CriticalPathMethod(CPM)inProjectManagement
ByFahadUsmani 136Comments

Ifyouhaveexperienceinprojectmanagement,youmighthaveheardaboutthecriticalpathmethod(CPM)aprojectmodeling
techniquedevelopedbyMorganR.WalkerandJamesE.Kellyinlate1950s(Wikipedia).

Thecriticalpathmethod(CPM)isusedextensivelybyprojectplannersworldwidefordevelopingtheprojectscheduleinalltypesof
projectsincludingIT,research,andconstruction.

ThismethodisabasisoftheprojectscheduleandisdiscussedverybroadlyinthePMBOKGuide.Youcanexpecttoseetwotothree
questions,ormore,inyourPMPexamfromthistopic.

Inthisblogpost,Iwilldiscussthecriticalpathwitharealworldexample,identifythecriticalpathinanetworkdiagram,andcalculatethe
floatforeachpath.Iwillthenlistsomeofthebenefitsandlimitationsofthecriticalpathmethod.

Onceyoubecomefamiliarwithit,IwillwalkyouthrougheverysteprequiredforcalculatingEarlyStart,EarlyFinishwithforward
pass,andthencalculateLateStart,LateFinishwithbackwardpass.

Makesureyouunderstandeachstepdescribed,otherwiseyoumightfacesomedifficultieswhenworkingwiththesecalculations.Ifyou
feelyouneedanyclarification,feelfreetoreachouttomeatanytime.

CriticalPath
Ifyoulookatanynetworkdiagram,youwillnoticemanypathsoriginatingfromonepointandendingatanotherpoint.Everypathwill
havesomeduration.Thepathwiththelongestdurationisknownasthecriticalpath.

Thecriticalpathcanbedefinedinmanywaysincluding:

https://pmstudycircle.com/2014/01/criticalpathmethodcpminprojectmanagement/ 1/33
12/19/2017 CriticalPathMethod(CPM)inProjectManagement

Thelongestpathinthenetworkdiagram,or 400PMPExamSampleQuestions TryitOut


Theshortestdurationinwhichtheprojectcanbecompleted.

Now,arethesetwodefinitionsaresimilar,oraretheyoppositetoeachother?

Infact,bothdefinitionsaretryingtoconveythesamemessage.Theymightseemoppositetoyoubecausethefirstdefinitionistalking
aboutthelongestpathandtheseconddefinitionistalkingabouttheshortestduration.

However,theybotharethesame.

Forexample,letssayyoureceivedaprojecttobuildthreebuildingsinonelocation.Thefirstbuildingisthelargestbuilding,thesecond
buildingisamediumsizedbuilding,andthethirdbuildingisthesmallestbuilding.

Youdevelopthenetworkdiagramwhichconsistsofthreepathseachpathresembleseachbuilding.

Youcalculatethedurationforeachpath.Forthefirstbuilding,thedurationis31months,thesecondbuildingwilltake18months,and
thethirdbuildingwillrequire13months.

Thefirstpathrepresentsthelargestbuildingthesecondpathrepresentsthemediumsizedbuilding,andthethirdpath,thesmallest
building.

Now,reviewtheabovediagram.

Didyounoticethatthepathforthefirstbuildingisthelongestdurationofallthree?Itisthirteenmonthslongerthanthesecondpath,
and18monthslongerthanthethirdpath.Thismeansthatifyoustartworkingonthefirstbuilding,youcanwait13monthsbefore
workingonthesecondbuildingbecauseyoucancompletesecondbuildingin18months.

Likewise,youcouldwait18monthstostartworkingonthethirdbuildingbecauseitwilltakeonly13monthstocomplete.Thismeans
thatevenifyoustartworkingonthethirdbuildingafter18monthsfromtheprojectstartdate,youcancompleteitontime.

Thiswaitingperiodisknownasthefloatorslack.

So,whichisthecriticalpathinthisnetworkdiagramofthreepaths?

Ofcourse,itisthelongestpathonthenetworkdiagram,becauseyoucannotcompleteyourprojectbeforeconstructingthefirstbuilding.
Althoughyoucancompletetheothertwobuildingsquickly,untilyoucompletethefirstbuilding,yourprojectisnotconsideredcomplete.

Hence,thecriticalpathisthelongestpathonthenetworkdiagram.

Now,whatistheshortestdurationinwhichyoucancompletetheproject?

https://pmstudycircle.com/2014/01/criticalpathmethodcpminprojectmanagement/ 2/33
12/19/2017 CriticalPathMethod(CPM)inProjectManagement

Sureenough,itis31months,becauseyoucannotcompleteyourprojectbefore31months,andthisisthedurationofthecriticalpath.
400PMPExamSampleQuestions TryitOut

Hence,thecriticalpathistheshortestdurationinwhichyoucancompletetheproject.

So,yousee,bothdefinitionsarethesame.

Wecanconcludethatthecriticalpathisthesequenceofactivitiesfromstarttoend,andithasthelongestdurationamongallpathsina
networkdiagram.

Inidealconditions,anetworkdiagram,andtherefore,theproject,shouldhaveonlyonecriticalpath.However,ifthenetworkdiagram
hasmorethanonecriticalpath,youwillbeinadifficultsituation.Inthiscase,youwillhavetomanagemorethanonepathinparallel.

Asweknow,thecriticalpathhasthelongestduration,anditsdurationisknownasthedurationoftheproject.Sinceactivitiesona
criticalpathhavenofloatorslack,noactivityshouldbedelayed.Ifthishappens,theprojectwillbedelayed.However,ifthereare
delays,youcanuseaschedulecompressiontool,suchasfasttrackingorschedulecrashing,tobringtheprojectontrack.

Visit:FastTrackingandCrashing

Note:Youmustalwaysupdatethenetworkdiagramifthereisanychangetoitsothatyoucanhaveabetterunderstandingofactivities
andpredictthefloat,projectcompletiondates,etc.

ProcedureforFindingtheCriticalPathinaNetworkDiagram
Thefollowingistheproceduretofindthecriticalpathonanetworkdiagram:

Drawthenetworkdiagram.
Identifyallpathsinthenetworkdiagram.
Findthedurationofeachpath.
Thepathwiththelargestdurationisthecriticalpath.

Letslookattheaboveprocedureinaction.

Example
Basedonthebelownetworkdiagram,identifythetotalpaths,criticalpath,andfloatforeachpath.

