Professional Documents
Culture Documents
Unit 6-2 PDF
Unit 6-2 PDF
In the planning scenario, the settings you make and the items you define include the
following:
1)The plants for which the simulation is to be executed
2)The planned independent requirements versions (active or inactive) that are to be
simulated
3)The opening stock on which the simulation is based (zero stock, safety stock, plant stock
at the time of planning, and average plant stock)
4)Whether fixed receipts (purchase orders, production orders, and material reservations)
are to be included in the net requirements calculation
5)Whether dependent requirements are generated for consumption-based materials,
KANBAN materials, and bulk material
6)What is the version of the available capacity used in the simulation
Consumption-based materials:
They are not planned inMRP because no dependent requirements are created for them. In
long-term planning, dependent requirements can be created for consumption-based
materials, bulk material, and KANBAN materials, that is, the material is planned in the
scenario as though it were a material planned using MRP.
Planning scenario (2):
In the planning scenario, you also set the following:
1)Whether the system should work with direct production. That is, whether during
planning, it should create a collective order for materials that are to be produced directly.
When using direct production in long-term planning, only the header order can be
changed, not the subordinate orders in the collective order.
2)Whether the long-term planning should be executed as gross requirements planning and
whether the calculation of scrap in the long-term planning run should be deactivated.
3)Whether long-term planning BOMs should be used.
4)Whether firmed planned orders are to be transferred (copied) from operative MRP to
longterm planning (the firmed planned orders can be changed) and whether firmed
purchase requisitions in operative planning are to be taken into account in the simulative
planning area (these cannot be changed).
5)Whether the planning time fence applies in long-term planning for materials that are
affected by a planning time fence in MRP.
6)Whether sales orders are to be included in long-term planning (these cannot be
changed).
7)Whether make-to-order production or individual project planning should be executed for
the materials in the corresponding strategy. Make-to-order planning presupposes that
sales orders with a requirements type for make-to-order planning are taken into account. If
the Make-to-order and project planning indicator is not set, the sales orders with a make
to-order planning requirements type are ignored in the scenario.
Simulative planned Independent Requirements: Fig 153
Several planned independent requirements versions can be created for one material.
Planned independent requirements versions can be created using the following:
1)The sales and operations planning for a material or a product group
2)The results of flexible planning from sales and operations planning
3)Forecasting
4)Planned independent requirements of other materials
5)Planned independent requirements versions of the same materials
6)Manually
A planned independent requirements version can be set as active or inactive. Inactive
versions are created for simulation purposes. Only active planned independent
requirements versions are taken into account in operative planning.
Planned independent requirements are created for each MRP area Sales orders are
assigned to an MRP area according to their storage location (the issue storage location in
the Shipping screen of the item details).
Dependent requirements are automatically assigned to an MRP area in the planning run,
depending on their production or issue storage location.
The requirement elements (such as planned independent requirements and sales order)
are covered following the assignment to an MRP area within this MRP area. If a production
storage location (or an external procurement storage location) is determined for a
corresponding procurement element (that is the relevant planned order) that does not
belong to this MRP area, then the receiving storage location of the MRP area is used
instead.
Special Procurement Types in the MRP Area : fig 178
Materials that are planned in an MRP area can be procured using the special procurement
type Stock Transfer From Plant To MRP Area.
You have to create a special procurement key in customizing for MRP which contains
procurement type U (stock transfer), and your own plant as the stock transfer plant.
The stock transfer process takes place in storage location MRP. A stock transfer
reservation is created at MRP area level, and a reservation with reference to this stock
transfer reservation is created at plant level.
ATP check with MRP areas:
As soon as MRP with MRP areas has been activated, the Available-to-Promise (ATP)
check is also activated at MRP area level. The availability check is then carried out for the
individual MRP areas.
Sales orders for make-to-order production are always planned in the plant MRP area. For
the customer requirements types in make-to-stock production, the assignment to a MRP
area is made using the storage location.
As in the previous ATP check at plant level, the ATP check can be carried out with or
without the storage location check in Customizing, depending on how the availability
check is controlled.
Scope of planning with MRP areas: Fig 180:
The total planning run can be triggered for each plant, for example, as a background job
with a variant for each plant to be planned. In planning with MRP areas, it is also possible
to plan only individual MRP areas.
You can group together several MRP areas or plants in a scope of planning for a
planning sequence and plan on a cross-plant basis in a total planning run. The
system automatically takes mutual dependencies, such as those arising through
stock transfer, into account.
You define the scope of planning for total planning in the Customizing activity Define
Scope of Planning for Total Planning for MRP. You can also specify only an individual
MRP area in the scope of planning.
Notes: MPS:
• This is planning procedure thro which we can plan some high value critical items
separately.
• Pre-req to use MPS: MRP type M0, M1, M2, M3, M4
• MPS is top level planning. We cannot execute MPS & MRP together. First MPS, then
MRP.
• MPS run will explode BOM to only one level & it will give procurement proposal for only
MPS item. For next item it will generate only dep req.
• We can declare any items as MPS items (FERT, HALB or ROH) if it is of high value &
critical.
Long Term Planning: Simulative planning in a simulative area
• Operative data (master data & transaction data) can be used for simulation.
• LTP can be done for long term & short term both.
• LTP includes all items (MRP, MPS, CBP)
• We cannot convert planned order to prodn order/process order or purchase requisition to
purchase order. For conversion we need to transfer simulative data from simulative area to
operative area for actual MRP via demand mgmt.
• Pre-Req to use LTP concept: A planning scenario must be created, released & saved.
• We can use SOP Data in LTP.
• Objectives of LTP: To optimize inventory, controlling, mtrl planning, purchasing,capacity
planning.
Multi-site Planning:
•Stock Transfer Procedure
! One step procedure (MIGO/MBIB/Mov Type 301)
! Two step procedure (MIGO/MBIB/Mov Type 303 & 305(put away movement))
! With stock transport order (STO)
! ! With delivery
! ! Without delivery
• Withdrawal from alt plant
•Planning plant & prodn plant (separate) thro spl proc key 80 or 90