SCHEDULE PEMBANGUNAN 1

QUANTITY
NO URAIAN PEKERJAAN PCS / UNIT Minggu 1
SET 1 2 3 4 5
1 2 3 4 5
A. PEKERJAAN PERSIAPAN
1 Persiapan Moulding 1 Lot
2 Persiapan Alat, Tempat & Kelengkapan Kerja 1 Lot

B. PEKERJAAN LAMBUNG, BANGUNAN ATAS, & OUT FITTING


1 Laminasi Hull 1 Lot
2 Laminasi Superstructure 1 Lot
3 Laminasi Frame & Girder 1 Lot
4 Laminasi Deck 1 Lot
6 Laminasi Outfitting 1 Lot
7 Konstruksi 1 Lot
8 Assembly 1 Lot
9 Pemasangan Outfitting 1 Lot
10 Interior 1 Lot

C. PEKERJAAN FINISHING
1 Primer Finishing 1 Lot
2 Total Finishing 1 Lot

D. PEKERJAAN SISTEM
1 Instalasi Mesin Induk 1 Lot
3 Instalasi Steering & Control System 1 Lot
4 Instalasi Propulsi 1 Lot
5 Instalasi Main Power & Distribution Cable 1 Lot
6 Instalasi Navigation & Communication Cable 1 Lot
7 Instalasi Main Switch Board & Distribution Board 1 Lot
8 Intslasi Mesin Penarik Jaring 1 Lot
9 Instalasi Genset & Peralatan Listrik 1 Lot
10 Instalasi Peralatan Navigasi & Komunikasi 1 Lot

E. PERLENGKAPAN
1 Instalasi Perlengkapan Keselamatan 1 Lot
3 Pengurusan Surat-Surat Kapal 1 Lot

E. LAUNCHING, TEST & TRIAL


1 Dock Trial 1 lot
2 Lauching 1 Lot
3 Sea Trial 1 Lot
BANGUNAN 1 UNIT KAPAL IKAN 10 GT

SCHEDULE PEMBANGUNAN 1 UNIT KAPAL IKAN 10 GT


Minggu 1 Minggu 2 Minggu 3 Minggu 4 Minggu 5 Minggu 6 Minggu 7 Minggu 8
6 7 1 2 3 4 5 6 7 1 2 3 4 5 6 7 1 2 3 4 5 6 7 1 2 3 4 5 6 7 1 2 3 4 5 6 7 1 2 3 4 5 6 7 1
5 6 6 7 8 9 10 19
Minggu 8
2 3 4 5 6 7
19
RENCANA ANGGARAN BIAYA (RAB)

HARGA SATUAN JUMLAH


NO URAIAN PEKERJAAN VOLUME SAT
(Rp) (Rp)
I. PEKERJAAN PERSIAPAN
1.1. Moulding
1.1.1. Pembersihan Moulding (Lambung) 340.0000 M2 6,750.00 2,295,000.00
1.1.2. Pembersihan Moulding (Bangunan Atas) 56.0000 M2 23,868.02 1,336,609.33
3,631,609.33

1.2. Persiapan Alat, Tempat & Kelengkapan Kerja


1.2.1. Persiapan Alat 148.2500 M3 16,600.00 2,460,950.00
1.2.2. Persiapan Tempat 0.0000 M3 21,790.00 0.00
1.2.3. Persiapan Kelengkapan Kerja 0.0000 M3 30,502.50 0.00
2,460,950.00

II. PEKERJAAN LAMBUNG, BANGUNAN ATAS, & OUTFITTING


2.1. Laminasi Hull
2.1.1. Pelapisan Wax pada Moulding (Lambung) 2.5744 M3 2,522,380.27 6,493,615.76
2.1.2. Pelapisan PVA pada Moulding (Lambung) 3.7960 M 3
840,091.40 3,188,986.95
2.1.3. Pelapisan GealCoat pada Moulding (Lambung) 4.9800 M3 3,616,849.70 18,011,911.50
2.1.4. Pelapisan FRP pada Moulding (Lambung) 3.4300 M3 3,115,744.55 10,687,003.82
2.1.5. Pelepasan produk 5.4600 M 3
2,437,479.00 13,308,635.33
51,690,153.37

2.2. Laminasi Superstructure (Bangunan Atas)


2.2.1. Pelapisan Wax pada Moulding (Bangunan Atas) 2.5744 M3 2,522,380.27 6,493,615.76
2.2.2. Pelapisan PVA pada Moulding (Bangunan Atas)
2.2.3. Pelapisan GealCoat pada Moulding (Bangunan At 0.8920 M3 502,503.60 448,233.21
2.2.4. Pelapisan FRP pada Moulding (Bangunan Atas)
2.2.5. Pelepasan produk
6,941,848.97

