk. 384.73
Grand total = Tk. 6,995.10
Rate per sft. = Tk. 218.60
Rate per sqm. = Tk. 2,353.01
2) Semi- skilled technician 3/4 No. @ Tk. 450.00 each = Tk. 337.50
3) Tools and plant, sundries etc. L.S. = Tk. 180.00
Sub total (C) = Tk. 1,042.50
Total (A+B+C) = Tk. 13,122.32
Profit 10.00% = Tk. 1,312.23
Overhead 3.50% = Tk. 459.28
= Tk. 14,893.83
Add VAT with adjustment factor 1.0582 4.50% = Tk. 709.23
Grand total = Tk. 15,603.06
Rate Per sft. = Tk. 571.12
Rate per sqm. = Tk. 6,147.54
Say, Tk. 6,148 .00 Per sqm.
Analysis of PWD SoR 2014 for Civil Works 260
of 0.99 mm thick
1 x 7'-0"= 7 rft.
2 x 3'-0"= 6 rft.
= 13 rft. @ Tk. 16.80 Per rft. = Tk. 218.40
= Tk. 22,124.55
Cutting wastage 3% = Tk. 663.74
Sub total (A) = Tk. 22,788.29
(B) Cost of accessories:
(1) Swing door clouser 2 sets @ Tk. 2,627.03 Per set = Tk. 5,254.06
(2) Swing door lock 1 set @ Tk. 572.70 Per set = Tk. 572.70
(3) Swing door mohiar 21 rft. @ Tk. 4.25 Per rft. = Tk. 89.25
(4) Flush bolt 2 sets @ Tk. 307.43 Per set. = Tk. 614.86
(5) Bolts and screws in/c sealants L.S. = Tk. 603.91
Sub total (B) = Tk. 7,134.78
(C) Labour charge for fabrication, assembling and fitting-fixing in position
(1) Skilled technician 3 No. @ Tk. 700.00 each = Tk. 2,100.00
(2) Semi- skilled technician 3 No. @ Tk. 450.00 each = Tk. 1,350.00
(3) Tools and plant, sundries etc. L.S. = Tk. 1,225.00
Sub total (C) = Tk. 4,675.00
Total (A+B+C) = Tk. 34,598.07
Profit 10.00% = Tk. 3,459.81
Overhead 3.50% = Tk. 1,210.93
= Tk. 39,268.81
Add VAT with adjustment factor 1.0582 5.50% = Tk. 2,285.48
Grand total = Tk. 41,554.29
Rate Per sft. = Tk. 277.03
Rate per sqm. = Tk. 2,981.95
of 1.5 mm thick
1 x 6'-9"= 6.75 rft. @ Tk. 63.00 Per rft. = Tk. 425.25
= Tk. 5,520.64
Cutting wastage 3% = Tk. 165.62
Sub total (A) = Tk. 5,686.26
(B) Cost of accessories:
(1) Sliding door key lock 2 sets @ Tk. 172.98 Per set = Tk. 345.96
(2) Sliding door wheel 4 No. @ Tk. 43.26 each = Tk. 173.04
(3) Sliding door mohiar 50 rft. @ Tk. 1.36 Per rft. = Tk. 68.00
(4) Sliding door neoprene 50 rft. @ Tk. 2.73 Per rft. = Tk. 136.50
(5) Bolts and screws in/c sealants L.S. = Tk. 68.25
Sub total (B) = Tk. 791.75
(C) Labour charge for fabrication, assembling and fitting-fixing in position
(1) Skilled technician 2 No. @ Tk. 700.00 each = Tk. 1,400.00
(2) Semi- skilled technician 2 No. @ Tk. 450.00 each = Tk. 900.00
(3) Tools and plant, sundries etc. L.S. = Tk. 367.50
Sub total (C) = Tk. 2,667.50
Total (A+B+C) = Tk. 9,145.51
Profit 10.00% = Tk. 914.55
Overhead 3.50% = Tk. 320.09
= Tk. 10,380.15
Add VAT with adjustment factor 1.0582 5.50% = Tk. 604.14
Grand total = Tk. 10,984.29
Rate Per sft. = Tk. 224.17
Rate per sqm. = Tk. 2,412.97
of 1.5 mm thick
1 x 7'-0"= 7 rft. @ Tk. 75.60 Per rft. = Tk. 529.20
8. 34.40 mm, 32.10 mm interlock
of 1.5 mm thick
2 x 7'-0"= 14 rft. @ Tk. 79.80 Per rft. = Tk. 1,117.20
9. 31.75 mm shutter divider
of 1.5 mm thick
1 x 5'-9"= 5.75 rft. @ Tk. 63.00 Per rft. = Tk. 362.25
10. 7.14 mm spandrel of 1.4 mm to
1.5 mm thick
12 x 2'-6" = 30 rft. @ Tk. 70.35 Per rft. = Tk. 2,110.50
= Tk. 7,089.34
Cutting wastage 3% = Tk. 212.68
Sub total (A) = Tk. 7,302.02
(B) Cost of accessories:
(1) Sliding door key lock 2 sets @ Tk. 172.98 Per set = Tk. 345.96
(2) Sliding door wheel 2 Nos. @ Tk. 43.26 each = Tk. 86.52
(3) Sliding door mohiar 46 rft. @ Tk. 1.36 Per rft. = Tk. 62.56
(4) Sliding door neoprene 52 rft. @ Tk. 2.73 Per rft. = Tk. 141.96
(5) Bolts and screws in/c sealants L.S. = Tk. 54.65
Sub total (B) = Tk. 691.65
(C) Labour charge for fabrication, assembling and fitting-fixing in position
(1) Skilled technician 2 No. @ Tk. 700.00 each = Tk. 1,400.00
(2) Semi- skilled technician 2 No. @ Tk. 450.00 each = Tk. 900.00
(3) Tools and plant, sundries etc. L.S. = Tk. 367.50
Sub total (C) = Tk. 2,667.50
Total (A+B+C) = 10,661.17
Profit 10.00% = Tk. 1,066.12
Overhead 3.50% = Tk. 373.14
= Tk. 12,100.43
Add VAT with adjustment factor 1.0582 5.50% = Tk. 704.26
Grand total = Tk. 12,804.69
Rate Per sft. = Tk. 304.87
Rate per sqm. = Tk. 3,281.62
= Tk. 8,044.33
Add VAT with adjustment factor 1.0582 5.50% = Tk. 468.19
Grand total = Tk. 8,512.52
Rate Per sft. = Tk. 378.33
Rate per sqm. = Tk. 4,072.34
(1) Skilled technician 3/4 No. @ Tk. 700.00 each = Tk. 525.00
(2) Semi- skilled technician 3/4 No. @ Tk. 450.00 each = Tk. 337.50
(3) Tools and plant, sundries etc. L.S. = Tk. 245.00
Sub total (C) = Tk. 1,107.50
Total (A+B+C) = 6,774.33
Profit 10.00% = Tk. 677.43
Overhead 3.50% = Tk. 237.10
= Tk. 7,688.86
Add VAT with adjustment factor 1.0582 5.50% = Tk. 447.50
Grand total = Tk. 8,136.36
Rate Per sft. = Tk. 434.63
Rate per sqm. = Tk. 4,678.36
(1) Sliding window key lock 2 set @ Tk. 172.98 Per set = Tk. 345.96
(2) Sliding window wheel 4 Nos. @ Tk. 43.26 each = Tk. 173.04
(3) Sliding window mohiar 22 rft. @ Tk. 1.36 Per rft. = Tk. 29.92
(4) Sliding window neoprene 22 rft. @ Tk. 2.73 Per rft. = Tk. 60.06
(5) Sealant 100 gm @ Tk. 2.47 Per gm = Tk. 247.00
(6) Bolts and screws L.S. = Tk. 122.50
Sub total (B) = Tk. 978.48
(C) Labour charge for fabrication, assembling and fitting-fixing in position
(1) Skilled technician 3/4 No. @ Tk. 700.00 each = Tk. 525.00
(2) Semi- skilled technician 3/4 No. @ Tk. 450.00 each = Tk. 337.50
(3) Tools and plant, sundries etc. L.S. = Tk. 245.00
Sub total (C) = Tk. 1,107.50
Total (A+B+C) = 6,528.58
Profit 10.00% = Tk. 652.86
Overhead 3.50% = Tk. 228.50
= Tk. 7,409.94
Add VAT with adjustment factor 1.0582 5.50% = Tk. 431.27
Grand total = Tk. 7,841.21
Rate Per sft. = Tk. 418.87
Rate per sqm. = Tk. 4,508.72
of 1.5 mm thick
1 x 4'-6"= 4.5 rft. @ Tk. 49.35 Per rft. = Tk. 222.08
7. 49.20 mm, 26.20 mm shutter lock
of 1.5 mm thick
1 x 4'-6"= 4.5 rft. @ Tk. 77.70 Per rft. = Tk. 349.65
8. 34.40 mm, 32.10 mm inter lock
of 1.5 mm thick (0.665 kg/m)
2 x 4'-6"= 9 rft. @ Tk. 81.90 Per rft. = Tk. 737.10
9. 37.78 mm, 31.78 mm bottom cover
of 1.5 mm thick
1 x 5'-0"= 5 rft. @ Tk. 34.65 Per rft. = Tk. 173.25
10. 76.20 mm, 38.10 mm grouve cover
of 1.5 mm thick
1 x 5'-0"= 5 rft. @ Tk. 86.10 Per rft. = Tk. 430.50
11. 57.15 mm, 15.80 mm grouve cover
of 1.5 mm thick
1 x 5'-0"= 5 rft. @ Tk. 50.40 Per rft. = Tk. 252.00
12. 76.20 mm, 38.10 mm, 57.15 mm top &
side of 1.5 mm thick
1 x 5'-0"= 5 rft.
3 x 2'-6"= 7.5 rft.
= 12.5 rft. @ Tk. 103.95 Per rft. = Tk. 1,299.38
= Tk. 5,601.76
Cutting wastage 3% = Tk. 168.05
Total (A) = Tk. 5,769.81
(B) Cost of accessories:
(1) Sliding door key lock 1 set @ Tk. 67.28 Per set. = Tk. 67.28
(2) Sliding door wheel 2 Nos. @ Tk. 43.26 each = Tk. 86.52
(3) Sliding door mohiar 33 rft. @ Tk. 1.36 Per rft. = Tk. 44.88
(4) Sliding neoprene 28 rft. @ Tk. 2.73 Per rft. = Tk. 76.44
(5) Bolts and screws in/c sealants L.S. = Tk. 171.87
Total (B) = Tk. 446.99
(C) Labour charge for fabrication, assembling and fitting-fixing in position
(1) Skilled technician 1.25 No. @ Tk. 700.00 each = Tk. 875.00
(2) Semi- skilled technician 1.25 No. @ Tk. 450.00 each = Tk. 562.50
(3) Tools and plant, sundries etc. L.S. = Tk. 245.00
Sub total (C) = Tk. 1,682.50
Total (A+B+C) = 7,899.30
Profit 10.00% = Tk. 789.93
Overhead 3.50% = Tk. 276.48
= Tk. 8,965.71
Add VAT with adjustment factor 1.0582 5.50% = Tk. 521.81
Grand total = Tk. 9,487.52
Rate Per sft. = Tk. 271.07
Rate per sqm. = Tk. 2,917.80
Say, Tk. 2,918 .00 Per sqm.
Item No.- 14.8.2
Supplying, fitting and fixing aluminium sliding and fixed composite window frame
and shutter (bronze colour)
Considering 1 No. window
Considering 5'-0" x 7'-0" = 35 sft. of work
(A) Cost of aluminium sections:
1. 75.50mm, 32 mm outer bottom (high)
of 1.5 mm thick
1 x 5'-0"= 5 rft. @ Tk. 78.75 Per rft. = Tk. 393.75
2. 75.5 mm, 26.80 mm outer top
of 1.5 mm thick
Analysis of PWD SoR 2014 for Civil Works 293
(1) Skilled technician 1.25 No. @ Tk. 700.00 each = Tk. 875.00
(2) Semi- skilled technician 1.25 No. @ Tk. 450.00 each = Tk. 562.50
(3) Tools and plant, sundries etc. L.S. = Tk. 245.00
Sub total (C) = Tk. 1,682.50
Total (A+B+C) = 7,501.25
Profit 10.00% = Tk. 750.13
Overhead 3.50% = Tk. 262.54
= Tk. 8,513.92
Add VAT with adjustment factor 1.0582 5.50% = Tk. 495.52
Grand total = Tk. 9,009.44
Rate Per sft. = Tk. 257.41
Rate per sqm. = Tk. 2,770.76
(1) Skilled technician 2.75 No. @ Tk. 700.00 each = Tk. 1,925.00
(2) Semi- skilled technician 2.75 No. @ Tk. 450.00 each = Tk. 1,237.50
(3) Tools and plant, sundries etc. L.S. = Tk. 490.00
Sub total (C) = Tk. 3,652.50
Total (A+B+C) = 25,590.19
Profit 10.00% = Tk. 2,559.02
Overhead 3.50% = Tk. 895.66
= Tk. 29,044.87
Add VAT with adjustment factor 1.0582 5.50% = Tk. 1,690.44
Grand total = Tk. 30,735.31
Rate Per sft. = Tk. 439.08
Rate per sqm. = Tk. 4,726.26
(1) Skilled technician 1.00 No. @ Tk. 700.00 each = Tk. 700.00
(2) Semi- skilled technician 1.00 No. @ Tk. 450.00 each = Tk. 450.00
(3) Tools and plant, sundries etc. L.S. = Tk. 490.00
Sub total (C) = Tk. 1,640.00
Total (A+B+C) = 11,372.47
Profit 10.00% = Tk. 1,137.25
Overhead 3.50% = Tk. 398.04
= Tk. 12,907.76
Add VAT with adjustment factor 1.0582 5.50% = Tk. 751.24
Grand total = Tk. 13,659.00
Rate Per sft. = Tk. 546.36
Rate per sqm. = Tk. 5,881.02
Supplying, fitting and fixing of aluminium curtain wall and aluminium top hung/casement windows ad per the US Architectural aluminium Manufacturer's Association (AA
Considering : 1X 9'-0"X9'-7" = 86.22 sft
A. Cost of Materials
1) Curtain wall sub mullium (100mm X 50 mm X 2.00 mm)
4 X 9'-0' = 36.00 rft
4 X 9'-7' = 38.32 "
74.32 sft.
Add 3% wastage= 2.2296 sft.
76.55 sft. @ Tk. 324.45 Per rft. = Tk. 24,836.65
2) Casement outer frame (29mm X 20 mm X 1.20 mm)
2X 2 X 3'-2' = 12.68 rft
2X 2 X 3'-0' = 12.00 "
= 24.68 sft.
Add 3% wastage= 0.7404 sft.
25.42 sft. @ Tk. 33.60 Per rft. = Tk. 854.11
3) Casement outer section (52mm X 22 mm X 40mm X 1.5 mm)
2X 2 X 3'-2' = 12.68 rft
2X 2 X 3'-0' = 12.00 "
= 24.68 sft.
Add 3% wastage= 0.7404 sft.
25.42 sft. @ Tk. 155.40 Per rft. = Tk. 3,950.27
4) Aluminium angle (50mm X 50 mm X 6mm)
16 X 2' = 2.67 sft.
Add 3% wastage= 0.0801 sft.
2.75 sft. @ Tk. 180.60 Per rft. = Tk. 496.65
5) Aluminium cover (50mm X 6 mm X 1.5mm)
24 X 3' = 6.00 sft.
Add 3% wastage= 0.18 sft.
6.18 sft. @ Tk. 64.54 Per rft. = Tk. 398.86
6) 50mm X 6 mm X 1.5mm angle for casement shutter
12 X 2' = 2.00 sft.
Add 3% wastage= 0.06 sft.
2.06 sft. @ Tk. 55.26 Per rft. = Tk. 113.84
Sub Total (A) = Tk. 30,650.38
B Hard ware accessories:
1. Steel rowel bolt 32 Pcs @ Tk. 35.34 Each = Tk. 1,130.88
2. 2" SS Screw 65 Pcs @ Tk. 1.91 Each = Tk. 124.15
3. Rivets (Big) 230 Pcs @ Tk. 1.86 Each = Tk. 427.80
4. Rivets (Normal) 40 Pcs @ Tk. 4.62 Each = Tk. 184.80
5. Norton Tap 72 Pcs @ Tk. 25.71 Each = Tk. 1,851.12
6. Masking tape 1 Pcs @ Tk. 23.78 Each = Tk. 23.78
7. Structural sealant 6 Pcs @ Tk. 9.00 Each = Tk. 54.00
8. Casement 4-bar huge 4 Pcs @ Tk. 501.51 Each = Tk. 2,006.04
9. Casement handle 2 Pcs @ Tk. 206.45 Each = Tk. 412.90
10. Sealant Gum 2 Pcs @ Tk. 340.79 Each = Tk. 681.58
11. Arm lock 4 Pcs @ Tk. 375.04 Each = Tk. 1,500.16
12. M.S. angle 16 Pcs @ Tk. 90.22 Each = Tk. 1,443.52
Sub Total (b) = Tk. 9,840.73
C a) Labour Charge:
i) Skilled Technician 10 No. @ Tk. 700.00 Each = Tk. 7,000.00
ii) Semi-Skilled Technician 10 No. @ Tk. 450.00 Each = Tk. 4,500.00
iii) Machineries L.S. = Tk. 600.00
b) Labour cost for civil work
i) Mason 3 No. @ Tk. 389.00 Each = Tk. 1,167.00
ii) Ordinary Labour 3 No. @ Tk. 245.00 Each = Tk. 735.00
D Cost of high scaffolding L.S. = Tk. 300.00
E Carriage and Sundries L.S. = Tk. 700.00
Analysis of PWD SoR 2014 for Civil Works 311
= Tk. 1,495.02
Add VAT with adjustment factor 1.0582 5.50% = Tk. 87.01
Grand total = Tk. 1,582.03
Average of A & B = Tk. 1,771.18
(i) Ground floor Rate per sft = Tk. 17.71
Rate per sqm. = Tk. 190.63
(i) For ground floor Say, Tk. 117 .00 Per sqm.
(i) For ground floor Say, Tk. 359 .00 Per sqm.
(a) Cement 0.25 bag. @ Tk. 440.00 Per bag = Tk. 110.00
(b) Sand 1.5 cft. @ Tk. 1,700.00 Per % cft. = Tk. 25.50
(c) Plaster (1:4) 18 sft. @ Tk. 15.27 Per sft. = Tk. 274.86
(d) Mason 0.75 Nos. @ Tk. 389.00 each = Tk. 291.75
(e) Labour 0.50 Nos. @ Tk. 245.00 each = Tk. 122.50
Total = Tk. 824.61
Profit 10.00% = Tk. 82.46
Overhead 3.50% = Tk. 28.86
= Tk. 935.93
Add VAT with adjustment factor 1.0582 5.50% = Tk. 54.47
Grand total = Tk. 990.40
Rate per sft. = Tk. 165.07
Rate per sqm. = Tk. 1,776.81
(a) 0'-3" x 0'-3" Brick work (1:6) 6.25 cft. @ Tk. 132.89 Per cft. = Tk. 830.56
(b) Extra labour for brick moulding
& plastering 100 rft. @ Tk. 24.50 Per rft. = Tk. 2,450.00
(c) (3" + 3" + 3")= 9" width
and 1/2" thick cement plaster (1:6)
from item No. 123(a) - I 75 sft @ Tk. 15.27 Per sft. = Tk. 1,145.25
Total = Tk. 4,425.81
Profit 10.00% = Tk. 442.58
Overhead 3.50% = Tk. 154.90
= Tk. 5,023.29
Add VAT with adjustment factor 1.0582 5.50% = Tk. 292.36
Grand total = Tk. 5,315.65
Rate per rft. = Tk. 53.16
Rate per rm. = Tk. 174.42
= Tk. 1,604.89
Add VAT with adjustment factor 1.0582 5.50% = Tk. 93.41
Grand total = Tk. 1,698.30
Rate per sft. = Tk. 16.98
Rate per sqm. = Tk. 182.77
Renewing plaster in/c damp proof treatment with chemical Desalt S-01 & Foam Lub
Assuming cost for removing plaster and replasteing damp proping Treatment with chemical.
Considering 100 sft. of work
a) I) Striping of old plaster (R.S.1) 9.29 sqm @ Tk. 8.00 Per sqm = Tk. 74.32
II) Re plastering with (1:6) 100 sft @ Tk. 993.00 Per % sft = Tk. 993.00
b) I) De-salt S-01 on brick surface (400 sft covered with 1 liter
0.25
so 100.00
litersft of @
work requireed
Tk. 1/4
350.00
liter) Per liter = Tk. 87.50
ii) Foam lub or equivalent grounting in brick surface 3 coats
0.66150.00lbsft covered
@ withTk.
1 liter, 100.00
233.00sft of work required
Per lb0.66
= lb Tk. 153.78
iii) Foam lub with cement morter for plasteng (250 ml with
187.5
per bag of
mlcement@, so 100
Tk.
sft of work
233.00
required 187.50
Per
ml)liter = Tk. 43.69
iv) De-salt S-01 in plaster surface 400.00 sft covered with0.25
1 liter, so lb
100.00 sft
@ of work
Tk.equired
350.00
1/4 liter Per lb = Tk. 87.50
v) Labour fro De-salting. Foam lub groutng etc. 0.25 lb @ Tk. 245.00 Per lb = Tk. 61.25
Total = Tk. 1,501.04
Profit 10.00% = Tk. 150.10
Overhead 3.50% = Tk. 52.54
= Tk. 1,703.68
Add VAT with adjustment factor 1.0582 5.50% = Tk. 99.16
Grand total = Tk. 1,802.84
Rate per sft. = Tk. 18.03
Rate per sqm. = Tk. 194.07
= Tk. 3,361.91
Add VAT with adjustment factor 1.0582 5.50% = Tk. 195.67
Grand total = Tk. 3,557.58
Rate per rft.. = Tk. 355.76
Rate per rm = Tk. 1,167.25
(b) Sand filling 20 cft. @ Tk. 900.00 Per % sft. = Tk. 180.00
(c) Cement concrete(1:3:6) at 3 nos. joint 3.93 cft. @ Tk. 14,713.64 Per % cft. = Tk. 578.25
(d) Labour charge for laying pipe maintaining proper
slope in/c cost of gasket etc.
(i) Head mason 0.25 No. @ Tk. 493.00 each = Tk. 123.25
(ii) Mason 0.25 No. @ Tk. 389.00 each = Tk. 97.25
(iii) Skilled labour 1 No. @ Tk. 303.00 each = Tk. 303.00
Total = Tk. 4,161.75
Profit 10.00% = Tk. 416.18
Overhead 3.50% = Tk. 145.66
= Tk. 4,723.59
Add VAT with adjustment factor 1.0582 5.50% = Tk. 274.92
Grand total = Tk. 4,998.51
Rate per rft. = Tk. 277.70
Rate per rm. = Tk. 911.13
(b) Sand filling 25 cft. @ Tk. 900.00 Per % sft. = Tk. 225.00
(c) Cement concrete(1:3:6) at 2 nos. junctions 4.82 cft. @ Tk. 14,713.64 Per % cft. = Tk. 709.20
(d) Labour charge for laying pipe maintaining proper
slope in/c cost of gasket etc.
(i) Head mason 0.25 No. @ Tk. 493.00 each = Tk. 123.25
(ii) Mason 0.25 No. @ Tk. 389.00 each = Tk. 97.25
(iii) Skilled labour 1.5 Nos. @ Tk. 303.00 each = Tk. 454.50
Total = Tk. 5,425.20
Profit 10.00% = Tk. 542.52
Overhead 3.50% = Tk. 189.88
= Tk. 6,157.60
Add VAT with adjustment factor 1.0582 5.50% = Tk. 358.38
Grand total = Tk. 6,515.98
Rate per rft. = Tk. 362.00
Rate per rm. = Tk. 1,187.72
1 x 8'-0" x 1'-6"= 12.00 sft. @ Tk. 1,906.00 Per % sft. = Tk. 228.72
(g) Labour for fitting-fixing the gate:
(i) Mason 0.5 No. @ Tk. 389.00 each = Tk. 194.50
(ii) Skilled labour 0.5 No. @ Tk. 303.00 each = Tk. 151.50
Total = Tk. 17,479.18
Profit 10.00% = Tk. 1,747.92
Overhead 3.50% = Tk. 611.77
= Tk. 19,838.87
Add VAT with adjustment factor 1.0582 5.50% = Tk. 1,154.64
Grand total = Tk. 20,993.51
Rate per sft. = Tk. 328.02
Rate per sqm. = Tk. 3,530.81
(v) Handle with 5/8" dia M.S rod 4 Nos @ Tk. 54.96 each = Tk. 219.84
(vi) Electrodes 70 pcs. @ Tk. 10.00 Per pc. = Tk. 700.00
(vii) Greese 0.5 Ibs. @ Tk. 56.00 Per Ib. = Tk. 28.00
(c) Making gate in work-shop
(i) Welder/ fabricator 5 Nos. @ Tk. 423.00 each = Tk. 2,115.00
(ii) Helper to welder 5 Nos. @ Tk. 304.00 each = Tk. 1,520.00
(iii) Ordinary labour 5 Nos. @ Tk. 245.00 each = Tk. 1,225.00
(d) Carrying cost: materials & finished gate. L.S. = Tk. 367.50
Sub-total = Tk. 20,623.74
(e) Workshop charge 10% = Tk. 2,062.37
Total = Tk. 22,686.11
(f) Anciliary work for fitting-fixing the gate:
(i) Making holes 14.00 Nos. @ Tk. 15.20 each = Tk. 212.80
(ii) Making groove (channel) on floor:
1 x 8'-0"= 8.00 rft. @ Tk. 15.20 Per rft. = Tk. 121.60
(iii) Cost of CC (1:2:4):
14 x 6" x 4" x 4"= 1.00 cft (say) @ Tk. 17,637.01 Per % cft. = Tk. 176.37
(iv) 1/2" thick plaster (1:4)
3 x 8'-0" x 1'-0"= 24.00 sft. @ Tk. 1,527.00 Per % sft. = Tk. 366.48
(v) Repairing floor and plaster with neat cement finish:
1 x 8'-0" x 1'-6"= 12.00 sft. @ Tk. 1,906.00 Per % sft. = Tk. 228.72
(g) Labour for fitting-fixing the gate:
(i) Mason 0.5 No. @ Tk. 389.00 each = Tk. 194.50
(ii) Skilled labour 0.5 No. @ Tk. 303.00 each = Tk. 151.50
Total = Tk. 24,138.08
Profit 10.00% = Tk. 2,413.81
Overhead 3.50% = Tk. 844.83
= Tk. 27,396.72
Add VAT with adjustment factor 1.0582 5.50% = Tk. 1,594.52
Grand total = Tk. 28,991.24
Rate per sft. = Tk. 452.99
Rate per sqm. = Tk. 4,875.98
= 39.19 rft.
= 50.16 Ibs. @ Tk. 25.40 Per Ib. = Tk. 1,274.06
(iii) 2" x 1/4" F.I. bar for rails: @ 1.7 Ibs per rft.
2 x 3.142 x 10'-0"/4= 15.71 rft.
Add wastage 5%= 0.79 rft.
16.50 rft.
= 28.05 Ibs. @ Tk. 25.40 Per Ib = Tk. 712.47
(iv) 5/8" M.S. rod: @ 1.043 Ibs per rft.:
2 x 21 x 0'-8"= 28.14 rft.
2 x 19 x 3'-6"= 133.00 rft.
2 x 38 x 0'-3"= 19.00 rft.
180.14 rft.
Add wastage 5%= 9.01 rft.
= 189.15 rft.
= 197.28 Ibs. @ Tk. 25.40 Per Ib. = Tk. 5,010.91
(v) 1/8" thick M.S. plate: @ 5.10 lbs per sft.
2 x 2 x 1'-0" x 1'-0"= 4.00 sft.
2 x 1'-0" x 6" = 1 sft.
5.00 sft.
Add wastage 5%= 0.25 sft.
= 5.25 sft.
= 26.78 Ibs. @ Tk. 38.55 Per Ib. = Tk. 1,032.37
(vi) 1/4" thick M.S. plate: @ 10.2 Ibs per sft.
2 x 0-6" x 0'-6"= 0.50 sft.
Add wastage 5%= 0.03 sft.
= 0.53 sft.
= 5.41 Ibs. @ Tk. 38.55 Per Ib. = Tk. 208.56
(vii) 18 BWG M.S. plate: 2.04 Ibs per sft.
2 x 5'-0" x 2'-6"= 25.00 sft.
Add wastage 5%= 1.25 sft.
= 26.25 sft.
= 53.55 Ibs. @ Tk. 38.55 Per Ib. = Tk. 2,064.35
(b) Fittings and consumables
(i) Hinges for pocket gate: 2 Nos. @ Tk. 38.00 each = Tk. 76.00
(ii) 1.5" dia heavy duty wheel 2 Nos. @ Tk. 145.00 each = Tk. 290.00
(iii) Locking arrangement 3 Nos. @ Tk. 229.00 each = Tk. 687.00
(iv) Clamp with huskel dumney 6 Nos. @ Tk. 120.00 each = Tk. 720.00
(v) Clamp for rails 16 Nos. @ Tk. 28.00 each = Tk. 448.00
(vi) Electrodes 200 Pc. @ Tk. 10.00 each = Tk. 2,000.00
(c) Making steel gate in work-shop
(i) Welder / fabricator 6 Nos. @ Tk. 423.00 each = Tk. 2,538.00
(ii) Helper 5 Nos. @ Tk. 304.00 each = Tk. 1,520.00
(iii) Ordinary labour 5 Nos. @ Tk. 245.00 each = Tk. 1,225.00
(d) Carrying materials to work-shop & gate to site L.S. = Tk. 367.50
Sub-total = Tk. 24,944.41
(e) Work-shop charges 10% = Tk. 2,494.44
Total = Tk. 27,438.85
(f) Ancillary work for fitting -fixing the gate:
(i) Making holes 6 Nos. @ Tk. 12.67 each = Tk. 76.02
(ii) Plain concrete: (1:2:4)
6 x 10" x 6" x 6"= 1.25 cft.
