S.No. SOR (B&R) Description of Item Unit Nos Length Width Depth Quantity Rate Amount
2017
(ii) Excavation for Hume Pipe 1200 Dia NP4 Laying Cum 1.00 12.00 1.90 1.00 22.8
For Abutment Bottom/ Head wall Cum 2 6.55 1.5 0.15 2.95
For Pipe Bedding Cum 1 13 1.9 0.15 3.71
Total : Cum 6.653 3,409.00 22,678.37
Providing concrete craddle bedding in M-15 grade concrete
3 9.6
as per clause 2900 and as per section 1700 and 2900.
For Encasing of Pipe Cum 1 13.40 1.9 1.8 45.83
Deduction for Pipe 1 15.15
Total : Cum 30.681 4,115.00 126,250.83
Providing and laying Plain/Reinforced cement concrete in
open foundation including form work shuttering etc.
4 12.8(B) complete as per drawing and technical specifications and as
per relevant clauses of sections 1500, 1700 & 2100 with .PCC
GRADE M20
For Head wall Cum 2 6.5 0.70 2.9 26.39
Deduction for pipe Cum 2 1.00 1.77 0.8 2.83
Total : Cum 23.564 5,025.00 118,409.10
MP PWD
S.No. SOR (B&R) Description of Item Unit Nos Length Width Depth Quantity Rate Amount
2017
Paining two coats after filling the surface with synthetic Sq M 1 48.00 1425.888
2.00 6.55 0.40 0
enamel paint in all shades on new plastered concrete
surfaces
1 4.00 0.60 1.90 4.56
1 4.00 0.16 0.40 0.256