TECHNICAL REPORT AND ESTIMATE

RETAINING WALL

THE REPORT

The Ground : The ground is not leveled to one another and it overgrown by grass.

Wall : On the retaining wall has not been covered by stone.

THE ESTIMATE

The Ground : Clean up the grass, measure the slope and the flatness of the ground to one another.
It takes one day with 3 workers. The wages of the worker is Rp. 60,000,- a day. Rp. 180,000,- .

Wall : Arrange the stone, make mortar with comparison 1:4 . 1m3 needs 14 kg PC and 120 kg
sand. 18 m3 it needs 252 kg PC and 2160 kg sand.