16'-0" x 6" x 4"= 2.67 cft.
2 x 4 x 6" x 4"= 1.33 cft.
5.25 cft. @ Tk. 17,637.01 Per % cft. = Tk. 925.94
(g) Labour charge for hoisting the gate in position
(i) Mason 1 No. @ Tk. 389.00 each = Tk. 389.00
(ii) Mason helper 2 No. @ Tk. 304.00 each = Tk. 608.00
Analysis of PWD SoR 2014 for Civil Works 339
Manufacturing, supplying, fitting and fixing of G.I. pipe gate excluding cost of painting.
Considering 1 No. of gate
Considering 10'-0" x 6'-8"= 66.67 sft. in two parts
(a) Cost of materials
(i) 1.5" dia G.I. pipe
2 x 4 x 5'-0"= 40.00 rft.
4 x 6'-8"= 26.67 rft.
= 66.67 rft.
Add wastage 5%= 3.33 rft.
= 70.00 rft. @ Tk. 169.31 Per rft. = Tk. 11,851.70
(ii) 3/4" dia G.I. pipe
Vertical post: 2 x 19 x 6'-8"= 253.33 rft.
Pocket gate: 2 x 2'-0"= 4.00 rft.
2 x 4'-5"= 8.83 rft.
1 x 2'-2"= 2.17 rft.
= 268.33 rft.
Add 5% wastage= 13.42 rft.
281.75 rft. @ Tk. 74.07 Per rft. = Tk. 20,869.22
(iii) 18 BWG M.S. plate for middle part: @ 2.04 lbs per sft.
2 x 5'-0" x 3'-4"= 33.33 sft.
Add wastage 5%= 1.67 sft.
= 35.00 sft.
= 71.40 Ibs. @ Tk. 38.55 Per Ib. = Tk. 2,752.47
(b) Fittings and consumables
(i) Locking arrangement 2 Nos. @ Tk. 229.00 each = Tk. 458.00
(ii) 5" long hinges 2 Nos. @ Tk. 38.00 each = Tk. 76.00
(iii) Clamp with huskel dumney 6 Nos. @ Tk. 120.00 each = Tk. 720.00
(iv) 5/8" dia M.S. socket bolt 2 Nos. @ Tk. 164.00 each = Tk. 328.00
(v) Electrodes 120 Pc. @ Tk. 10.00 each = Tk. 1,200.00
(c) Making steel gate in work-shop
(i) Welder / fabricator 4 Nos. @ Tk. 423.00 each = Tk. 1,692.00
(ii) Helper 4 Nos. @ Tk. 304.00 each = Tk. 1,216.00
(iii) Ordinary labour 4 Nos. @ Tk. 245.00 each = Tk. 980.00
(d) Carrying materials to work-shop & gate to site L.S. = Tk. 367.50
Sub-total = Tk. 42,510.89
(e) Work-shop charges 10% = Tk. 4,251.09
Total = Tk. 46,761.98
(f) Ancillary work for fitting-fixing the gate:
(i) Making holes 6 Nos. @ Tk. 12.67 each = Tk. 76.02
(ii) Plain concrete: (1:2:4)
6 x 10" x 6" x 6"= 1.25 cft. @ Tk. 17,637.01 Per % cft. = Tk. 220.46
(g) Labour charge for hoisting the gate in position
(i) Mason 1 No. @ Tk. 389.00 each = Tk. 389.00
(ii) Mason helper 1 No. @ Tk. 304.00 each = Tk. 304.00
(iii) Ordinary labour 1 No. @ Tk. 245.00 each = Tk. 245.00
Total = Tk. 47,996.46
Profit 10.00% = Tk. 4,799.65
Overhead 3.50% = Tk. 1,679.88
= Tk. 54,475.99
Add VAT with adjustment factor 1.0582 5.50% = Tk. 3,170.56
Grand total = Tk. 57,646.55
Rate per sft. = Tk. 864.66
Rate per sqm. = Tk. 9,307.20
Manufacturing, supplying, fitting and fixing of rolling shutter made of 24 SWG G.P. sheet
excluding cost of painting.
Considering 1 No. rolling shutter
Considering 10'-0" x 6'-0"= 60 sft. of work
(a) Materials:
(i) 24 SWG G.P. sheet with 1/2" dia folding at the other end (@ 1 Ibs per rft.)
44 (2.75"+3.14 x 0.5"+3.14 x 0.375) x 10'-0"
= 121.00 sft.
Side patty: 2 x 10'-0" x 0'-3"= 5.00 sft.
126.00 sft.
Add 5% wastage= 6.05 sft.
132.05 sft.
= 132.05 lbs @ Tk. 41.04 Per Ib. = Tk. 5,419.33
(ii) 26 SWG cover sheet: @ 0.85 Ibs per sft.
6'-0" x 4'-0"= 24.0 sft.
Add 5% wastage= 1.2 sft.
25.2 sft.
= 21.42 Ibs. @ Tk. 38.55 Per Ib. = Tk. 825.74
(iii) 1.5" dia G.I. pipe 6.33 rft. @ Tk. 169.31 Per rft. = Tk. 1,071.73
(iv) 1" x 1" x 1/8" M.S. angle: @ 0.8 per rft.:
1 x 6'-0"= 6 rft.
= 4.8 lbs @ Tk. 28.34 Per Ib. = Tk. 136.03
(v) 1/4" thick M.S. plate: @ 10.21 lbs per sft.
Side guide: 2 x 2 x 4" x 10'-6"= 14.0 sft.
Mid guide: 2 x 6" x 10'-6"= 10.5 sft.
4 x 0'-2" x 0'-3"= 0.17 sft.
= 24.67 sft.
Add wastage 5%= 1.23 sft.
25.90 sft.
= 264.44 Ibs. @ Tk. 28.34 Per Ib = Tk. 7,494.23
(vi) 1" x 1/8" F.I. bar: @ 0.425 Ibs per rft.
Side guide channel: 2 x 2 x 10'-0"= 40 rft.
Mid guide channel: 2 x 10'-0"= 20 rft.
Guide channel to punkha:
2 x 2'-3"= 4.5 rft.
Guide channel to handle:
2 x 0'-9"= 1.5 rft.
= 66.0 rft.
Add 5% wastage= 3.3 rft.
69.3 rft.
= 29.4525 Ibs. @ Tk. 25.40 Per lb = Tk. 748.09
(vii) 1/8" thick M.S. plate for punkha & folded plate: @ 5.10 lbs per sft.
2 x 1'-3" x 1'-0"= 2.50 sft.
1 x 6'-0" x 0'-3"= 1.50 sft.
= 4.00 sft.
Add 5% wastage= 0.20 sft.
4.20 sft.
= 12.75 Ibs. @ Tk. 38.55 Per Ib. = Tk. 491.51
(b) Fittings, hardwares and consumables
(i) Best quality china made spring:
3 x 11'-0"= 33 rft. @ Tk. 24.00 Per rft. = Tk. 792.00
(ii) Spring box 3 Nos. @ Tk. 103.00 each = Tk. 309.00
(iii) Nut bolt, 1/2" dia maximum 2.5" long 18 Nos. @ Tk. 9.00 each = Tk. 162.00
(iv) Rivet:
Side patty= 176 Nos.
For fixing top tail= 9 Nos.
Analysis of PWD SoR 2014 for Civil Works 345
= 162.04 rft.
@ 1.489 rft/lbs
= 241.278 Ibs. @ Tk. 28.34 Per Ib. = Tk. 6,837.82
(iii) 12mm x 12mm M.S. Solid square bar
2 X 22 x 1'-10.5"= 82.5 rft.
2 X 22 x 1'-11"= 84.33 rft.
166.83 rft.
Add wastage 5%= 8.3415 rft.
= 175.1715 rft.
@ 0.851 rft/lbs
= 149.071 Ibs. @ Tk. 28.57 Per Ib. = Tk. 4,258.96
(b) Fittings and consumables:
i) Hinges 3" long 12.00 Nos @ Tk. 5.00 Each = Tk. 60.00
ii) Locking arrangement 2.00 Nos. @ Tk. 229.00 Each = Tk. 458.00
iii) Clamp (6" long) 6 Nos. @ Tk. 25.00 Each = Tk. 150.00
iv) Electrodes 200 Pc @ Tk. 10.00 Per pc = Tk. 2,000.00
(c) Making steel gate in work-shop
(i) Welder/ fabricator 6 Nos. @ Tk. 423.00 each = Tk. 2,538.00
(ii) Helper 5 Nos. @ Tk. 304.00 each = Tk. 1,520.00
(iii) Ordinary labour 5 Nos. @ Tk. 245.00 each = Tk. 1,225.00
(d) Carrying cost: materials & finished gate. L.S. = Tk. 50.00
Sub-total = Tk. 21,255.59
(e) Workshop charge 10% = Tk. 2,125.56
Total = Tk. 23,381.15
(f) Ancillary work for fitting-fixing the gate:
i) Making holes L.S. = Tk. 196.00
ii) Cost of CC (1:2:4):
6 x 10" x 6" x 6"= 1.25 cft @ Tk. 176.37 Per cft. = Tk. 220.46
(g) Labour for fitting-fixing the gate:
i) Mason 1 No. @ Tk. 389.00 each = Tk. 389.00
ii) Skilled labour 2 Nos. @ Tk. 303.00 each = Tk. 606.00
iii) Ordinary labour 1 No. @ Tk. 245.00 each = Tk. 245.00
Total = Tk. 25,037.61
Profit 10.00% = Tk. 2,503.76
Overhead 3.50% = Tk. 876.32
= Tk. 28,417.69
Add VAT with adjustment factor 1.0582 4.50% = Tk. 1,353.22
Grand total = Tk. 29,770.91
Rate per sft. = Tk. 451.96
Rate per sqm. = Tk. 4,864.90
Manufacturing, supplying, fitting and fixing G.I. pipe stair railing with the provision of 6" x 2.5"
hand rails (excluding cost of wood for hand rail) excluding cost of painting.
Considering 1 No. of railing
Considering 9'-9" x 2'-10"= 27.6 sft. of work
(a) Materials:
(i) 1/2" dia G.I. pipe:
10 x 3'-1"= 30.8 rft.
Add wastage 5%= 1.54 rft.
= 32.34 rft. @ Tk. 50.00 Per rft. = Tk. 1,617.00
(ii) 2" x 2" x 1/4" thick M.S. plate: @ 10.21 lbs per rft.
10 x 2" x 2"= 0.28 sft.
Add wastage 5%= 0.01 sft.
= 0.29 sft.
= 2.96 Ibs. @ Tk. 38.55 Per lb. = Tk. 114.11
(iii) 1.5" x 1/4" M.S. F.I. bar: @ 1.28 Ibs. per rft.
1 x 9'-9"= 9.75 rft.
Add wastage 5%= 0.49 rft.
= 10.24 rft.
= 13.11 lbs. @ Tk. 25.40 Per Ib. = Tk. 332.99
(b) Fittings, hardwares and consumables:
(i) Electrodes: 10.00 Nos. @ Tk. 10.00 each = Tk. 100.00
(c) Labour for fabrication and making post and railing support etc.
(i) Welder / fabricator 0.50 Nos. @ Tk. 423.00 each = Tk. 211.50
(ii) Welder helper 0.75 Nos. @ Tk. 304.00 each = Tk. 228.00
(iii) Ordinary labour 1.00 Nos. @ Tk. 245.00 each = Tk. 245.00
(d) Carrying of materials to work-shop and fabricated materials to site: = Tk. 100.00
Sub-total = Tk. 2,948.60
(e) Work-shop charges: 10% = Tk. 294.86
Total = Tk. 3,243.46
(f) Ancillary works for fitting -fixing the railing:
(i) Labour charge for cutting: 2" x 2" x 6" size grooves
20 Nos @ Tk. 10.13 each = Tk. 202.60
(ii) CC (1:2:4): 20 x 2" x 2" x 6"= 0.28 cft. @ Tk. 17,637.01 Per % cft. = Tk. 49.38
(g) Labour charge for fitting fixing the stair railing at site
(i) Mason 0.25 No. @ Tk. 389.00 each = Tk. 97.25
(ii) Mason helper 0.50 No. @ Tk. 304.00 each = Tk. 152.00
(iii) Ordinary labour 0.50 No. @ Tk. 245.00 each = Tk. 122.50
(iv) Welder/fabricator 0.25 No. @ Tk. 423.00 each = Tk. 105.75
(v) Welder helper 0.50 No. @ Tk. 304.00 each = Tk. 152.00
Grand total = Tk. 4,124.94
Profit 10.00% = Tk. 412.49
Overhead 3.50% = Tk. 144.37
= Tk. 4,681.80
Add VAT with adjustment factor 1.0582 5.50% = Tk. 272.49
Grand total = Tk. 4,954.29
Rate per sft. = Tk. 179.50
Rate per sqm. = Tk. 1,932.14
(a) Materials:
(i) 1.5" x 1.5" x 1/4" M.S. angle: @ 2.34 Ibs. per rft.
2 x 3'-3"= 6.50 rft.
Horizontal: 2 x 7'-9"= 15.50 rft.
= 22 rft.
Add wastage 5%= 1.1 rft.
23.1 rft.
= 54.05 Ibs. @ Tk. 28.34 Per lb. = Tk. 1,531.78
(ii) 1/4" dia M.S. rod: @ 0.167 lbs. per rft.
20 x 3'-3"= 65.00 rft.
8 x 7'-9"= 62.00 rft.
Analysis of PWD SoR 2014 for Civil Works 359
127.00 rft.
Add wastage 5%= 6.35 rft.
= 133.35 rft.
= 22.27 lbs. @ Tk. 26.76 Per Ib. = Tk. 595.95
(b) Fittings, hardwares and consumables:
(i) Electrodes in/c electricity 35.00 Nos. @ Tk. 10.00 each = Tk. 350.00
(c) Labour for making grill fencing
(i) Welder / fabricator 1.00 No. @ Tk. 423.00 each = Tk. 423.00
(ii) Welder helper 1.00 No. @ Tk. 304.00 each = Tk. 304.00
(iii) Ordinary labour 1.00 No. @ Tk. 245.00 each = Tk. 245.00
(d) Carrying of materials to work-shop and fabricated materials to site: = Tk. 183.75
Sub-total = Tk. 3,633.48
(e) Work-shop charges: 10% = Tk. 363.35
Total = Tk. 3,996.83
(f) Labour charge for fitting-fixing the grill fencing:
(i) Welder / fabricator 0.50 No. @ Tk. 423.00 each = Tk. 211.50
(ii) Welder helper 0.50 No. @ Tk. 304.00 each = Tk. 152.00
Grand total = Tk. 4,360.33
Profit 10.00% = Tk. 436.03
Overhead 3.50% = Tk. 152.61
= Tk. 4,948.97
Add VAT with adjustment factor 1.0582 5.50% = Tk. 288.04
Grand total = Tk. 5,237.01
Rate per sft. = Tk. 207.90
Rate per sqm. = Tk. 2,237.84
(a) Materials:
(i) 1.5" x 1.5" x 1/4" M.S. angle for box post: @ 2.34 Ibs. per rft.
2 x 6'-3"= 12.5 rft.
Add wastage 5%= 0.63 rft.
= 13.13 rft.
= 30.72 Ibs. @ Tk. 28.34 Per lb. = Tk. 870.60
(ii) 1.5" x 1/4" M.S. plate: @ 10.20 lbs. per sft.
2 x 1.5" x 1.5"= 0.030 sft.
Add wastage 5%= 0.002 sft.
= 0.032 sft.
= 0.33 lbs. @ Tk. 38.55 Per Ib. = Tk. 12.72
(b) Fittings, hardwares and consumables:
(i) Electrodes in/c electricity 12.00 Nos. @ Tk. 10.00 each = Tk. 120.00
(c) Labour for making grill fencing
(i) Welder / fabricator 0.20 No. @ Tk. 423.00 each = Tk. 84.60
(ii) Welder helper 0.20 No. @ Tk. 304.00 each = Tk. 60.80
(iii) Ordinary labour 0.20 No. @ Tk. 245.00 each = Tk. 49.00
(d) Carrying of materials to work-shop and fabricated materials to site: = Tk. 20.00
Sub-total = Tk. 1,217.72
(e) Work-shop charges: 10% = Tk. 121.77
Total = Tk. 1,339.49
(f) Labour charge for fitting-fixing the grill fencing:
(i) Mason 0.20 No. @ Tk. 389.00 each = Tk. 77.80
(ii) Mason helper 0.20 No. @ Tk. 304.00 each = Tk. 60.80
Analysis of PWD SoR 2014 for Civil Works 360
13. Bottom cap/end cap for head rail 2 Nos. @ Tk. 9.97 each = Tk. 19.94
14. Tape holder 2 Nos. @ Tk. 5.51 each = Tk. 11.02
15. Steel washer 2 Nos. @ Tk. 7.44 each = Tk. 14.88
16. Head cap set 2 Nos. @ Tk. 11.89 each = Tk. 23.78
17. Handling cord 81.97 rft. @ Tk. 3.34 Per rft. = Tk. 273.78
18. Labour cost 48 sft. @ Tk. 2.72 Per sft. = Tk. 130.56
Total = Tk. 4,716.88
Profit 10.00% = Tk. 471.69
Overhead 3.50% = Tk. 165.09
= Tk. 5,353.66
Add VAT with adjustment factor 1.0582 5.50% = Tk. 311.59
Grand total = Tk. 5,665.25
Rate per sft. = Tk. 118.03
Rate per sqm. = Tk. 1,270.47
= Tk. 4,759.34
Add VAT with adjustment factor 1.0582 5.50% = Tk. 277.00
Grand total = Tk. 5,036.34
Rate per sft. = Tk. 314.77
Rate per sqm. = Tk. 3,388.18
23.1.2 For each additional lift of one foot beyond 5'-0" and upto 10'-0"
Considering 1000 cft. of excavation work
(i) Extra labour 1/2 No. @ Tk. 245.00 each = Tk. 122.50
Profit 10.00% = Tk. 12.25
Overhead 3.50% = Tk. 4.29
= Tk. 139.04
Add VAT with adjustment factor 1.0582 5.50% = Tk. 8.09
Grand total = Tk. 147.13
Rate per cft. = Tk. 0.15
Rate per cum. = Tk. 5.30
23.1.3 For each additional lift of one foot beyond 10'-0" and upto 15'-0"
Considering 1000 cft. of excavation work
(i) Extra labour 3/4 No. @ Tk. 245.00 each = Tk. 183.75
Profit 10.00% = Tk. 18.38
Overhead 3.50% = Tk. 6.43
= Tk. 208.56
Add VAT with adjustment factor 1.0582 5.50% = Tk. 12.14
Grand total = Tk. 220.70
Rate per cft. = Tk. 0.22
Rate per cum. = Tk. 7.77
Say Tk. 7.77 Per cum.
23.1.4 For each additional lift of one foot beyond 15'-0" and upto 20'-0"
Considering 1000 cft. of excavation work
(i) Extra labour 1 No. @ Tk. 245.00 each = Tk. 245.00
Profit 10.00% = Tk. 24.50
Overhead 3.50% = Tk. 8.58
= Tk. 278.08
Add VAT with adjustment factor 1.0582 5.50% = Tk. 16.18
Grand total = Tk. 294.26
Rate per cft. = Tk. 0.29
Rate per cum. = Tk. 10.24
Say, Tk. 10.24 Per cum.
23.1.5 Extra each additional lead of 100'-0"
Analysis of PWD SoR 2014 for Civil Works 376
maintenance, driver etc. 0.06 day @ Tk. 1,268.00 Per day = Tk. 76.08
8 Local carries Sundries T & P etc. L. S. Tk. 50.00
Total = Tk. 28,132.00
Profit 10.00% = Tk. 2,813.20
Overhead 3.50% = Tk. 984.62
= Tk. 31,929.82
Add VAT with adjustment factor 1.0582 5.50% = Tk. 1,858.35
Grand total = Tk. 33,788.17
Rate per cft. = Tk. 95.68
Rate per cum. = Tk. 3,378.94
Say, Tk. 3,379 .00 Per cum.
Item No.- 24.11
2" compacted bitumenous carpeting (with stone chips / boulder)
Considering 100 sft. of work
(a) Cost of materials
(i) Boulder for stone chips 21 cft. @ Tk. 12,500.00 Per % cft. = Tk. 2,625.00
(ii) Bitumen 86 lbs. @ Tk. 29.63 Per Ib. = Tk. 2,548.18
(iii) Sand (F.M. 1.2) 4 cft. @ Tk. 1,700.00 Per % cft. = Tk. 68.00
(iv) Fire wood 2.5 Mnds. @ Tk. 194.00 Per mnds. = Tk. 485.00
Total (a) = Tk. 5,726.18
(b) Labour charges:
(i) For breaking stone chips 21 cft. @ Tk. 1,531.07 Per % cft. = Tk. 321.52
(ii) For heating & mixing stone
chips and bitumen 2 Nos. @ Tk. 245.00 each = Tk. 490.00
(iii) For brooming & cleaning the base
Ordinary labour 1/2 No. @ Tk. 245.00 each = Tk. 122.50
(iv) Labour for spreading 1/2 No. @ Tk. 245.00 each = Tk. 122.50
(v) Skilled labour for levelling
& hand packing 1/2 No. @ Tk. 303.00 each = Tk. 151.50
(vi) Labour for sand blinding 1/4 No. @ Tk. 245.00 each = Tk. 61.25
(vii) Head mason 1/16 No. @ Tk. 493.00 each = Tk. 30.81
(viii) Mason 1/4 No. @ Tk. 389.00 each = Tk. 97.25
(ix) Sundries and T & P L.S. = Tk. 81.67
Total (c) = Tk. 1,479.00
(c) Roller charges:
(i) Hire charge of 8 ton to 12 ton
roller (two steel drum roller) 0.14 day @ Tk. 5,063.00 Per day = Tk. 708.82
(ii) Fuel & lubricants, spares,
maintenance, driver etc. 0.14 day @ Tk. 1,268.00 Per day = Tk. 177.52
Total (c) = Tk. 886.34
Total (a+b+c) = Tk. 8,091.52
Profit 10.00% = Tk. 809.15
Overhead 3.50% = Tk. 283.20
= Tk. 9,183.87
Add VAT with adjustment factor 1.0582 5.50% = Tk. 534.51
Grand total = Tk. 9,718.38
Rate per sft. = Tk. 97.18
Rate per sqm. = Tk. 1,046.05
Say, Tk. 1,046 .00 Per sqm.