Theabovenetworkdiagramhasfivepathsthepathsandtheirdurationareasfollows:

1.Start>A>B>C>End,duration:31days.
2.Start>D>E>F>End,duration:18days.
3.Start>D>B>C>End,duration:26days.
4.Start>G>H>I>End,duration:13days.
5.Start>G>E>F>End,duration:16days.

https://pmstudycircle.com/2014/01/criticalpathmethodcpminprojectmanagement/ 3/33
12/19/2017 CriticalPathMethod(CPM)inProjectManagement

Sincethedurationofthefirstpathisthelongest,itisthecriticalpath.Thefloatonthecriticalpathiszero.
400PMPExamSampleQuestions TryitOut

ThefloatforthesecondpathStart>D>E>F>End=durationofthecriticalpathdurationofthepathStart>D>E>F>End

=3118=13

Hence,thefloatforthesecondpathis13days.

Usingthesameprocess,wecancalculatethefloatforotherpathsaswell.

Floatforthethirdpath=3126=5days.
Floatforthefourthpath=3113=18days.
Floatforthefifthpath=3116=15days.

CalculateEarlyStart(ES),EarlyFinish(EF),LateStart(LS),andLateFinish(LF)
Wehaveidentifiedthecriticalpath,andthedurationoftheotherpaths,itstimetomoveontomoreadvancedcalculations,EarlyStart,
EarlyFinish,LateStartandLateFinish.

CalculatingEarlyStart(ES)andEarlyFinish(EF)
TocalculatetheEarlyStartandEarlyFinishdates,weuseforwardpasswewillstartfromthebeginningandproceedtotheend.

EarlyStart(ES)forthefirstactivityonanypathwillbe1,becausenoactivitycanbestartedbeforethefirstday.Thestartpointforany
activityorstepalongthepathistheendpointofthepredecessoractivityonthepathplusone.

TheformulausedforcalculatingEarlyStartandEarlyFinishdates.

EarlyStartoftheactivity=EarlyFinishofpredecessoractivity+1
EarlyFinishoftheactivity=Activityduration+EarlyStartofactivity1

EarlyStartandEarlyFinishDatesforthepathStart>A>B>C>End

EarlyStartofactivityA=1(Sincethisisthefirstactivityofthepath)

EarlyFinishofactivityA=ESofactivityA+activityduration1
=1+101=10

EarlyStartofactivityB=EFofpredecessoractivity+1
=10+1=11

EarlyFinishofactivityB=ESofactivityB+activityduration1
=11+121=22

https://pmstudycircle.com/2014/01/criticalpathmethodcpminprojectmanagement/ 4/33
12/19/2017 CriticalPathMethod(CPM)inProjectManagement

EarlyStartofactivityC=EFofpredecessoractivity+1
400PMPExamSampleQuestions TryitOut
=22+1=23

EarlyFinishofactivityC=ESofactivityC+activityduration1
=23+91=31

EarlyStartandEarlyFinishDatesforthepathStart>D>E>F>End

EarlyStartofactivityD=1(Sincethisisthefirstactivityofthepath)

EarlyFinishofactivityD=1+51=5

EarlyStartofactivityE=EFofpredecessoractivity+1

SincetheActivityEhastwopredecessoractivities,whichonewillyouselect?YouwillselecttheactivitywiththegreaterEarlyFinish
date.EarlyFinishofactivityDis5,andEarlyFinishofactivityGis3(wewillcalculateitlater).

Therefore,wewillselecttheEarlyFinishofactivityDtofindtheEarlyStartofactivityE.

EarlyStartofactivityE=EFofpredecessoractivity+1
=5+1=6

EarlyFinishofactivityE=6+71=12

EarlyStartofactivityF=12+1=13

EarlyFinishofactivityF=13+61=18

EarlyStartandEarlyFinishDatesforthepathStart>G>H>I>End

EarlyStartofactivityG=1(Sincethisisthefirstactivityofthepath)

https://pmstudycircle.com/2014/01/criticalpathmethodcpminprojectmanagement/ 5/33
12/19/2017 CriticalPathMethod(CPM)inProjectManagement

EarlyFinishofactivityG=1+31=3 400PMPExamSampleQuestions TryitOut

EarlyStartofactivityH=3+1=4
EarlyFinishofactivityH=4+41=7

EarlyStartofactivityI=7+1=8
EarlyFinishofactivityI=8+61=13

CalculatingLateStart(LS)andLateFinish(LF)
WehavecalculatedEarlyStartandEarlyFinishdatesofallactivities.NowitistimetocalculatetheLateStartandLateFinishdates.

LateFinishofthelastactivityinanypathwillbethesameastheLastFinishofthelastactivityonthecriticalpath,becauseyoucannot
continueanyactivityoncetheprojectiscompleted.

ThefulausedforLateStartandLateFinishdates:

LateStartofActivity=LateFinishofactivityactivityduration+1
LateFinishofActivity=LateStartofsuccessoractivity1

TocalculatetheLateStartandLateFinish,weusebackwardpassi.e.wewillstartfromthelastactivityandmovebacktowardsthefirst
activity.

LateStartandLateFinishDatesforthepathStart>A>B>C>End

Onacriticalpath,EarlyStart,andEarlyFinishdateswillbethesameasLateStartandLateFinishdates.

LateStartandLateFinishDatesforthepathStart>D>E>F>End

LateFinishofactivityF=31(becauseyoucannotallowanyactivitytocrosstheprojectcompletiondate)

https://pmstudycircle.com/2014/01/criticalpathmethodcpminprojectmanagement/ 6/33
12/19/2017 CriticalPathMethod(CPM)inProjectManagement

LateStartofactivityF=LFofactivityFactivityduration+1
400PMPExamSampleQuestions TryitOut
=316+1=26

LateFinishofactivityE=LSofsuccessoractivity1
=LSofactivityF1
=261=25

LateStartofActivityE=LFofactivityEactivityduration+1
=257+1=19

LateFinishofactivityD=LSofsuccessoractivity1

Ifyoulookatthenetworkdiagram,youwillnoticethatactivityDhastwosuccessoractivities,BandE.So,whichactivitywillyouselect?

Youwillselecttheactivitywiththeearlier(least)LateStartdate.Here,LateStartofactivityBis11,andLateStartofactivityEis19.

Therefore,youwillselectactivityBwhichhastheearlierLateStartdate.

Hence,

LateFinishofactivityD=LSofactivityB1
=111=10

LateStartofActivityD=LFofactivityDactivityduration+1
=105+1=6

LateStartandLateFinishDatesforthepathStart>G>H>I>End

LateFinishofactivityI=31(becauseyoucannotallowanyactivitytocrosstheprojectcompletiondate)
LateStartofactivityI=316+1=26

LateFinishofactivityH=261=25
LateStartofactivityH=254+1=22

LateFinishofActivityG=191=18(wewillchoosethelatestartofactivityE,notactivityH,becausetheLateStartofactivityEis
earlierthantheLateStartofactivityH)

LateStartofactivityG=183+1
=16

CalculatetheFreeFloat
Istronglyrecommendyoureadmyblogpostontotalfloatandfreefloattogetabetterunderstandingbeforeproceedingfurther.

