Professional Documents
Culture Documents
(Sub-section 208)
Article Page
1. Scope 208-1
5. Dewatering 208- 3
1.0 SCOPE
The Contractor shall make all excavations for piping and appurtenant
structures in any material encountered to the depth and grades indicated
on the plans, shall backfill such excavations and dispose of excess or
unsuitable materials from such excavations, and shall provide and place
necessary borrow material to properly backfill excavations, all as indicated
on the drawings, specified herein, or as directed by the Engineer.
2.1 The Contractor shall provide suitable and safe temporary bridges,
crossings or access ways during construction to maintain traffic
and/or provide access to private property, and shall remove said
structures after construction is complete.
2.2 The extent of excavation open at any one time will be held to a
minimum consistent with normal and orderly prosecution of the
work but shall always be confined to the limits set by the Engineer
for the prevailing conditions.
4.1 The Contractor shall provide and install such sheeting and shoring
as may be required to support the sides of any excavation to
prevent earth movement that could endanger the work, workers, or
any existing structures, or to confine the construction within a
specified area such as an easement or street right-of-way. It shall
be the Contractor’s responsibility to place this sheeting and shoring
for such protective purposes without the Engineer’s instructions.
4.3 Steel sheeting shall be left in place only when so authorized by the
Engineer. The top of steel sheeting left in place shall be no less
than 30 inches below grade unless otherwise shown on the
drawings, or directed by the Engineer.
4.4 All sheeting extending below the level of 1 foot above the top of
pipelines shall be cut off as directed by the Engineer and left in
place. All sheeting to be removed shall be carefully extracted in
such manner as not to endanger other structures and all voids left
shall be immediately backfilled with approved material and
compacted as required.
4.5 Steel drag shields or trench boxes may be used. Voids left by the
advancement of the drag shield shall be carefully backfilled and
compacted in accordance with trench backfill requirements.
5.1 The Contractor shall at all times during construction provide ample
means and devices with which to promptly remove and dispose of
all water entering the trench and structure excavations and shall
keep said excavations acceptably dry (as approved by Owner’s
representative), until the pipe and/or structures to be built therein
are installed and backfilling is completed. All water pumped or
drained from the site shall be disposed of in a suitable manner
without damage to structures, pavement, pipes, electrical conduits,
or any other work or property or surrounding environments.
5A.3 All piping laid under wet trench conditions must be cleaned to the
satisfaction of the County. For sanitary sewers and force mains,
cleaning shall be performed by pigging or other approved method
and shall take place prior to acceptance of the completed piping
installation and approval for payment. For water mains, cleaning
shall be as above and must occur prior to chlorination for
bacteriological sampling. The Contractor is responsible for all
piping and other modifications necessary to facilitate cleaning
operations.
6.1 All excavation for piping shall be open cut. Directional boring may
be permitted when specifically called for on the Plans. Trench
sides shall be approximately vertical between an elevation of 1 foot
above the top of the pipe and the centerline of the pipe; otherwise,
trench sides shall be as vertical as possible or to the soil angle of
repose as required by OSHA Standards. Trench may be excavated
by machinery to a depth that will not disturb the finish grade.
6.3 Bell holes shall be dug to permit the entire straight barrel of the pipe
to rest on the undisturbed trench bottom. Boulders or loose rocks,
which might bear against the pipe, will not be permitted in the
trench bottom. Embedded material shall be worked in under the
haunches of the pipe to ensure complete contact with the pipe
bottom.
7.1 The Contractor will be held responsible for prosecuting the Work in
accordance with the lines and grades shown on the Contract
Drawings. Banks of excavation shall be sloped at a safe angle or
shoring shall be used.
7.4 Where structures are not supported on piles, all loam, organic, or
other unsuitable material shall be removed and replaced with
suitable material as defined by the specifications.
13.0 TESTING
13.4. Placing permanent construction over fill that has not been tested
and approved is not allowed.
The Contractor shall refill settlement in all backfilled areas and restore
surfaces to their original condition prior to settlement (i.e. new asphalt
surface course, base course, concrete, top soil, sod, or seeded and
mulched fill. The surfaces of backfilled areas shall be maintained in a safe
and satisfactory condition at all times until the expiration of the one year
warranty period.
If, in the opinion of the Engineer, it is necessary to control dust from time
to time during the progress of the work, the Contractor shall do so with no
additional compensation.
16.1. Citrus County recognizes that sewage may be released from pipes
in the course of performing the work. Contractor shall minimize the
amount of sewage released into excavations by notifying affected
parties (homeowners or businesses) of the service interruption, pre-
draining affected lines, ensuring pump station (non) operating
status, etc. All appropriate agencies must be notified immediately
of the sewage spill by the contractor. Contractor shall take
precautions to prevent sewage from contacting the ground. If
sewage contacts the ground, Contractor shall take appropriate
measures to disinfect the affected area where the sewage release
occurred. When pooling sewage is observed, Contractor shall
vacuum remove the sewage or remove the sewage by other means
acceptable to the Citrus County Inspector and dispose of the
sewage in accordance with environmental and public health
regulations. This can include pumping to the nearest available in-
service sanitary manhole. Sanitary systems found plugged due to
this type of pumping activity shall be cleaned at the Contractor’s
expense.
16.2. Contractor shall inform the Citrus County Inspector of spills which
contact the ground estimated to be in excess of five (5) gallons.
Spills less than five gallons, which contact the ground, shall be
noted in the Contractor’s field logbook. Notification of the inspector
does not mitigate Contractor’s responsibility to take corrective
action. If Citrus County is fined as a result of a sewage spill
associated with the work, Citrus County will require the Contractor
to reimburse Citrus County for the fine amount.
For the various items of work specified in this section, when direct
payment is not provided for in the contract proposal quantities, the cost
thereof shall be included in the price for related items set forth in the
proposal and no separate, or extra payment will be allowed therefor.