2.3. Laminasi Frame & Girder


2.3.1. Pembuatan Frame Dan Girder 2.5744 M3 2,522,380.27 6,493,615.76
2.3.2. Pelapisan Frame pada Frame dan Girder
6,493,615.76

2.4. Laminasi Deck


2.4.1. Pelapisan Wax pada Lantai Cetak 2.5744 M3 2,522,380.27 6,493,615.76
2.4.2. Pelapisan PVA pada Lantai Cetak
2.4.3. Pelapisan FRP pada Lantai Cetak
2.4.4. Pelepasan produk
6,493,615.76

3.2. Kusen
2.3.1. Kusen Pintu dan Jendela 1.2541 M3 2,786,375.00 3,494,392.89
3,494,392.89

IV. PEKERJAAN KAP DAN ATAP


4.1. Kap dan Rangka Atap
4.1.1.. Balok Dinding 8/12 0.2939 M3 16,037.50 4,713.42
4.1.2. Pekerjaan Kuda-Kuda 1.3629 M3 2,419,981.29 3,298,192.51
4.1.3. Pekerjaan Rangka Atap 138.0646 M3 34,345.00 4,741,828.69
4.1.4. Pekerjaan Listplank 3/25 53.9000 M3 28,935.00 1,559,596.50
4.1.5. Gording 8/12 5.6300 M 3
689,120.96 3,879,751.00
4.1.6. Talang 17.0000 M' 519,704.83 8,834,982.17
22,319,064.29
4.2. Atap
4.2.1. Pemasangan Atap 158.0646 M2 43,785.80 6,920,984.96
4.2.2. Pemasangan Perabung 34.1700 M3 130,387.47 4,455,339.71
11,376,324.68

V. PEKERJAAN PLAFOND
5.1. Balok Plafond
5.1.1. Rangka Plafon 207.0075 M2 36,913.93 7,641,460.07
7,641,460.07
5.2. Memasang Plafond
5.2.1. Memasang Plafond Gypsum 165.6500 M2 64,214.67 10,637,159.53
5.2.2. Memasang Lis Plafond 179.9500 12,394.20 2,230,336.29
12,867,495.82
VI. PEKERJAAN PLASTERAN
6.1. Plasteran
6.1.1. Plasteran Dinding (1:2) 134.5000 M2 26,166.30 3,519,366.81
6.1.2. Plasteran Dinding (1:4) 780.2350 M2 22,553.96 17,597,388.98
6.1.3. Aian 914.7350 M2 4,837.48 4,425,013.64
25,541,769.43
6.2. Turap Porslen
6.2.1. Pasangan Turap Porslent 47.2160 M2 114,875.64 5,423,968.22
5,423,968.22

VII. PEKERJAAN LANTAI


7.1. Urugan Bawah Lantai
7.1.1. Urugan Pasir 11.2648 107,150.00 1,207,023.32
1,207,023.32
7.2. Pasangan Lantai
7.2.1. Pasangan Lantai Kramik 33 x 33 182.3750 M2 127,032.22 23,167,501.85
7.2.2. Pasangan Lantai Kramik 20 x 20 24.6325 M2 148,382.22 3,655,025.13
26,822,526.98

VIII. PEKERJAAN PINTU DAN JENDELA


8.1. Pintu dan Jendela
8.1.1. Pasangan Pintu 28.9350 Bh 521,600.00 15,092,496.00
8.1.2. Pasangan Jendela kaca 17.0000 M2 219,829.17 3,737,095.83
18,829,591.83
8.2. Kaca
8.2.1. Pasangan Kaca Tebal 15 mm 71.5420 M2 112,829.75 8,072,065.97
8,072,065.97
8.3. Penggantung/Kunci
8.3.1. Pasangan Engsel Pintu 68.0000 Bh 25,592.50 1,740,290.00
8.3.3. Pasangan Kunci Taman Antik 12.0000 Bh 144,595.00 1,735,140.00
3,475,430.00

IX. PEKERJAAN PENGECATAN


9.1. Mendempul dan Mrnggosok Kayu 90.9809 M2 7,414.50 674,577.88
9.2. Mengecat Kayu Baru 610.5400 M2 20,915.50 12,769,749.37
9.3. Mengecat Tembok Baru 464.7500 M2 14,340.80 6,664,886.80
20,109,214.05

