Dear Sir,

We, M/s Dayim Punj Lloyd Construction Contracting Co. Ltd are bidding for YANBU-
NORTH JIDDAH PIPELINE PROJECT of SAUDI ARAMCO in KSA. The purpose of
the proposed facilities is to efficiently meet the Kingdom’s refined product demands in
Makkah Province. A new pipeline system (YNJ-1 & YNJ-2) with ultimate capacity of 577
MBD (240 MBD & 337 MBD respectively) is planned to deliver products from the
proposed Yanbu’ Distribution Hub to the existing and expanded North Jiddah Bulk Plant
facility.

The pipelines shall use a dual pipeline arrangement to deliver two grades of gasoline
(PG91 & PG95), ULSD and Jet A-1 refined products to an upgraded and expanded NJBP
as follows:
 YNJ-1: 20” X 330 KM gasoline pipeline (PG91 & PG95)
 YNJ-2: 24” X 330 KM ULSD & Jet A-1 pipeline

In this endeavor of ours, we require your services for the Service of “Chemical
Cleaning of New Twin Pipeline”. Kindly arrange to provide us your most competitive
offer.

Brief Details of the Project

Project: YANBU – NORTH JIDDAH PIPELINE PROJECT (YBN 1 & 2)

Client: SAUDI ARAMCO

Location: KINGDOM OF SAUDI ARABIA (KSA)

Brief Details of our Requirement

Item:

Chemical Cleaning of New Twin Pipeline as per attached Scope of Work, Specifications.

Pipe Dia: 24” & 20”

You are requested to give your offer including supply of chemical, Equipment, Manpower etc.

Timelines / Project Schedule/Productivity

1. Activity Start Schedule :

 For Base Case – Jan’19


 For Alternate Case – Feb’20
Offer Submission & Deadline

Documents to be submitted along with commercial proposal:

 Chemical Cleaning Procedure


 Commitment Letter (Format as attached).
 Production Norms
 Manpower and Equipment Deployment Schedule
 Organization Chart
 Pre-Qualifications Documents

Offer Validity : : Till Oct-2016

Deadline: You are requested to submit your technical & commercial offer last by 21st
April, 2016.