Visit:TotalFloatandFreeFloat
https://pmstudycircle.com/2014/01/criticalpathmethodcpminprojectmanagement/ 7/33
12/19/2017 CriticalPathMethod(CPM)inProjectManagement

TheformulafortheFreeFloatis: 400PMPExamSampleQuestions TryitOut

FreeFloat=ESofnextactivityEFofcurrentactivity1

BenefitsoftheCriticalPathMethod
Thefollowingareafewbenefitsofthecriticalpathmethod:

Itshowsthegraphicalviewoftheproject.
Itdiscoversandmakesdependenciesvisible.
Ithelpsinprojectplanning,scheduling,andcontrolling.
Ithelpsincontingencyplanning.
Itshowsthecriticalpath,andidentifiescriticalactivitiesrequiringspecialattention.
Ithelpsyouassignthefloattoactivitiesandflexibilitytofloatactivities.
Itshowsyouwhereyouneedtotakeactiontobringprojectbackontrack.

Althoughthecriticalpathisveryusefultoolinprojectplanning,italsohassomelimitationsanddrawbacks.

LimitationsanddrawbacksoftheCriticalPathMethod
Becausethecriticalpathmethodisanoptimalplanningtool,italwaysassumesthatallresourcesareavailablefortheprojectatall
times.
Itdoesnotconsiderresourcedependencies.
Therearechancesofmisusingfloatorslack.
Lessattentiononnoncriticalactivities,thoughsometimestheymayalsobecomecriticalactivities.
Projectsbasedonthecriticalpathoftenfailtobecompletedwithintheapprovedtimeduration.

Toovercometheseshortcomingsofthecriticalpath,thecriticalchainmethodwasdeveloped.Inthecriticalchainmethodresource
constraintsarealsotakenintoconsiderationwhiledevelopingthenetworkdiagram.

Visit:CriticalChainMethodinProjectManagement

Summary
Thecriticalpathmethodhashelpedmanyprojectmanagersdevelopandmanagetheirschedule.Inthecriticalpathmethod,youwill
drawanetworkdiagramwithmultiplepaths.Thepathwiththelongestdurationisknownasthecriticalpath.Duringyourproject
executionyourmainemphasiswillbeonthispath,becausethisisthelongestdurationpathandthedurationofthispathwillbeduration
oftheproject.

Asaprojectmanageryouhavetokeepaneyeonyournetworkdiagramandtakepromptcorrectiveactionwhenevernecessary.

Ifyouhaveanycommentsorquestions,youcandosointhecommentssectionbelow.

IfyouareinterestedinlearningallthemathematicalformulasforthePMPexam,youcantrymyPMPFormulaGuide.Youcanalsotry
myPMPQuestionBankandPMPMockTesttopracticePMPexamsamplequestions.

j 269 f 11 h 3 s 4

Comments

bravesays
February2,2014at12:47PM

Greatjob,ithelpsmealotontheCriticalPathsdefinition,istronglyagreewithFahadwhathesaid.

Reply

https://pmstudycircle.com/2014/01/criticalpathmethodcpminprojectmanagement/ 8/33
12/19/2017 CriticalPathMethod(CPM)inProjectManagement

400PMPExamSampleQuestions TryitOut
FahadUsmanisays
February11,2014at11:18AM

Thanksbraveforyourcomment.

Reply

harishchandrasays
June27,2016at11:04AM

LotofthanksIamtheMBA2ndSem.Student.WhenIwasseentheIcannotunderstandbutyouareclearlydefined
aboutCPMproblemissolutionitsgivesmetobetterideas.thanksonceagain..

Reply

FahadUsmanisays
June30,2016at10:54AM

YouarewelcomeHarish.

Reply

ksays
October31,2016at1:21PM

thiswashelpful

Reply

FahadUsmanisays
October31,2016at4:08PM

ThanksKforyourcomment.

Reply

chandrasays
November23,2016at5:54PM

canuexplainitincludinglagalso

Reply

FahadUsmanisays
November30,2016at1:17PM

Innextupdate,Iwilltrytoaddamorecomplexexample.

Reply

Garysays
January17,2017at7:31AM

https://pmstudycircle.com/2014/01/criticalpathmethodcpminprojectmanagement/ 9/33
12/19/2017 CriticalPathMethod(CPM)inProjectManagement

HiFahad, 400PMPExamSampleQuestions TryitOut


First,Thankyouforsharingyourknowledge,itisgreatlyappreciated!
IrecentlytookthePMPexam.IntheexamtheyhaveadifferentwayofrepresentingthePNDsquestionstheydonotlooklikewhat
youareshowinghereespeciallythetables.Canyoushowdifferentstylesoftablesanddiagrams?
Thanks

Reply

FahadUsmanisays
January18,2017at7:54AM

Canyouprovidemeanyexampleofit?

Reply

SayedQasimsays
February10,2014at8:17AM

Excellentposts,Pleasecontinue.

Reply

FahadUsmanisays
February11,2014at11:19AM

Thanksforstoppingby

Reply

JimMcKsays
February12,2014at11:46PM

WhilecalculationsusingtheDay1methodarequitesimple,doyounotbelievethatcalculatingtheCriticalPathislessinvolvedusingtheDay0
method?IknowthatbotharecorrectandperhapsitsjustamatterofpreferencebutitjustseemstomethatDay0allowsyoutodothe
calculationonsightandyoudonthavetotrack+/days.Thatbeingsaid,IamstudyingformyPMPexamandwouldappreciateguidanceifIam
notlookingatthisissuethewayIshouldbe.

Thankyouinadvanceforyourthoughts,advice&direction.

JimMcKinney

Reply

FahadUsmanisays
February13,2014at2:44PM

Itisyourchoicewhetheryouchosetostartfor0or1.IonlyfollowedtheconventionusedbythePMBOKguide.

Moreover,itsoundsgoodwhenyousay:Hey!todayismyfirstdayoftheproject,insteadofsayingHey!todayismyzerodayofthe
project

Reply

https://pmstudycircle.com/2014/01/criticalpathmethodcpminprojectmanagement/ 10/33
12/19/2017 CriticalPathMethod(CPM)inProjectManagement

400PMPExamSampleQuestions TryitOut

Donaldsays
February18,2016at9:18AM

IamthankfulforyourgreatworkMrFahad.itreallyhelpedmeinmyprojectmanagementcourse.

thanks.

Reply

FahadUsmanisays
February21,2016at1:42PM

YouarewelcomeDonald.

Reply

Malonesays
February13,2014at3:10PM

Iamabeginner.Formethisarticleislikeaboon.YoumadetheconceptofCPMlooksoeasy.Lookforwardtomanymoresucharticles.Good
Going.