X. PEK. INSTALASI DAN SANITASI


10.1 Listrik
10.1.1 Pemasangan Listrik Baru 1.0000 Ls 9,380,200.00 9,380,200.00
9,380,200.00
10.2. Sanitair dan Instalasi Air
10.2.1. Pemasangna Kloset Jongkok 2.0000 Bh 604,640.00 1,209,280.00
10.2.2. Pemasangan Kloset Duduk 2.0000 Bh 2,193,695.00 4,387,390.00
10.2.3. Pemasangan Floor Draine 4.0000 Bh 25,725.00 102,900.00
10.2.4. Pemasangan Bak Cuci Piring 1.0000 Bh 346,747.50 346,747.50
10.2.5. Pemasangan Wastafel 2.0000 Bh 1,200,220.00 2,400,440.00
10.2.6. Pem. Pipa Air 3" Per M' 30.0000 M' 108,337.50 3,250,125.00
10.2.7. Pem. Pipa Air 3/4" AW Per M' 42.0000 M' 28,514.00 1,197,588.00
10.2.8. Pem. Pipa Air 1/2" AW Per M' 46.5300 M' 21,570.00 1,003,652.10
10.2.9. Pem. Kran Air 3/4" atau 1/2" 8.0000 Bh 47,075.00 376,600.00
14,274,722.60

XI. PEK. PERLENGKAPAN LUAR


11.1 Rabat Beton (1:3:5) 21.2100 641,206.40 13,599,987.74
11.2 Bak Kontrol 1.0000 331,601.21 331,601.21
11.3 Septictank 1.0000 1,138,954.58 1,138,954.58
11.4 Resapan 1.0000 1,690,248.83 1,690,248.83
16,760,792.36
SCHEDULE KEDATANGAN MATE

KAPAL IKAN 10 GT
10 GT SC
No Nama Barang Minggu 1
Jumlah
1 2 3

A. PEKERJAAN PERSIAPAN:
1 Moulding (Lambung) 1 Ls
2 Moulding (Bangunan Atas) 1 Ls
3 Alat kerja 1 Ls
4 Keel Block 15 Bh

B. PEKERJAAN LAMBUNG & BANGUNAN ATAS


1 Resin @225 Kg 6 Drum
2 CSM 300 @30 Kg 12 Roll
3 WR @50 Kg 6 Roll
4 Catalyst 45 Kg
5 Cobalt 17 Kg
6 Wax 12 Klng
7 Pigment Putih 14 Kg
8 Pigment Biru 28 Kg
9 Gealcoat@225Kg 1 Drum
10 PVA 3 Kg
11 Styrene Monomer (SM) 14 Kg
12 Talk 20 Zak
13 Foam Lembaran Tebal 50mm 40 Lembar
14 Roll Bulu Kecil 12 Bh
15 Roll Bulu Besar 6 Bh
16 Roll Besi 2 Bh
17 Mata Gerinda Potong 12 Bh
18 Mata Gerinda Kasar 24 Bh
19 Kuas 2,5" 14 Bh
20 Thinner A Biasa 14 Liter
21 Kayu Fender Ukuran 6 x 12 x 4meter 6 Lonjor
22 Kayu Pondasi Hauler 8 x 12 4 Meter
23 Pipa PVC 6" (Ducting) 2 Lonjor
24 Elbow PVC 6" 4 Bh
25 Kaca Depan Kanan/Kiri Tempered Frame Hitam 2 Bh
26 Kaca Tengah Tempered Frame Hitam 1 Bh
27 Kaca Bulat dia.300 Frame Hitam 3 Bh
28 Baut Kaca SS M6x3cm 180 Set
29 Jendela Geser Ukuran 40 x 60 Frame Hitam 1 Bh
30 Ventilator Kisi-Kisi SS ukuran 20 x 30 1 Bh
31 Triplex 10mm 5 Lmbar
32 Skrup 1" 1 Dus
33 Lem Fox Kuning 5 Kg

C. SISTEM PERPIPAAN
1 Pipa PVC 1,5" 3 Lonjor
2 Stop Kran PVC 1,5" 3 Lonjor
3 Elbow PVC 1,5" 4 Bh
4 Pipa Galvanize 3" 1 Lonjor
5 Pipa Galvanize 2" 2 Lonjor
6 Elbow 0,5" 4 Bh
7 Selang Bening 3/8" 2 Meter
8 Selang Bilga 1" 6 meter
9 Packing TBA 5mm 2 m2
10 Packing Karet 5mm (Air Tawar) 2 m2
11 Lem PVC 4 Bh

D. FINISHING :
1 Amplas 100 25 Meter
2 Amplas 150 25 Meter
3 Amplas 400 25 Meter
4 Kain Kompon 4 Bh
5 Kompon 2 Kg
6 Isolasi Kertas Kecil 25 Bh
7 Isolasi Kertas Besar 25 Bh
8 Koran Bekas 4 Kg
9 Thinner A SPC 14 Liter
10 Cat Putih 6 Kg

