diketahui

b = 300 mm
d = 550 mm
fc = 22 mpa 25
fy = 415 mpa
LL = 45 kn/m
berat beton 24 kn/m3
As = 2712.96 mm2

cek tulangan
jarak antar tulangan 30
= 100
33.33333333 ok
cek beban

beban mat = 3.96 kN


beban hidup = 45 kn

beban ultmate = 1.2 DL + 1.6 LL


= 76.752

Monen ultmate = 1/12 ql^2


= 159.9

cek momen berdasarkan dimensi dan tulangan

p = As/ b.d pmin = 1.4/fy


= 0.016442182 = 0.003373
p > pmin ok

pb = 0.024215087 fc 25 fc 22 Pmaks<p tdak ok


pmaks = 0.75*pb
= 0.018161315 mutu beton dinaikkan

pmak>p ok

a = 176.6083765 88.30419
Mn = 519813341.8
519.8133418
Mu = 415.8506735 Kn

Mu dari gaya 159.9 ok