Reply

FahadUsmanisays
February14,2014at8:48PM

ThankyouMaloneforyourcomment.

Reply

samsabasays
March6,2014at11:30PM

Ialreadyrecommendedthisarticletomyclassmates.wearetakingschedulingandcostcontrolcourse.
Ilikeit,andmyfriendstoo.Itissimpleandeasytounderstandtheconcept.Thanks.

Reply

FahadUsmanisays
March8,2014at3:38PM

Thanks.

Letmeknowifyouwantmetowriteonanytopic.

Reply

BayuGebeyehusays
June18,2015at3:34PM

Itaninterestingapproachyoudidanditwasmorefriendlytounderstand
Keepitup

https://pmstudycircle.com/2014/01/criticalpathmethodcpminprojectmanagement/ 11/33
12/19/2017 CriticalPathMethod(CPM)inProjectManagement

Manythanks 400PMPExamSampleQuestions TryitOut

Reply

FahadUsmanisays
June19,2015at11:04AM

ThanksBayuforyourcomment.

Reply

senedusays
November2,2015at10:02PM

Thanksomuch.Itisveryhelpful.

Reply

FahadUsmanisays
November3,2015at2:06PM

YouarewelcomeSenedu.

Reply

Ajsays
March18,2014at2:08AM

Fahad,
Thanksforagreatarticle.Iamcurrentlyinaprojectmanagement/operationsmanagementcourseandamstrugglingwiththeassignment.Would
youbewillingtotakealookandmaybegivemesomeadviceonhowtoproceed?

Thanks,
AJ

Reply

FahadUsmanisays
March18,2014at12:38PM

Youcansendmemailatfahad@pmstudycircle.com

Reply

Emmanuelsays
March21,2014at4:53PM

ThisarticleoffersasimplisticapproachtoCPM,Ireallyenjoyedreadingit.

Reply

FahadUsmanisays

https://pmstudycircle.com/2014/01/criticalpathmethodcpminprojectmanagement/ 12/33
12/19/2017 CriticalPathMethod(CPM)inProjectManagement
March23,2014at8:08AM
400PMPExamSampleQuestions TryitOut
ThanksEmmanuel

Reply

Mayokperesays
June10,2014at4:35AM

Brilliantwriteup!Ireallyenjoyedyourwriteup&lotsofdoubtshavebeencleardupGladIfoundyoursitebeforemyexams.canyouenlightenme
onthelimitationsofnetworkdiagrams?Manythanks.keepthegoodworksup.

Reply

FahadUsmanisays
June11,2014at7:28AM

Iftheprojectislargeandcomplexwithmanyactivitiesandrelationship,itmightgetdifficulttomanageandtakepropercontrolonit.

Reply

Somsays
June14,2014at4:28PM

ExcellentpostFahad.Verywellexplained.

Reply

FahadUsmanisays
June15,2014at7:25AM

ThanksSomforyourcomment.

Reply

mbalisays
July29,2014at1:30PM

Higuys,

iamaladyfromSouthAfricaandIamstrugglingwiththissubjectoncriticalpath.canyoukindlyhelpmeindrawingthenetworkdiagramforthe
following

activityDaysImmediatepredecessor
A10
B11
C9A,B
D5A,B
E8A,B
F13C,E
G5C,D
H10G
I6F,G
J9E,H
K11J

https://pmstudycircle.com/2014/01/criticalpathmethodcpminprojectmanagement/ 13/33
12/19/2017 CriticalPathMethod(CPM)inProjectManagement

Reply
400PMPExamSampleQuestions TryitOut

FahadUsmanisays
July29,2014at3:08PM

Pleasecheckyouremail.

Reply

nikunjdudhatrasays
May1,2016at8:38AM

Plzsendmealsosolution

Reply

MuziKhathidesays
August15,2014at10:18AM

Imhalfwaythroughthearticle,willfinishwhenimathomebutwantedtocommendyouonajobwelldoneFahad.

Gettingsomuchunderstanding.ImwritingmyCAPMexamintwoweekstimeandthisishelpingclearsomethingsup.

Reply

FahadUsmanisays
August15,2014at1:12PM

Imgladyoufindituseful.

Reply

MohammedEzazsays
August28,2014at3:42PM

HiFahad,
Firstofall,thanksalotforthiswonderfullpost,Onesmalldoubt,
Aspermyunderstanding,ActivityA,D&GarestartsinParellel,IfyesthenhowthefloatperiodforActivityG=2wasitnot7?
7sinceActivityAendson10thdayandGearlyendon3sodifferenceis7.
SamecalculationholdsgoodgorActivityDwhichiscorrect(Float=5).

ThanksinAdvance
Ezaz

Reply

FahadUsmanisays
August29,2014at1:23PM

Pleaserefermyblogpostontotalfloatandfreefloat:

https://pmstudycircle.com/2013/03/totalfloatversusfreefloat/

Reply

https://pmstudycircle.com/2014/01/criticalpathmethodcpminprojectmanagement/ 14/33
12/19/2017 CriticalPathMethod(CPM)inProjectManagement

400PMPExamSampleQuestions TryitOut

Rajeshsays
January5,2015at6:55AM

HiFahad,

CouldyoupleasehelpmeinsolvingthebelowCPMquestionwithFFLag

http://www.oliverlehmann.com/pmpselftest/75freequestions.htm

Ques31.

.Activity1hasadurationof20days,activity2of10days,activity3of5daysandactivity4of6days.

WhatistheminimumtotaldurationbetweenthemilestonesAandB?

36days
37days
39days
42days

Thanks,
Rajesh

Reply

TauseefQuresheysays
February15,2015at7:55AM

CanweincreaseFloatorSlackfortheotherpathsbyusingScheduleCompressiontechniquesi.eCrashingTechniquesorFasttrackingtechnique
intheotherpaths?

Reply

FahadUsmanisays
February16,2015at9:13PM

Reducingdurationofotherpathsdoesnotmakesensebecausedurationofthecriticalpathisthedurationofyourproject.

Incrashingorfasttracking,youraimistodecreasethedurationofthecriticalpath.

Reply

ZeeshanAzharsays
February25,2015at9:42PM

SimpleststepbysteplearningofCPM.

ThumbsupFahad!

Reply

FahadUsmanisays
February28,2015at11:48AM

ThanksZeeshan.

Reply

https://pmstudycircle.com/2014/01/criticalpathmethodcpminprojectmanagement/ 15/33
12/19/2017 CriticalPathMethod(CPM)inProjectManagement

400PMPExamSampleQuestions TryitOut

MuhammadAnjumsays
March1,2015at6:54AM

InCPMnetworking,wenormallyconsiderFSrelationshipwith0lag.ButinactualworkingwealsouseFF,SSandSFlinkswithsomevalueoflag
time.So,inthiscase,howshallwecalculateournetworkdiagram(early&latedates,total&freefloat)?
Willuyoupleasegiveanyexampleofittounderstandtheconceptbetter?