B. SISTEM PERMESINAN :
1 Mesin Tempel 25 HP 2 Set
3 Pipa Galvanize 2,5" 1 Lnjr
4 Pipa Galvanize 6" 1 Meter
6 Elbow 2,5" 1 Ls
7 Pipa Galvanize 1" 1 Lnjr
8 Elbow 1" 1 Ls
9 Sea Chest 2" 1 Bh
10 Stop Kran Kuningan 2" 1 Bh
11 Water Strainer 2" 1 Bh
12 Plat Engine Belt 10mm ukuran 40 x 200mm 2 Bh
13 Baut 5/8" x 5cm 1 Ls
14 Ring Pir 5/8" 1 Ls
15 Ring Plat 5/8" 1 Ls
16 Plat Kuningan 5mm ukuran 30x30 1 Bh
17 Racor 500 GPH 1 Bh
18 Selang Solar Ukuran 1/2" 10 Meter
19 Nipple (Cucut) Kuningan Ukuran 1/2" 4 Bh
20 Stop Kran Kuningan 1/2" 1 Bh
21 Double Nipple Galvanize 1/2" 2 Bh
24 Koker + Remes Packing 2 Bh
25 Flange (sesuai Gear Box) 1 Bh
26 Propeller ukuran 24 x 26 (4 Daun) 1 Bh
27 Baut Propeller Kuningan + Spie 1 Bh
28 Penekan Remes Packing 1 Set
33 Hydraulic Single Cylinder 1 Set
34 Selang Hydraulic 3/8" 20 Meter
35 Oli Hydraulic SAE 10 5 Liter
36 Oli Gear Box SAE 90 10 Liter
37 Oli Mesin SAE40 25 Liter
38 Helm Pump 1 Set
39 Steering Whell 1 St
40 Remote Cable 5 Meter
41 Handle Control 1 Bh
42 Ekstenstion Indicator Main Engine 1 Set
43 Water Cooler Pump SS 1" 1 Set
44 Baut 1/2x 10 1 Ls
45 Lossdrat 5/8 1 Ls
47 Zink Anode 2 Bh
48 Accu 120 Ah 2 Bh
49 Kepala Accu 4 Bh
50 Kabel Accu 2 Meter
51 Skun Accu 8 Bh
52 Portable Genset 5000 Watt 1 Set
53 Hand Pump 1 Bh
54 Box Toolkit & Perlengkapan Mesin 1 Set

C. SISTEM KELISTRIKAN & NAVIGASI :


1 Kabel NYM 2 x 1,5mm 60 Meter
2 Kabel NYMHY 2x1,5mm 58 Meter
3 Shore Connection 1 Bh
4 Panel Induk (MSB) Ukuran 30 x 40 1 Bh
5 Kabel BC30 10 Meter
6 Penangkal Petir 1 Bh
7 Panel DC 2 Bh
8 Switch Battery 2 Bh
9 Switch Dashboard 8 Gang DC 1 Bh
10 Switch Dashboard 6 Gang AC 1 Bh
11 Pompa Bilga DC 2 Bh
12 MCB 1 Phase 6A 2 Bh
13 MCB 1 Phase 1A 2 Bh
14 Fedder Panel 1 Ls
15 Kabel Ties 1 Box
16 Terminal Panel 1 Ls
17 Volt Meter 1 Bh
18 Ampere Meter 1 Bh
19 Pilot Lamp Indicator Panel 1 Bh
21 Lampu penerangan DC 3 Bh
22 Lampu Penerangan AC 4 Bh
23 Lampu Kerja 300 Watt 4 Bh
24 Lampu Navigasi 1 Ls
25 Radio VHF Marine + Antenna 1 Set
26 GPS MAP 1 Set
27 Compass Magnetic 1 Bh
28 Teropong 1 Bh
29 Peta Laut 1 Bh
30 Bendera Isyarat 1 Bh
31 Bendera Nasional 1 Bh

E. PERLENGKAPAN
1 Life Jacket 10 Bh
2 APAR 2,5 Kg 2 Bh
3 Ring Bouy 2 Bh
4 Kotak P3K & Isinya 1 Bh
5 Perlengkapan Memasak & Makan 1 Paket
6 Jangkar 20 Kg 2 Bh
7 Tali Jangkar 16mm 100 Meter
8 Tali Tambat 16mm 50 Meter
9 Tali Buang 10mm +Bandul 80 Meter
10 Damprah Ban Bekas 6 Bh
11 Surat Kapal 1 Set
DATANGAN MATERIAL

L IKAN 10 GT
SCHEDULE KEDATANGAN MATERIAL
Minggu 1 Minggu 2 Minggu 3 Minggu 4 Minggu 5 Minggu 6 Minggu 7 Minggu 8
4 1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4
31250000