Item No.- 24.12
1.5" compacted bitumenous carpeting (with stone chips/boulder)
Considering 100 sft. of work
(a) Cost of materials
(i) Boulder for stone chips 15.75 cft. @ Tk. 12,500.00 Per % cft. = Tk. 1,968.75
(ii) Bitumen 65 lbs. @ Tk. 29.63 Per Ib. = Tk. 1,925.95
(iii) Sand (F.M. 1.2) 4 cft. @ Tk. 1,700.00 Per % cft. = Tk. 68.00
(iv) Fire wood 2 Mnds. @ Tk. 194.00 Per mnd. = Tk. 388.00
Analysis of PWD SoR 2014 for Civil Works 383
roller (two steel drum roller) 0.14 day @ Tk. 5,063.00 Per day = Tk. 708.82
(ii) Fuel & lubricants, spares,
maintenance, driver etc. 0.14 day @ Tk. 1,268.00 Per day = Tk. 177.52
Total (C) = Tk. 886.34
Total (A+B+C) = Tk. 4,841.93
Profit 10.00% = Tk. 484.19
Overhead 3.50% = Tk. 169.47
= Tk. 5,495.59
Add VAT with adjustment factor 1.0582 5.50% = Tk. 319.85
Grand total = Tk. 5,815.44
Rate per sft. = Tk. 58.15
Rate per sqm. = Tk. 625.93
26.1.1.2 Coloured commode (Bangladeshi), size(mm) 465 x 340 x 415. wt.: 14 kg. or equivalent
Considering 1 No. of fixture
1. Coloured commode 1 No. @ Tk. 1,400.00 each = Tk. 1,400.00
2. Accessories:
(a) Seat cover 1 No. @ Tk. 718.20 each = Tk. 718.20
3. Fitting fixing materials:
(a) Cement mortar (1:4)
(i) Cement 0.1 bag. @ Tk. 440.00 Per bag = Tk. 44.00
(ii) Sand (F.M. 1.2) 0.5 cft. @ Tk. 1,700.00 Per % cft. = Tk. 8.50
(b) Nuts with washer 4 Nos. @ Tk. 22.21 each = Tk. 88.84
4. Labour:
(a) Plumber 0.25 No. @ Tk. 440.00 each = Tk. 110.00
(b) Skilled labour 0.5 No. @ Tk. 303.00 each = Tk. 151.50
(c) Ordinary labour 0.5 No. @ Tk. 245.00 each = Tk. 122.50
Total = Tk. 2,643.54
Profit 10.00% = Tk. 264.35
Overhead 3.50% = Tk. 92.52
= Tk. 3,000.41
Add VAT with adjustment factor 1.0582 5.50% = Tk. 174.63
Grand total = Tk. 3,175.04
Rate per No. = Tk. 3,175.04
26.1.1.3 Special coloured commode (Bangladeshi), size(mm) 465 x 340 x 415. wt.: 14 kg.or equivalent
Considering 1 No. of fixture
1. Special coloured commode 1 No. @ Tk. 1,470.00 each = Tk. 1,470.00
2. Accessories:
(a) Seat cover 1 No. @ Tk. 718.20 each = Tk. 718.20
3. Fitting fixing materials:
(a) Cement mortar (1:4)
(i) Cement 0.1 bag. @ Tk. 440.00 Per bag = Tk. 44.00
Analysis of PWD SoR 2014 for Civil Works 396
(ii) Sand (F.M. 1.2) 0.5 cft. @ Tk. 1,700.00 Per % cft. = Tk. 8.50
(b) Nuts with Washer 4 Nos. @ Tk. 22.21 each = Tk. 88.84
4. Labour:
(a) Plumber 0.25 No. @ Tk. 440.00 each = Tk. 110.00
(b) Skilled labour 0.5 No. @ Tk. 303.00 each = Tk. 151.50
(c) Ordinary labour 0.5 No. @ Tk. 245.00 each = Tk. 122.50
Total = Tk. 2,713.54
Profit 10.00% = Tk. 271.35
Overhead 3.50% = Tk. 94.97
= Tk. 3,079.86
Add VAT with adjustment factor 1.0582 5.50% = Tk. 179.25
Grand total = Tk. 3,259.11
Rate per No. = Tk. 3,259.11
26.2.1.2 Coloured low -down (Bangladeshi), size(mm) 490 x 190 x 350. wt.: 14 kg. or equivalent
Considering 1 No. of fixture
1. Coloured low-down 1 No. @ Tk. 1,550.00 each = Tk. 1,550.00
2. Accessories:
(a) 32 mm dia plastic pipe 1 No. @ Tk. 79.77 each = Tk. 79.77
3. Fitting fixing materials:
(a) Clamp 2 Nos. @ Tk. 45.55 each = Tk. 91.10
(i) 50 mm rowel plug with screws 4 Nos. @ Tk. 8.56 each = Tk. 34.24
(ii) 75 mm screw, rowel plug 3 Nos. @ Tk. 12.76 each = Tk. 38.28
4. Labour:
(a) Plumber 0.25 No. @ Tk. 440.00 each = Tk. 110.00
(b) Skilled labour 0.5 No. @ Tk. 303.00 each = Tk. 151.50
Total = Tk. 2,054.89
Profit 10.00% = Tk. 205.49
Overhead 3.50% = Tk. 71.92
= Tk. 2,332.30
Analysis of PWD SoR 2014 for Civil Works 397
26.2.1.3 Special coloured low -down (Bangladeshi), size(mm) 490 x 190 x 350. wt.: 14 kg. or equivalent
Considering 1 No. of fixture
1. Special coloured low-down 1 No. @ Tk. 1,860.00 each = Tk. 1,860.00
2. Accessories:
(a) 32 mm dia plastic pipe 1 No. @ Tk. 79.77 each = Tk. 79.77
3. Fitting fixing materials:
(a) Clamp 2 Nos. @ Tk. 45.55 each = Tk. 91.10
(i) 50 mm rowel plug with screws 4 Nos. @ Tk. 8.56 each = Tk. 34.24
(ii) 75 mm screw, rowel plug 3 Nos. @ Tk. 12.76 each = Tk. 38.28
4. Labour:
(a) Plumber 0.25 No. @ Tk. 440.00 each = Tk. 110.00
(b) Skilled labour 0.5 No. @ Tk. 303.00 each = Tk. 151.50
Total = Tk. 2,364.89
Profit 10.00% = Tk. 236.49
Overhead 3.50% = Tk. 82.77
= Tk. 2,684.15
Add VAT with adjustment factor 1.0582 5.50% = Tk. 156.22
Grand total = Tk. 2,840.37
Rate per No. = Tk. 2,840.37
26.3.1.2 Coloured combicloset (Bangladeshi), size(mm) 700 x 410 x 795. wt.: 31.5 kg. or equivalent
Analysis of PWD SoR 2014 for Civil Works 398
26.3.1.3 Special coloured combicloset (Bangladeshi), size (mm) 700 x 410 x 795. wt.: 31.5 kg. or equivalent
Considering 1 No. of fixture
1. Special coloured combicloset: 1 No. @ Tk. 4,818.50 each = Tk. 4,818.50
2. Accessories:
(a) Flushing equipment 1 No. @ Tk. 1,012.27 each = Tk. 1,012.27
(b) Seat cover 1 No. @ Tk. 718.20 each = Tk. 718.20
3. Fitting fixing materials:
(a) Cement mortar (1:4)
(i) Cement 0.1 bag. @ Tk. 440.00 Per bag = Tk. 44.00
(ii) Sand (F.M. 1.2) 0.5 cft. @ Tk. 1,700.00 Per % cft. = Tk. 8.50
(b) Nuts with washer 4 Nos. @ Tk. 22.21 each = Tk. 88.84
4. Labour:
(a) Plumber 0.25 No. @ Tk. 440.00 each = Tk. 110.00
(b) Skilled labour 1 No. @ Tk. 303.00 each = Tk. 303.00
(c) Ordinary labour 0.5 No. @ Tk. 245.00 each = Tk. 122.50
Total = Tk. 7,225.81
Profit 10.00% = Tk. 722.58
Overhead 3.50% = Tk. 252.90
= Tk. 8,201.29
Add VAT with adjustment factor 1.0582 5.50% = Tk. 477.32
Grand total = Tk. 8,678.61
Rate per No. = Tk. 8,678.61
26.3.2.1 White combicloset, size (mm) 700 x 370 x 795. wt.: 32.5 kg. or equivalent
Considering 1 No. of fixture
1. White Combicloset 1 No. @ Tk. 6,500.00 each = Tk. 6,500.00
2. Accessories:
(a) Flushing equpment 1 No. @ Tk. 1,012.27 each = Tk. 1,012.27
(b) Seat-cover 1 No. @ Tk. 718.20 each = Tk. 718.20
3. Fitting fixing materials:
(a) Cement mortar (1:4)
Analysis of PWD SoR 2014 for Civil Works 399
(i) Cement 0.1 bag. @ Tk. 440.00 Per bag = Tk. 44.00
(ii) Sand (F.M. 1.2) 0.5 cft. @ Tk. 1,700.00 Per % cft. = Tk. 8.50
(b) Nuts with washer 4 Nos. @ Tk. 22.21 each = Tk. 88.84
4. Labour:
(a) Plumber 0.25 No. @ Tk. 440.00 each = Tk. 110.00
(b) Skilled labour 1 No. @ Tk. 303.00 each = Tk. 303.00
(c) Ordinary labour 0.5 No. @ Tk. 245.00 each = Tk. 122.50
Total = Tk. 8,907.31
Profit 10.00% = Tk. 890.73
Overhead 3.50% = Tk. 311.76
= Tk. 10,109.80
Add VAT with adjustment factor 1.0582 5.50% = Tk. 588.40
Grand total = Tk. 10,698.20
Rate per No. = Tk. 10,698.20
26.3.3.1 White combicloset, size (mm) 700 x 360 x 785. wt.: 36(+/-)36.5 kg. or equivalent
Considering 1 No. of fixture
1. White Combicloset 1 No. @ Tk. 10,500.00 each = Tk. 10,500.00
2. Accessories:
(a) Flushing equpment 1 No. @ Tk. 1,012.27 each = Tk. 1,012.27
(b) Seat-cover 1 No. @ Tk. 718.20 each = Tk. 718.20
3. Fitting fixing materials:
(a) Cement mortar (1:4)
(i) Cement 0.1 bag. @ Tk. 440.00 Per bag = Tk. 44.00
(ii) Sand (F.M. 1.2) 0.5 cft. @ Tk. 1,700.00 Per % cft. = Tk. 8.50
(b) Nuts with washer 4 Nos. @ Tk. 22.21 each = Tk. 88.84
4. Labour:
(a) Plumber 0.25 No. @ Tk. 440.00 each = Tk. 110.00
(b) Skilled labour 1 No. @ Tk. 303.00 each = Tk. 303.00
(c) Ordinary labour 0.5 No. @ Tk. 245.00 each = Tk. 122.50
Total = Tk. 12,907.31
Profit 10.00% = Tk. 1,290.73
Overhead 3.50% = Tk. 451.76
= Tk. 14,649.80
Add VAT with adjustment factor 1.0582 5.50% = Tk. 852.63
Grand total = Tk. 15,502.43
Rate per No. = Tk. 15,502.43
26.4.1 White combicloset (Bangladeshi), size (mm) 725x360x840 42.7 kg.or equivalent
Considering 1 No. of fixture
1. White combicloset 1 No. @ Tk. 15,500.00 each = Tk. 15,500.00
2. Accessories:
(a) Flushing equipment 1 No. @ Tk. 883.29 each = Tk. 883.29
(b) Seat-cover 1 No. @ Tk. 718.20 each = Tk. 718.20
3. Fitting fixing materials:
(a) Cement mortar (1:4)
(i) Cement 0.1 bag. @ Tk. 440.00 Per bag = Tk. 44.00
(ii) Sand (F.M. 1.2) 0.5 cft. @ Tk. 1,700.00 Per % cft. = Tk. 8.50
(b) Nuts with washer 4 Nos. @ Tk. 22.21 each = Tk. 88.84
4. Labour:
(a) Plumber 0.25 No. @ Tk. 440.00 each = Tk. 110.00
(b) Skilled labour 1 No. @ Tk. 303.00 each = Tk. 303.00
(c) Ordinary labour 0.5 No. @ Tk. 245.00 each = Tk. 122.50
Analysis of PWD SoR 2014 for Civil Works 400
26.4.2 Coloured combicloset (Bangladeshi), size (mm) 700 x 410 x 795. wt.: 34.5 kg.or equivalent
Considering 1 No. of fixture
1. Coloured combicloset: 1 No. @ Tk. 20,925.00 each = Tk. 20,925.00
2. Accessories:
(a) a) Flushing equipment 1 No. @ Tk. 883.29 each = Tk. 883.29
(b) Seat cover 1 No. @ Tk. 718.20 each = Tk. 718.20
3. Fitting fixing materials:
(a) Cement mortar (1:4)
(i) Cement 0.1 bag. @ Tk. 440.00 Per bag = Tk. 44.00
(ii) Sand (F.M. 1.2) 0.5 cft. @ Tk. 1,700.00 Per % cft. = Tk. 8.50
(b) Nuts with washer 4 Nos. @ Tk. 22.21 each = Tk. 88.84
4. Labour:
(a) Plumber 0.25 No. @ Tk. 440.00 each = Tk. 110.00
(b) Skilled labour 1 No. @ Tk. 303.00 each = Tk. 303.00
(c) Ordinary labour 0.5 No. @ Tk. 245.00 each = Tk. 122.50
Total = Tk. 23,203.33
Profit 10.00% = Tk. 2,320.33
Overhead 3.50% = Tk. 812.12
= Tk. 26,335.78
Add VAT with adjustment factor 1.0582 5.50% = Tk. 1,532.77
Grand total = Tk. 27,868.55
Rate per No. = Tk. 27,868.55
26.4.3 Special coloured combicloset (Bangladeshi), size (mm) 700 x 410 x 795. wt.: 34.5 kg.or equivalent
Considering 1 No. of fixture
1. Special coloured combicloset: 1 No. @ Tk. 23,250.00 each = Tk. 23,250.00
2. Accessories:
(a) Flushing equipment 1 No. @ Tk. 883.29 each = Tk. 883.29
(b) Seat cover 1 No. @ Tk. 718.20 each = Tk. 718.20
3. Fitting fixing materials:
(a) Cement mortar (1:4)
(i) Cement 0.1 bag. @ Tk. 440.00 Per bag = Tk. 44.00
(ii) Sand (F.M. 1.2) 0.5 cft. @ Tk. 1,700.00 Per % cft. = Tk. 8.50
(b) Nuts with washer 4 Nos. @ Tk. 22.21 each = Tk. 88.84
4. Labour:
(a) Plumber 0.25 No. @ Tk. 440.00 each = Tk. 110.00
(b) Skilled labour 1 No. @ Tk. 303.00 each = Tk. 303.00
(c) Ordinary labour 0.5 No. @ Tk. 245.00 each = Tk. 122.50
Total = Tk. 25,528.33
Profit 10.00% = Tk. 2,552.83
Overhead 3.50% = Tk. 893.49
= Tk. 28,974.65
Add VAT with adjustment factor 1.0582 5.50% = Tk. 1,686.35
Grand total = Tk. 30,661.00
Rate per No. = Tk. 30,661.00
Analysis of PWD SoR 2014 for Civil Works 401
26.5.1.2 Coloured long pan (Bangladeshi), size (mm) 570 x 445 x 290. wt. 12 kg.or equivalent
Considering 1 No. of fixture
1. Coloured long pan: 1 No. @ Tk. 1,204.50 each = Tk. 1,204.50
2. Fitting fixing materials:
(a) Cement mortar (1:4)
(i) Cement 0.1 bag. @ Tk. 440.00 Per bag = Tk. 44.00
(ii) Sand (F.M. 1.2) 0.5 cft. @ Tk. 1,700.00 Per % cft. = Tk. 8.50
3. Labour:
(a) Plumber 0.25 No. @ Tk. 440.00 each = Tk. 110.00
(b) Skilled labour 0.5 No. @ Tk. 303.00 each = Tk. 151.50
(c) Ordinary labour 0.5 No. @ Tk. 245.00 each = Tk. 122.50
Total = Tk. 1,641.00
Profit 10.00% = Tk. 164.10
Overhead 3.50% = Tk. 57.44
= Tk. 1,862.54
Add VAT with adjustment factor 1.0582 5.50% = Tk. 108.40
Grand total = Tk. 1,970.94
Rate per No. = Tk. 1,970.94
Say, Tk. 1,971 .00 each
26.5.1.3 Special coloured long pan (Bangladeshi), size (mm) 570 x 445 x 290. wt. 12 kg.or equivalent
Considering 1 No. of fixture
1. Special coloured long pan: 1 No. @ Tk. 1,265.00 each = Tk. 1,265.00
2. Fitting fixing materials:
(a) Cement mortar (1:4)
(i) Cement 0.1 bag. @ Tk. 440.00 Per bag = Tk. 44.00
(ii) Sand (F.M. 1.2) 0.5 cft. @ Tk. 1,700.00 Per % cft. = Tk. 8.50
3. Labour:
(a) Plumber 0.25 No. @ Tk. 440.00 each = Tk. 110.00
(b) Skilled labour 0.5 No. @ Tk. 303.00 each = Tk. 151.50
(c) Ordinary labour 0.5 No. @ Tk. 245.00 each = Tk. 122.50
Analysis of PWD SoR 2014 for Civil Works 402
26.5.2.1 White long pan (Bangladeshi), size(mm) 540 x 470 x 290. wt. 16 kg.or equivalent
Considering 1 No. of fixture
1. White long pan: 1 No. @ Tk. 1,387.00 each = Tk. 1,387.00
2. Fitting fixing materials:
(a) Cement mortar (1:4)
(i) Cement 0.1 bag. @ Tk. 440.00 Per bag = Tk. 44.00
(ii) Sand (F.M. 1.2) 0.5 cft. @ Tk. 1,700.00 Per % cft. = Tk. 8.50
3. Labour:
(a) Plumber 0.25 No. @ Tk. 440.00 each = Tk. 110.00
(b) Skilled labour 0.5 No. @ Tk. 303.00 each = Tk. 151.50
(c) Ordinary labour 0.5 No. @ Tk. 245.00 each = Tk. 122.50
Total = Tk. 1,823.50
Profit 10.00% = Tk. 182.35
Overhead 3.50% = Tk. 63.82
= Tk. 2,069.67
Add VAT with adjustment factor 1.0582 5.50% = Tk. 120.46
Grand total = Tk. 2,190.13
Rate per No. = Tk. 2,190.13
26.5.2.2 Coloured long pan (Bangladeshi), size (mm) 540 x 470 x 290. wt. 16 kg..or equivalent
Considering 1 No. of fixture
1. Coloured long pan: 1 No. @ Tk. 1,733.75 each = Tk. 1,733.75
2. Fitting fixing materials:
(a) Cement mortar (1:4)
(i) Cement 0.1 bag. @ Tk. 440.00 Per bag = Tk. 44.00
(ii) Sand (F.M. 1.2) 0.5 cft. @ Tk. 1,700.00 Per % cft. = Tk. 8.50
3. Labour:
(a) Plumber 0.25 No. @ Tk. 440.00 each = Tk. 110.00
(b) Skilled labour 0.5 No. @ Tk. 303.00 each = Tk. 151.50
(c) Ordinary labour 0.5 No. @ Tk. 245.00 each = Tk. 122.50
Total = Tk. 2,170.25
Profit 10.00% = Tk. 217.03
Overhead 3.50% = Tk. 75.96
= Tk. 2,463.24
Add VAT with adjustment factor 1.0582 5.50% = Tk. 143.36
Grand total = Tk. 2,606.60
Rate per No. = Tk. 2,606.60
26.5.2.3 Special coloured long pan (Bangladeshi), size (mm) 540 x 470 x 290. wt. 16 kg..or equivalent
Considering 1 No. of fixture
1. Special coloured long pan: 1 No. @ Tk. 2,080.50 each = Tk. 2,080.50
2. Fitting fixing materials:
(a) Cement mortar (1:4)
Analysis of PWD SoR 2014 for Civil Works 403
(i) Cement 0.1 bag. @ Tk. 440.00 Per bag = Tk. 44.00
(ii) Sand (F.M. 1.2) 0.5 cft. @ Tk. 1,700.00 Per % cft. = Tk. 8.50
3. Labour:
(a) Plumber 0.25 No. @ Tk. 440.00 each = Tk. 110.00
(b) Skilled labour 0.5 No. @ Tk. 303.00 each = Tk. 151.50
(c) Ordinary labour 0.5 No. @ Tk. 245.00 each = Tk. 122.50
Total = Tk. 2,517.00
Profit 10.00% = Tk. 251.70
Overhead 3.50% = Tk. 88.10
= Tk. 2,856.80
Add VAT with adjustment factor 1.0582 5.50% = Tk. 166.27
Grand total = Tk. 3,023.07
Rate per No. = Tk. 3,023.07
26.6.2 Coloured long pan (Bangladeshi), size(mm) 560 x 290 x 270. wt. 7.1 kg. omitted
Considering 1 No. of fixture
1. Coloured long pan: 1 No. @ Tk. - each = Tk. -
2. Fitting fixing materials:
(a) Cement mortar (1:4)
(i) Cement 0.1 bag. @ Tk. 440.00 Per bag = Tk. 44.00
(ii) Sand (F.M. 1.2) 0.5 cft. @ Tk. 1,700.00 Per % cft. = Tk. 8.50
3. Labour:
(a) Plumber 0.25 No. @ Tk. 440.00 each = Tk. 110.00
(b) Skilled labour 0.5 No. @ Tk. 303.00 each = Tk. 151.50
(c) Ordinary labour 0.5 No. @ Tk. 245.00 each = Tk. 122.50
Total = Tk. 436.50
Profit 10.00% = Tk. 43.65
Overhead 3.50% = Tk. 15.28
= Tk. 495.43
Add VAT with adjustment factor 1.0582 5.50% = Tk. 28.83
Grand total = Tk. 524.26
Rate per No. = Tk. 524.26
Analysis of PWD SoR 2014 for Civil Works 404
26.6.3
Special coloured long pan (Bangladeshi), size (mm) 560 x 290 x 270. wt. 7.1 kg.or equivalent
omitted
Considering 1 No. of fixture
1. Special coloured long pan: 1 No. @ Tk. - each = Tk. -
2. Fitting fixing materials:
(a) Cement mortar (1:4)
(i) Cement 0.1 bag. @ Tk. 440.00 Per bag = Tk. 44.00
(ii) Sand (F.M. 1.2) 0.5 cft. @ Tk. 1,700.00 Per % cft. = Tk. 8.50
3. Labour:
(a) Plumber 0.25 No. @ Tk. 440.00 each = Tk. 110.00
(b) Skilled labour 0.5 No. @ Tk. 303.00 each = Tk. 151.50
(c) Ordinary labour 0.5 No. @ Tk. 245.00 each = Tk. 122.50
Total = Tk. 436.50
Profit 10.00% = Tk. 43.65
Overhead 3.50% = Tk. 15.28
= Tk. 495.43
Add VAT with adjustment factor 1.0582 5.50% = Tk. 28.83
Grand total = Tk. 524.26
Rate per No. = Tk. 524.26
= Tk. 164.15
Add VAT with adjustment factor 1.0582 5.50% = Tk. 9.55
Grand total = Tk. 173.70
Rate per No. = Tk. 173.70
26.9.1.3 Special coloured w-basin, (Bangladeshi) 204 size (mm) 5approx. 600x465x225, 14kg
1. Considering 1 No. of fixture
2. Special coloured wash-basin 1 No. @ Tk. 1,430.00 each = Tk. 1,430.00
(a) Accessories:
(b) 32 mm dia PVC waste pipe 1 No. @ Tk. 158.12 each = Tk. 158.12
(c) Grating with brass coupling 1 No. @ Tk. 277.75 each = Tk. 277.75
(d) CP chain with rubber plug 1 No. @ Tk. 48.43 each = Tk. 48.43
3. Fitting fixing materials:
(a) Cement mortar (1:4)
(i) Cement 0.01 bag. @ Tk. 440.00 Per bag = Tk. 4.40
(ii) Sand (F.M. 1.2) 0.05 cft. @ Tk. 1,700.00 Per % cft. = Tk. 0.85
(b) CI brakets 1 Pair @ Tk. 113.45 Per pair = Tk. 113.45
4. Labour:
(a) Plumber 0.15 No. @ Tk. 440.00 each = Tk. 66.00
(b) Skilled labour 0.2 No. @ Tk. 303.00 each = Tk. 60.60
(c) Ordinary labour 0.4 No. @ Tk. 245.00 each = Tk. 98.00
Total = Tk. 2,257.60
Profit 10.00% = Tk. 225.76
Overhead 3.50% = Tk. 79.02
= Tk. 2,562.38
Add VAT with adjustment factor 1.0582 5.50% = Tk. 149.13
Grand total = Tk. 2,711.51
Rate per No. = Tk. 2,711.51
(b) Grating with brass coupling 1 No. @ Tk. 277.75 each = Tk. 277.75
(c) CP chain with rubber plug 1 No. @ Tk. 48.43 each = Tk. 48.43
3. Fitting fixing materials:
(a) Cement mortar (1:4)
(i) Cement 0.01 bag. @ Tk. 440.00 Per bag = Tk. 4.40
(ii) Sand (F.M. 1.2) 0.05 cft. @ Tk. 1,700.00 Per % cft. = Tk. 0.85
(b) CI brakets 1 Pair @ Tk. 113.45 Per pair = Tk. 113.45
4. Labour:
(a) Plumber 0.15 No. @ Tk. 440.00 each = Tk. 66.00
(b) Skilled labour 0.2 No. @ Tk. 303.00 each = Tk. 60.60
(c) Ordinary labour 0.4 No. @ Tk. 245.00 each = Tk. 98.00
Total = Tk. 11,627.60
Profit 10.00% = Tk. 1,162.76
Overhead 3.50% = Tk. 406.97
= Tk. 13,197.33
Add VAT with adjustment factor 1.0582 5.50% = Tk. 768.10
Grand total = Tk. 13,965.43
Rate per No. = Tk. 13,965.43
(b) Accessories:
(i) Grating with brass coupling 1 No. @ Tk. 277.75 each = Tk. 277.75
(ii) 32 mm dia PVC waste pipe 1 No. @ Tk. 158.12 each = Tk. 158.12
(c) Fitting fixing materials:
(i) 75 mm rowel plug 2 Nos. @ Tk. 12.76 each = Tk. 25.52
(d) Labour:
(i) Plumber 0.15 No. @ Tk. 440.00 each = Tk. 66.00
(ii) Skilled labour 0.2 No. @ Tk. 303.00 each = Tk. 60.60
(iii) Ordinary labour 0.4 No. @ Tk. 245.00 each = Tk. 98.00
Total = Tk. 2,557.99
Profit 10.00% = Tk. 255.80
Overhead 3.50% = Tk. 89.53
= Tk. 2,903.32
Add VAT with adjustment factor 1.0582 5.50% = Tk. 168.98
Grand total = Tk. 3,072.30
Rate per No. = Tk. 3,072.30
(b) 32 mm dia PVC waste pipe 1 No. @ Tk. 158.12 each = Tk. 158.12
(c) CP chain with plug 1 No. @ Tk. 48.43 each = Tk. 48.43
3. Fitting fixing materials:
(a) CI braket: heavy type 1 Pair @ Tk. 138.05 Per pair = Tk. 138.05
(b) Cement mortar (1:4):
(i) Cement 0.015 bag. @ Tk. 440.00 Per bag = Tk. 6.60
(ii) Sand 0.075 cft. @ Tk. 1,700.00 Per % cft. = Tk. 1.28
4. Labour:
(a) Plumber 0.2 No. @ Tk. 440.00 each = Tk. 88.00
(b) Skilled labour 0.3 No. @ Tk. 303.00 each = Tk. 90.90
Total = Tk. 2,345.07
Profit 10.00% = Tk. 234.51
Overhead 3.50% = Tk. 82.08
= Tk. 2,661.66
Add VAT with adjustment factor 1.0582 5.50% = Tk. 154.91
Grand total = Tk. 2,816.57
Rate per No. = Tk. 2,816.57
(i) Cement 0.015 bag. @ Tk. 440.00 Per bag = Tk. 6.60
(ii) Sand 0.075 cft. @ Tk. 1,700.00 Per % cft. = Tk. 1.28
4. Labour:
(a) Plumber 0.2 No. @ Tk. 440.00 each = Tk. 88.00
(b) Skilled labour 0.3 No. @ Tk. 303.00 each = Tk. 90.90
Total = Tk. 3,405.62
Profit 10.00% = Tk. 340.56
Overhead 3.50% = Tk. 119.20
= Tk. 3,865.38
Add VAT with adjustment factor 1.0582 5.50% = Tk. 224.97
Grand total = Tk. 4,090.35
Rate per No. = Tk. 4,090.35
(a) Super quality CP towel rail 1 No. @ Tk. 417.44 each = Tk. 417.44
(b) Fitting fixing materials:
(i) Rowel plug and screw 4 Nos. @ Tk. 8.56 each = Tk. 34.24
(c) Labour:
(i) Plumber 0.04 No. @ Tk. 440.00 each = Tk. 17.60
(ii) Skilled labour 0.08 No. @ Tk. 303.00 each = Tk. 24.24
(iii) Ordinary labour 0.15 No. @ Tk. 245.00 each = Tk. 36.75
Total = Tk. 530.27
Profit 10.00% = Tk. 53.03
Overhead 3.50% = Tk. 18.56
= Tk. 601.86
Add VAT with adjustment factor 1.0582 5.50% = Tk. 35.03
Grand total = Tk. 636.89
Rate per No. = Tk. 636.89
1. White porcelain toilet paper holder 1 No. @ Tk. 126.00 each = Tk. 126.00
2. Fitting fixing materials:
(a) Cement mortar (1:4):
(i) Cement 0.01 bag. @ Tk. 440.00 Per bag = Tk. 4.40
Analysis of PWD SoR 2014 for Civil Works 419
(ii) Sand (F.M. 1.2) 0.05 cft. @ Tk. 1,700.00 Per % cft. = Tk. 0.85
3. Labour:
(a) Plumber 0.025 No. @ Tk. 440.00 each = Tk. 11.00
(b) Skilled labour 0.05 No. @ Tk. 303.00 each = Tk. 15.15
(c) Ordinary labour 0.01 No. @ Tk. 245.00 each = Tk. 2.45
Total = Tk. 159.85
Profit 10.00% = Tk. 15.99
Overhead 3.50% = Tk. 5.59
= Tk. 181.43
Add VAT with adjustment factor 1.0582 5.50% = Tk. 10.56
Grand total = Tk. 191.99
Rate per No. = Tk. 191.99
1. White porcelain toilet paper holder 1 No. @ Tk. 450.00 each = Tk. 450.00
2. Fitting fixing materials:
(a) Cement mortar (1:4):
(i) Cement 0.01 bag. @ Tk. 440.00 Per bag = Tk. 4.40
(ii) Sand (F.M. 1.2) 0.05 cft. @ Tk. 1,700.00 Per % cft. = Tk. 0.85
3. Labour:
(a) Plumber 0.025 No. @ Tk. 440.00 each = Tk. 11.00
(b) Skilled labour 0.05 No. @ Tk. 303.00 each = Tk. 15.15
(c) Ordinary labour 0.01 No. @ Tk. 245.00 each = Tk. 2.45
Total = Tk. 483.85
Profit 10.00% = Tk. 48.39
Overhead 3.50% = Tk. 16.93
= Tk. 549.17
Add VAT with adjustment factor 1.0582 5.50% = Tk. 31.96
Grand total = Tk. 581.13
Analysis of PWD SoR 2014 for Civil Works 420
1. 125 mm dia stainless steel grating 1 No. @ Tk. 114.24 each = Tk. 114.24
2. Fitting fixing materials:
(a) Cement mortar (1:4):
(i) Cement 0.01 bag. @ Tk. 440.00 Per bag = Tk. 4.40
(ii) Sand (F.M. 1.2) 0.05 cft. @ Tk. 1,700.00 Per % cft. = Tk. 0.85
3. Labour:
(a) Skilled labour 0.15 No. @ Tk. 303.00 each = Tk. 45.45
Total = Tk. 164.94
Profit 10.00% = Tk. 16.49
Overhead 3.50% = Tk. 5.77
= Tk. 187.20
Add VAT with adjustment factor 1.0582 5.50% = Tk. 10.90
Grand total = Tk. 198.10
Rate per No. = Tk. 198.10
(v) Rowel plug & screw 6 Nos. @ Tk. 22.83 each = Tk. 136.98
(vi) Scaffolding 18 rft. @ Tk. 2.26 Per rft. = Tk. 40.68
(d) Labour:
(i) Plumber 0.1 No. @ Tk. 440.00 each = Tk. 44.00
(ii) Skilled labour 0.2 No. @ Tk. 303.00 each = Tk. 60.60
(iii) Ordinary labour 0.4 No. @ Tk. 245.00 each = Tk. 98.00
Total = Tk. 4,397.32
Profit 10.00% = Tk. 439.73
Overhead 3.50% = Tk. 153.91
= Tk. 4,990.96
Add VAT with adjustment factor 1.0582 5.50% = Tk. 290.48
Grand total = Tk. 5,281.44
Rate per rm. = Tk. 962.01
(iii) Ordinary labour 0.325 No. @ Tk. 245.00 each = Tk. 79.63
Total = Tk. 1,525.71
Profit 10.00% = Tk. 152.57
Overhead 3.50% = Tk. 53.40
= Tk. 1,731.68
Add VAT with adjustment factor 1.0582 5.50% = Tk. 100.79
Grand total = Tk. 1,832.47
Rate per rft. = Tk. 91.62
Rate Per rm = Tk. 300.61
26.38.2 20 mm dia G.I pipe: connection including nipple, elbow, reducers, plug, Tee etc. complete.
Considering 20 rft. long one pipe
(a) 20 mm dia G.I. pipe: 20 rft. @ Tk. 74.07 Per rft. = Tk. 1,481.40
(b) Fittings:
(i) Elbow 1 No. @ Tk. 30.07 each = Tk. 30.07
(ii) Tee 1 No. @ Tk. 40.99 each = Tk. 40.99
(iii) Nipple 0.5 No. @ Tk. 28.22 each = Tk. 14.11
(iv) Plug 0.5 No. @ Tk. 19.69 each = Tk. 9.85
(v) Reducer 1 No. @ Tk. 34.83 each = Tk. 34.83
(vi) Socket 1 No. @ Tk. 24.01 each = Tk. 24.01
(c) Jointing & fixing materials
(i) Teflon tape 3.2 gm. @ Tk. 1.82 Per gm. = Tk. 5.82
(ii) Clamp 2 Nos. @ Tk. 7.29 each = Tk. 14.58
(iii) Rowel plug & screw 4 Nos. @ Tk. 5.71 each = Tk. 22.84
(iv) Scaffolding 20 rft. @ Tk. 2.26 Per rft. = Tk. 45.20
(d) Labour:
(i) Plumber 0.125 No. @ Tk. 440.00 each = Tk. 55.00
(ii) Skilled labour 0.25 No. @ Tk. 303.00 each = Tk. 75.75
(iii) Ordinary labour 0.5 No. @ Tk. 245.00 each = Tk. 122.50
Total = Tk. 1,976.95
Profit 10.00% = Tk. 197.70
Overhead 3.50% = Tk. 69.19
= Tk. 2,243.84
Add VAT with adjustment factor 1.0582 5.50% = Tk. 130.59
Grand total = Tk. 2,374.43
Rate per rft. = Tk. 118.72
Rate per rm. = Tk. 389.52
26.38.3 25 mm dia G.I pipe: connection including nipple, elbow, reducers, plug, Tee etc. complete.
