Professional Documents
Culture Documents
(TKI 3105):
4 Theory of Constraints (ToC)
Optimised Production Technology (OPT)
Andi Sudiarso & Colleagues
Mechanical & Industrial Engineering
Faculty of Engineering
Gadjah Mada University
Introduction (1)
` Developing production planning and control would
be simple, except for the existence of random
problems, such as machine breakdown, worker
absenteeism, scrap and rework, lack of a part, and
order changes, and the fact that the operations are
linked one to another random fluctuations and
dependent events.
` MRP is to eliminate the dependence by having a
large inventory buffer at every work station.
` JIT is to eliminate the random problems by seeking
out the root cause of each problem and correcting
it, for example preventive maintenance to eliminate
machine breakdown.
Introduction (2)
` Both MRP and JIT practitioners believe that an ideal
plant is a balanced plant, i.e. every resource has the
same output capability relative to the plans need.
` The ToC approach is to accept the existence of an
unbalanced plant, i.e. some resources have less
relative output capability than the others. The most
limited resource is called the constraint.
` ToC eliminates dependencies by creating a material
buffer, but only at the constraint. Non-constraint
resources have a capacity buffer, i.e. excess
capacity.
Introduction (3)
` To add inventory to a non-constraint resource
causes lead time to increase and WIP inventory to
increase while providing little tangible benefits.
` ToC agrees with JIT that an inventory is a waste, if
the inventory is planned at a non-constraint
resource. However, by buffering the constraint
from random problems at other resources, an
inventory buffer at the constraint does add value
and hence it is not a waste.
` ToC does not eliminate all problems, only those
that threatens the constraint, in spite of the
constraints inventory buffer.
Company goal
` Operational measures:
Throughput
the rate of making money through sales
Inventory
the total money invested as products for sales
Operating expense
the total money that spent by the company to
change the inventory to throughput
Operational goal
` Operational goal:
a.
b.
Spare
parts
Y works 75% or spare parts pile up (on the assembly station)
d.
Finished
products
Y works 75% or finished products pile up (same demand assumed)
Number of bottleneck resources
` Is it possible to have more than one
bottleneck machine?
1500 3000
1000 1250
Raw
material 1 2 m CCR n Customers
Product Network
OPT
Resource Description
BUILDNET
Software (1)
OPT.SERVE Master
Engineering Network
SPLIT
OPT
Reports
OPT Software (2)
` BUILDNET module: to develop final product
network based on the database of MRP II
system, including bill of material, routings,
inventories, work centers, and market
requirements.
` SERVE module: to calculate the load profile
and the average utilization for each resource.
` SPLIT module: to divide product network into
two groups: critical and non-critical
resources. It also allocates buffer at the
correct locations.
OPT Software (3)
` OPT module: to create schedule (critical
resources are scheduled first) and reports,
load profile for BR (CCR) and NBR, and the
estimation of completion time.
See you again