Labor Resource Plan Overview

The document is a resource-labor plan for an ERC Refinery project that shows the estimated labor needs by resource type and month from April 2017 through November 2017. It lists 14 different resource types like laborers, surveyors, carpenters, and their estimated work hours. The total estimated labor hours needed for the entire project period is 20,459 hours.

Uploaded by

Ahmed Sakr
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
40 views1 page

Labor Resource Plan Overview

The document is a resource-labor plan for an ERC Refinery project that shows the estimated labor needs by resource type and month from April 2017 through November 2017. It lists 14 different resource types like laborers, surveyors, carpenters, and their estimated work hours. The total estimated labor hours needed for the entire project period is 20,459 hours.

Uploaded by

Ahmed Sakr
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd

ERC Refinery - roads and fence 29-Apr-17 09:02

Resource - Labor Plan

Resource ID Resource Name Resource Type Remaining Early Units Apr 2017 May 2017 Jun 2017 Jul 2017 Aug 2017 Sep 2017 Oct 2017 Nov 2017 Period Total
01-Apr-17 - 30-Nov-17

MP-Lab MP-Labour Labor 756 1920 1517 464 364 201 86 5 5313
MP-Srv MP-Surveyor Labor 26 46 44 42 46 42 44 6 296
MP-Scf MP-Schafolder Labor 40 56 184 372 288 108 1048
MP-Car MP-Carpenter Labor 600 1650 2190 1090 440 5970
MP-Stf MP-Steel Fixer Labor 130 630 1186 1538 917 671 169 30 5271
MP-Con MP-Concrete worker Labor 60 165 219 109 44 597
MP-Mas MP-Masonary Labor 46 76 76 36 234
MP-Pnt MP-Painter Labor 15 21 54 62 23 175
MP-Lod MP-Loader Operator Labor 18 60 101 53 14 246
MP-Jcp MP-Jcp Operator Labor 42 180 166 32 420
MP-Trk MP-Truck Driver Labor 38 110 162 113 75 42 48 6 593
MP-Elc MP-Elctrical Tech. Labor 13 23 22 21 23 21 22 3 148
MP-Mec MP-Mechanical Tech Labor 13 23 22 21 23 21 22 3 148

Total 1035 3692 5152 4974 3163 1868 522 53 20459

(c) Primavera Systems, Inc. Page 1 of 1