Considering 20 rft. long one pipe
(a) 25 mm dia G.I. pipe: 20 rft. @ Tk. 99.61 Per rft. = Tk. 1,992.20
(b) Fittings:
(i) Elbow 1 No. @ Tk. 38.66 each = Tk. 38.66
(ii) Tee 1 No. @ Tk. 46.27 each = Tk. 46.27
(iii) Nipple 1 No. @ Tk. 36.70 each = Tk. 36.70
(iv) Plug 1 No. @ Tk. 25.27 each = Tk. 25.27
(v) Reducer 1 No. @ Tk. 48.42 each = Tk. 48.42
(vi) Socket 1 No. @ Tk. 37.93 each = Tk. 37.93
(c) Jointing & fixing materials
(i) Teflon tape 4.2 gm. @ Tk. 1.82 Per gm. = Tk. 7.64
(ii) Clamp 2 Nos. @ Tk. 9.11 each = Tk. 18.22
(iii) Rowel plug & screw 4 Nos. @ Tk. 7.13 each = Tk. 28.52
(iv) Scaffolding 20 rft. @ Tk. 2.26 Per rft. = Tk. 45.20
Analysis of PWD SoR 2014 for Civil Works 429
(d) Labour:
(i) Plumber 0.125 No. @ Tk. 440.00 each = Tk. 55.00
(ii) Skilled labour 0.25 No. @ Tk. 303.00 each = Tk. 75.75
(iii) Ordinary labour 0.5 No. @ Tk. 245.00 each = Tk. 122.50
Total = Tk. 2,578.28
Profit 10.00% = Tk. 257.83
Overhead 3.50% = Tk. 90.24
= Tk. 2,926.35
Add VAT with adjustment factor 1.0582 5.50% = Tk. 170.32
Grand total = Tk. 3,096.67
Rate per rft. = Tk. 154.83
Rate per rm = Tk. 508.00
Say, Tk. 508 .00 Per rm
26.38.4 32 mm dia G.I pipe: connection including nipple, elbow, reducers, plug, Tee etc. complete.
Considering 20 rft. long one pipe
(a) 32 mm dia G.I. pipe: 20 rft. @ Tk. 124.90 Per rft. = Tk. 2,498.00
(b) Fittings:
(i) Elbow 1 No. @ Tk. 65.28 each = Tk. 65.28
(ii) Tee 1 No. @ Tk. 87.50 each = Tk. 87.50
(iii) Nipple 0.5 No. @ Tk. 63.52 each = Tk. 31.76
(iv) Plug 0.5 No. @ Tk. 38.43 each = Tk. 19.22
(v) Reducer 1 No. @ Tk. 72.29 each = Tk. 72.29
(vi) Socket 1 No. @ Tk. 61.52 each = Tk. 61.52
(c) Jointing & fixing materials
(i) Teflon tape 5.2 gm. @ Tk. 1.82 Per gm. = Tk. 9.46
(ii) Clamp 2 Nos. @ Tk. 9.11 each = Tk. 18.22
(iii) Rowel plug & screw 4 Nos. @ Tk. 7.13 each = Tk. 28.52
(iv) Scaffolding 20 rft. @ Tk. 2.26 Per rft. = Tk. 45.20
(d) Labour:
(i) Plumber 0.125 No. @ Tk. 440.00 each = Tk. 55.00
(ii) Skilled labour 0.5 No. @ Tk. 303.00 each = Tk. 151.50
(iii) Ordinary labour 0.5 No. @ Tk. 245.00 each = Tk. 122.50
Total = Tk. 3,265.97
Profit 10.00% = Tk. 326.60
Overhead 3.50% = Tk. 114.31
= Tk. 3,706.88
Add VAT with adjustment factor 1.0582 5.50% = Tk. 215.74
Grand total = Tk. 3,922.62
Rate per rft. = Tk. 196.13
Rate per rm = Tk. 643.50
Say, Tk. 644 .00 Per rm
26.38.5 40 mm dia G.I pipe: connection including nipple, elbow, reducers, plug, Tee etc. complete.
Considering 20 rft. long one pipe
(a) 40 mm dia G.I. pipe: 20 rft. @ Tk. 169.31 Per rft. = Tk. 3,386.20
(b) Fittings:
(i) Elbow 1 No. @ Tk. 81.73 each = Tk. 81.73
(ii) Tee 1 No. @ Tk. 103.49 each = Tk. 103.49
(iii) Nipple 1 No. @ Tk. 69.22 each = Tk. 69.22
(iv) Plug 1 No. @ Tk. 48.61 each = Tk. 48.61
(v) Reducer 1 No. @ Tk. 103.23 each = Tk. 103.23
(vi) Socket 1 No. @ Tk. 64.90 each = Tk. 64.90
(c) Jointing & fixing materials
(i) Teflon tape 6.3 gm. @ Tk. 1.82 Per gm. = Tk. 11.47
(ii) Clamp 2 Nos. @ Tk. 9.11 each = Tk. 18.22
(iii) Rowel plug & screw 4 Nos. @ Tk. 7.13 each = Tk. 28.52
Analysis of PWD SoR 2014 for Civil Works 430
26.38.6 50 mm dia G.I. pipe: connection including nipple, elbow, reducers, plug, Tee etc. complete.
Considering 20 rft. long one pipe
(a) 50 mm dia G.I. pipe: 20 rft. @ Tk. 197.33 Per rft. = Tk. 3,946.60
(b) Fittings:
(i) Elbow 1 No. @ Tk. 115.59 each = Tk. 115.59
(ii) Tee 1 No. @ Tk. 162.01 each = Tk. 162.01
(iii) Nipple 1 No. @ Tk. 91.15 each = Tk. 91.15
(iv) Plug 1 No. @ Tk. 60.91 each = Tk. 60.91
(v) Reducer 1 No. @ Tk. 105.56 each = Tk. 105.56
(vi) Socket 1 No. @ Tk. 97.92 each = Tk. 97.92
(c) Jointing & fixing materials
(i) Teflon tape 8.2 gm. @ Tk. 1.82 Per gm. = Tk. 14.92
(ii) Clamp (F.I. bar) 2 Nos. @ Tk. 27.33 each = Tk. 54.66
(iii) Rowel plug & screw 4 Nos. @ Tk. 8.56 each = Tk. 34.24
(iv) Scaffolding 20 rft. @ Tk. 2.26 Per rft. = Tk. 45.20
(d) Labour:
(i) Plumber 0.5 No. @ Tk. 440.00 each = Tk. 220.00
(ii) Skilled labour 1 No. @ Tk. 303.00 each = Tk. 303.00
(iii) Ordinary labour 1 No. @ Tk. 245.00 each = Tk. 245.00
Total = Tk. 5,496.76
Profit 10.00% = Tk. 549.68
Overhead 3.50% = Tk. 192.39
= Tk. 6,238.83
Add VAT with adjustment factor 1.0582 5.50% = Tk. 363.11
Grand total = Tk. 6,601.94
Rate per rft. = Tk. 330.10
Rate per rm. = Tk. 1,083.06
26.38.7 62 mm dia G.I pipe: connection including nipple, elbow, reducers, plug, Tee etc. complete.
Considering 20 rft. long one pipe
(a) 62 mm dia G.I. pipe: 20 rft. @ Tk. 277.79 Per rft. = Tk. 5,555.80
(b) Fittings:
(i) Elbow 1 No. @ Tk. 196.98 each = Tk. 196.98
(ii) Tee 1 No. @ Tk. 223.18 each = Tk. 223.18
(iii) Nipple 1 No. @ Tk. 155.88 each = Tk. 155.88
(iv) Plug 1 No. @ Tk. 91.75 each = Tk. 91.75
(v) Reducer 1 No. @ Tk. 144.45 each = Tk. 144.45
(vi) Socket 1 No. @ Tk. 133.32 each = Tk. 133.32
(c) Jointing & fixing materials
(i) Teflon tape 10.5 gm. @ Tk. 1.82 Per gm. = Tk. 19.11
(ii) Clamp (F.I. bar) 2 Nos. @ Tk. 27.33 each = Tk. 54.66
(iii) Rowel plug & screw 4 Nos. @ Tk. 8.56 each = Tk. 34.24
(iv) Scaffolding 20 rft. @ Tk. 2.26 Per rft. = Tk. 45.20
(d) Labour:
(i) Plumber 0.5 No. @ Tk. 440.00 each = Tk. 220.00
(ii) Skilled labour 1.5 Nos. @ Tk. 303.00 each = Tk. 454.50
(iii) Ordinary labour 2 Nos. @ Tk. 245.00 each = Tk. 490.00
Total = Tk. 7,819.07
Profit 10.00% = Tk. 781.91
Overhead 3.50% = Tk. 273.67
= Tk. 8,874.65
Add VAT with adjustment factor 1.0582 5.50% = Tk. 516.51
Grand total = Tk. 9,391.16
Rate per rft. = Tk. 469.56
Rate per rm. = Tk. 1,540.63
Say, Tk. 1,541 .00 Per rm
26.38.8 75 mm dia G.I pipe: connection including nipple, elbow, reducers, plug, Tee etc. complete.
Considering 20 rft. long one pipe
(a) 75 mm dia G.I. pipe: 20 rft. @ Tk. 330.99 Per rft. = Tk. 6,619.80
(b) Fittings:
(i) Elbow 1 No. @ Tk. 352.01 each = Tk. 352.01
(ii) Tee 1 No. @ Tk. 400.01 each = Tk. 400.01
(iii) Nipple 1 No. @ Tk. 239.50 each = Tk. 239.50
(iv) Plug 1 No. @ Tk. 156.54 each = Tk. 156.54
(v) Reducer 1 No. @ Tk. 216.85 each = Tk. 216.85
(vi) Socket 1 No. @ Tk. 194.56 each = Tk. 194.56
(c) Jointing & fixing materials
(i) Teflon tape 12.5 gm. @ Tk. 1.82 Per gm. = Tk. 22.75
(ii) Clamp (F.I. bar) 2 Nos. @ Tk. 36.44 each = Tk. 72.88
(iii) Rowel plug & screw 4 Nos. @ Tk. 11.41 each = Tk. 45.64
(iv) Scaffolding 20 rft. @ Tk. 2.26 Per rft. = Tk. 45.20
(d) Labour:
(i) Plumber 0.75 No. @ Tk. 440.00 each = Tk. 330.00
(ii) Skilled labour 1.5 Nos. @ Tk. 303.00 each = Tk. 454.50
(iii) Ordinary labour 2 Nos. @ Tk. 245.00 each = Tk. 490.00
Total = Tk. 9,640.24
Profit 10.00% = Tk. 964.02
Overhead 3.50% = Tk. 337.41
= Tk. 10,941.67
Add VAT with adjustment factor 1.0582 5.50% = Tk. 636.82
Grand total = Tk. 11,578.49
Rate per rft. = Tk. 578.92
Rate per rm. = Tk. 1,899.44
Say, Tk. 1,899 .00 Per rm
26.38.9 100 mm dia G.I pipe: connection including nipple, elbow, reducers, plug, Tee etc. complete.
Analysis of PWD SoR 2014 for Civil Works 432
The costing is based on one distribution line from upper tank to 4th & 4th floor toilet of a 5 storied building
(a) 19 mm dia uPVC pipe 70 rft. @ Tk. 23.30 Per rft. = Tk. 1,631.00
(b) Fittings:
(i) 19 mm uPVC plain Tee 5 Nos. @ Tk. 25.61 each = Tk. 128.05
(ii) 19 mm uPVC plain elbow 10 Nos. @ Tk. 20.90 each = Tk. 209.00
(iii) 19 mm uPVC plain socket 4 Nos. @ Tk. 15.18 each = Tk. 60.72
(iv) 19 x 12 mm uPVC round Tee 5 Nos. @ Tk. 28.38 each = Tk. 141.90
(v) 19 x 12 mm uPVC round elbow 10 Nos. @ Tk. 30.64 each = Tk. 306.40
(c) Jointing & fixing materials
(i) Solvent cement 50 gm. @ Tk. 1.63 Per gm. = Tk. 81.50
(d) Labour:
(i) Plumber 1 No. @ Tk. 440.00 each = Tk. 440.00
(ii) Skilled labour 1 No. @ Tk. 303.00 each = Tk. 303.00
(iii) Labour 1 No. @ Tk. 245.00 each = Tk. 245.00
Total = Tk. 3,546.57
Profit 10.00% = Tk. 354.66
Overhead 3.50% = Tk. 124.13
= Tk. 4,025.36
Add VAT with adjustment factor 1.0582 5.50% = Tk. 234.28
Grand total = Tk. 4,259.64
Rate per rft. = Tk. 60.85
Rate per rm. = Tk. 199.65
(d) Labour:
(i) Plumber 0.25 No. @ Tk. 440.00 each = Tk. 110.00
(ii) Skilled labour 0.5 No. @ Tk. 303.00 each = Tk. 151.50
Total = Tk. 1,407.05
Profit 10.00% = Tk. 140.71
Overhead 3.50% = Tk. 49.25
= Tk. 1,597.01
Add VAT with adjustment factor 1.0582 5.50% = Tk. 92.95
Grand total = Tk. 1,689.96
Rate per rft. = Tk. 84.50
Rate per rm. = Tk. 277.24
(i) Solvent cement 50 gm. @ Tk. 1.63 Per gm. = Tk. 81.50
(d) Labour:
(i) Plumber 1 No. @ Tk. 440.00 each = Tk. 440.00
(ii) Skilled labour 1 No. @ Tk. 303.00 each = Tk. 303.00
(iii) Labour 1 No. @ Tk. 245.00 each = Tk. 245.00
Total = Tk. 6,112.18
Profit 10.00% = Tk. 611.22
Overhead 3.50% = Tk. 213.93
= Tk. 6,937.33
Add VAT with adjustment factor 1.0582 5.50% = Tk. 403.76
Grand total = Tk. 7,341.09
Rate per rft. = Tk. 104.87
Rate per rm. = Tk. 344.08
(iv) 12 mm ABS plain socket 6 Nos. @ Tk. 24.46 each = Tk. 146.76
(v) 12 mm ABS thread plug 5 Nos. @ Tk. 270.82 each = Tk. 1,354.10
(c) Jointing & fixing materials
(i) Adhesive solution for jointing 400 gm. @ Tk. 3.09 Per gm. = Tk. 1,236.00
(d) Labour:
(i) Plumber 1 No. @ Tk. 440.00 each = Tk. 440.00
(ii) Skilled labour 2 Nos. @ Tk. 303.00 each = Tk. 606.00
(iii) Ordinary labour 2 Nos. @ Tk. 245.00 each = Tk. 490.00
Total = Tk. 12,367.76
Profit 10.00% = Tk. 1,236.78
Overhead 3.50% = Tk. 432.87
= Tk. 14,037.41
Add VAT with adjustment factor 1.0582 5.50% = Tk. 816.99
Grand total = Tk. 14,854.40
Rate per rft. = Tk. 123.79
Rate per rm. = Tk. 406.15
(ii) Sand (F.M. 1.2) 1 cft. @ Tk. 1,700.00 Per % cft. = Tk. 17.00
3. Excavation 175.16 cft. @ Tk. 2,271.58 Per % 0 cft. = Tk. 397.89
4. Bedding by sand (F.M. 1.2) 21.96 cft. @ Tk. 1,700.00 Per cft. = Tk. 373.32
5. Labour:
(a) Plumber 0.5 No. @ Tk. 440.00 each = Tk. 220.00
(b) Skilled labour 0.5 No. @ Tk. 303.00 each = Tk. 151.50
(c) Ordinary labour 2 Nos. @ Tk. 245.00 each = Tk. 490.00
Total = Tk. 10,114.63
Profit 10.00% = Tk. 1,011.46
Overhead 3.50% = Tk. 354.01
= Tk. 11,480.10
Add VAT with adjustment factor 1.0582 5.50% = Tk. 668.15
Grand total = Tk. 12,148.25
Rate per rm. = Tk. 2,212.80
26.46.4 uPVC waste pipe 280 mm dia wall thickness 6.9 mm - 8.6 mm for underground laying.
Considering 20 rft. long one pipe
(a) 280 mm uPVC pipe: 20 rft. @ Tk. 525.55 Per rft. = Tk. 10,511.00
(b) Jointing materials
(i) Solvent cement 330 gm @ Tk. 1.63 Per gm. = Tk. 537.90
(c) Excavation 87.5 cft. @ Tk. 2,271.58 Per % 0 cft. = Tk. 198.76
(d) Bedding by sand (F.M. 0.8) 52.5 cft. @ Tk. 1,419.46 Per cft. = Tk. 745.22
(e) Labour:
(i) Plumber 0.25 No. @ Tk. 440.00 each = Tk. 110.00
(ii) Skilled labour 0.5 No. @ Tk. 303.00 each = Tk. 151.50
(iii) Ordinary labour 1 No. @ Tk. 245.00 each = Tk. 245.00
Total = Tk. 12,499.38
Profit 10.00% = Tk. 1,249.94
Overhead 3.50% = Tk. 437.48
= Tk. 14,186.80
Add VAT with adjustment factor 1.0582 5.50% = Tk. 825.69
Grand total = Tk. 15,012.49
Rate per rft. = Tk. 750.62
Rate Per rm. = Tk. 2,462.78
Say, Tk. 2,463 .00 Per rm
26.46.5 uPVC waste pipe 315 mm dia wall thickness 7.7 mm - 9.7 mm for underground laying
Considering 20 rft. long one pipe
(a) 315 mm uPVC pipe: 20 rft. @ Tk. 755.23 Per rft. = Tk. 15,104.60
(b) Jointing materials
(i) Solvent cement 330 gm @ Tk. 1.63 Per gm. = Tk. 537.90
(c) Excavation 87.5 cft. @ Tk. 2,271.58 Per % 0 cft. = Tk. 198.76
(d) Bedding by sand (F.M. 0.8) 52.5 cft. @ Tk. 1,419.46 Per cft. = Tk. 745.22
(e) Labour:
(i) Plumber 0.25 No. @ Tk. 440.00 each = Tk. 110.00
(ii) Skilled labour 0.5 No. @ Tk. 303.00 each = Tk. 151.50
(iii) Ordinary labour 1 No. @ Tk. 245.00 each = Tk. 245.00
Total = Tk. 17,092.98
Profit 10.00% = Tk. 1,709.30
Overhead 3.50% = Tk. 598.25
= Tk. 19,400.53
Analysis of PWD SoR 2014 for Civil Works 447
(iii) Ordinary labour 0.07 No. @ Tk. 245.00 each = Tk. 17.15
Total = Tk. 513.93
Profit 10.00% = Tk. 51.39
Overhead 3.50% = Tk. 17.99
= Tk. 583.31
Add VAT with adjustment factor 1.0582 5.50% = Tk. 33.95
Grand total = Tk. 617.26
Rate per No. = Tk. 617.26
(iii) Ordinary labour 0.15 No. @ Tk. 245.00 each = Tk. 36.75
Total = Tk. 1,357.64
Profit 10.00% = Tk. 135.76
Overhead 3.50% = Tk. 47.52
= Tk. 1,540.92
Add VAT with adjustment factor 1.0582 5.50% = Tk. 89.68
Grand total = Tk. 1,630.60
Rate per No. = Tk. 1,630.60
(iii) Ordinary labour 0.225 No. @ Tk. 245.00 each = Tk. 55.13
Total = Tk. 5,970.93
Profit 10.00% = Tk. 597.09
Overhead 3.50% = Tk. 208.98
= Tk. 6,777.00
Add VAT with adjustment factor 1.0582 5.50% = Tk. 394.43
Grand total = Tk. 7,171.43
Rate per No. = Tk. 7,171.43
(ii) Skilled labour 0.09 No. @ Tk. 303.00 each = Tk. 27.27
(iii) Ordinary labour 0.07 No. @ Tk. 245.00 each = Tk. 17.15
Total = Tk. 627.03
Profit 10.00% = Tk. 62.70
Overhead 3.50% = Tk. 21.95
= Tk. 711.68
Add VAT with adjustment factor 1.0582 5.50% = Tk. 41.42
Grand total = Tk. 753.10
Rate per No. = Tk. 753.10
(ii) Skilled labour 0.12 No. @ Tk. 303.00 each = Tk. 36.36
(iii) Ordinary labour 0.15 No. @ Tk. 245.00 each = Tk. 36.75
Total = Tk. 1,682.22
Profit 10.00% = Tk. 168.22
Overhead 3.50% = Tk. 58.88
= Tk. 1,909.32
Add VAT with adjustment factor 1.0582 5.50% = Tk. 111.12
Grand total = Tk. 2,020.44
Rate per No. = Tk. 2,020.44
(ii) Skilled labour 0.09 No. @ Tk. 303.00 each = Tk. 27.27
(iii) Ordinary labour 0.07 No. @ Tk. 245.00 each = Tk. 17.15
Total = Tk. 513.93
Profit 10.00% = Tk. 51.39
Overhead 3.50% = Tk. 17.99
= Tk. 583.31
Add VAT with adjustment factor 1.0582 5.50% = Tk. 33.95
Grand total = Tk. 617.26
Rate per No. = Tk. 617.26
(iii) Ordinary labour 0.15 No. @ Tk. 245.00 each = Tk. 36.75
Total = Tk. 1,357.64
Profit 10.00% = Tk. 135.76
Overhead 3.50% = Tk. 47.52
= Tk. 1,540.92
Add VAT with adjustment factor 1.0582 5.50% = Tk. 89.68
Grand total = Tk. 1,630.60
Rate per No. = Tk. 1,630.60
3. Labour:
(a) Plumber 0.03 No. @ Tk. 440.00 each = Tk. 13.20
(b) Skilled labour 0.06 No. @ Tk. 303.00 each = Tk. 18.18
(c) Ordinary labour 0.124 No. @ Tk. 245.00 each = Tk. 30.38
Total = Tk. 923.65
Profit 10.00% = Tk. 92.37
Overhead 3.50% = Tk. 32.33
= Tk. 1,048.35
Add VAT with adjustment factor 1.0582 5.50% = Tk. 61.02
Grand total = Tk. 1,109.37
Rate per No. = Tk. 1,109.37
(ii) Skilled labour 0.07 No. @ Tk. 303.00 each = Tk. 21.21
(iii) Ordinary labour 0.162 No. @ Tk. 245.00 each = Tk. 39.69
Total = Tk. 808.69
Profit 10.00% = Tk. 80.87
Overhead 3.50% = Tk. 28.30
= Tk. 917.86
Add VAT with adjustment factor 1.0582 5.50% = Tk. 53.42
Grand total = Tk. 971.28
Rate per No. = Tk. 971.28
special quality stop cock 1 No. @ Tk. 739.70 each = Tk. 739.70
(b) Fitting-fixing materials
(i) Teflon tape 0.53 rft. @ Tk. 1.82 Per rft. = Tk. 0.96
(c) Labour:
(i) Plumber 0.0125 No. @ Tk. 440.00 each = Tk. 5.50
(ii) Skilled labour 0.025 No. @ Tk. 303.00 each = Tk. 7.58
(iii) Ordinary labour 0.048 No. @ Tk. 245.00 each = Tk. 11.76
Total = Tk. 765.50
Profit 10.00% = Tk. 76.55
Overhead 3.50% = Tk. 26.79
= Tk. 868.84
Add VAT with adjustment factor 1.0582 5.50% = Tk. 50.57
Grand total = Tk. 919.41
Rate per No. = Tk. 919.41
(a) Stop cock concealed (heavy) 1 No. @ Tk. 952.15 each = Tk. 952.15
(b) Fitting-fixing materials
(i) Teflon tape 0.53 rft. @ Tk. 1.82 Per rft. = Tk. 0.96
(c) Labour:
(i) Plumber 0.0125 No. @ Tk. 440.00 each = Tk. 5.50
(ii) Skilled labour 0.025 No. @ Tk. 303.00 each = Tk. 7.58
(iii) Ordinary labour 0.048 No. @ Tk. 245.00 each = Tk. 11.76
Total = Tk. 977.95
Profit 10.00% = Tk. 97.80
Overhead 3.50% = Tk. 34.23
= Tk. 1,109.98
Add VAT with adjustment factor 1.0582 5.50% = Tk. 64.60
Grand total = Tk. 1,174.58
Rate per No. = Tk. 1,174.58
type angle stop cock 1 No. @ Tk. 636.47 each = Tk. 636.47
(b) Fitting-fixing materials
(i) Teflon tape 0.53 rft. @ Tk. 1.82 Per rft. = Tk. 0.96
(c) Labour:
(i) Plumber 0.0125 No. @ Tk. 440.00 each = Tk. 5.50
(ii) Skilled labour 0.025 No. @ Tk. 303.00 each = Tk. 7.58
(iii) Ordinary labour 0.048 No. @ Tk. 245.00 each = Tk. 11.76
Total = Tk. 662.27
Profit 10.00% = Tk. 66.23
Overhead 3.50% = Tk. 23.18
= Tk. 751.68
Add VAT with adjustment factor 1.0582 5.50% = Tk. 43.75
Grand total = Tk. 795.43
Rate per No. = Tk. 795.43
type angle stop cock 1 No. @ Tk. 766.53 each = Tk. 766.53
(b) Fitting-fixing materials
(i) Teflon tape 0.53 rft. @ Tk. 1.82 Per rft. = Tk. 0.96
(c) Labour:
(i) Plumber 0.0125 No. @ Tk. 440.00 each = Tk. 5.50
(ii) Skilled labour 0.025 No. @ Tk. 303.00 each = Tk. 7.58
(iii) Ordinary labour 0.048 No. @ Tk. 245.00 each = Tk. 11.76
Total = Tk. 792.33
Profit 10.00% = Tk. 79.23
Overhead 3.50% = Tk. 27.73
= Tk. 899.29
Add VAT with adjustment factor 1.0582 5.50% = Tk. 52.34
Grand total = Tk. 951.63
Rate per No. = Tk. 951.63
Say, Tk. 952 .00 each
Item No.- 26.64
Groove cutting in brick work, RCC floor etc. and cement mortaring after laying pipe
26.64.1 Groove size: 40 x 40 mm (for laying 12 to 20 mm dia pipe)
Considering 3 meter long groove
(a) Labour cutting and filling groove
(i) Plumber 0.06 No. @ Tk. 440.00 each = Tk. 26.40
(ii) Skilled labour 0.12 No. @ Tk. 303.00 each = Tk. 36.36
(iii) Ordinary labour 0.248 No. @ Tk. 245.00 each = Tk. 60.76
(b) Cement mortar (1:4)
(i) Cement 0.024 bag @ Tk. 440.00 Per bag = Tk. 10.56
(ii) Sand (F.M. 1.2) 0.12 cft. @ Tk. 1,700.00 Per % cft. = Tk. 2.04
Total = Tk. 123.52
Profit 10.00% = Tk. 12.35
Overhead 3.50% = Tk. 4.32
= Tk. 140.19
Add VAT with adjustment factor 1.0582 5.50% = Tk. 8.16
Grand total = Tk. 148.35
Rate per rm. = Tk. 49.45
26.68.2 Food-grade plastic internal mini water tank for the use in kitchen, bathroom & toilet for
emergency storage and supply of water: 300 liter capacity
Considering 1 No. of fixture
(a) 300 literplastic water tank 1 No. @ Tk. 3,690.00 each = Tk. 3,690.00
(b) Carrying up to site L.S. = Tk. 183.75
(c) Fitting-fixing materials
(i) Teflon tape 4.2 rft. @ Tk. 1.82 Per rft. = Tk. 7.64
(ii) 3/4" dia ball cock 1 No. @ Tk. 231.50 each = Tk. 231.50
(iii) Nipple with jam-nuts 1 No. @ Tk. 122.37 each = Tk. 122.37
(d) Labour for lifting, installation & connecting pipes
(i) Plumber 1 No. @ Tk. 440.00 each = Tk. 440.00
(ii) Skilled labour 1 No. @ Tk. 303.00 each = Tk. 303.00
Total = Tk. 4,978.26
Analysis of PWD SoR 2014 for Civil Works 477
26.68.3 Food-grade plastic internal mini water tank for the use in kitchen, bathroom & toilet for
emergency storage and supply of water: 500 liter capacity
Considering 1 No. of fixture
(a) 500 liter plastic water tank 1 No. @ Tk. 5,000.00 each = Tk. 5,000.00
(b) Carrying up to site L.S. = Tk. 458.15
(c) Fitting-fixing materials
(i) Teflon tape 4.2 rft. @ Tk. 1.82 Per rft. = Tk. 7.64
(ii) 3/4" dia ball cock 1 No. @ Tk. 231.50 each = Tk. 231.50
(iii) Nipple with jam-nuts 1 No. @ Tk. 122.37 each = Tk. 122.37
(d) Labour for lifting, installation & connecting pipes
(i) Plumber 1 No. @ Tk. 440.00 each = Tk. 440.00
(ii) Skilled labour 1 No. @ Tk. 303.00 each = Tk. 303.00
Total = Tk. 6,562.66
Profit 10.00% = Tk. 656.27
Overhead 3.50% = Tk. 229.69
= Tk. 7,448.62
Add VAT with adjustment factor 1.0582 5.50% = Tk. 433.52
Grand total = Tk. 7,882.14
Rate per No. = Tk. 7,882.14
26.69.2 Food-grade foreign made stainless steel water tank: 1000 liter capacity
Considering 1 No. of fixture
(a) 1000 liter stainless steel water tank 1 No. @ Tk. 14,036.63 each = Tk. 14,036.63
(b) Carrying up to site L.S. = Tk. 183.75
(c) Ffitting-fixing materials
(i) 1/2" ball cock 1 No. @ Tk. 231.50 Per rft. = Tk. 231.50
(ii) 1/2" dia G.I. pipe with jum-nuts 1 No. @ Tk. 80.42 each = Tk. 80.42
(iii) Other small fittings in/c out-let pipe & flange etc. L.S. = Tk. 245.00
(d) Labour for lifting, installation & connecting pipes
(i) Plumber 1 No. @ Tk. 440.00 each = Tk. 440.00
(ii) Skilled labour 2 Nos. @ Tk. 303.00 each = Tk. 606.00
Total = Tk. 15,823.30
Profit 10.00% = Tk. 1,582.33
Overhead 3.50% = Tk. 553.82
= Tk. 17,959.45
Add VAT with adjustment factor 1.0582 5.50% = Tk. 1,045.26
Grand total = Tk. 19,004.71
Rate per No. = Tk. 19,004.71
26.69.3 Food-grade foreign made stainless steel water tank: 2000 liter capacity
Considering 1 No. of fixture
(a) 2000 liter stainless steel water tank 1 No. @ Tk. 24,056.59 each = Tk. 24,056.59
(b) Carrying L.S. = Tk. 367.50
(c) Fitting-fixing materials
(i) 1/2" ball cock 1 No. @ Tk. 231.50 Per rft. = Tk. 231.50
(ii) 1/2" dia G.I. pipe with jum-nuts 1 No. @ Tk. 80.42 each = Tk. 80.42
(iii) Other small fittings in/c out-let pipe & flange etc. L.S. = Tk. 367.50
(d) Labour for lifting, installation & connecting pipes
(i) Plumber 1.5 No. @ Tk. 440.00 each = Tk. 660.00
(ii) Skilled labour 3 Nos. @ Tk. 303.00 each = Tk. 909.00
Total = Tk. 26,672.51
Profit 10.00% = Tk. 2,667.25
Overhead 3.50% = Tk. 933.54
= Tk. 30,273.30
Add VAT with adjustment factor 1.0582 5.50% = Tk. 1,761.94
Grand total = Tk. 32,035.24
Rate per No. = Tk. 32,035.24
26.69.4 Food-grade foreign made stainless steel water tank: 4000 liter capacity
Considering 1 No. of fixture
(a) 4000 liter stainless steel tank 1 No. @ Tk. 49,191.06 each = Tk. 49,191.06
(b) Carrying up to site L.S. = Tk. 612.50
(c) Fitting-fixing materials
(i) 1/2" ball cock 1 No. @ Tk. 231.50 Per rft. = Tk. 231.50
(ii) 1/2" dia G.I. pipe with jum-nuts 1 No. @ Tk. 80.42 each = Tk. 80.42
(iii) Other small fittings in/c out-let pipe & flange etc. L.S. = Tk. 490.00
(d) Labour for lifting, installation & connecting pipes
(i) Plumber 2 No. @ Tk. 440.00 each = Tk. 880.00
(ii) Skilled labour 4 Nos. @ Tk. 303.00 each = Tk. 1,212.00
Total = Tk. 52,697.48
Profit 10.00% = Tk. 5,269.75
Overhead 3.50% = Tk. 1,844.41
= Tk. 59,811.64
Analysis of PWD SoR 2014 for Civil Works 479
26.69.5 Food-grade foreign made stainless steel water tank: 6000 liter capacity
Considering 1 No. of fixture
(a) 6000 liter stainless steel water tank 1 No. @ Tk. 53,481.79 each = Tk. 53,481.79
(b) Carrying up to site L.S. = Tk. 735.00
(c) Fitting-fixing materials
(i) 1/2" ball cock 1 No. @ Tk. 231.50 Per rft. = Tk. 231.50
(ii) Over-flow 1/2" dia
(iii) G.I. pipe with jum-nuts 1 No. @ Tk. 80.42 each = Tk. 80.42
(iv) Other small fittings in/c out-let pipe & flange etc. L.S. = Tk. 612.50
(d) Labour for lifting, installation & connecting pipes
(i) Plumber 2 No. @ Tk. 440.00 each = Tk. 880.00
(ii) Skilled labour 4 Nos. @ Tk. 303.00 each = Tk. 1,212.00
Total = Tk. 57,233.21
Profit 10.00% = Tk. 5,723.32
Overhead 3.50% = Tk. 2,003.16
= Tk. 64,959.69
Add VAT with adjustment factor 1.0582 5.50% = Tk. 3,780.72
Grand total = Tk. 68,740.41
Rate per No. = Tk. 68,740.41
26.75.2 Inspection pit of internal size: 525 x 525 mm & depth 675 to 825 mm (av. 750 mm)
for single 9" dia size RCC or 300 mm plastic/PVC pipes
Considering 1 No. pit
1. Earth-work:
1 x 3-7" x 3'-7" x 3'-0"= 38.45 cft. @ Tk. 2,271.58 Per % 0 cft. = Tk. 87.34
2. Brick-flat soling:
1 x 3'-5" x 3'-5"= 11.7 sft. @ Tk. 2,744.25 Per % sft. = Tk. 321.08
3. C.C. (1:3:6) on soling:
1 x 3'-5" x 3'-5" x 0'-3"= 2.92 cft. @ Tk. 14,713.64 Per % cft. = Tk. 429.64
4. C.C. (1:3:6) for invert:
1 x 1'-9" x 1'-9" x 0'-2"= 0.51 cft. @ Tk. 14,713.64 Per % cft. = Tk. 75.04
5. Brick-work (1:6):
2 x (3'-5" + 1'-9") x 2'-6" x 0'-10"= 21.46 cft. @ Tk. 12,557.68 Per % cft. = Tk. 2,694.88
6. 12 mm plaster with n.c.f.:
4 x (1'-9" x 2'-6") + 1'-9" x 1'-9"= 20.56 sft. @ Tk. 1,906.00 Per % sft. = Tk. 391.87
7. Extra labour for making invert & side back-filling:
a) Plumber 0.125 No. @ Tk. 440.00 each = Tk. 55.00
b) Skilled labour 0.2 No. @ Tk. 303.00 each = Tk. 60.60
c) Ordinary labour 0.235 No. @ Tk. 245.00 each = Tk. 57.58
Total = Tk. 4,173.03
Profit 10.00% = Tk. 417.30
Overhead 3.50% = Tk. 146.06
= Tk. 4,736.39
Add VAT with adjustment factor 1.0582 5.50% = Tk. 275.66
Grand total = Tk. 5,012.05
Rate per No. = Tk. 5,012.05
Analysis of PWD SoR 2014 for Civil Works 482
26.75.3 Inspection pit of internal size: 600 x 600 mm & depth 750 to 900 mm (av. 825 mm)
for single 12" dia size RCC or 375 mm plastic/PVC pipes
Considering 1 No. pit
1. Earth-work:
1 x 3'-11" x 3'-11" x 3'-3"= 49.94 cft. @ Tk. 2,271.58 Per % 0 cft. = Tk. 113.44
2. Brick-flat soling:
1 x 3'-8" x 3'-8"= 13.47 sft. @ Tk. 2,744.25 Per % sft. = Tk. 369.65
3. C.C. (1:3:6) on soling:
1 x 3'-8" x 3'-8" x 0'-3"= 3.37 cft. @ Tk. 14,713.64 Per % cft. = Tk. 495.85
4. C.C. (1:3:6) for invert:
1 x 2'-0" x 2'-0" x 0'-2"= 0.67 cft. @ Tk. 14,713.64 Per % cft. = Tk. 98.58
5. Brick-work (1:6):
2 x (3'-8" + 2'-0") x 2'-9" x 0'-10"=
31.19 cft. @ Tk. 12,557.68 Per % cft. = Tk. 3,916.74
6. 12 mm plaster with n.c.f.:
4 x (2'-0" x 2'-9") + 2'-6" x 2'-6"= 28.25 sft. @ Tk. 1,906.00 Per % sft. = Tk. 538.45
