GOVERNMENT OF ANDHRA PRADESH
FINANCE (FMU-WR.!) DEPART MENT
Memo No. 47027/297/2017 Dated: 13-09-2017
Sub: Finance Department- Implementation of GST in works
contracts-Recommendations of the Committee- Instructions
issued- Regarding.
Ref: 1. G.O.Rt No. 1688 Finance (FMU-WR.I) Dept. Dt.28-07-017.
2. Minutes of the meeting held on 11-08-2017 on
implementation of GST.
some
Government. vide G.O. cited constituted a Committee to formulate
guidelines on implementation of GST in works contracts withthe following
terms of reference.
2. Procedure to be adopted for implementation of GST
1. In the ongoing works, in which provision for VAT is made in the
data of the estimate.
2. In the ongoing works, in which provision is made for VAT outside
ECV.
3.In the works for which tenders are called for and
Agreements are yet to be concluded.
4. In the new estimates and in the bid documents.
3. After detailed discussions, the Committee observed that the provisions
made in the estimate towards VAT and also the agreement conditions
regarding deduction/reimbursement of VAT or other taxes like service tax,
CST are varying from Department to Department and also depending on the
funding agency (eg: World Bank contracts). Therefore, one method may not
be possible to adopt for all the types of contracts.
4. In the cases of new estimates, the Committee observed that the basic rate
of all the inputs without tax elements (that are subsumed in GST) has to be
adopted in the preparation of estimates, duly providing the GST component
as applicable on works contract outside ECV and added to the bill.
5. To arrive at the unit costs of all the SSR items, the Committee
recommended that the Board of Chief Engineers may be called upon to take
up on emergency basis and constitute select groups entrusting each group
with the task of arriving at the basic rate (without the element of tax) for
certain items.
6. As the process suggested above will take some more time and in order to
see that the progress of works is not hampered and to ensure that the
agencies are not put to inconvenience in getting payments, the committee
recommended that the intermediate payments for the work done on or after
01-07-2017 may be made without adding any % towards GST to the bill
amount and the agencies will have to be assured that they will be
compensated with the due amount towards GST as per rates arrived by the
department and after concluding the supplemental agreements.
7. After careful examination, the Government accepted the
recommendations of the Committee and all the departments connected with
the works contracts are directed to make intermediate payments for the work
done on or after 01-07-2017, without adding any % towards GST to the bill
amount. The agencies executing the works will be compensated with the due
amount towards GST as per rates arrived by the department after concluding
the supplemental agreements. Where the due amount towards GST as per
rates arrived by the Department is less than the amount paid, the same shall
be recovered from the contractor.8. The Board of Chief Engineers is directed to arrive at the unit costs of all
the SSR items on emergency basis by 15-9-2017 by constituting select
groups entrusting each group with the task of arriving at the basic rate
(without the element of tax) for certain items.
MUDDADA RAVI CHANDRA
SPECIAL CHIEF SECRETARY TO GOVERNMENT (FAC)
To
All Department of Secretariat
All the Members of the Committee
All Engineering Department
All the Corporations
Director of Works Accounts, Ibrahimpatnam
Copy to : P.S. to P.F.S.
SC/SF
// FORWARDED BY ORDERS //
oh,
SECTION OFFICER