Professional Documents
Culture Documents
Cash Flow A List of Assumptions
Cash Flow A List of Assumptions
Main Contractor retainage to Sub-Contractor: 10% each payment. The total will
be pay with the last payment.
Sub-Contractor retainage to Material Supplier: 10% each payment. The total will
be pay with the last payment.
The Cash Flow is going to be made by week, assuming each month has 4 weeks.
Material cost is paid after 1-month delay, every month after receive main
contractor payment
Main contractor monthly payments are made after 4 weeks (at the end of the
week) the monthly bill is submitted.
Interest is paid monthly at the end of each month before receive main contractor
payment and pay materials after pay labor of the fourth week of each month.
Direct Cost is split equally among the 6 months to meet the requirement of 25%
completion of direct cost in the first three-month, 50% on the next three months
and 25% on the last three months.
Results
The total gross profit is $21,277.15 USD. (Without interest)
The total interest paid is $4,826.33 USD, which is 22,68% of the gross profit. (high
interest cost)
The maximum cash out flow is $136,761.75 USD before getting payment in the month 4