7. Extra labour for making invert & side back-filling:
(a) Plumber 0.14 No. @ Tk. 440.00 each = Tk. 61.60
(b) Skilled labour 0.23 No. @ Tk. 303.00 each = Tk. 69.69
(c) Ordinary labour 0.27 No. @ Tk. 245.00 each = Tk. 66.15
Total = Tk. 5,730.15
Profit 10.00% = Tk. 573.02
Overhead 3.50% = Tk. 200.56
= Tk. 6,503.73
Add VAT with adjustment factor 1.0582 5.50% = Tk. 378.52
Grand total = Tk. 6,882.25
Rate per No. = Tk. 6,882.25
26.75.4 Master-pit of Size: 600 x 500 mm & average depth 750 mm for Septic tank.
Considering 1 No. pit
1. Earth-work:
1 x 2'-3" x 4'-0" x 3'-0"= 27.96 cft. @ Tk. 2,271.58 Per % 0 cft. = Tk. 63.51
2. Brick-flat soling:
1 x 3'-8" x 2'-6"= 9.175 sft. @ Tk. 2,744.25 Per % sft. = Tk. 251.78
3. C.C. (1:3:6) on soling:
1 x 1'-6" x 2'-0" x 0'-3"= 0.94 cft. @ Tk. 14,713.64 Per % cft. = Tk. 138.31
4. C.C. (1:3:6) for channel making:
1 x 1'-6" x 2'-6" x 0'-4"= 1.24 cft. @ Tk. 14,713.64 Per % cft. = Tk. 182.45
5. Brick-work (1:6):
2 x 1'-8" x 2'-2" x 0'-10"= 6.02 cft.
1 x 3' - 8" x 2' - 2" x 10" = 6.61 cft.
12.63 cft. @ Tk. 12,557.68 Per % cft. = Tk. 1,586.03
6. 12 mm plaster with n.c.f.:
(2' - 0" + 1' - 8" + 1' - 8") x 2' - 2" = 11.5661 sft.
(2' - 6" + 2' - 6" + 3' - 8") x 1' - 0" = 8.67 sft.
1' - 6" x 2' - 6" = 3.75 sft.
23.99 sft. @ Tk. 1,906.00 Per % sft. = Tk. 457.25
7. Extra labour for making channel & back-fill to side:
(a) Plumber 0.125 No. @ Tk. 440.00 each = Tk. 55.00
(b) Skilled labour 0.125 No. @ Tk. 303.00 each = Tk. 37.88
(c) Ordinary labour 0.125 No. @ Tk. 245.00 each = Tk. 30.63
8. Reinforcement: 3/8" dia M.S. rod
4 x 2' -6" x 0.375 Ibs/rft. = 3.75 Ibs
Analysis of PWD SoR 2014 for Civil Works 483
4 x 3'-8" x 0'-3" + 3'-8" x 3'-8"= 17.14 sft. @ Tk. 1,906.00 Per % sft. = Tk. 326.69
4. Extra labour for placing pit cover
Ordinary labour 0.1 No. @ Tk. 245.00 each = Tk. 24.50
Total = Tk. 1,443.34
Profit 10.00% = Tk. 144.33
Overhead 3.50% = Tk. 50.52
= Tk. 1,638.19
Add VAT with adjustment factor 1.0582 5.50% = Tk. 95.34
Grand total = Tk. 1,733.53
Rate per No. = Tk. 1,733.53
26.77.2 1050 x 1050 x 75 mm size pit cover with 18" dia C.I. man-hole cover.
Considering 1 No. pit cover with man-hole cover
1. R.C.C. (1:2:4) for slab:
1 x (3'-5" x 3'-5"- 0.785 x 1'-6" x 1'-6") x 0'-3" =
2.48 cft. @ Tk. 17,255.06 Per % cft. = Tk. 427.93
2. 1% re-inforcement in/c fabrication 12.15 Ibs. @ Tk. 30.93 Per Ibs. = Tk. 375.80
3. 12 mm plaster with n.c.f.:
4 x (3'-5" x 0'-3" + 3'-5" x 3'-5" - 0.785 x 1'-6" x 1'-6") =
13.35 sft. @ Tk. 1,906.00 Per % sft. = Tk. 254.45
4. 18" dia water sealed heavy type C.I. man-hole cover with locking
arrangement in/c making holes. 1 No. @ Tk. 1,026.84 each = Tk. 1,026.84
5. Extra labour for placing pit cover
Ordinary labour 0.1 No. @ Tk. 245.00 each = Tk. 24.50
Total = Tk. 2,109.52
Profit 10.00% = Tk. 210.95
Overhead 3.50% = Tk. 73.83
= Tk. 2,394.30
Add VAT with adjustment factor 1.0582 5.50% = Tk. 139.35
Grand total = Tk. 2,533.65
Rate per No. = Tk. 2,533.65
Analysis of PWD SoR 2014 for Civil Works 485
26.77.3 1100 x 1100 x 75 mm size pit cover with 18" dia C.I. man-hole cover.
Considering 1 No. pit cover with man-hole cover
1. R.C.C. (1:2:4) for slab:
1 x (3'-8" x 3'-8"- 0.785 x 1'-6" x 1'-6") x 0'-3" =
2.93 cft. @ Tk. 17,255.06 Per % cft. = Tk. 505.57
2. 1% re-inforcement in/c fabrication 14.36 Ibs. @ Tk. 30.93 Per Ibs. = Tk. 444.15
3. 12 mm plaster with n.c.f.:
4 x (3'-8" x 0'-3" + 3'-8" x 3'-8" - 0.785 x 1'-6" x 1'-6") =
15.37 sft. @ Tk. 1,906.00 Per % sft. = Tk. 292.95
4. 18" dia water sealed heavy type C.I. man-hole cover with locking
arrangement in/c making holes. 1 No. @ Tk. 1,026.84 each = Tk. 1,026.84
5. Extra labour for placing pit cover
Ordinary labour 0.1 No. @ Tk. 245.00 each = Tk. 24.50
Total = Tk. 2,294.01
Profit 10.00% = Tk. 229.40
Overhead 3.50% = Tk. 80.29
= Tk. 2,603.70
Add VAT with adjustment factor 1.0582 5.50% = Tk. 151.54
Grand total = Tk. 2,755.24
Rate per No. = Tk. 2,755.24
26.78.2 520 x 525 mm and depth 675 - 825 mm, average 750 mm for single 225 mm dia RCC pipes and 400 mm
dia PVC pipe with pitcover and 450 mm dia C.I. Man-hole cover
Item No. 241/A2 + 242/B2 = Tk. 7,546
Say, Tk. 7,546 .00 each
26.78.3 600 x 600 mm and depth 750 - 900 mm, average 825 mm for single 300 mm dia RCC pipes and 400 mm
dia PVC pipe with pitcover and 450 mm dia C.I. Man-hole cover
Item No. 241/A3 + 242/B3 = Tk. 9,637.00
Say, Tk. 9,637 .00 each
1 x 24' - 8" x 8' - 6" x 4" = 69.20 cft. @ Tk. 17,255.06 Per % cft. = Tk. 11,940.50
7. Formwork 230.00 sft. @ Tk. 35.48 Per sft. = Tk. 8,160.40
8. Brick-work (1:6):
2 x 24'-8" x 2'-0" x 10" = 81.90 cft.
2 x 24'-8" x 1'-0" x 5" = 20.72 cft.
2 x (24'-8" + 6'-10") x 6'-8" x 10" 348.8 cft.
Total = 451.42 cft. @ Tk. 12,557.68 Per % cft. = Tk. 56,687.88
9. 5" thick brick-work (1:6)
6'-0" x 4'-5" = 26.52 sft.
6'-0" x 5'-6" = 33.00 sft.
59.52 sft. @ Tk. 6,175.43 Per % sft. = Tk. 3,675.62
10. 12 mm plaster with n.c.f.:
Floor: 1 x 22' - 2" x 6' - 0" = 133.02 sft.
Walls:2x(22'-2"+ 5'-11") x 6'-7.5" = 371.78 sft.
Tie: 1 x 6' - 0" x 2' - 7" = 15.48 sft.
Outside: 2x(24'-8"+ 8'-6")x1'-6" = 99.51 sft.
619.79 sft. @ Tk. 1,906.00 Per % sft. = Tk. 11,813.20
11. RCC Tees 2 Nos. @ Tk. 436.03 each = Tk. 872.06
12. 40 grade re-inforcement & fabrication 1212.00 Ibs. @ Tk. 30.93 Per Ibs. = Tk. 37,487.16
13. 18" dia water sealed heavy type C.I. man-hole cover with locking
arrangement in/c making holes. 3 Nos. @ Tk. 1,026.84 each = Tk. 3,080.52
14. Side filling, dressing, inside cleaning etc. L.S. = Tk. 1,225.00
Total = Tk. 196,307.67
Profit 10.00% = Tk. 19,630.77
Overhead 3.50% = Tk. 6,870.77
= Tk. 222,809.21
Add VAT with adjustment factor 1.0582 5.50% = Tk. 12,967.72
Grand total = Tk. 235,776.93
Rate per No. = Tk. 235,776.93
(excluding cost of reinforcement) 13.51 cft. @ Tk. 17,255.06 Per % cft. = Tk. 2,331.16
3. 10" Honeycomb brick-work (1:6) in cement mortar
(87.57% of solid b/work). 104.18 cft. @ Tk. 10,996.76 Per % cft. = Tk. 11,456.42
4. 10" solid brick-work (1:6) 107.66 cft. @ Tk. 12,557.68 Per % cft. = Tk. 13,519.60
5. R.C.C. (1:2:4) in curb well with 1.25% re-inforcement
(excluding cost of re-inforcement) 9.86 cft. @ Tk. 17,255.06 Per % cft. = Tk. 1,701.35
6. 40 grade reinforcement &
fabrication 1.25% 143.14 Ibs. @ Tk. 30.93 Per Ibs. = Tk. 4,427.32
7. 18" dia water sealed heavy type C.I. man-hole cover with locking
arrangement in/c making holes. 1 No. @ Tk. 1,026.84 each = Tk. 1,026.84
8. Supply and filling graded
khoa and sand. 251 cft. @ Tk. 81.05 Per cft. = Tk. 20,343.55
Total = Tk. 56,394.07
Profit 10.00% = Tk. 5,639.41
Overhead 3.50% = Tk. 1,973.79
= Tk. 64,007.27
Add VAT with adjustment factor 1.0582 5.50% = Tk. 3,725.29
Grand total = Tk. 67,732.56
Rate per No. = Tk. 67,732.56
(87.57% of solid b/work). 84.68 cft. @ Tk. 10,996.76 Per % cft. = Tk. 9,312.06
4. 10" solid brick-work (1:6) 87.45 cft. @ Tk. 12,557.68 Per % cft. = Tk. 10,981.69
5. R.C.C. (1:2:4) in curb well with 1.5% re-inforcement
(excluding cost of reinforcement) 6.92 cft. @ Tk. 17,255.06 Per % cft. = Tk. 1,194.05
6. 40 grade reinforcement &
fabrication 1.25% 109.64 Ibs. @ Tk. 30.93 Per Ibs. = Tk. 3,391.17
7. 18" dia water sealed heavy type C.I. man-hole cover with locking
arrangement in/c making holes. 1 No. @ Tk. 1,026.84 each = Tk. 1,026.84
8. Supply and filling graded
khoa and sand. 144.24 cft. @ Tk. 81.05 Per cft. = Tk. 11,690.65
Total = Tk. 40,683.69
Profit 10.00% = Tk. 4,068.37
Overhead 3.50% = Tk. 1,423.93
= Tk. 46,175.99
Add VAT with adjustment factor 1.0582 5.50% = Tk. 2,687.49
Grand total = Tk. 48,863.48
Rate per No. = Tk. 48,863.48
= Tk. 642.45
Add VAT with adjustment factor 1.0582 5.50% = Tk. 37.39
Grand total = Tk. 679.84
Rate per rm = Tk. 679.84
27.4.1.2 Development using 2 test tube-wells 150% = Say, Tk. 9,279 .00 LS
27.4.1.3 Development using 3 test tube-wells 200% = Say, Tk. 12,372 .00 LS
27.4.2.1 For 1 test tube-wells 115% Say, Tk. 35.57 Per meter
27.4.2.2 For 2 test tube-wells 115% Say, Tk. 53.35 Per meter
27.4.2.3 For 3 test tube-wells 115% Say, Tk. 71.14 Per meter
(1) Cost for furnishing design of tube-well considering 2 bore = Tk. 18,666.67
(2) Testing of water collected from 2 test bore = Tk. 10,920.00
(3) Sieve analysis for sand
from different layers 6 tests @ Tk. 1,123.00 Per test = Tk. 6,738.00
(3) Maintaining the bore holes and tools and plants etc. at site untill
satisfactory results are obtained from laboratory, filling and sealing
the bore holes 2 No. @ Tk. 4,000.00 Per test bore = Tk. 8,000.00
Tk. 44,324.67
Profit 10.00% = Tk. 4,432.47
Overhead 3.50% = Tk. 1,551.36
= Tk. 50,308.50
Add VAT with adjustment factor 1.0582 5.50% = Tk. 2,928.01
Grand total = Tk. 53,236.51
(1) Cost for furnishing design of tube-well considering 3 bore = Tk. 28,000.01
(2) Testing of water collected from 3 test bore = Tk. 16,380.00
(3) Sieve analysis for sand
from different layers 9 tests @ Tk. 1,123.00 Per test = Tk. 10,107.00
(3) Maintaining the bore holes and tools and plants etc. at site untill
satisfactory results are obtained from laboratory, filling and sealing
the bore holes 3 No. @ Tk. 4,000.00 Per test bore = Tk. 12,000.00
Tk. 66,487.01
Profit 10.00% = Tk. 6,648.70
Overhead 3.50% = Tk. 2,327.05
= Tk. 75,462.76
Add VAT with adjustment factor 1.0582 5.50% = Tk. 4,392.01
Grand total = Tk. 79,854.77
PRODUCTION WELL
27.13.2 Development of tube well for the depth beyond 200 m: = Tk. 28,256.80
27.21.2 Development of tube well for the depth beyond 200 m: = Tk. 34,067.52
Say, Tk. 34,068 .00 each
27.29.1 Development of tube well for depth up to 200 m. L.S. = Tk. 29,243.18
Profit 10.00% = Tk. 2,924.32
Overhead 3.50% = Tk. 1,023.51
= Tk. 33,191.01
Add VAT with adjustment factor 1.0582 5.50% = Tk. 1,931.75
Total = Tk. 35,122.76
Say, Tk. 35,123 .00 each
27.29.2 Development of tube well for the depth beyond 200 m: = Tk. 42,147.31
Analysis of PWD SoR 2014 for Civil Works 515
= Tk. 343.68
Add VAT with adjustment factor 1.0582 5.50% = Tk. 20.00
Grand total = Tk. 363.68
Rate each. = Tk. 363.68
27.37.1 Development of tube well for depth up to 200 m. L.S. = Tk. 34,814.71
Profit 10.00% = Tk. 3,481.47
Overhead 3.50% = Tk. 1,218.51
= Tk. 39,514.69
Add VAT with adjustment factor 1.0582 5.50% = Tk. 2,299.79
Total = Tk. 41,814.48
27.37.2 Development of tube well for the depth beyond 200 m: = Tk. 47,389.74
Say, Tk. 47,390 .00 each
(c) Local carriage, welding & other necessary cost L.S. = Tk. 294.00
Total = Tk. 54,341.78
Profit 10.00% = Tk. 5,434.18
Overhead 3.50% = Tk. 1,901.96
= Tk. 61,677.92
Add VAT with adjustment factor 1.0582 5.50% = Tk. 3,589.72
Grand total = Tk. 65,267.64
Rate per rm. = Tk. 10,699.61
27.45.2 Development of tube well for the depth beyond 200 m: = Tk. 47,389.74
= Tk. 4,086.29
Add VAT with adjustment factor 1.0582 5.50% = Tk. 237.83
Grand total = Tk. 4,324.12
Rate per rm. = Tk. 43.24
Considering 1 meter
(a) 400 mm dia 6 mm
thick M.S. housing pipe 1 meter @ Tk. 11,042.23 Per meter = Tk. 11,042.23
(b) Carriage of materials L.S. = Tk. 122.50
Total = Tk. 11,164.73
Profit 10.00% = Tk. 1,116.47
Overhead 3.50% = Tk. 390.77
= Tk. 12,671.97
Add VAT with adjustment factor 1.0582 5.50% = Tk. 737.52
Grand total = Tk. 13,409.49
Rate per rm. = Tk. 13,409.49
27.52.2 Development of tube well for the depth beyond 200 m: = Tk. 43,194.13
Say, Tk. 43,194 .00 each
Filling the bore hole around the well from top to the shrouding to G.L. as per specification
Considering 100 meter
(a) Foreman 1 No. @ Tk. 567.00 each = Tk. 567.00
(b) Skilled labour 9 No. @ Tk. 303.00 each = Tk. 2,727.00
(c) Local carriage, T & P L.S. = Tk. 306.25
Total = Tk. 3,600.25
Profit 10.00% = Tk. 360.03
Overhead 3.50% = Tk. 126.01
= Tk. 4,086.29
Add VAT with adjustment factor 1.0582 5.50% = Tk. 237.83
Grand total = Tk. 4,324.12
Rate per rm. = Tk. 43.24
27.59.2 Development of tube well for the depth beyond 200 m: = Tk. 25,282.21
Considering 1 No.
(a) 6 mm thick 150 mm
dia M.S. cap 1 No. @ Tk. 990.23 each = Tk. 990.23
(b) Carriage of materials L.S. = Tk. 16.33
Total = Tk. 1,006.56
Profit 10.00% = Tk. 100.66
Overhead 3.50% = Tk. 35.23
= Tk. 1,142.45
Add VAT with adjustment factor 1.0582 5.50% = Tk. 66.49
Grand total = Tk. 1,208.94
Rate each. = Tk. 1,208.94
= Tk. 44,694.85
Add VAT with adjustment factor 1.0582 5.50% = Tk. 2,601.28
Grand total = Tk. 47,296.13
Rate per rm. = Tk. 7,753.46
27.66.2 Development of tube well for the depth beyond 200 m: = Tk. 32,174.88
27.73.2 Development of tube well for the depth beyond 200 m: = Tk. 39,805.79
Say, Tk. 39,806 .00 each
Item No.- 27.74
Long term pumping test of the well by required capacity pump including drawdown and recovery
test etc. complete
Considering 72 hrs.
1. Hire charge of pump in/c
spare and maintenance 72 hrs @ Tk. 359.75 Per hour = Tk. 25,902.00
2. Fuel for pump:
@ 4.375 liter per hour 270 liter @ Tk. 83.81 Per liter = Tk. 22,628.70
3. Foreman: @ 1 No. per 8 hrs 9 Nos. @ Tk. 567.00 each = Tk. 5,103.00
4. Skilled labour 6 Nos. @ Tk. 303.00 each = Tk. 1,818.00
5. Local carriage, T & P L.S. = Tk. 857.50
Total = Tk. 56,309.20
Profit 10.00% = Tk. 5,630.92
Overhead 3.50% = Tk. 1,970.82
= Tk. 63,910.94
Add VAT with adjustment factor 1.0582 5.50% = Tk. 3,719.68
Grand total = Tk. 67,630.62
Rate per hour = Tk. 939.31
Supplying and sinking of 50 mm dia water grade uPVC pipe having wall thickness 2.5 mm to 3.00 mm
for tube well including fitting fixing.
Considering 1 rft.
(a) 50 mm dia uPVC pipe 1 rft. @ Tk. 78.32 Per rft. = Tk. 78.32
(b) Labour for sinking and other costs L.S. = Tk. 24.50
Total = Tk. 102.82
Profit 10.00% = Tk. 10.28
Overhead 3.50% = Tk. 3.60
= Tk. 116.70
Add VAT with adjustment factor 1.0582 5.50% = Tk. 6.79
Grand total = Tk. 123.49
Rate per rm. = Tk. 405.17
(g) Tie foot ball 1 No. @ Tk. 30.00 each = Tk. 30.00
(h) Tie planger 1 pair @ Tk. 59.84 Per pair = Tk. 59.84
((i) 3/8" dia socket 3 No. @ Tk. 15.33 each = Tk. 45.99
(j) 3/8" dia nut 4 No. @ Tk. 14.00 each = Tk. 56.00
(k) Solution (big size) 1 No. @ Tk. 283.00 each = Tk. 283.00
(l) Tape 2 No. @ Tk. 22.00 each = Tk. 44.00
Sub total (A) = Tk. 4,045.70
(B) Workshop charge for cutting M.S. rod in suitable
size threaded and necessary welding L.S = Tk. 490.00
(C) Labour cost
(a) Plumber 1 No. @ Tk. 440.00 each = Tk. 440.00
(b) Skilled labour 1 No. @ Tk. 303.00 each = Tk. 303.00
Sub total (C) = Tk. 300.00
Total (A+B+C) = Tk. 4,835.70
Profit 10.00% = Tk. 483.57
Overhead 3.50% = Tk. 169.25
= Tk. 5,488.52
Add VAT with adjustment factor 1.0582 5.50% = Tk. 319.44
Grand total = Tk. 5,807.96
Rate each. = Tk. 5,807.96
Installation of 50 PSI API 5L, Grade-B ERW M.S. Pipe line for supplying
Titas Gas 25 mm ND (33.40 mm O.D) M.S. pipe.