Reply

FahadUsmanisays
March1,2015at1:31PM

IwilladdthesecaseswhenIwillupdatethisblogpost.

Reply

Santoshsays
April2,2015at12:17AM

HiFahad,

DoesPMPexamaskssuchcalculationquestionsonCPM/ForwardPass/BackwardPass?

Thanks,
Santosh

Reply

FahadUsmanisays
April2,2015at7:36AM

Yes.

Reply

yousefsays
April2,2015at2:58PM

theansweris42days

Reply

Rogersays
April23,2015at3:11PM

HiFahad,
Iwillhaveexamaboutconstrucitonplanningandcpmcalculation..Ihavebasicinformation,IcancpmcalculatingbyArrowandNodediagram.But
Iamconfusedwhentherearelimitedresouce.Inthelastexam,MyInstructergavesquestionaboutconstrucitondesigningandgaveconstruction
calendar.Inthequestion,therearethreefloor,andsecondfloordependedfirst,thirdfloordependedsecondfloor.Alsolimitedresource.Icant
solvethis.PleasehelpmeaboutthisquestionsIcantfindanyresourcesorexampleaboutit.
Inadddition,sheaskedquesitonaboutdesigninbirdgeandshewantscpmcalculations.Butshedidntgivedependence.So?mustlearnstepsof
designinbridge.
Thanks..

https://pmstudycircle.com/2014/01/criticalpathmethodcpminprojectmanagement/ 16/33
12/19/2017 CriticalPathMethod(CPM)inProjectManagement

vathan1234@gmail.com
400PMPExamSampleQuestions TryitOut

Reply

FahadUsmanisays
April24,2015at5:17PM

Firstofall,makealistofallactivities,thenfindthedependencies.Afterit,drawthediagramandthenyoucanapplytheresources.

Reply

turansays
April27,2015at8:10PM

howcan?applyresources?

Reply

FahadUsmanisays
April30,2015at8:41AM

Forexampleletssaythatanactivityrequirestwopeopletocompletetheworkintwodaysbutafterreviewingtheresources
youfindthatyouhaveonlyoneworkeravailableatthattime,soyoumayincreasethedurationoftheactivitytofourdaysto
inyourdiagram.

Reply

LWarrensays
May6,2015at5:14AM

Whenataskhastwosuccessors,whichsuccessortaskdoyouusetocalculateFreeFloatonthepredecessortask.Forexample,inyourdiagram,
tocalculatetheFreeFloatfortaskD,wouldyouusetheESfortaskBortaskEinthecalculation?

Reply

FahadUsmanisays
May8,2015at1:23PM

Pleasereadmybelowgivenblogpostonfreeandtotalfloat,Itexplainseverythingindetail:

https://pmstudycircle.com/2013/03/totalfloatversusfreefloat/

Reply

Hollysays
May11,2015at11:09PM

IamstudyingformyPMPexam.ithoughtiunderstoodtheCPMwhenexplainedinclass.butafteristudiedyourpost,ijustwishedyouweremy
teacher!!

Thanksamillion..youarethebest!

Reply

https://pmstudycircle.com/2014/01/criticalpathmethodcpminprojectmanagement/ 17/33
12/19/2017 CriticalPathMethod(CPM)inProjectManagement

400PMPExamSampleQuestions TryitOut
FahadUsmanisays
May12,2015at10:05AM

ThanksHollyforyourcomment.LetmeknowifyouneedanyfurtherhelpforyourPMPexampreparation.

Reply

TauseefQuresheysays
May12,2015at3:44PM

Howwecanhavemorethanonecriticalpath,ifwedothenhowwecanmanagemorethanonecriticalpathandwhichcriticalpathwillrepresent
projectduration?

Reply

FahadUsmanisays
May17,2015at2:02PM

Ifthedurationoftwopathissame,youwillhavetwocriticalpathandyouhavetomanagebothofthem.Thedurationofthesepathwillbe
thedurationoftheproject(bothdurationwillbethesame).

Reply

ErastusNyagahsays
June2,2015at10:50PM

amdoingaprojectandallmytasksareshownascritical.Whatcouldbeamiss

Reply

FahadUsmanisays
June5,2015at12:31PM

Doyoumeanthatallpathsarehavingequalduration?

Reply

vetuusays
July12,2015at11:07PM

iamaladyfromSouthAfricaandIamstrugglingwiththissubjectoncriticalpath.canyoukindlyhelpmeindrawingthenetworkdiagramforthe
following:
A2
B4
CB5
DA4
EA,C6
FB,D2
G5
HE,F,G
IA3
JI,H,2
K,H4
L,J,K6
https://pmstudycircle.com/2014/01/criticalpathmethodcpminprojectmanagement/ 18/33
12/19/2017 CriticalPathMethod(CPM)inProjectManagement

M,F,L,I4 400PMPExamSampleQuestions TryitOut


N,L5
O,N,D,M6
P,M2
Q,O,P,M3
R,N,Q5
S,O2

Reply

Madhansays
July26,2015at2:05PM

Ilikedthewayyouhaveexplained,verysimpleandeasytounderstand.
IwouldliketoknowaboutPERTalso,pleasesharethelink

Reply

FahadUsmanisays
July26,2015at11:06PM

HereisthelinkoftheblogpostonPERT:

https://pmstudycircle.com/2013/08/pertprogramevaluationandreviewtechnique/

Reply

kisholoysays
July31,2015at9:18AM

Thanksalotforthishardwork,ItclearsallthedoubtsaboutCritical,greatjob
kisholoy

Reply

FahadUsmanisays
August7,2015at1:46PM

YouarewelcomeKisholoy.

Reply

Sumantsays
August6,2015at4:11PM

HiFahad,

Thanksforthis,itisselfsufficientandselfexplanatory,butwhatistheTotalfloatandFreefloatinthisexample.

Reply

FahadUsmanisays
August7,2015at1:46PM

Youcanreadbelowgivenblogpostfortotalfloatandfreefloat:

https://pmstudycircle.com/2014/01/criticalpathmethodcpminprojectmanagement/ 19/33
12/19/2017 CriticalPathMethod(CPM)inProjectManagement

https://pmstudycircle.com/2013/03/totalfloatversusfreefloat/
400PMPExamSampleQuestions TryitOut

Reply

Tessysays
August19,2015at2:28PM

Thisreallyhelpedalot.Yourexplanationmadeitsoeasyandunderstandable.

