Comparison baseline-31 july-17

Remaining
Finish date Actual status Behind Ahead Remarks
Days

Description Org.B.Line Rev.B.LINE Start Date Finish Date % Completion

Sliding from SKMH


Excavation of plot 17th DEC,16 28 FEB,17 1st Oct,16 1st April,17 100% 32
side
Raft foundation 24th DEC,16 25th March 17 25th Oct 16 4th April,17 100% 11
Columns,S.walls,Retaing
wall,Lift walls (Basement-4 29 Jan,17 30th March,17 27th Nov,16 12th April,17 100% 13
vertical)

Basement-3 Floor slab 10th FEB,17 8th April,17 16 DEC,16 14th April,17 100% 6

Columns , S.walls,
Retaining walls,Lift walls 1st March,17 15th April,17 16th Dec,16 1st May,17 100% 16
(Basement-3 verticals)

Basement-2 floor slab 12th March,17 25th April,17 26th Jan,17 9th May,17 100% 15

Columns , S.walls,
Retaining walls,Lift walls 1st April,17 6th May,17 11th FEB,17 9th June 100% 34
(Basement-2 verticals

Basement-1 floor slab 12th April 17 16 May,17 1st March,17 18th June,17 100% 31

Columns , S.walls,
Retaining walls,Lift walls 2nd May,17 21th May,17 11th Feb,17 95% 72
(Basement-1 verticals

Ground Floor Slab 13th May,17 1st Jun,17 15th July-17 20% 60
Columns , S.walls, Lift
27th May,17 12th Jun,17 42
walls (G/F- verticals)