Considering 100 rft. of pipe line
(a) Materials:
(i) Cost of pipe 100 rft. @ Tk. 122.37 Per rft = Tk. 12,237.00
(ii) Cost of tape: 2" x 200'-0" 1.5 Roll @ Tk. 1,145.93 Per roll = Tk. 1,718.90
(iii) Cost of primer 0.65 liter @ Tk. 267.33 Per liter = Tk. 173.76
(b) Labour:
(i) Cutting trenches:
100'-0" x 1'-6" x 3'-0"= 450.00 cft. @ Tk. 2,271.58 Per % 0 cft. = Tk. 1,022.21
(ii) Laying and back-filling in/c levelling the top
surface with excavated earth 100 rft. @ Tk. 11.39 Per rft. = Tk. 1,139.00
(iii) Skilled labour for applying primer, wrapping the
pipe with tap in/c scrapping 100 rft. @ Tk. 7.58 Per rft. = Tk. 758.00
(iv) Carrying from Titas Gas store to work side in/c loading & unloading L.S. = Tk. 367.50
Total = Tk. 17,416.37
Incidental charges 10.00% = Tk. 1,741.64
Profit 10.00% = Tk. 1,741.64
Overhead 3.50% = Tk. 60.96
= Tk. 20,960.61
Add VAT with adjustment factor 1.0582 5.50% = Tk. 1,219.93
Grand total = Tk. 22,180.54
Rate per rft. = Tk. 221.81
Rate per rm = Tk. 727.76
Supplying different sizes Tee, Elbow, Reducer, Plug, Socket: 50 mm x 90o mm Elbow
Considering 1 No. elbow
(a) Elbow (as per Titas Gas rate) = Tk. 164.93
(b) Carrying charge L.S. = Tk. 12.25
Total = Tk. 177.18
Incidental charges 10.00% = Tk. 17.72
Profit 10.00% = Tk. 17.72
Overhead 3.50% = Tk. 0.62
= Tk. 213.24
Add VAT with adjustment factor 1.0582 5.50% = Tk. 12.41
Grand total = Tk. 225.65
= Tk. 4,570.17
Add VAT with adjustment factor 1.0582 5.50% = Tk. 265.99
Grand total = Tk. 4,836.16
(a) DURS BAN 20EC 25 liter @ Tk. 654.73 Per liter = Tk. 16,368.25
(b) Labour 1.50 Nos. @ Tk. 245.00 each = Tk. 367.50
(c) Skilled technician 0.25 No. @ Tk. 700.00 each = Tk. 175.00
(d) T & P and hand spray L.S. = Tk. 7.45
(e) Local carriage L.S. = Tk. 39.20
Total = Tk. 16,957.40
Profit 10.00% = Tk. 1,695.74
Overhead 3.50% = Tk. 593.51
= Tk. 19,246.65
Add VAT with adjustment factor 1.0582 5.50% = Tk. 1,120.17
Grand total = Tk. 20,366.82
Rate per sqm. = Tk. 203.67
from the existing finished F.L./G.L. inside and outside the building and applying the
emulsion of anti-termite chemicals DURSBAN 20EC to be mixed with water
at 1:19 ratio into the holes @ 25 ml per hole in/c mending good the damages.
Considering 100 holes
(a) DURS BAN 20EC 1.25 liter @ Tk. 654.73 Per liter = Tk. 818.41
(b) Labour for cutting holes 100 holes @ Tk. 12.25 Per hole = Tk. 1,225.00
(c) C.C. (1:2:4):
100 x 1/2 x 1/2 x 9"= 1.56 cft. @ Tk. 176.37 Per cft. = Tk. 275.14
(d) Labour for preparing & applying
(i) Skilled labour 2.00 Nos. @ Tk. 303.00 each = Tk. 606.00
(ii) Skilled technician 0.25 No. @ Tk. 700.00 each = Tk. 175.00
(e) T & P, sundries, drilling machine & sprayer L.S. = Tk. 39.72
(f) Local carriage L.S. = Tk. 78.40
Total = Tk. 3,217.67
Profit 10.00% = Tk. 321.77
Overhead 3.50% = Tk. 112.62
= Tk. 3,652.06
Add VAT with adjustment factor 1.0582 5.50% = Tk. 212.55
Grand total = Tk. 3,864.61
Rate per hole. = Tk. 38.65
= Tk. 1,392.87
Add VAT with adjustment factor 1.0582 5.50% = Tk. 81.07
Grand total = Tk. 1,473.94
Rate each.. = Tk. 1,473.94
(v) Transportation of block 116 Nos. @ Tk. 3.18 each = Tk. 368.88
(b) Labour
(i) Head mason 0.1 No. @ Tk. 493.00 each = Tk. 49.30
(ii) Mason 1 No. @ Tk. 389.00 each = Tk. 389.00
(iii) Ordinary Labour 2.5 Nos. @ Tk. 245.00 each = Tk. 612.50
(c) Scaffolding 25 sft. @ Tk. 7.20 Per sft. = Tk. 180.00
(d) Local carriage, curing & sundries etc LS. = Tk. 122.50
Total = Tk. 4,625.61
Profit 10.00% = Tk. 462.56
Overhead 3.50% = Tk. 161.90
= Tk. 5,250.07
Add VAT with adjustment factor 1.0582 5.50% = Tk. 305.56
Grand total = Tk. 5,555.63
Rate per sft. = Tk. 55.56
30.1.1 Ground floor Rate per sqm. = Tk. 598.05
30.1.2 Add for each addl. floor up to 5th floor (@ 0.75 No. lab. per % sft.) Per sqm = Tk. 24.82
30.1.3 Add for each addl floor for 6th floor to 9th floor (@ 1 No. lab. per % sft.) Per sqm = Tk. 33.10
30.1.4 Add for each addl floor for 10th floor and above (@ 1.25 Nos. lab. per % sft.) Per sqm = Tk. 41.37
30.2.2 Add for each addl. floor up to 5th floor (@ 0.75 No. lab. per % sft.) Per sqm = Tk. 24.82
30.2.3 Add for each addl floor for 6th floor to 9th floor (@ 1 No. lab. per % sft.) Per sqm = Tk. 33.10
30.2.4 Add for each addl floor for 10th floor and above (@ 1.25 Nos. lab. per % sft.) Per sqm = Tk. 41.37
30.3.2 Add for each addl. floor up to 5th floor (@ 0.75 No. lab. per % sft.) Per sqm = Tk. 24.82
30.3.3 Add for each addl floor for 6th floor to 9th floor (@ 1 No. lab. per % sft.) Per sqm = Tk. 33.10
30.3.4 Add for each addl floor for 10th floor and above (@ 1.25 Nos. lab. per % sft.) Per sqm = Tk. 41.37
30.4.2 Add for each addl. floor up to 5th floor (@ 0.75 No. lab. per % sft.) Per sqm = Tk. 24.82
30.4.3 Add for each addl floor for 6th floor to 9th floor (@ 1 No. lab. per % sft.) Per sqm = Tk. 33.10
30.4.4 Add for each addl floor for 10th floor and above (@ 1.25 Nos. lab. per % sft.) Per sqm = Tk. 41.37
30.5.2 Add for each addl. floor up to 5th floor (@ 1 lab. per % sft.) Per sqm = Tk. 33.10
30.5.3 Add for each addl floor for 6th floor to 9th floor (@ 1.25 No. lab. per % sft.) Per sqm = Tk. 41.37
30.5.4 Add for each addl floor for 10th floor and above (@ 1.5 Nos. lab. per % sft.) Per sqm = Tk. 49.65
30.6.2 Add for each addl. floor up to 5th floor (@ 1 lab. per % sft.) Per sqm = Tk. 33.10
30.6.3 Add for each addl floor for 6th floor to 9th floor (@ 1.25 No. lab. per % sft.) Per sqm = Tk. 41.37
30.6.4 Add for each addl floor for 10th floor and above (@ 1.5 Nos. lab. per % sft.) Per sqm = Tk. 49.65
30.7.2 Add for each addl. floor up to 5th floor (@ 1 lab. per % sft.) Per sqm = Tk. 33.10
30.7.3 Add for each addl floor for 6th floor to 9th floor (@ 1.25 No. lab. per % sft.) Per sqm = Tk. 41.37
30.7.4 Add for each addl floor for 10th floor and above (@ 1.5 Nos. lab. per % sft.) Per sqm = Tk. 49.65
(iii) Ordinary Labour 3.25 Nos. @ Tk. 245.00 each = Tk. 796.25
(c) Scaffolding 25 sft. @ Tk. 7.20 Per sft. = Tk. 180.00
(d) Local carriage, curing & sundries etc. LS. = Tk. 122.50
Total = Tk. 8,639.86
Profit 10.00% = Tk. 863.99
Overhead 3.50% = Tk. 302.40
= Tk. 9,806.25
Add VAT with adjustment factor 1.0582 5.50% = Tk. 570.73
Grand total = Tk. 10,376.98
Rate per sft. = Tk. 103.77
30.8.1 Ground floor Rate per sqm. = Tk. 1,116.98
30.8.2 Add for each addl. floor up to 5th floor (@ 1 lab. per % sft.) Per sqm = Tk. 33.10
30.8.3 Add for each addl floor for 6th floor to 9th floor (@ 1.25 No. lab. per % sft.) Per sqm = Tk. 41.37
30.8.4 Add for each addl floor for 10th floor and above (@ 1.5 Nos. lab. per % sft.) Per sqm = Tk. 49.65
30.9.2 Add for each addl. floor up to 5th floor (@ 1.25 No. lab. per % sft.) Per sqm = Tk. 41.37
30.9.3 Add for each addl floor for 6th floor to 9th floor (@ 1.5 No. lab. per % sft.) Per sqm = Tk. 49.65
30.9.4 Add for each addl floor for 10th floor and above (@ 1.75 Nos. lab. per % sft.) Per sqm = Tk. 57.92
(ii) Cement 0.85 bag @ Tk. 440.00 Per bag = Tk. 374.00
(iii) Mortar mix 0.026 liter @ Tk. 244.42 Per liter = Tk. 6.35
(iv) Sand (F.M. 1.2) 7.00 cft. @ Tk. 1,700.00 Per % cft. = Tk. 119.00
(v) Transportation of block 116 Nos. @ Tk. 6.84 each = Tk. 793.44
(b) Labour
(i) Head mason 0.1 No. @ Tk. 493.00 each = Tk. 49.30
(ii) Mason 1.5 Nos. @ Tk. 389.00 each = Tk. 583.50
(iii) Ordinary Labour 3.5 Nos. @ Tk. 245.00 each = Tk. 857.50
(c) Scaffolding 25 sft. @ Tk. 7.20 Per sft. = Tk. 180.00
(d) Local carriage, curing & sundries etc. LS. = Tk. 122.50
Total = Tk. 10,000.35
Profit 10.00% = Tk. 1,000.04
Overhead 3.50% = Tk. 350.01
= Tk. 11,350.40
Add VAT with adjustment factor 1.0582 5.50% = Tk. 660.60
Grand total = Tk. 12,011.00
30.10.1 Ground floor Rate per sft. = Tk. 120.11
Rate per sqm. = Tk. 1,292.86
30.10.2 Add for each addl. floor up to 5th floor (@ 1.25 No. lab. per % sft.) Per sqm = Tk. 41.37
30.10.3 Add for each addl floor for 6th floor to 9th floor (@ 1.5 No. lab. per % sft.) Per sqm = Tk. 49.65
30.10.4 Add for each addl floor for 10th floor and above (@ 1.75 Nos. lab. per % sft.) Per sqm = Tk. 57.92
30.11.2 Add for each addl. floor up to 5th floor (@ 1 No. lab. per % pc.) each = Tk. 3.08
30.11.3 Add for each addl floor for 6th floor to 9th floor (@ 1.25 No. lab. per % pc.) each = Tk. 3.84
30.11.4 Add for each addl floor for 10th floor and above (@ 1.5 Nos. lab. per % pcs.) each = Tk. 4.61
(ii) Transportation of block 102 Nos. @ Tk. 7.60 each = Tk. 775.20
(b) Ordinary Labour
(i) Lifting & placing on shutter 102 Nos. @ Tk. 6.13 each = Tk. 625.26
(ii) Local carriage, sundries etc. 102 Nos. @ Tk. 2.45 each = Tk. 249.90
Total = Tk. 9,988.86
Profit 10.00% = Tk. 998.89
Overhead 3.50% = Tk. 349.61
= Tk. 11,337.36
Add VAT with adjustment factor 1.0582 5.50% = Tk. 659.85
Grand total = Tk. 11,997.21
30.12.1 Ground floor Rate each. = Tk. 119.97
Say, Tk. 120 .00 each.
30.12.2 Add for each addl. floor up to 5th floor (@ 1.25 No. lab. per % pc.) each = Tk. 3.84
30.12.3 Add for each addl floor for 6th floor to 9th floor (@ 1.5 No. lab. per % pc.) each = Tk. 6.92
30.12.4 Add for each addl floor for 6th floor to 9th floor (@ 1.75 No. lab. per % pc.) each = Tk. 8.07
30.18.1.2 Add for each addl. floor up to 5th floor (@ 1 No. lab. per % sft.) Per sqm = Tk. 31.28
30.18.1.3 Add for each addl floor for 6th floor to 9th floor (@ 1.25 Nos. lab. per % sft.) Per sqm = Tk. 39.10
30.18.1.4 Add for each addl floor for 10th floor and above (@ 1.5 Nos. lab. per % sft.) Per sqm = Tk. 46.92
(iv) Transportation 100 sft. @ Tk. 1.65 Per sft. = Tk. 165.00
(b) Labour
(i) Mason 2 Nos. @ Tk. 389.00 each = Tk. 778.00
(ii) Ordinary Labour 4 Nos. @ Tk. 245.00 each = Tk. 980.00
(c) Local carriage, storage & sundries etc. L.S. = Tk. 98.00
(d) Tools & machinery 100 sft. @ Tk. 2.45 Per sft. = Tk. 245.00
Total = Tk. 8,003.20
Profit 10.00% = Tk. 800.32
Overhead 3.50% = Tk. 280.11
= Tk. 9,083.63
Add VAT with adjustment factor 1.0582 5.50% = Tk. 528.68
Grand total = Tk. 9,612.31
Rate per sft. = Tk. 96.12
30.18.2.1 Ground floor Rate per sqm. = Tk. 1,034.64
30.18.2.2 Add for each addl. floor up to 5th floor (@ 1 No. lab. per % sft.) Per sqm = Tk. 31.28
30.18.2.3 Add for each addl floor for 6th floor to 9th floor (@ 1.25 Nos. lab. per % sft.) Per sqm = Tk. 39.10
30.18.2.4 Add for each addl floor for 10th floor and above (@ 1.5 Nos. lab. per % sft.) Per sqm = Tk. 46.92
30.19.1.2 Add for each addl. floor up to 5th floor (@ 1 No. lab. per % sft.) Per sqm = Tk. 31.28
30.19.1.3 Add for each addl floor for 6th floor to 9th floor (@ 1.25 Nos. lab. per % sft.) Per sqm = Tk. 39.10
30.19.1.4 Add for each addl floor for 10th floor and above (@ 1.5 Nos. lab. per % sft.) Per sqm = Tk. 46.92
30.19.2.2 Add for each addl. floor up to 5th floor (@ 1 No. lab. per % sft.) Per sqm = Tk. 31.28
30.19.2.3 Add for each addl floor for 6th floor to 9th floor (@ 1.25 Nos. lab. per % sft.) Per sqm = Tk. 39.10
30.19.2.4 Add for each addl floor for 10th floor and above (@ 1.5 Nos. lab. per % sft.) Per sqm = Tk. 46.92
30.20.1.2 Add for each addl. floor up to 5th floor (@ 1 No. lab. per % sft.) Per sqm = Tk. 31.28
30.20.1.3 Add for each addl floor for 6th floor to 9th floor (@ 1.25 Nos. lab. per % sft.) Per sqm = Tk. 39.10
30.20.1.4 Add for each addl floor for 10th floor and above (@ 1.5 Nos. lab. per % sft.) Per sqm = Tk. 46.92
30.20.2.2 Add for each addl. floor up to 5th floor (@ 1 No. lab. per % sft.) Per sqm = Tk. 31.28
30.20.2.3 Add for each addl floor for 6th floor to 9th floor (@ 1.25 Nos. lab. per % sft.) Per sqm = Tk. 39.10
30.20.2.4 Add for each addl floor for 10th floor and above (@ 1.5 Nos. lab. per % sft.) Per sqm = Tk. 46.92
30.20.3.2 Add for each addl. floor up to 5th floor (@ 1 No. lab. per % sft.) Per sqm = Tk. 31.28
30.20.3.3 Add for each addl floor for 6th floor to 9th floor (@ 1.25 Nos. lab. per % sft.) Per sqm = Tk. 39.10
30.20.3.4 Add for each addl floor for 10th floor and above (@ 1.5 Nos. lab. per % sft.) Per sqm = Tk. 46.92
(iii) Sand 16.25 cft. @ Tk. 1,700.00 Per % cft. = Tk. 276.25
(iv) Transportation 220 Nos. @ Tk. 2.49 each = Tk. 547.80
(b) Labour
(i) Cladding work in/c screening
sand & nominal curing 100 sft. @ Tk. 19.06 Per sft. = Tk. 1,906.00
(ii) Scaffolding 25 sft. @ Tk. 7.20 Per sft. = Tk. 180.00
(iii) Tools and machinery 100 sft. @ Tk. 2.45 Per sft. Tk. 245.00
(iv) Labour for local carriage sundries etc. 0.75 No. @ Tk. 245.00 each = Tk. 183.75
Total = Tk. 8,585.80
Profit 10.00% = Tk. 858.58
Overhead 3.50% = Tk. 300.50
= Tk. 9,744.88
Add VAT with adjustment factor 1.0582 5.50% = Tk. 567.16
Grand total = Tk. 10,312.04
Rate per sft. = Tk. 103.12
30.20.4.1 Ground floor Rate per sqm. = Tk. 1,109.98
30.20.4.2 Add for each addl. floor up to 5th floor (@ 1 No. lab. per % sft.) Per sqm = Tk. 31.28
30.20.4.3 Add for each addl floor for 6th floor to 9th floor (@ 1.25 Nos. lab. per % sft.) Per sqm = Tk. 39.10
30.20.4.4 Add for each addl floor for 10th floor and above (@ 1.5 Nos. lab. per % sft.) Per sqm = Tk. 46.92
30.20.5.2 Add for each addl. floor up to 5th floor (@ 1 No. lab. per % sft.) Per sqm = Tk. 31.28
30.20.5.3 Add for each addl floor for 6th floor to 9th floor (@ 1.25 Nos. lab. per % sft.) Per sqm = Tk. 39.10
30.20.5.4 Add for each addl floor for 10th floor and above (@ 1.5 Nos. lab. per % sft.) Per sqm = Tk. 46.92
roof tiles in/c wastage 102.0 Nos. @ Tk. 41.07 each = Tk. 4,189.14
(ii) J-hook with nut & washer 60.00 Nos. @ Tk. 9.00 each = Tk. 540.00
(iii) Transportation 102 Nos. @ Tk. 3.00 each = Tk. 306.00
(b) Labour
(i) Lifting & placing on shutter 102.0 Nos. @ Tk. 2.45 Per sft. = Tk. 249.90
(c) Tools and machinery for 102.0 Nos. @ Tk. 3.68 Per sft. Tk. 375.36
Total = Tk. 5,660.40
Profit 10.00% = Tk. 566.04
Overhead 3.50% = Tk. 198.11
= Tk. 6,424.55
Add VAT with adjustment factor 1.0582 5.50% = Tk. 373.92
Grand total = Tk. 6,798.47
Rate each. = Tk. 67.98
Item No.- 31.2 Field vist, BH Coordinate settings and inspection of sampling and samples by the Geo-tech. Expert / Engineer
Considering 1 No. site
Field visit and(a)inspection of sampling and samples by the Geo-tech. Expert / Engineer in/c
3 Conv unit
& DA, 1438 = Tk. 4,314.00
(b) Setting location & Cordinates of BH in X,Y,Z from
surveyer
datum 0.25 day 1200 300
Helper to surveyer 0.25 day 750 187.5
Profit 10.00% = Tk. 431.40
Overhead 3.50% = Tk. 150.99
= Tk. 5,383.89
Add VAT with adjustment factor 1.0582 5.50% = Tk. 313.35
Total = Tk. 5,697.24
Rate per site = Tk. 5,697.24
31.3.2 Installation of boring equipment at site: For depth of water above 750 mm and up to 1500 mm
Considering 1 point
(a) Man-power
(i) Foreman (1 x 1/16) 0.06 manday @ Tk. 670.00 each = Tk. 40.20
(ii) Rig operators (1 x 1/8) 0.13 manday @ Tk. 603.00 each = Tk. 78.39
(iii) Skilled labour (6 x 1/8) 0.75 mandays @ Tk. 375.00 each = Tk. 281.25
(iv) Unskilled labour (2 x 1/8) 0.25 manday @ Tk. 245.00 each = Tk. 61.25
(b) Material
(i) Bamboo for platform (using 6 times) 268 rft. @ Tk. 12.00 Per rft. = Tk. 536.00
(ii) Wooden plank (using 6times)
10 x 8'-0" x 12" x 1.5"= 12 cft. @ Tk. 470.00 Per cft. = Tk. 940.00
(iii) Rope (using 4 times) 8 kg. @ Tk. 45.00 Per kg. = Tk. 90.00
(iv) Hire charge of small boat 1 No. @ Tk. 688.00 Tk. 688.00
in/c boatman & helper, 1 No. @ Tk. 700.00 Per day = Tk. 700.00
(v) Tools & plant, sundries, consumables, local carrying 4 No. Tk. 245.00 L.S. = Tk. 980.00
Total = Tk. 4,395.09
Profit 10.00% = Tk. 439.51
Overhead 3.50% = Tk. 153.83
= Tk. 4,988.43
Add VAT with adjustment factor 1.0582 5.50% = Tk. 290.33
Grand total = Tk. 5,278.76
Re-use to other bore point 0.8 Rate per point = Tk. 4,223.01
31.3.3 Installation of boring equipment at site: For depth of water above 1500 mm (stagnant water)
Considering 1 point
(a) Man-power
(i) Foreman (1 x 1/16) 0.06 manday @ Tk. 670.00 each = Tk. 40.20
(ii) Rig operators (1 x 1/8) 0.13 manday @ Tk. 603.00 each = Tk. 78.39
(iii) Skilled labour (6 x 1/8) 0.75 mandays @ Tk. 375.00 each = Tk. 281.25
(iv) Unskilled labour (2 x 1/8) 0.25 manday @ Tk. 245.00 each = Tk. 61.25
(b) Material
(i) Bamboo for platform (using 6 times) 260 rft. @ Tk. 12.00 each = Tk. 520.00
(ii) Wooden plank (using 6 times)
15 x 8'-0" x 12" x 1.5"= 15 cft. @ Tk. 470.00 Per cft. = Tk. 1,175.00
(iii) Rope (using 4 times) 20 kg. @ Tk. 45.00 Per kg. = Tk. 225.00
(iv) Hire charge of small boat 1 no Tk. 688.00
in/c boatman & helper. 1 No. @ Tk. 700.00 Per day = Tk. 700.00
(v) Drum (defects free, using 8 times) 22 Nos. @ Tk. 995.00 each = Tk. 2,736.25
(vi) Tools & plant, anchor, sundries, consumables, local carrying4 uni Tk. 245.00 = Tk. 980.00
Total = Tk. 6,797.34
Profit 10.00% = Tk. 679.73
Overhead 3.50% = Tk. 237.91
= Tk. 7,714.98
Add VAT with adjustment factor 1.0582 5.50% = Tk. 449.02
Grand total = Tk. 8,164.00
Re-use to other bore point 0.7 Rate per point = Tk. 5,714.80
(a) Hire charge of boring rig 0.4 day @ Tk. 2,750.00 Per day = Tk. 1,100.00
(b) Wages for man power
(i) Foreman
(1 x 20% per day x 0.4 day) 0.08 manday @ Tk. 670.00 each = Tk. 53.60
(ii) Rig operator
(1 x 30% per day x 0.4 day) 0.12 manday @ Tk. 603.00 each = Tk. 72.36
(iii) Helper to rig operators
(5 x 50% per day x 0.4 day) 1.00 mandays @ Tk. 375.00 each = Tk. 375.00
Total = Tk. 1,600.96
Profit 10.00% = Tk. 160.10
Overhead 3.50% = Tk. 56.03
= Tk. 1,817.09
Add VAT with adjustment factor 1.0582 5.50% = Tk. 105.76
Grand total = Tk. 1,922.85
Rate per meter = Tk. 213.65
31.4.2 Boring 100 mm dia bore-hole by wash boring method: 15 meter to 25 meter
(a) Hire charge of boring rig 0.44 day @ Tk. 2,750.00 Per day = Tk. 1,210.00
(b) Wages for man power
(i) Foreman
(1 x 20% per day x 0.4 4day) 0.09 manday @ Tk. 670.00 each = Tk. 60.30
(ii) Rig operator
(1 x 30% per day x 0.44 day) 0.13 manday @ Tk. 603.00 each = Tk. 78.39
(iii) Helper to rig operators
(5 x 50% per day x 0.44 day) 1.10 mandays @ Tk. 375.00 each = Tk. 412.50
Total = Tk. 1,761.19
Profit 10.00% = Tk. 176.12
Overhead 3.50% = Tk. 61.64
= Tk. 1,998.95
Add VAT with adjustment factor 1.0582 5.50% = Tk. 116.34
Grand total = Tk. 2,115.29
Rate per meter = Tk. 235.03
31.4.3 Boring 100 mm dia bore-hole by wash boring method: 25 meter to 35 meter
(a) Hire charge of boring rig 0.45 days @ Tk. 2,750.00 Per day = Tk. 1,237.50
(b) Wages for man power
(i) Foreman
(1 x 20% per day x 0.45day) 0.090 manday @ Tk. 670.00 each = Tk. 60.30
(ii) Rig operator
(1 x 30% per day x 0.45 day) 0.135 manday @ Tk. 603.00 each = Tk. 81.41
(iii) Helper to rig operators
(5 x 50% per day x 0.45day) 1.13 manday @ Tk. 375.00 each = Tk. 423.75
Total = Tk. 1,802.96
Profit 10.00% = Tk. 180.30
Overhead 3.50% = Tk. 63.10
= Tk. 2,046.36
Add VAT with adjustment factor 1.0582 5.50% = Tk. 119.10
Grand total = Tk. 2,165.46
Rate per meter = Tk. 240.61
Analysis of PWD SoR 2014 for Civil Works 586
31.4.4 Boring 100 mm dia bore-hole by wash boring method: 35 meter to 45 meter
(a) Hire charge of boring rig 0.46 day @ Tk. 2,750.00 Per day = Tk. 1,265.00
(b) Wages for man power
(i) Foreman 0.092 manday @ Tk. 670.00 each = Tk. 61.64
(1 x 20% per day x 0.46day)
(ii) Rig operator 0.138 manday @ Tk. 603.00 each = Tk. 83.21
(1 x 30% per day x 0.46 day)
(iii) Helper to rig operators 1.15 mandays @ Tk. 375.00 each = Tk. 431.25
(5 x 50% per day x 0.46day) Total = Tk. 1,841.10
Profit 10.00% = Tk. 184.11
Overhead 3.50% = Tk. 64.44
= Tk. 2,089.65
Add VAT with adjustment factor 1.0582 5.50% = Tk. 121.62
Grand total = Tk. 2,211.27
Rate per meter = Tk. 245.70
31.4.5 Boring 100 mm dia bore-hole by wash boring method: 45m & above
(a) Hire charge of boring rig 0.48 day @ Tk. 2,750.00 Per day = Tk. 1,320.00
(b) Wages for man power
(i) Foreman 0.10 manday @ Tk. 670.00 each = Tk. 67.00
(1 x 20% per day x 0.48day)
(ii) Rig operator 0.14 manday @ Tk. 603.00 each = Tk. 84.42
(1 x 30% per day x 0.48 day)
(iii) Helper to rig operators 1.20 manday @ Tk. 375.00 each = Tk. 450.00
(5 x 50% per day x 0.48day) Total = Tk. 1,921.42
Profit 10.00% = Tk. 192.14
Overhead 3.50% = Tk. 67.25
= Tk. 2,180.81
Add VAT with adjustment factor 1.0582 5.50% = Tk. 126.93
Grand total = Tk. 2,307.74
Rate per meter = Tk. 256.42
= Tk. 507.64
Add VAT with adjustment factor 1.0582 5.50% = Tk. 29.55
Grand total = Tk. 537.19
Rate per point = Tk. 89.53
(i) Collection, preservation, transportation and incidental charges L.S. = Tk. 80.40
Profit 10.00% = Tk. 8.04
Overhead 3.50% = Tk. 2.81
= Tk. 91.25
Add VAT with adjustment factor 1.0582 5.50% = Tk. 5.31
Total = Tk. 96.56
Rate per sample = Tk. 96.56
31.32.1 Bore Hole depth 0 to 15m per bore 1 Tk. 7,222.50 each = Tk. 7,222.50
15 Total = Tk. 7,222.50
f=samplecollection , test, report 2.25 Profit 10.00% = Tk. 722.25
boring/m Tk. 214 Overhead 3.50% = Tk. 252.79
= Tk. 8,197.54
Add VAT with adjustment factor 1.0582 5.50% = Tk. 477.11
Grand total Tk. 8,674.65
31.32.2 Bore Hole depth 0 to 18m per bore 1 LS Tk. 7,583.63 each = Tk. 7,583.63
Total = Tk. 7,583.63
Tk. 7,222.50 Profit 10.00% = Tk. 758.36
f=1.05 1.05 Overhead 3.50% = Tk. 265.43
= Tk. 8,607.42
Add VAT with adjustment factor 1.0582 5.50% = Tk. 500.96
Grand total Tk. 9,108.38
31.32.3 Bore Hole depth 0 to 20m per bore 1 LS Tk. 9,461.48 each = Tk. 9,461.48
20 Total = Tk. 9,461.48
Tk. 7,222.50 Profit 10.00% = Tk. 946.15
1.31 Overhead 3.50% = Tk. 331.15
= Tk. 10,738.78
Add VAT with adjustment factor 1.0582 5.50% = Tk. 625.01
Grand total Tk. 11,363.79
31.32.4 Bore Hole depth 0 to 25m per bore 1 LS Tk. 11,353.77 each = Tk. 11,353.77
25 Total = Tk. 11,353.77
Tk. 7,222.50 Profit 10.00% = Tk. 1,135.38
1.572 Overhead 3.50% = Tk. 397.38
= Tk. 12,886.53
Add VAT with adjustment factor 1.0582 5.50% = Tk. 750.01
Grand total Tk. 13,636.54
31.32.5 Bore Hole depth 0 to 30m per bore 1 LS Tk. 13,624.52 each = Tk. 13,624.52
30 Total = Tk. 13,624.52
Tk. 7,222.50 Profit 10.00% = Tk. 1,362.45
1.8864 Overhead 3.50% = Tk. 476.86
= Tk. 15,463.83
Add VAT with adjustment factor 1.0582 5.50% = Tk. 900.01
Grand total Tk. 16,363.84
31.32.6 Bore Hole depth 0 to 35m per bore 1 Tk. 16,349.43 each = Tk. 16,349.43