Plskeepupthegoodwork.

Reply

FahadUsmanisays
August19,2015at10:48PM

ThankyouTessyforyourcomment.

Reply

Sarahsays
September1,2015at5:34PM

Plsfahadreallyneedhelpondrawingthisnetworkdiagramtriedbutnotsosureifitscorrectanditsreallyurgentitsanassignmentat
school.thanks
Activitypreceedingactivityduration
A._.11
B._.8
C._.14
D.A,B.15
E.D.6
F.E.14
G.E.12
H.F.4
I.G,H.13
J.G,H.10
K.H.12
L.I.6
M.J,K,L.5
N.J,K,L.7
OC,M,N.15
P.O.3
Q.O.4
RP,Q.7

Determinetheprojectdurationandwhatarethechancesthatdprojectwouldbecompletedin85weeksafterthecommencementofwork

Reply

FahadUsmanisays
September3,2015at8:35AM

Iwillchecktheemailandletyouknow.

Reply

https://pmstudycircle.com/2014/01/criticalpathmethodcpminprojectmanagement/ 20/33
12/19/2017 CriticalPathMethod(CPM)inProjectManagement

400PMPExamSampleQuestions TryitOut

Mattsays
September25,2015at8:09PM

Hi!

Willthelastforwardpasscalculationforthefinalactivityendupbeingthelargestnumberoutofalloftheforwardpasscalculations?Irecentlydida
problemwherethelastforwardpasscalculationwasntthelargestnumberofalloftheforwardpassresults.MaybeImadeamatherror?

Thanks

Reply

FahadUsmanisays
September27,2015at6:28PM

HelloMatt,

Ihaverepliedtoyouremail.

Reply

Laurensays
October5,2015at5:58PM

Greatexplanationandexample!

Reply

FahadUsmanisays
October13,2015at11:17AM

ThanksLaurenforyourcomment.

Reply

vinodsays
October6,2015at8:41AM

HisirihavedoubtindefinitionofcriticalpathYouhavesaidthatpathwiththelongestdurationisknownasthecriticalpath.andafterthatyou
havegivenotherdefinitionascriticalpathisshortestdurationinwhichtheprojectcanbecompleted.Youhaveusebothshortestandlongest
durationpleaseclarifymethispoint

Reply

vinodsays
October6,2015at8:47AM

sorrymybadipostthatcommentbeforereadingtheexplanationthatyouhavegiven.actuallyuhavegivenclearexplanationaboutthedoubtthati
haveintheblogonlysorryforthatcomment.

Reply

FahadUsmanisays

https://pmstudycircle.com/2014/01/criticalpathmethodcpminprojectmanagement/ 21/33
12/19/2017 CriticalPathMethod(CPM)inProjectManagement
October13,2015at11:18AM
400PMPExamSampleQuestions TryitOut
Noproblem.

Reply

Saqibsays
November20,2015at9:24AM

AssalamOAlikumFahad
cantherebemorethanoneCPinNetwork?ifYesthenplssharesomeexampleinbelowformatsothaticandesigntheCPMandfindoutthe
morethanoneCPatmyown.Thankyou

ActivityDescriptionPredecessorsTime(days)
AInitialPaperwork3
BBuildBodyA3
CBuildFrameA2
DFinishBodyB3
EFinishFrameC7
FFinalPaperworkB,C3
GMountBodytoFrameD,E6
HInstallSkirtonFrameC2

Reply

FahadUsmanisays
November20,2015at12:49PM

Okay,Iwilltrytoupdatethisblogposttoincludethisinformation.

Reply

Saqibsays
November20,2015at9:54AM

AAFahad
iwanttoknowcantherebemorethanonecriticalpathinaNetwork?ifyesplsshareanexamplesothaticanfindoutbymyownthemultiple
CPs.
thankyou

Reply

FahadUsmanisays
November20,2015at12:49PM

Ifyouhavemorethanonecriticalpath,theriskwillbemoreandyouhavewatchoutforbothpaths.

Reply

TauseefQuresheysays
January17,2016at6:57AM

HowwecanfindoutFreeFloatfortheactivitiesbyBackwardPassmethod.InyouPMPFormulaguideonlyForwardPassMethodismentioned.
CanyouletmeknowhowfreefloatcanbecalculatedfromBackwardPassMethod.withexamples.

https://pmstudycircle.com/2014/01/criticalpathmethodcpminprojectmanagement/ 22/33
12/19/2017 CriticalPathMethod(CPM)inProjectManagement

Thankyouverymuchforthis 400PMPExamSampleQuestions TryitOut

AllahHafiz

Reply

FahadUsmanisays
January18,2016at11:19AM

Hereisthecompleteblogpostontotalfloatandfreefloat:

https://pmstudycircle.com/2013/03/totalfloatversusfreefloat/

Pleasereadthisblogpost.

Reply

YBsays
January21,2016at6:27AM

HiFahad,
Excellantpresentation,ilikeyoursimpleexplainationwiththesimplerealisticexamples.greatjob!

forLSandLFformulasIthinkitimportanttoshowthebrackets

forexample
LateStartofactivityF=(LFofactivityFactivityduration)+1
=316+1=26thisiscorrectrepresentation

ifsameformulawithoutbracketcouldbeinterpretedas
LateStartofactivityF=LFofactivityFactivityduration+1
=316+1
=317=24whichisincorrect.

Reply

FahadUsmanisays
January22,2016at2:08PM

Signof6isnegativeand1ispositive,theyarenevergoingtobeaddedtoeachotherregardlessthepositionsofbrackets.

Reply

YBsays
January23,2016at6:34AM

ofcourse,Iwasmakingpointthattherechanceoferrorislessandeasiertoremember,assomebooksstartwithzeroasfirstday.
thanksagain.
Youhaveverygoodskillofpresentation.

Reply

FahadUsmanisays
February8,2016at7:35AM

Itisyourpersonalchoice,youarefreetofollowyourchoice.

https://pmstudycircle.com/2014/01/criticalpathmethodcpminprojectmanagement/ 23/33
12/19/2017 CriticalPathMethod(CPM)inProjectManagement

Reply
400PMPExamSampleQuestions TryitOut

MJsays
February13,2016at9:20PM

HI

IamabouttogivethePMPtestforthesecondtime.InmyfirstexamtherewasanetworkdiagraminthequestionthatjusthadtheactivitiesABC
Detc,howeveritneverusedthetermStartorFinish.WasPMItryingtotrickmethere.shouldthereplybelikeunabletodetermineasthiswas
oneoftheoptions

Reply

FahadUsmanisays
February14,2016at7:42AM

Typeofdependencyisneededtodrawanetworkdiagram.InyourcaseIthinkunabletodeterminewillbetherightanswer.

