Professional Documents
Culture Documents
PROJECT REPORT:
CONTENT PAGE
DECLARATION 2/12
INTRODUCTION 3/12
OBJECTIVES 3/12
SCOPE OF WORK 3/12
METHODOLOGY 4/12
LITERATURE REVIEW 4/12
CONCEPT OF THE REEFMASTER ASSEMBLE 5/12
SPLITTER 6/12
ANALYSIS OF FIELD DATA 6/12
DRILLING 6/12
CHARGING OF BLASTHOLES 7/12
COMPARATIVE COST ANALYSIS 8/12
COMPARATIVE BLAST COST 9/12
THROW AND ROCK PILE PROFILE 10/12
OVERBREAKS/UNDERBREAK ANALYSIS 11/12
TIMING OF OPERATIONS 11/12
CONCLUSION 11/12
RECOMMENDATIONS 11/12
APPENDIX 12/12
Page 1 of 12
DECLARATION
We declare that the Reefmaster Project was duly executed and accepted by all parties involved.
………………………… …………………………….
Samuel Asante Haruna Karim
(Regional Manager, AEL North) (Area Manager Drill & Blast)
Page 2 of 12
INTRODUCTION
AngloGold Ashanti (Obuasi Mine) uses the Nonel shock systems for both stoping and
development. These products are Nonel Long Period (NLP) and Nonel Millisecond (NMS) delay
systems which are supplied by AEL Mining Services. The purpose of this project is to investigate
the use of the Nonel Reefmaster® Assemblies for underground applications.
This decision came in the wake of streamlining explosive and accessories types in use and to
maximise the benefits to Obuasi. While the unit price of Reefmaster Assembly is higher than the
NLP and NMS, it is important to compare the performance of the two products so as to quantify
the possible benefits.
AEL’s technical team together with AGA drill and blast section conducted a trial on the
application of Reefmasters for development and compared the results with the existing initiation
system. The criteria of measurement were:
Advance per blast
Muck pile profile and throw
Overbreak and underbreak
Timing of operations
Total initiation system cost
OBJECTIVES
The objectives of the project are to:
Study the application of the Reefmaster Assembly in underground development
Study the performance of the Reefmaster initiation system and the existing initiation
system.
Compare the performance of the Reefmaster initiation system to the existing initiation
system.
Compare the cost of the two systems.
Determine if any benefit yields a financial benefit.
SCOPE OF WORK
This project was limited to development headings. Field results of the project were compared to
the benchmark results of the existing NLP system.
Page 3 of 12
METHODOLOGY
The methods used for this Project included:
Training of selected blast men at training school on surface
Application of Reefmaster Assembly at selected underground development as directed
by Obuasi.
Data collection from underground development ends
Analysis of data from collected results
Comparison of performance of both initiation systems
Conclusion and recommendation based on performance compared.
LITERATURE REVIEW
The Reefmaster® Assemble is a non-electric initiation system developed to give the greatest
possible simplicity in both usage and storage. The system is based on a combination of in-hole
detonators and surface connector units (Fig. 1). All drill holes in the round are charged with
detonators that have the same delay time. The initiation sequence is then determined on the
surface by means of delays in the surface connector units. Owing to the uniform delay in the in-
hole detonators, there is a sufficient time delay to initiate all blast holes before any detonation
and ground movement occurs.
In-hole Detonator
Shock Tube
The difference between the NLP and Reefmaster is that the NLP shock tube assemblies are
heat sealed and has a Cobra clip on one end and an in hole detonator with a delay element on
other. Whereas the Reefmaster assembly has a connecting block at one end containing a
Page 4 of 12
surface delay detonator representing the inter-hole delay i.e. 176ms, and the other end has a
detonator with down-the-hole delay i.e. 4000 ms. All assemblies have the same set of inter-hole
and down-the hole delays. They are shown diagrammatically in Figure 2 and 3.
Detonator Shock tube Cobra clip
As can be seen in the sketch above, the signals comes in from the shock tube of the unit that
had been detonated first. The detonator in the connector block has a delay of 176ms signal
before it detonates the shock tube of the next unit. After detonation of the shock tube, the signal
Page 5 of 12
travels in both directions to set off the next Reefmaster connector block as well as the in-hole
detonator. Before the detonator of the connector block fires, it again has a delay of 176ms.
The in-hole detonator has a delay of 4000ms before it detonates the explosive in the hole. It
therefore takes about 23 Reefmaster connector block to detonate before the first in-hole
detonator will detonate.
An important point to note from the sketch is that each Reefmaster connector Block must be at
least 30cm from the next one when connecting up. This will ensure that there is enough run-up
time for the composition powder to intiate the delay element in the detonator.
SPLITTER
A Splitter is a non-electric initiation system which is designed for splitting a blast in multiple
sections on a blast face in underground mines. The unit consists of a 1m length of shock tube
equipped with 67ms or 176ms detonators in a connector block at both ends. Its function is to
receive a single signal and transmit it in two different directions. It is also used to simplify the tie-
up in the cut area.