35 Total = Tk. 16,349.43
Tk. 7,222.50 Profit 10.00% = Tk. 1,634.94
2.26368 Overhead 3.50% = Tk. 572.23
= Tk. 18,556.60
Add VAT with adjustment factor 1.0582 5.50% = Tk. 1,080.01
Grand total Tk. 19,636.61
31.32.7 Bore Hole depth 0 to 40m per bore 1 Tk. 19,619.31 each = Tk. 19,619.31
40 Total = Tk. 19,619.31
Tk. 7,222.50 Profit 10.00% = Tk. 1,961.93
2.716416 Overhead 3.50% = Tk. 686.68
= Tk. 22,267.92
Add VAT with adjustment factor 1.0582 5.50% = Tk. 1,296.02
Grand total Tk. 23,563.94
31.32.8 Bore Hole depth 0 to 45m per bore 1 Tk. 23,543.18 each = Tk. 23,543.18
45 Total = Tk. 23,543.18
Tk. 7,222.50 Profit 10.00% = Tk. 2,354.32
3.2596992 Overhead 3.50% = Tk. 824.01
= Tk. 26,721.51
Add VAT with adjustment factor 1.0582 5.50% = Tk. 1,555.22
Grand total Tk. 28,276.73
61554 105550
50700 97714
41759 90720
34395 84461
28330 78848
23334 73802
19219 69253
15830 65144
13039 61422
10739 58043
8846 54968
7286 52163
6001 49599
4943 47248
4071 45090
3353 43102
2762 41268
Analysis of PWD SoR 2014 for Civil Works 1281
Analysis of PWD SoR 2014 for Civil Works 1282
Analysis of PWD SoR 2014 for Civil Works 1283
Analysis of PWD SoR 2014 for Civil Works 1284
Analysis of PWD SoR 2014 for Civil Works 1285
Analysis of PWD SoR 2014 for Civil Works 1286
Analysis of PWD SoR 2014 for Civil Works 1287
Analysis of PWD SoR 2014 for Civil Works 1288
Analysis of PWD SoR 2014 for Civil Works 1289
Analysis of PWD SoR 2014 for Civil Works 1290
Analysis of PWD SoR 2014 for Civil Works 1291
Analysis of PWD SoR 2014 for Civil Works 1292
Analysis of PWD SoR 2014 for Civil Works 1293
Analysis of PWD SoR 2014 for Civil Works 1294
Analysis of PWD SoR 2014 for Civil Works 1295
Analysis of PWD SoR 2014 for Civil Works 1296
Analysis of PWD SoR 2014 for Civil Works 1297
Analysis of PWD SoR 2014 for Civil Works 1298
Analysis of PWD SoR 2014 for Civil Works 1299
Analysis of PWD SoR 2014 for Civil Works 1300
Analysis of PWD SoR 2014 for Civil Works 1301
Analysis of PWD SoR 2014 for Civil Works 1302
Analysis of PWD SoR 2014 for Civil Works 1303
Analysis of PWD SoR 2014 for Civil Works 1304
Analysis of PWD SoR 2014 for Civil Works 1305
Analysis of PWD SoR 2014 for Civil Works 1306
Analysis of PWD SoR 2014 for Civil Works 1307
Analysis of PWD SoR 2014 for Civil Works 1308
Analysis of PWD SoR 2014 for Civil Works 1309
Analysis of PWD SoR 2014 for Civil Works 1310
Analysis of PWD SoR 2014 for Civil Works 1311
Analysis of PWD SoR 2014 for Civil Works 1312
Analysis of PWD SoR 2014 for Civil Works 1313
Analysis of PWD SoR 2014 for Civil Works 1314
Analysis of PWD SoR 2014 for Civil Works 1315
Analysis of PWD SoR 2014 for Civil Works 1316
Analysis of PWD SoR 2014 for Civil Works 1317
Analysis of PWD SoR 2014 for Civil Works 1318
Analysis of PWD SoR 2014 for Civil Works 1319
Analysis of PWD SoR 2014 for Civil Works 1320
Analysis of PWD SoR 2014 for Civil Works 1321
Analysis of PWD SoR 2014 for Civil Works 1322
Analysis of PWD SoR 2014 for Civil Works 1323
Analysis of PWD SoR 2014 for Civil Works 1324
Analysis of PWD SoR 2014 for Civil Works 1325
Analysis of PWD SoR 2014 for Civil Works 1326
Analysis of PWD SoR 2014 for Civil Works 1327
Analysis of PWD SoR 2014 for Civil Works 1328
Analysis of PWD SoR 2014 for Civil Works 1329
Analysis of PWD SoR 2014 for Civil Works 1330
Analysis of PWD SoR 2014 for Civil Works 1331
Analysis of PWD SoR 2014 for Civil Works 1332
Analysis of PWD SoR 2014 for Civil Works 1333
Analysis of PWD SoR 2014 for Civil Works 1334
Analysis of PWD SoR 2014 for Civil Works 1335
Analysis of PWD SoR 2014 for Civil Works 1336
Analysis of PWD SoR 2014 for Civil Works 1337
Analysis of PWD SoR 2014 for Civil Works 1338
Analysis of PWD SoR 2014 for Civil Works 1339
Analysis of PWD SoR 2014 for Civil Works 1340
Analysis of PWD SoR 2014 for Civil Works 1341
Analysis of PWD SoR 2014 for Civil Works 1342
Analysis of PWD SoR 2014 for Civil Works 1343
Analysis of PWD SoR 2014 for Civil Works 1344
Analysis of PWD SoR 2014 for Civil Works 1345
Analysis of PWD SoR 2014 for Civil Works 1346
Analysis of PWD SoR 2014 for Civil Works 1347
Analysis of PWD SoR 2014 for Civil Works 1348
Analysis of PWD SoR 2014 for Civil Works 1349
Analysis of PWD SoR 2014 for Civil Works 1350
Analysis of PWD SoR 2014 for Civil Works 1351
Analysis of PWD SoR 2014 for Civil Works 1352
Analysis of PWD SoR 2014 for Civil Works 1353
Analysis of PWD SoR 2014 for Civil Works 1354
Analysis of PWD SoR 2014 for Civil Works 1355
Analysis of PWD SoR 2014 for Civil Works 1356
Analysis of PWD SoR 2014 for Civil Works 1357
Analysis of PWD SoR 2014 for Civil Works 1358
Analysis of PWD SoR 2014 for Civil Works 1359
Analysis of PWD SoR 2014 for Civil Works 1360
Analysis of PWD SoR 2014 for Civil Works 1361
Analysis of PWD SoR 2014 for Civil Works 1362
Analysis of PWD SoR 2014 for Civil Works 1363
Analysis of PWD SoR 2014 for Civil Works 1364
Analysis of PWD SoR 2014 for Civil Works 1365
Analysis of PWD SoR 2014 for Civil Works 1366
Analysis of PWD SoR 2014 for Civil Works 1367
Analysis of PWD SoR 2014 for Civil Works 1368
Analysis of PWD SoR 2014 for Civil Works 1369
Analysis of PWD SoR 2014 for Civil Works 1370
Analysis of PWD SoR 2014 for Civil Works 1371
Analysis of PWD SoR 2014 for Civil Works 1372
Analysis of PWD SoR 2014 for Civil Works 1373
Analysis of PWD SoR 2014 for Civil Works 1374
Analysis of PWD SoR 2014 for Civil Works 1375
Analysis of PWD SoR 2014 for Civil Works 1376
Analysis of PWD SoR 2014 for Civil Works 1377
Analysis of PWD SoR 2014 for Civil Works 1378
Analysis of PWD SoR 2014 for Civil Works 1379
Analysis of PWD SoR 2014 for Civil Works 1380
Analysis of PWD SoR 2014 for Civil Works 1381
Analysis of PWD SoR 2014 for Civil Works 1382
Analysis of PWD SoR 2014 for Civil Works 1383
Analysis of PWD SoR 2014 for Civil Works 1384
Analysis of PWD SoR 2014 for Civil Works 1385
Analysis of PWD SoR 2014 for Civil Works 1386
Analysis of PWD SoR 2014 for Civil Works 1387
Analysis of PWD SoR 2014 for Civil Works 1388
Analysis of PWD SoR 2014 for Civil Works 1389
Analysis of PWD SoR 2014 for Civil Works 1390
Analysis of PWD SoR 2014 for Civil Works 1391
Analysis of PWD SoR 2014 for Civil Works 1392
Analysis of PWD SoR 2014 for Civil Works 1393
Analysis of PWD SoR 2014 for Civil Works 1394
Analysis of PWD SoR 2014 for Civil Works 1395
Analysis of PWD SoR 2014 for Civil Works 1396
Analysis of PWD SoR 2014 for Civil Works 1397
Analysis of PWD SoR 2014 for Civil Works 1398
Analysis of PWD SoR 2014 for Civil Works 1399
Analysis of PWD SoR 2014 for Civil Works 1400
Analysis of PWD SoR 2014 for Civil Works 1401
Analysis of PWD SoR 2014 for Civil Works 1402
Analysis of PWD SoR 2014 for Civil Works 1403
Analysis of PWD SoR 2014 for Civil Works 1404
Analysis of PWD SoR 2014 for Civil Works 1405
Analysis of PWD SoR 2014 for Civil Works 1406
Analysis of PWD SoR 2014 for Civil Works 1407
Analysis of PWD SoR 2014 for Civil Works 1408
Analysis of PWD SoR 2014 for Civil Works 1409
Analysis of PWD SoR 2014 for Civil Works 1410
Analysis of PWD SoR 2014 for Civil Works 1411
Analysis of PWD SoR 2014 for Civil Works 1412
Analysis of PWD SoR 2014 for Civil Works 1413
Analysis of PWD SoR 2014 for Civil Works 1414
Analysis of PWD SoR 2014 for Civil Works 1415
Analysis of PWD SoR 2014 for Civil Works 1416
Analysis of PWD SoR 2014 for Civil Works 1417
Analysis of PWD SoR 2014 for Civil Works 1418
Analysis of PWD SoR 2014 for Civil Works 1419
Analysis of PWD SoR 2014 for Civil Works 1420
Analysis of PWD SoR 2014 for Civil Works 1421
Analysis of PWD SoR 2014 for Civil Works 1422
Analysis of PWD SoR 2014 for Civil Works 1423
Analysis of PWD SoR 2014 for Civil Works 1424
Analysis of PWD SoR 2014 for Civil Works 1425
Analysis of PWD SoR 2014 for Civil Works 1426
Analysis of PWD SoR 2014 for Civil Works 1427
Analysis of PWD SoR 2014 for Civil Works 1428
Analysis of PWD SoR 2014 for Civil Works 1429
Analysis of PWD SoR 2014 for Civil Works 1430
Analysis of PWD SoR 2014 for Civil Works 1431
Analysis of PWD SoR 2014 for Civil Works 1432
Analysis of PWD SoR 2014 for Civil Works 1433
Analysis of PWD SoR 2014 for Civil Works 1434
Analysis of PWD SoR 2014 for Civil Works 1435
Analysis of PWD SoR 2014 for Civil Works 1436
Analysis of PWD SoR 2014 for Civil Works 1437
Analysis of PWD SoR 2014 for Civil Works 1438
Analysis of PWD SoR 2014 for Civil Works 1439
Analysis of PWD SoR 2014 for Civil Works 1440
Analysis of PWD SoR 2014 for Civil Works 1441
Analysis of PWD SoR 2014 for Civil Works 1442
Analysis of PWD SoR 2014 for Civil Works 1443
Analysis of PWD SoR 2014 for Civil Works 1444
Analysis of PWD SoR 2014 for Civil Works 1445
Analysis of PWD SoR 2014 for Civil Works 1446
Analysis of PWD SoR 2014 for Civil Works 1447
Analysis of PWD SoR 2014 for Civil Works 1448
Analysis of PWD SoR 2014 for Civil Works 1449
Analysis of PWD SoR 2014 for Civil Works 1450
Analysis of PWD SoR 2014 for Civil Works 1451
Analysis of PWD SoR 2014 for Civil Works 1452
Analysis of PWD SoR 2014 for Civil Works 1453
Analysis of PWD SoR 2014 for Civil Works 1454
Analysis of PWD SoR 2014 for Civil Works 1455
Analysis of PWD SoR 2014 for Civil Works 1456
Analysis of PWD SoR 2014 for Civil Works 1457
Analysis of PWD SoR 2014 for Civil Works 1458
Analysis of PWD SoR 2014 for Civil Works 1459
Analysis of PWD SoR 2014 for Civil Works 1460
Analysis of PWD SoR 2014 for Civil Works 1461
Analysis of PWD SoR 2014 for Civil Works 1462
Analysis of PWD SoR 2014 for Civil Works 1463
Analysis of PWD SoR 2014 for Civil Works 1464
Analysis of PWD SoR 2014 for Civil Works 1465
Analysis of PWD SoR 2014 for Civil Works 1466
Analysis of PWD SoR 2014 for Civil Works 1467
Analysis of PWD SoR 2014 for Civil Works 1468
Analysis of PWD SoR 2014 for Civil Works 1469
Analysis of PWD SoR 2014 for Civil Works 1470
Analysis of PWD SoR 2014 for Civil Works 1471
Analysis of PWD SoR 2014 for Civil Works 1472
Analysis of PWD SoR 2014 for Civil Works 1473
Analysis of PWD SoR 2014 for Civil Works 1474
Analysis of PWD SoR 2014 for Civil Works 1475
Analysis of PWD SoR 2014 for Civil Works 1476
Analysis of PWD SoR 2014 for Civil Works 1477
Analysis of PWD SoR 2014 for Civil Works 1478
Analysis of PWD SoR 2014 for Civil Works 1479
Analysis of PWD SoR 2014 for Civil Works 1480
Analysis of PWD SoR 2014 for Civil Works 1481
Analysis of PWD SoR 2014 for Civil Works 1482
Analysis of PWD SoR 2014 for Civil Works 1483
Analysis of PWD SoR 2014 for Civil Works 1484
Analysis of PWD SoR 2014 for Civil Works 1485
Analysis of PWD SoR 2014 for Civil Works 1486
Analysis of PWD SoR 2014 for Civil Works 1487
Analysis of PWD SoR 2014 for Civil Works 1488
Analysis of PWD SoR 2014 for Civil Works 1489
Analysis of PWD SoR 2014 for Civil Works 1490
Analysis of PWD SoR 2014 for Civil Works 1491
Analysis of PWD SoR 2014 for Civil Works 1492
Analysis of PWD SoR 2014 for Civil Works 1493
Analysis of PWD SoR 2014 for Civil Works 1494
Analysis of PWD SoR 2014 for Civil Works 1495
Analysis of PWD SoR 2014 for Civil Works 1496
Analysis of PWD SoR 2014 for Civil Works 1497
Analysis of PWD SoR 2014 for Civil Works 1498
Analysis of PWD SoR 2014 for Civil Works 1499
Analysis of PWD SoR 2014 for Civil Works 1500
Analysis of PWD SoR 2014 for Civil Works 1501
Analysis of PWD SoR 2014 for Civil Works 1502
Analysis of PWD SoR 2014 for Civil Works 1503
Analysis of PWD SoR 2014 for Civil Works 1504
Analysis of PWD SoR 2014 for Civil Works 1505
Analysis of PWD SoR 2014 for Civil Works 1506
Analysis of PWD SoR 2014 for Civil Works 1507
Analysis of PWD SoR 2014 for Civil Works 1508
Analysis of PWD SoR 2014 for Civil Works 1509
Analysis of PWD SoR 2014 for Civil Works 1510
Analysis of PWD SoR 2014 for Civil Works 1511
Analysis of PWD SoR 2014 for Civil Works 1512
Analysis of PWD SoR 2014 for Civil Works 1513
Analysis of PWD SoR 2014 for Civil Works 1514
Analysis of PWD SoR 2014 for Civil Works 1515
Analysis of PWD SoR 2014 for Civil Works 1516
Analysis of PWD SoR 2014 for Civil Works 1517
Analysis of PWD SoR 2014 for Civil Works 1518
Analysis of PWD SoR 2014 for Civil Works 1519
Analysis of PWD SoR 2014 for Civil Works 1520
Analysis of PWD SoR 2014 for Civil Works 1521
Analysis of PWD SoR 2014 for Civil Works 1522
Analysis of PWD SoR 2014 for Civil Works 1523
Analysis of PWD SoR 2014 for Civil Works 1524
Analysis of PWD SoR 2014 for Civil Works 1525
Analysis of PWD SoR 2014 for Civil Works 1526
Analysis of PWD SoR 2014 for Civil Works 1527
Analysis of PWD SoR 2014 for Civil Works 1528
Analysis of PWD SoR 2014 for Civil Works 1529
Analysis of PWD SoR 2014 for Civil Works 1530
Analysis of PWD SoR 2014 for Civil Works 1531
Analysis of PWD SoR 2014 for Civil Works 1532
Analysis of PWD SoR 2014 for Civil Works 1533
Analysis of PWD SoR 2014 for Civil Works 1534
Analysis of PWD SoR 2014 for Civil Works 1535
Analysis of PWD SoR 2014 for Civil Works 1536
Analysis of PWD SoR 2014 for Civil Works 1537
Analysis of PWD SoR 2014 for Civil Works 1538
Analysis of PWD SoR 2014 for Civil Works 1539
Analysis of PWD SoR 2014 for Civil Works 1540
Analysis of PWD SoR 2014 for Civil Works 1541
Analysis of PWD SoR 2014 for Civil Works 1542
Analysis of PWD SoR 2014 for Civil Works 1543
Analysis of PWD SoR 2014 for Civil Works 1544
Analysis of PWD SoR 2014 for Civil Works 1545
Analysis of PWD SoR 2014 for Civil Works 1546
Analysis of PWD SoR 2014 for Civil Works 1547
Analysis of PWD SoR 2014 for Civil Works 1548
Analysis of PWD SoR 2014 for Civil Works 1549
Analysis of PWD SoR 2014 for Civil Works 1550
Analysis of PWD SoR 2014 for Civil Works 1551
Analysis of PWD SoR 2014 for Civil Works 1552
Analysis of PWD SoR 2014 for Civil Works 1553
Analysis of PWD SoR 2014 for Civil Works 1554
Analysis of PWD SoR 2014 for Civil Works 1555
Analysis of PWD SoR 2014 for Civil Works 1556
Analysis of PWD SoR 2014 for Civil Works 1557
Analysis of PWD SoR 2014 for Civil Works 1558
Analysis of PWD SoR 2014 for Civil Works 1559
Analysis of PWD SoR 2014 for Civil Works 1560
Analysis of PWD SoR 2014 for Civil Works 1561
Analysis of PWD SoR 2014 for Civil Works 1562
Analysis of PWD SoR 2014 for Civil Works 1563
Analysis of PWD SoR 2014 for Civil Works 1564
Analysis of PWD SoR 2014 for Civil Works 1565
Analysis of PWD SoR 2014 for Civil Works 1566
Analysis of PWD SoR 2014 for Civil Works 1567
Analysis of PWD SoR 2014 for Civil Works 1568
Analysis of PWD SoR 2014 for Civil Works 1569
Analysis of PWD SoR 2014 for Civil Works 1570
Analysis of PWD SoR 2014 for Civil Works 1571
Analysis of PWD SoR 2014 for Civil Works 1572
Analysis of PWD SoR 2014 for Civil Works 1573
Analysis of PWD SoR 2014 for Civil Works 1574
Analysis of PWD SoR 2014 for Civil Works 1575
Analysis of PWD SoR 2014 for Civil Works 1576
Analysis of PWD SoR 2014 for Civil Works 1577
Analysis of PWD SoR 2014 for Civil Works 1578
Analysis of PWD SoR 2014 for Civil Works 1579
Analysis of PWD SoR 2014 for Civil Works 1580
Analysis of PWD SoR 2014 for Civil Works 1581
Analysis of PWD SoR 2014 for Civil Works 1582
Analysis of PWD SoR 2014 for Civil Works 1583
Analysis of PWD SoR 2014 for Civil Works 1584
Analysis of PWD SoR 2014 for Civil Works 1585
Analysis of PWD SoR 2014 for Civil Works 1586
Analysis of PWD SoR 2014 for Civil Works 1587
Analysis of PWD SoR 2014 for Civil Works 1588
Analysis of PWD SoR 2014 for Civil Works 1589
Analysis of PWD SoR 2014 for Civil Works 1590
Analysis of PWD SoR 2014 for Civil Works 1591
Analysis of PWD SoR 2014 for Civil Works 1592
Analysis of PWD SoR 2014 for Civil Works 1593
Analysis of PWD SoR 2014 for Civil Works 1594
Analysis of PWD SoR 2014 for Civil Works 1595
Analysis of PWD SoR 2014 for Civil Works 1596
Analysis of PWD SoR 2014 for Civil Works 1597
Analysis of PWD SoR 2014 for Civil Works 1598
Analysis of PWD SoR 2014 for Civil Works 1599
Analysis of PWD SoR 2014 for Civil Works 1600
Analysis of PWD SoR 2014 for Civil Works 1601
Analysis of PWD SoR 2014 for Civil Works 1602
Analysis of PWD SoR 2014 for Civil Works 1603
Analysis of PWD SoR 2014 for Civil Works 1604
Analysis of PWD SoR 2014 for Civil Works 1605
Analysis of PWD SoR 2014 for Civil Works 1606
Analysis of PWD SoR 2014 for Civil Works 1607
Analysis of PWD SoR 2014 for Civil Works 1608
Analysis of PWD SoR 2014 for Civil Works 1609
Analysis of PWD SoR 2014 for Civil Works 1610
Analysis of PWD SoR 2014 for Civil Works 1611
Analysis of PWD SoR 2014 for Civil Works 1612
Analysis of PWD SoR 2014 for Civil Works 1613
Analysis of PWD SoR 2014 for Civil Works 1614
Analysis of PWD SoR 2014 for Civil Works 1615
Analysis of PWD SoR 2014 for Civil Works 1616
Analysis of PWD SoR 2014 for Civil Works 1617
Analysis of PWD SoR 2014 for Civil Works 1618
Analysis of PWD SoR 2014 for Civil Works 1619
Analysis of PWD SoR 2014 for Civil Works 1620
Analysis of PWD SoR 2014 for Civil Works 1621
Analysis of PWD SoR 2014 for Civil Works 1622
Analysis of PWD SoR 2014 for Civil Works 1623
Analysis of PWD SoR 2014 for Civil Works 1624
Analysis of PWD SoR 2014 for Civil Works 1625
Analysis of PWD SoR 2014 for Civil Works 1626
Analysis of PWD SoR 2014 for Civil Works 1627
Analysis of PWD SoR 2014 for Civil Works 1628
Analysis of PWD SoR 2014 for Civil Works 1629
Analysis of PWD SoR 2014 for Civil Works 1630
Analysis of PWD SoR 2014 for Civil Works 1631
Analysis of PWD SoR 2014 for Civil Works 1632
Analysis of PWD SoR 2014 for Civil Works 1633
Analysis of PWD SoR 2014 for Civil Works 1634
Analysis of PWD SoR 2014 for Civil Works 1635
Analysis of PWD SoR 2014 for Civil Works 1636
Analysis of PWD SoR 2014 for Civil Works 1637
Analysis of PWD SoR 2014 for Civil Works 1638
Analysis of PWD SoR 2014 for Civil Works 1639
Analysis of PWD SoR 2014 for Civil Works 1640
Analysis of PWD SoR 2014 for Civil Works 1641
Analysis of PWD SoR 2014 for Civil Works 1642
Analysis of PWD SoR 2014 for Civil Works 1643
Analysis of PWD SoR 2014 for Civil Works 1644
Analysis of PWD SoR 2014 for Civil Works 1645
Analysis of PWD SoR 2014 for Civil Works 1646
Analysis of PWD SoR 2014 for Civil Works 1647
Analysis of PWD SoR 2014 for Civil Works 1648
Analysis of PWD SoR 2014 for Civil Works 1649
Analysis of PWD SoR 2014 for Civil Works 1650
Analysis of PWD SoR 2014 for Civil Works 1651
Analysis of PWD SoR 2014 for Civil Works 1652
Analysis of PWD SoR 2014 for Civil Works 1653
Analysis of PWD SoR 2014 for Civil Works 1654
Analysis of PWD SoR 2014 for Civil Works 1655
Analysis of PWD SoR 2014 for Civil Works 1656
Analysis of PWD SoR 2014 for Civil Works 1657
Analysis of PWD SoR 2014 for Civil Works 1658
Analysis of PWD SoR 2014 for Civil Works 1659
Analysis of PWD SoR 2014 for Civil Works 1660
Analysis of PWD SoR 2014 for Civil Works 1661
Analysis of PWD SoR 2014 for Civil Works 1662
Analysis of PWD SoR 2014 for Civil Works 1663
Analysis of PWD SoR 2014 for Civil Works 1664
Analysis of PWD SoR 2014 for Civil Works 1665
Analysis of PWD SoR 2014 for Civil Works 1666
Analysis of PWD SoR 2014 for Civil Works 1667
Analysis of PWD SoR 2014 for Civil Works 1668
Analysis of PWD SoR 2014 for Civil Works 1669
Analysis of PWD SoR 2014 for Civil Works 1670
Analysis of PWD SoR 2014 for Civil Works 1671
Analysis of PWD SoR 2014 for Civil Works 1672
Analysis of PWD SoR 2014 for Civil Works 1673
Analysis of PWD SoR 2014 for Civil Works 1674
Analysis of PWD SoR 2014 for Civil Works 1675
Analysis of PWD SoR 2014 for Civil Works 1676
Analysis of PWD SoR 2014 for Civil Works 1677
Analysis of PWD SoR 2014 for Civil Works 1678
Analysis of PWD SoR 2014 for Civil Works 1679
Analysis of PWD SoR 2014 for Civil Works 1680
Analysis of PWD SoR 2014 for Civil Works 1681
Analysis of PWD SoR 2014 for Civil Works 1682
Analysis of PWD SoR 2014 for Civil Works 1683
Analysis of PWD SoR 2014 for Civil Works 1684
Analysis of PWD SoR 2014 for Civil Works 1685
Analysis of PWD SoR 2014 for Civil Works 1686
Analysis of PWD SoR 2014 for Civil Works 1687
Analysis of PWD SoR 2014 for Civil Works 1688
Analysis of PWD SoR 2014 for Civil Works 1689
Analysis of PWD SoR 2014 for Civil Works 1690
Analysis of PWD SoR 2014 for Civil Works 1691
Analysis of PWD SoR 2014 for Civil Works 1692
Analysis of PWD SoR 2014 for Civil Works 1693
Analysis of PWD SoR 2014 for Civil Works 1694
Analysis of PWD SoR 2014 for Civil Works 1695
Analysis of PWD SoR 2014 for Civil Works 1696
Analysis of PWD SoR 2014 for Civil Works 1697
Analysis of PWD SoR 2014 for Civil Works 1698
Analysis of PWD SoR 2014 for Civil Works 1699
Analysis of PWD SoR 2014 for Civil Works 1700
Analysis of PWD SoR 2014 for Civil Works 1701
Analysis of PWD SoR 2014 for Civil Works 1702
Analysis of PWD SoR 2014 for Civil Works 1703
Analysis of PWD SoR 2014 for Civil Works 1704
Analysis of PWD SoR 2014 for Civil Works 1705
Analysis of PWD SoR 2014 for Civil Works 1706
Analysis of PWD SoR 2014 for Civil Works 1707
Analysis of PWD SoR 2014 for Civil Works 1708
Analysis of PWD SoR 2014 for Civil Works 1709
Analysis of PWD SoR 2014 for Civil Works 1710
Analysis of PWD SoR 2014 for Civil Works 1711
Analysis of PWD SoR 2014 for Civil Works 1712
Analysis of PWD SoR 2014 for Civil Works 1713
Analysis of PWD SoR 2014 for Civil Works 1714
Analysis of PWD SoR 2014 for Civil Works 1715
Analysis of PWD SoR 2014 for Civil Works 1716
Analysis of PWD SoR 2014 for Civil Works 1717
Analysis of PWD SoR 2014 for Civil Works 1718
Analysis of PWD SoR 2014 for Civil Works 1719
Analysis of PWD SoR 2014 for Civil Works 1720
Analysis of PWD SoR 2014 for Civil Works 1721
Analysis of PWD SoR 2014 for Civil Works 1722
Analysis of PWD SoR 2014 for Civil Works 1723
Analysis of PWD SoR 2014 for Civil Works 1724
Analysis of PWD SoR 2014 for Civil Works 1725
Analysis of PWD SoR 2014 for Civil Works 1726
Analysis of PWD SoR 2014 for Civil Works 1727
Analysis of PWD SoR 2014 for Civil Works 1728
Analysis of PWD SoR 2014 for Civil Works 1729