Reply

Mwambasays
February19,2016at10:03AM

GoodmorningSir,amaladyfromZambiaandIamstrugglingwiththissubjectoncriticalpath.Pleasehelpwiththestepstofollowwhendrawing
thenetworkdiagrams.Ihavenoticedyouarequietgoodwiththistopic.Godblessyou.

Reply

FahadUsmanisays
February21,2016at1:55PM

OkayMwamba,Iwillsoonupdatethisblogposttoaccommodateyourrequest.

Reply

MbaliKhumalosays
March5,2016at6:43PM

GreetingsFahad.

IfIhavetwopathswithaslack/floatofzerobutwithdifferentdurations,whichoneisthecriticalpath?

Regards
Mbali

Reply

FahadUsmanisays
March8,2016at8:16AM

Thismeansbothpathsarehavingsamedurationandsobothofthemwillbecriticalpaths.

Reply

https://pmstudycircle.com/2014/01/criticalpathmethodcpminprojectmanagement/ 24/33
12/19/2017 CriticalPathMethod(CPM)inProjectManagement

400PMPExamSampleQuestions TryitOut

Fergusonsays
March16,2016at2:18PM

Thanksthiswilldefinitelyhelp.

Reply

FahadUsmanisays
March17,2016at8:10AM

YouarewelcomeFerguson.

Reply

kssays
May15,2016at6:25AM

LateFinishofactivityF=31(becauseyoucannotallowanyactivitytocrosstheprojectcompletiondate)

Idontunderstandtheabovestatement.IthoughttheLFoftheFshouldbesameasEFonthebackwardpass.
Howisit31.
SamegoeswithactivityI.

PleaseexplaintheLFonactivityFandI.

Reply

FahadUsmanisays
May16,2016at8:19PM

Sincetheprojectfinisheson31thereforeyoucannotallowanyactivityonanyotherpathtocompleteafter31.

Reply

Anandsays
September8,2016at9:59AM

Hi
CanyouPleaseanswerofthisQuestion?

ThedurationofactivityBis25days,theearlystartisday20andthelatestartisday30.activitiesC,DandHallhaveafinishtostart
dependencywiththisactivity.ActivityHisacriticalactivity.ThisimpliesthatactivityB.

A)isalsoacriticalactivityasHcanonlybeginonceBiscompleted

B)mustbecompletedbyday45toavoiddelayingH

C)Doesnotlieonthecriticalpath

D)hasafloatof25days

E)isnotcriticalandthereforecannotbeconnectedwithactivityH

Reply

https://pmstudycircle.com/2014/01/criticalpathmethodcpminprojectmanagement/ 25/33
12/19/2017 CriticalPathMethod(CPM)inProjectManagement

mercysays 400PMPExamSampleQuestions TryitOut


September30,2016at10:34PM

hi,iamabeginnerandfoundthisveryhelpfulsinceiamanelearner

thankyou!

Reply

FahadUsmanisays
October3,2016at7:32AM

YouarewelcomeMercy.

Reply

RituPalodsays
October21,2016at9:02AM

greatexplanation.reallyhelped

Reply

FahadUsmanisays
October23,2016at10:46PM

ThanksRitu.

Reply

CharlottePrinsloosays
December1,2016at3:42PM

TaskPredecessorDuration(days)
AStart5
BA5
CA6
DB,C13
EB6
FD4
GC9
HE,F,&G2

HiFahad.pleaseassitmewithdiagram,iamstrugglingandcametoyourblogwhilstsearchingforguidance,Iamaladyandisstudyingparttime,
thisispartofmyassignment,PLEASEHELP.

thankingyouinadvance

Reply

FahadUsmanisays
December4,2016at1:50PM

Sendmeyourquestiononmyemail,Iwilltrytoreplyyou.

Reply

https://pmstudycircle.com/2014/01/criticalpathmethodcpminprojectmanagement/ 26/33
12/19/2017 CriticalPathMethod(CPM)inProjectManagement

400PMPExamSampleQuestions TryitOut

SYMsays
January3,2017at6:46AM

Thiswassuperblyhelpful!Thankyou!!!!

Reply

FahadUsmanisays
January3,2017at9:51AM

YouarewelcomeSym.

Reply

SatishAvatesays
February16,2017at6:41PM

VerygoodinformationonCPM,

Reply

FahadUsmanisays
February18,2017at5:31PM

ThanksSatishforyourcomment.

Reply

Khansays
February17,2017at6:29PM

whatainfoushareHeadsoffdear

Reply

FahadUsmanisays
February18,2017at5:32PM

ThanksKhan.

Reply

AndyKaufman,PMPsays
April18,2017at7:22PM

ThisisaGREATpost.Thankyouforexplainingitsoclearly,Fahad.Thisvideoisofferedasasupplement,foryourconsideration:
https://www.youtube.com/watch?v=0Lo4zsBbjE

Italsousesthe+1/1approachinsteadofthestartingwithzero.

Thankyouagainforthetremendouslyhelpfulassistanceyouareprovidingpeople!

Reply

https://pmstudycircle.com/2014/01/criticalpathmethodcpminprojectmanagement/ 27/33
12/19/2017 CriticalPathMethod(CPM)inProjectManagement

400PMPExamSampleQuestions TryitOut
FahadUsmanisays
April19,2017at7:30AM

ThanksAndy.

Reply

Gailsays
May13,2017at11:12PM

DearFahad,

Thankyouverymuchforpostingyourarticle.

IaminresearchingCPAformyexamnextweekandstrugglingtofindtheanswerstoquestionssuchas

WhatdifficultiesdoesCPAface?
WhereCPAcangowrong?
CasestudieswhereCPAhasnotworked
AnalyseandevaluatethelimitationsofCPA?

Reply

FahadUsmanisays
May14,2017at10:10AM

Readthisblogpost:

https://pmstudycircle.com/2014/02/criticalchainmethodccminprojectmanagement/

Reply

ShafiqUrRehmansays
May16,2017at1:18AM

HiFahad,

ThanksforyourallpostaboutCPM.

Canyoupleaseshareyouremailanddoyouhaveanymocktestsforpracticethatwecanpurchase.

Thanks

Reply

FahadUsmanisays
May19,2017at9:56AM

Youcandetailsofmymocktesthere:

https://pmstudycircle.com/pmpquestionbank/

Reply

https://pmstudycircle.com/2014/01/criticalpathmethodcpminprojectmanagement/ 28/33
12/19/2017 CriticalPathMethod(CPM)inProjectManagement

400PMPExamSampleQuestions TryitOut
Lucernsays
July20,2017at5:17PM

IhaveonequestiononProjectTimeManagement.
Questionis:
Ascheduleactivitymaybegin10daysbeforethepredecessoractivityfinishes.
Thisisanexampleof:
a.FinishtoStart
b.StarttoFinish
c.StarttoStart
d.FinishtoFinish

Whatistheanswerandwhy?
Thanksinadvance.