DRILLING
Before the commencement of any drilling, the perimeter of the round at the face was established
using colour paints and tapes. Holes were drilled using a jack hammer at the face. Holes
diameter was 38mm with an average length of 2.4m. The drilling pattern and the heading
dimensions are presented in the table blow.
Page 6 of 12
Number of Drilled Number of holes Spacing
Heading Size Burden (m)
holes per round Blasted (m)
54 51 4m by 4m 1 1
On completion of drilling the round, all holes were flushed with compressed air to remove all
debris.
The drilling pattern and the cut are shown the figure below.
2
1m
grid
CHARGING OF BLASTHOLES
Holes were charged with ANFO using the ANFO loader. In most case the cut holes were first
primed with magnum buster while the remaining hole was not primed. This ensured improved
breakage in the cut region. All the holes were charge to the brim. No stemming was added on
top of the explosive to complete the charging.
The holes were connected with the aid of the block connector, which also contained a detonator.
The splitter was also used and it served the purpose of separating the blast into four parts. The
tie up is shown in the diagrams below.
Page 7 of 12
2
1m
grid
Page 8 of 12
NLP Reefmaster
Product Quantity Cost/unit Total Cost ($) Quantity Cost/unit Total Cost ($)
No. of shock tube 52 1.57 81.64 52 3.1 161.2
Detonating Cord 16 0.37 5.92 0 0 0
Capped Fuse 1 1.31 1.31 1 1.31 1.31
Splitters 0 0 0 2 2.87 5.74
Snap Line 0 0 0 1 2.29 2.29
Total $88.87 $170.54
The prices quoted are applicable to the 2009/2010 contract period. It can be seen that the
Reefmaster Assembly system is $81.67 more expensive per blast.
Planned Av.
Cost/meter Cost/Blast Actual
Advance/Blast Advance/Blast
System ($) (2.4m) Cost/Meter
(m) (m)
Based on the additional advance per blast generated by the Reefmaster Assembly system a
cost saving of $97.49 per blast is generated. This results in a $15.82 per blast benefit after
taking into account the higher costs of the Reefmaster Assemblies. It is important to notice that
the potential value that could have been added to your operation amounts to $139, 865.00
based on 8, 841m developed over the past 5 months.
Page 9 of 12
From the graph below, it can be seen that better advances per blast were achieved using
Reefmaster Assemblies.
2.5
2.4
2.3
Advance (m)
2.2 Rm
Av. Rm
2.1 Av. Lp
1.9
1.8
1 2 3 4 5 6 7 8 9 10
Blast Number
3.5
3
FACE HEIGHT (m)
2.5
1.5
0.5
0
1
3
5 S4
7
9 S3
11 S2
13
DISTANCE FROM FACE (m) S1 FACE WIDTH
(m)
Page 10 of 12
OVERBREAKS/UNDERBREAKS ANALYSIS
Full advance and sidewall control were successfully achieved as there were barrels of the drill
rods on the sidewalls after blast.
TIMING OF OPERATIONS
In general, the time taken to charge with the Reefmaster is far lesser than that of the NLP’s. On
the average, it took fifty (50) minutes to charge with the Reefmaster Assemblies as against one
and half hours (1:30min) with the NLP.
CONCLUSION
1. The advance per blast was not significantly different.
2. The distance of muck pile from the face was desirable as it did not affect equipment closer to
the face.
3. There were no over break was measured and barrels of drill rod on the walls were visible.
4. Total cost of blasting a round was higher with the Reefmaster Assemblies when compared to
the NLP’s. However, the potential value the Reefmaster could have added due to the
additional advance per blast over the past 5 months amounts to $139, 865.00 which negates
the higher unit cost.
5. Time used to charge and initiate a round with the Reefmaster was fifty minutes which is much
more productive when compared to the charging time of one and half hours with the NLP’s.
RECOMMENDATIONS
The Reefmaster Assembly trail was a success and it is recommended for use across the mine.
Initially the Reefmaster Assemblies can be used selectively until all the NLP’s are phased out.
Page 11 of 12
REEFMASTER PROJECT – APPENDIX
22# 314
1 51 3.8m by 3.7m 1 1 2.4 0 2.4 2 83% 14 55
x/c
30# 322
3 49 3.6m by 3.7m 1 1 2.4 0 2.4 2.4 100% 13 50
x/c
22#
4 37 4m by 2.2m 1 1 2.4 0 2.4 2.4 100% 14 30
373x/c
22#334
5 51 4m by 4.1m 1 1 2.4 0 2.4 2.4 100% 13.5 60
r/d
6 30#1 u/r 51 4.1m by 3.9m 1 1 2.4 0 2.4 2.4 100% 13 45
7 21 s/d 51 4.1m by 4.2m 1 1 2.4 0 2.4 2.4 100% 14 58
22# 386
8 51 4.6m by 4.3m 1 1 2.4 0 2.4 2.4 100% 15.5 60
u/r
32# 325
9 51 4.3m by 4.2m 1 1 2.4 0 2.4 2.3 96 15 60
x/c
10 21 s/d 51 4.1 by 4.2m 1 1 2.4 0 2.4 2.4 100% 13 60
Page 12 of 12