Analysis of PWD SoR 2014 for Civil Works 1730
Analysis of PWD SoR 2014 for Civil Works 1731
Analysis of PWD SoR 2014 for Civil Works 1732
Analysis of PWD SoR 2014 for Civil Works 1733
Analysis of PWD SoR 2014 for Civil Works 1734
Analysis of PWD SoR 2014 for Civil Works 1735
Analysis of PWD SoR 2014 for Civil Works 1736
Analysis of PWD SoR 2014 for Civil Works 1737
Analysis of PWD SoR 2014 for Civil Works 1738
Analysis of PWD SoR 2014 for Civil Works 1739
Analysis of PWD SoR 2014 for Civil Works 1740
Analysis of PWD SoR 2014 for Civil Works 1741
Analysis of PWD SoR 2014 for Civil Works 1742
Analysis of PWD SoR 2014 for Civil Works 1743
Analysis of PWD SoR 2014 for Civil Works 1744
Analysis of PWD SoR 2014 for Civil Works 1745
Analysis of PWD SoR 2014 for Civil Works 1746
Analysis of PWD SoR 2014 for Civil Works 1747
Analysis of PWD SoR 2014 for Civil Works 1748
Analysis of PWD SoR 2014 for Civil Works 1749
Analysis of PWD SoR 2014 for Civil Works 1750
Analysis of PWD SoR 2014 for Civil Works 1751
Analysis of PWD SoR 2014 for Civil Works 1752
Analysis of PWD SoR 2014 for Civil Works 1753
Analysis of PWD SoR 2014 for Civil Works 1754
Analysis of PWD SoR 2014 for Civil Works 1755
Analysis of PWD SoR 2014 for Civil Works 1756
Analysis of PWD SoR 2014 for Civil Works 1757
Analysis of PWD SoR 2014 for Civil Works 1758
Analysis of PWD SoR 2014 for Civil Works 1759
Analysis of PWD SoR 2014 for Civil Works 1760
Analysis of PWD SoR 2014 for Civil Works 1761
Analysis of PWD SoR 2014 for Civil Works 1762
Analysis of PWD SoR 2014 for Civil Works 1763
Analysis of PWD SoR 2014 for Civil Works 1764
Analysis of PWD SoR 2014 for Civil Works 1765
Analysis of PWD SoR 2014 for Civil Works 1766
Analysis of PWD SoR 2014 for Civil Works 1767
Analysis of PWD SoR 2014 for Civil Works 1768
Analysis of PWD SoR 2014 for Civil Works 1769
Analysis of PWD SoR 2014 for Civil Works 1770
Analysis of PWD SoR 2014 for Civil Works 1771
Analysis of PWD SoR 2014 for Civil Works 1772
Analysis of PWD SoR 2014 for Civil Works 1773
Analysis of PWD SoR 2014 for Civil Works 1774
Analysis of PWD SoR 2014 for Civil Works 1775
Analysis of PWD SoR 2014 for Civil Works 1776
Analysis of PWD SoR 2014 for Civil Works 1777
Analysis of PWD SoR 2014 for Civil Works 1778
Analysis of PWD SoR 2014 for Civil Works 1779
Analysis of PWD SoR 2014 for Civil Works 1780
Analysis of PWD SoR 2014 for Civil Works 1781
Analysis of PWD SoR 2014 for Civil Works 1782
Analysis of PWD SoR 2014 for Civil Works 1783
Analysis of PWD SoR 2014 for Civil Works 1784
Analysis of PWD SoR 2014 for Civil Works 1785
Analysis of PWD SoR 2014 for Civil Works 1786
Analysis of PWD SoR 2014 for Civil Works 1787
Analysis of PWD SoR 2014 for Civil Works 1788
Analysis of PWD SoR 2014 for Civil Works 1789
Analysis of PWD SoR 2014 for Civil Works 1790
Analysis of PWD SoR 2014 for Civil Works 1791
Analysis of PWD SoR 2014 for Civil Works 1792
Analysis of PWD SoR 2014 for Civil Works 1793
Analysis of PWD SoR 2014 for Civil Works 1794
Analysis of PWD SoR 2014 for Civil Works 1795
Analysis of PWD SoR 2014 for Civil Works 1796
Analysis of PWD SoR 2014 for Civil Works 1797
Analysis of PWD SoR 2014 for Civil Works 1798
Analysis of PWD SoR 2014 for Civil Works 1799
Analysis of PWD SoR 2014 for Civil Works 1800
Analysis of PWD SoR 2014 for Civil Works 1801
Analysis of PWD SoR 2014 for Civil Works 1802
Analysis of PWD SoR 2014 for Civil Works 1803
Analysis of PWD SoR 2014 for Civil Works 1804
Analysis of PWD SoR 2014 for Civil Works 1805
Analysis of PWD SoR 2014 for Civil Works 1806
Analysis of PWD SoR 2014 for Civil Works 1807
Analysis of PWD SoR 2014 for Civil Works 1808
Analysis of PWD SoR 2014 for Civil Works 1809
Analysis of PWD SoR 2014 for Civil Works 1810
Analysis of PWD SoR 2014 for Civil Works 1811
Analysis of PWD SoR 2014 for Civil Works 1812
Analysis of PWD SoR 2014 for Civil Works 1813
Analysis of PWD SoR 2014 for Civil Works 1814
Analysis of PWD SoR 2014 for Civil Works 1815
Analysis of PWD SoR 2014 for Civil Works 1816
Analysis of PWD SoR 2014 for Civil Works 1817
Analysis of PWD SoR 2014 for Civil Works 1818
Analysis of PWD SoR 2014 for Civil Works 1819
Analysis of PWD SoR 2014 for Civil Works 1820
Analysis of PWD SoR 2014 for Civil Works 1821
Analysis of PWD SoR 2014 for Civil Works 1822
Analysis of PWD SoR 2014 for Civil Works 1823
Analysis of PWD SoR 2014 for Civil Works 1824
Analysis of PWD SoR 2014 for Civil Works 1825
Analysis of PWD SoR 2014 for Civil Works 1826
Analysis of PWD SoR 2014 for Civil Works 1827
Analysis of PWD SoR 2014 for Civil Works 1828
Analysis of PWD SoR 2014 for Civil Works 1829
Analysis of PWD SoR 2014 for Civil Works 1830
Analysis of PWD SoR 2014 for Civil Works 1831
Analysis of PWD SoR 2014 for Civil Works 1832
Analysis of PWD SoR 2014 for Civil Works 1833
Analysis of PWD SoR 2014 for Civil Works 1834
Analysis of PWD SoR 2014 for Civil Works 1835
Analysis of PWD SoR 2014 for Civil Works 1836
Analysis of PWD SoR 2014 for Civil Works 1837
Analysis of PWD SoR 2014 for Civil Works 1838
Analysis of PWD SoR 2014 for Civil Works 1839
Analysis of PWD SoR 2014 for Civil Works 1840
Analysis of PWD SoR 2014 for Civil Works 1841
Analysis of PWD SoR 2014 for Civil Works 1842
Analysis of PWD SoR 2014 for Civil Works 1843
Analysis of PWD SoR 2014 for Civil Works 1844
Analysis of PWD SoR 2014 for Civil Works 1845
Analysis of PWD SoR 2014 for Civil Works 1846
Analysis of PWD SoR 2014 for Civil Works 1847
Analysis of PWD SoR 2014 for Civil Works 1848
Analysis of PWD SoR 2014 for Civil Works 1849
Analysis of PWD SoR 2014 for Civil Works 1850
Analysis of PWD SoR 2014 for Civil Works 1851
Analysis of PWD SoR 2014 for Civil Works 1852
Analysis of PWD SoR 2014 for Civil Works 1853
Analysis of PWD SoR 2014 for Civil Works 1854
Analysis of PWD SoR 2014 for Civil Works 1855
Analysis of PWD SoR 2014 for Civil Works 1856
Analysis of PWD SoR 2014 for Civil Works 1857
Analysis of PWD SoR 2014 for Civil Works 1858
Analysis of PWD SoR 2014 for Civil Works 1859
Analysis of PWD SoR 2014 for Civil Works 1860
Analysis of PWD SoR 2014 for Civil Works 1861
Analysis of PWD SoR 2014 for Civil Works 1862
Analysis of PWD SoR 2014 for Civil Works 1863
Analysis of PWD SoR 2014 for Civil Works 1864
Analysis of PWD SoR 2014 for Civil Works 1865
Analysis of PWD SoR 2014 for Civil Works 1866
Analysis of PWD SoR 2014 for Civil Works 1867
Analysis of PWD SoR 2014 for Civil Works 1868
Analysis of PWD SoR 2014 for Civil Works 1869
Analysis of PWD SoR 2014 for Civil Works 1870
Analysis of PWD SoR 2014 for Civil Works 1871
Analysis of PWD SoR 2014 for Civil Works 1872
Analysis of PWD SoR 2014 for Civil Works 1873
Analysis of PWD SoR 2014 for Civil Works 1874
Analysis of PWD SoR 2014 for Civil Works 1875
Analysis of PWD SoR 2014 for Civil Works 1876
Analysis of PWD SoR 2014 for Civil Works 1877
Analysis of PWD SoR 2014 for Civil Works 1878
Analysis of PWD SoR 2014 for Civil Works 1879
Analysis of PWD SoR 2014 for Civil Works 1880
Analysis of PWD SoR 2014 for Civil Works 1881
Analysis of PWD SoR 2014 for Civil Works 1882
Analysis of PWD SoR 2014 for Civil Works 1883
Analysis of PWD SoR 2014 for Civil Works 1884
Analysis of PWD SoR 2014 for Civil Works 1885
Analysis of PWD SoR 2014 for Civil Works 1886
Analysis of PWD SoR 2014 for Civil Works 1887
Analysis of PWD SoR 2014 for Civil Works 1888
Analysis of PWD SoR 2014 for Civil Works 1889
Analysis of PWD SoR 2014 for Civil Works 1890
Analysis of PWD SoR 2014 for Civil Works 1891
Analysis of PWD SoR 2014 for Civil Works 1892
Analysis of PWD SoR 2014 for Civil Works 1893
Analysis of PWD SoR 2014 for Civil Works 1894
Analysis of PWD SoR 2014 for Civil Works 1895
Analysis of PWD SoR 2014 for Civil Works 1896
Analysis of PWD SoR 2014 for Civil Works 1897
Analysis of PWD SoR 2014 for Civil Works 1898
Analysis of PWD SoR 2014 for Civil Works 1899
Analysis of PWD SoR 2014 for Civil Works 1900
Analysis of PWD SoR 2014 for Civil Works 1901
Analysis of PWD SoR 2014 for Civil Works 1902
Analysis of PWD SoR 2014 for Civil Works 1903
Analysis of PWD SoR 2014 for Civil Works 1904
Analysis of PWD SoR 2014 for Civil Works 1905
Analysis of PWD SoR 2014 for Civil Works 1906
Analysis of PWD SoR 2014 for Civil Works 1907
Analysis of PWD SoR 2014 for Civil Works 1908
Analysis of PWD SoR 2014 for Civil Works 1909
Analysis of PWD SoR 2014 for Civil Works 1910
Analysis of PWD SoR 2014 for Civil Works 1911
Analysis of PWD SoR 2014 for Civil Works 1912
Analysis of PWD SoR 2014 for Civil Works 1913
Analysis of PWD SoR 2014 for Civil Works 1914
Analysis of PWD SoR 2014 for Civil Works 1915
Analysis of PWD SoR 2014 for Civil Works 1916
Analysis of PWD SoR 2014 for Civil Works 1917
Analysis of PWD SoR 2014 for Civil Works 1918
Analysis of PWD SoR 2014 for Civil Works 1919
Analysis of PWD SoR 2014 for Civil Works 1920
Analysis of PWD SoR 2014 for Civil Works 1921
Analysis of PWD SoR 2014 for Civil Works 1922
Analysis of PWD SoR 2014 for Civil Works 1923
Analysis of PWD SoR 2014 for Civil Works 1924
Analysis of PWD SoR 2014 for Civil Works 1925
Analysis of PWD SoR 2014 for Civil Works 1926
Analysis of PWD SoR 2014 for Civil Works 1927
Analysis of PWD SoR 2014 for Civil Works 1928
Analysis of PWD SoR 2014 for Civil Works 1929
Analysis of PWD SoR 2014 for Civil Works 1930
Analysis of PWD SoR 2014 for Civil Works 1931
Analysis of PWD SoR 2014 for Civil Works 1932
Analysis of PWD SoR 2014 for Civil Works 1933
Analysis of PWD SoR 2014 for Civil Works 1934
Analysis of PWD SoR 2014 for Civil Works 1935
Analysis of PWD SoR 2014 for Civil Works 1936
Analysis of PWD SoR 2014 for Civil Works 1937
Analysis of PWD SoR 2014 for Civil Works 1938
Analysis of PWD SoR 2014 for Civil Works 1939
Analysis of PWD SoR 2014 for Civil Works 1940
Analysis of PWD SoR 2014 for Civil Works 1941
Analysis of PWD SoR 2014 for Civil Works 1942
Analysis of PWD SoR 2014 for Civil Works 1943
Analysis of PWD SoR 2014 for Civil Works 1944
Analysis of PWD SoR 2014 for Civil Works 1945
Analysis of PWD SoR 2014 for Civil Works 1946
Analysis of PWD SoR 2014 for Civil Works 1947
Analysis of PWD SoR 2014 for Civil Works 1948
Analysis of PWD SoR 2014 for Civil Works 1949
Analysis of PWD SoR 2014 for Civil Works 1950
Analysis of PWD SoR 2014 for Civil Works 1951
Analysis of PWD SoR 2014 for Civil Works 1952
Analysis of PWD SoR 2014 for Civil Works 1953
Analysis of PWD SoR 2014 for Civil Works 1954
Analysis of PWD SoR 2014 for Civil Works 1955
Analysis of PWD SoR 2014 for Civil Works 1956
Analysis of PWD SoR 2014 for Civil Works 1957
Analysis of PWD SoR 2014 for Civil Works 1958
Analysis of PWD SoR 2014 for Civil Works 1959
Analysis of PWD SoR 2014 for Civil Works 1960
Analysis of PWD SoR 2014 for Civil Works 1961
Analysis of PWD SoR 2014 for Civil Works 1962
Analysis of PWD SoR 2014 for Civil Works 1963
Analysis of PWD SoR 2014 for Civil Works 1964
Analysis of PWD SoR 2014 for Civil Works 1965
Analysis of PWD SoR 2014 for Civil Works 1966
Analysis of PWD SoR 2014 for Civil Works 1967
Analysis of PWD SoR 2014 for Civil Works 1968
Analysis of PWD SoR 2014 for Civil Works 1969
Analysis of PWD SoR 2014 for Civil Works 1970
Analysis of PWD SoR 2014 for Civil Works 1971
Analysis of PWD SoR 2014 for Civil Works 1972
Analysis of PWD SoR 2014 for Civil Works 1973
Analysis of PWD SoR 2014 for Civil Works 1974
Analysis of PWD SoR 2014 for Civil Works 1975
Analysis of PWD SoR 2014 for Civil Works 1976
Analysis of PWD SoR 2014 for Civil Works 1977
Analysis of PWD SoR 2014 for Civil Works 1978
Analysis of PWD SoR 2014 for Civil Works 1979
Analysis of PWD SoR 2014 for Civil Works 1980
Analysis of PWD SoR 2014 for Civil Works 1981
Analysis of PWD SoR 2014 for Civil Works 1982
Analysis of PWD SoR 2014 for Civil Works 1983
Analysis of PWD SoR 2014 for Civil Works 1984
Analysis of PWD SoR 2014 for Civil Works 1985
Analysis of PWD SoR 2014 for Civil Works 1986
Analysis of PWD SoR 2014 for Civil Works 1987
Analysis of PWD SoR 2014 for Civil Works 1988
Analysis of PWD SoR 2014 for Civil Works 1989
Analysis of PWD SoR 2014 for Civil Works 1990
Analysis of PWD SoR 2014 for Civil Works 1991
Analysis of PWD SoR 2014 for Civil Works 1992
Analysis of PWD SoR 2014 for Civil Works 1993
Analysis of PWD SoR 2014 for Civil Works 1994
Analysis of PWD SoR 2014 for Civil Works 1995
Analysis of PWD SoR 2014 for Civil Works 1996
Analysis of PWD SoR 2014 for Civil Works 1997
Analysis of PWD SoR 2014 for Civil Works 1998
Analysis of PWD SoR 2014 for Civil Works 1999
Analysis of PWD SoR 2014 for Civil Works 2000
Analysis of PWD SoR 2014 for Civil Works 2001
Analysis of PWD SoR 2014 for Civil Works 2002
Analysis of PWD SoR 2014 for Civil Works 2003
Analysis of PWD SoR 2014 for Civil Works 2004
Analysis of PWD SoR 2014 for Civil Works 2005
Analysis of PWD SoR 2014 for Civil Works 2006
Analysis of PWD SoR 2014 for Civil Works 2007
Analysis of PWD SoR 2014 for Civil Works 2008
Analysis of PWD SoR 2014 for Civil Works 2009
Analysis of PWD SoR 2014 for Civil Works 2010
Analysis of PWD SoR 2014 for Civil Works 2011
Analysis of PWD SoR 2014 for Civil Works 2012
Analysis of PWD SoR 2014 for Civil Works 2013
Analysis of PWD SoR 2014 for Civil Works 2014
Analysis of PWD SoR 2014 for Civil Works 2015
Analysis of PWD SoR 2014 for Civil Works 2016
Analysis of PWD SoR 2014 for Civil Works 2017
Analysis of PWD SoR 2014 for Civil Works 2018
Analysis of PWD SoR 2014 for Civil Works 2019
Analysis of PWD SoR 2014 for Civil Works 2020
Analysis of PWD SoR 2014 for Civil Works 2021
Analysis of PWD SoR 2014 for Civil Works 2022
Analysis of PWD SoR 2014 for Civil Works 2023
Analysis of PWD SoR 2014 for Civil Works 2024
Analysis of PWD SoR 2014 for Civil Works 2025
Analysis of PWD SoR 2014 for Civil Works 2026
Analysis of PWD SoR 2014 for Civil Works 2027
Analysis of PWD SoR 2014 for Civil Works 2028
Analysis of PWD SoR 2014 for Civil Works 2029
Analysis of PWD SoR 2014 for Civil Works 2030
Analysis of PWD SoR 2014 for Civil Works 2031
Analysis of PWD SoR 2014 for Civil Works 2032
Analysis of PWD SoR 2014 for Civil Works 2033
Analysis of PWD SoR 2014 for Civil Works 2034
Analysis of PWD SoR 2014 for Civil Works 2035
Analysis of PWD SoR 2014 for Civil Works 2036
Analysis of PWD SoR 2014 for Civil Works 2037
Analysis of PWD SoR 2014 for Civil Works 2038
Analysis of PWD SoR 2014 for Civil Works 2039
Analysis of PWD SoR 2014 for Civil Works 2040
Analysis of PWD SoR 2014 for Civil Works 2041
Analysis of PWD SoR 2014 for Civil Works 2042
Analysis of PWD SoR 2014 for Civil Works 2043
Analysis of PWD SoR 2014 for Civil Works 2044
Analysis of PWD SoR 2014 for Civil Works 2045
Analysis of PWD SoR 2014 for Civil Works 2046
Analysis of PWD SoR 2014 for Civil Works 2047
Analysis of PWD SoR 2014 for Civil Works 2048
Analysis of PWD SoR 2014 for Civil Works 2049
Analysis of PWD SoR 2014 for Civil Works 2050
Analysis of PWD SoR 2014 for Civil Works 2051
Analysis of PWD SoR 2014 for Civil Works 2052
Analysis of PWD SoR 2014 for Civil Works 2053
Analysis of PWD SoR 2014 for Civil Works 2054
Analysis of PWD SoR 2014 for Civil Works 2055
Analysis of PWD SoR 2014 for Civil Works 2056
Analysis of PWD SoR 2014 for Civil Works 2057
Analysis of PWD SoR 2014 for Civil Works 2058
Analysis of PWD SoR 2014 for Civil Works 2059
Analysis of PWD SoR 2014 for Civil Works 2060
Analysis of PWD SoR 2014 for Civil Works 2061
Analysis of PWD SoR 2014 for Civil Works 2062
Analysis of PWD SoR 2014 for Civil Works 2063
Analysis of PWD SoR 2014 for Civil Works 2064
Analysis of PWD SoR 2014 for Civil Works 2065
Analysis of PWD SoR 2014 for Civil Works 2066
Analysis of PWD SoR 2014 for Civil Works 2067
Analysis of PWD SoR 2014 for Civil Works 2068
Analysis of PWD SoR 2014 for Civil Works 2069
Analysis of PWD SoR 2014 for Civil Works 2070
Analysis of PWD SoR 2014 for Civil Works 2071
Analysis of PWD SoR 2014 for Civil Works 2072
Analysis of PWD SoR 2014 for Civil Works 2073
Analysis of PWD SoR 2014 for Civil Works 2074
Analysis of PWD SoR 2014 for Civil Works 2075
Analysis of PWD SoR 2014 for Civil Works 2076
Analysis of PWD SoR 2014 for Civil Works 2077
Analysis of PWD SoR 2014 for Civil Works 2078
Analysis of PWD SoR 2014 for Civil Works 2079
Analysis of PWD SoR 2014 for Civil Works 2080
Analysis of PWD SoR 2014 for Civil Works 2081
Analysis of PWD SoR 2014 for Civil Works 2082
Analysis of PWD SoR 2014 for Civil Works 2083
Analysis of PWD SoR 2014 for Civil Works 2084
Analysis of PWD SoR 2014 for Civil Works 2085
Analysis of PWD SoR 2014 for Civil Works 2086
Analysis of PWD SoR 2014 for Civil Works 2087
Analysis of PWD SoR 2014 for Civil Works 2088
Analysis of PWD SoR 2014 for Civil Works 2089
Analysis of PWD SoR 2014 for Civil Works 2090
Analysis of PWD SoR 2014 for Civil Works 2091
Analysis of PWD SoR 2014 for Civil Works 2092
Analysis of PWD SoR 2014 for Civil Works 2093
Analysis of PWD SoR 2014 for Civil Works 2094
Analysis of PWD SoR 2014 for Civil Works 2095
Analysis of PWD SoR 2014 for Civil Works 2096
Analysis of PWD SoR 2014 for Civil Works 2097
Analysis of PWD SoR 2014 for Civil Works 2098
Analysis of PWD SoR 2014 for Civil Works 2099
Analysis of PWD SoR 2014 for Civil Works 2100
Analysis of PWD SoR 2014 for Civil Works 2101
Analysis of PWD SoR 2014 for Civil Works 2102
Analysis of PWD SoR 2014 for Civil Works 2103
Analysis of PWD SoR 2014 for Civil Works 2104
Analysis of PWD SoR 2014 for Civil Works 2105
Analysis of PWD SoR 2014 for Civil Works 2106
Analysis of PWD SoR 2014 for Civil Works 2107
Analysis of PWD SoR 2014 for Civil Works 2108
Analysis of PWD SoR 2014 for Civil Works 2109
Analysis of PWD SoR 2014 for Civil Works 2110
Analysis of PWD SoR 2014 for Civil Works 2111
Analysis of PWD SoR 2014 for Civil Works 2112
Analysis of PWD SoR 2014 for Civil Works 2113
Analysis of PWD SoR 2014 for Civil Works 2114
Analysis of PWD SoR 2014 for Civil Works 2115
Analysis of PWD SoR 2014 for Civil Works 2116
Analysis of PWD SoR 2014 for Civil Works 2117
Analysis of PWD SoR 2014 for Civil Works 2118
Analysis of PWD SoR 2014 for Civil Works 2119
Analysis of PWD SoR 2014 for Civil Works 2120
Analysis of PWD SoR 2014 for Civil Works 2121
Analysis of PWD SoR 2014 for Civil Works 2122
Analysis of PWD SoR 2014 for Civil Works 2123
Analysis of PWD SoR 2014 for Civil Works 2124
Analysis of PWD SoR 2014 for Civil Works 2125
Analysis of PWD SoR 2014 for Civil Works 2126
Analysis of PWD SoR 2014 for Civil Works 2127
Analysis of PWD SoR 2014 for Civil Works 2128
Analysis of PWD SoR 2014 for Civil Works 2129
Analysis of PWD SoR 2014 for Civil Works 2130
Analysis of PWD SoR 2014 for Civil Works 2131
Analysis of PWD SoR 2014 for Civil Works 2132
Analysis of PWD SoR 2014 for Civil Works 2133
Analysis of PWD SoR 2014 for Civil Works 2134
Analysis of PWD SoR 2014 for Civil Works 2135
Analysis of PWD SoR 2014 for Civil Works 2136
Analysis of PWD SoR 2014 for Civil Works 2137
Analysis of PWD SoR 2014 for Civil Works 2138
Analysis of PWD SoR 2014 for Civil Works 2139
Analysis of PWD SoR 2014 for Civil Works 2140
Analysis of PWD SoR 2014 for Civil Works 2141
Analysis of PWD SoR 2014 for Civil Works 2142
Analysis of PWD SoR 2014 for Civil Works 2143
Analysis of PWD SoR 2014 for Civil Works 2144
Analysis of PWD SoR 2014 for Civil Works 2145
Analysis of PWD SoR 2014 for Civil Works 2146
Analysis of PWD SoR 2014 for Civil Works 2147
Analysis of PWD SoR 2014 for Civil Works 2148
Analysis of PWD SoR 2014 for Civil Works 2149
Analysis of PWD SoR 2014 for Civil Works 2150
Analysis of PWD SoR 2014 for Civil Works 2151
Analysis of PWD SoR 2014 for Civil Works 2152
Analysis of PWD SoR 2014 for Civil Works 2153
Analysis of PWD SoR 2014 for Civil Works 2154
Analysis of PWD SoR 2014 for Civil Works 2155
Analysis of PWD SoR 2014 for Civil Works 2156
Analysis of PWD SoR 2014 for Civil Works 2157
Analysis of PWD SoR 2014 for Civil Works 2158
Analysis of PWD SoR 2014 for Civil Works 2159
Analysis of PWD SoR 2014 for Civil Works 2160
Analysis of PWD SoR 2014 for Civil Works 2161
Analysis of PWD SoR 2014 for Civil Works 2162
Analysis of PWD SoR 2014 for Civil Works 2163
Analysis of PWD SoR 2014 for Civil Works 2164
Analysis of PWD SoR 2014 for Civil Works 2165
Analysis of PWD SoR 2014 for Civil Works 2166
Analysis of PWD SoR 2014 for Civil Works 2167
Analysis of PWD SoR 2014 for Civil Works 2168
Analysis of PWD SoR 2014 for Civil Works 2169
Analysis of PWD SoR 2014 for Civil Works 2170
Analysis of PWD SoR 2014 for Civil Works 2171
Analysis of PWD SoR 2014 for Civil Works 2172
Analysis of PWD SoR 2014 for Civil Works 2173
Analysis of PWD SoR 2014 for Civil Works 2174
Analysis of PWD SoR 2014 for Civil Works 2175
Analysis of PWD SoR 2014 for Civil Works 2176
Analysis of PWD SoR 2014 for Civil Works 2177
Analysis of PWD SoR 2014 for Civil Works 2178
Analysis of PWD SoR 2014 for Civil Works 2179
Analysis of PWD SoR 2014 for Civil Works 2180
Analysis of PWD SoR 2014 for Civil Works 2181
Analysis of PWD SoR 2014 for Civil Works 2182
Analysis of PWD SoR 2014 for Civil Works 2183
Analysis of PWD SoR 2014 for Civil Works 2184
Analysis of PWD SoR 2014 for Civil Works 2185
Analysis of PWD SoR 2014 for Civil Works 2186
Analysis of PWD SoR 2014 for Civil Works 2187
Analysis of PWD SoR 2014 for Civil Works 2188
Analysis of PWD SoR 2014 for Civil Works 2189
Analysis of PWD SoR 2014 for Civil Works 2190
Analysis of PWD SoR 2014 for Civil Works 2191
Analysis of PWD SoR 2014 for Civil Works 2192
Analysis of PWD SoR 2014 for Civil Works 2193
Analysis of PWD SoR 2014 for Civil Works 2194
Analysis of PWD SoR 2014 for Civil Works 2195
Analysis of PWD SoR 2014 for Civil Works 2196
Analysis of PWD SoR 2014 for Civil Works 2197
Analysis of PWD SoR 2014 for Civil Works 2198
Analysis of PWD SoR 2014 for Civil Works 2199