Reply

FahadUsmanisays
July24,2017at10:51AM

FinishtoStartwithtendayslead.

Reply

Nadeemsays
August19,2017at9:23AM

DearMr.Fahad

Ilikethestepbystepsimpleway,youexplained.Forwardpassandbackwardpasssoundsverycomplicatedbutafteryourexplainationtheseare
verysimple.Thanksandkeepitup.

Reply

FahadUsmanisays
November27,2017at10:22AM

ThanksNadeemforyourvisitandleavingyourcomment.

Reply

BalamuruganMunusamysays
August21,2017at6:21PM

DearMr.Farad,

Kindlyneedyourhelponsolvingthebelowquestion.Imstrugglingoncompletingthisquestion.

ActivityDescriptionPrecedingactivityDuration(hours)
AShutdownexistingcomputer2
BDisconnectwiringA5
CRemoveexistingcomputerB10
DRemoveexistingwiringB20
EInstallnewwiringD,C5
FTestnewwiringE3
GMoveinnewcomputerC12

https://pmstudycircle.com/2014/01/criticalpathmethodcpminprojectmanagement/ 29/33
12/19/2017 CriticalPathMethod(CPM)inProjectManagement

HConnectnewwiringF,G4 400PMPExamSampleQuestions TryitOut


IInstalloperatingsystemH6
JCheckmemoryI2
KCheckoperatingsystemI3
LCheckperipheralsJ,K4

(a)Constructanetworkdiagramforthisproject.
(b)Determinethecriticalpathandshowthisonyourdiagram.
(c)Whatistheoveralldurationoftheproject?
(d)Explainwhatwouldhappenifindependentlyanyofthefollowingweretohappen:
(i)ActivityBtooksevenhours
(ii)ActivityGtook18hours
(iii)ActivityCtook21hours
(iv)ActivitiesAandBcouldbedoneatthesametime.

Reply

ColinMcDanielsays
October5,2017at6:55AM

JosephPhillipsinhisbookAllinOneCAPM/PMPProjectManagementCertificationdoesaterriblejobexplainingfloatandhowtocalculateit.
Youdoanexcellentjob,butIdontunderstandwherethedivergentpathscomefrom/wheretheseoriginate?Noseemstoexplainthis.Inyour
example,youhavealinefromDtoBandGtoE.Whatdoesthisrepresentandhowaretheydetermined?

Thanks!

Reply

FahadUsmanisays
October5,2017at1:18PM

Youwilldetermineitduringyourprojectplanning.Theprocessiscalledactivitysequencing.

Reply

Chhayasays
November6,2017at6:44PM

Veryclearexplanationandreallyhelpful
Thankyousir

Reply

FahadUsmanisays
November27,2017at10:21AM

YouarewelcomeChhaya.

Reply

KabeerBalasays
November16,2017at3:07PM

HiFahadpleaseIneedhelpinthis
ActivityDurationpreceededby

https://pmstudycircle.com/2014/01/criticalpathmethodcpminprojectmanagement/ 30/33
12/19/2017 CriticalPathMethod(CPM)inProjectManagement

A3
400PMPExamSampleQuestions TryitOut
B2
C4B
D2A,C
E5A
F6E
G4E
H5G
I3D,F
J7G,I
K4G,I
L3H,K
Question:
1.Drawtheactivitydiagram
2.Calculatethefloat,Earlystart,Earlyfinish,LastStart,Lastfinishforeachactivity

Ihopeyouwillhelpmewiththis.thanks

Reply

Jillanisays
November25,2017at11:28AM

HiFahad

Couldyoupleaseexplainaboutthedummyactivity?Andalsocanadummyactivitybeonthecriticalpath?

Thanks
Jillani

Reply

FahadUsmanisays
November27,2017at10:21AM

Pleaserefertothefollowinglink:

https://projectmanagementknowledge.com/definitions/d/dummyactivity/

Reply

ronditysays
November30,2017at2:54PM

Extremelyinformative,likedthepost

Reply

FahadUsmanisays
December1,2017at4:46PM

ThanksRondityforyourcomment.

Reply

https://pmstudycircle.com/2014/01/criticalpathmethodcpminprojectmanagement/ 31/33
12/19/2017 CriticalPathMethod(CPM)inProjectManagement

400PMPExamSampleQuestions TryitOut
LeaveaReply
Youremailaddresswillnotbepublished.Requiredfieldsaremarked*

Comment

Name*

Email*

PostComment

EnterYourEmail

https://pmstudycircle.com/2014/01/criticalpathmethodcpminprojectmanagement/ 32/33
12/19/2017 CriticalPathMethod(CPM)inProjectManagement

400PMPExamSampleQuestions TryitOut

Searchthiswebsite Search

RECENTCOMMENTS

SaranyaonWhatisaScatterDiagram(CorrelationChart)?

OldoonAFew23CAPMContactHoursTrainingPrograms

JunaidonContingencyReservevsManagementReserve

MasoodUrRahmanonProjectCharterADocumenttoFormallyAuthorizetheProject

MasoodUrRahmanonProjectCharterADocumenttoFormallyAuthorizetheProject

SupratimBishnuonCanIRescheduleorCancelMyPMPCertificationExamAppointment?

MeetonWhataretheEligibilityRequirementsfortheCAPMCertificationExam?

JosephonTypesofProcurementContractsusedinProjectManagement

FahadUsmanion4ToolstoEstimateCostsintheProjectManagement

FahadUsmanionWhenWillIGetMyPMPCertificatefromthePMIbyRegularMailAfterPassingtheExam?

FahadUsmanionTotalFloatVersusFreeFloat

FahadUsmanionEnterpriseEnvironmentalFactors&OrganizationalProcessAssets

sachinon4ToolstoEstimateCostsintheProjectManagement

FahadUsmanionPMPQuestionBank:Version3.0isAvailableNow!

FahadUsmanionPMPQuestionBank:Version3.0isAvailableNow!

BABATOUREonWhenWillIGetMyPMPCertificatefromthePMIbyRegularMailAfterPassingtheExam?

RohitonPMPQuestionBank:Version3.0isAvailableNow!

JohnsononTotalFloatVersusFreeFloat

MasoodUrRahmanonEnterpriseEnvironmentalFactors&OrganizationalProcessAssets

SouravDuttaonPMPQuestionBank:Version3.0isAvailableNow!

CopyrightPMStudyCircle2017. FAQs|PDU|Books|About|Affiliate|Contact

https://pmstudycircle.com/2014/01/criticalpathmethodcpminprojectmanagement/ 33/33