You are on page 1of 14

Implementation Solution for Change

Implementation
Solution for SRB over
HSDPA Activation

Prepared by: Date: 28/01/2015

Reviewed by: Date:

Approved by: Date:

Technical support website: Technical support hotline: Page 1 of 14


http://support.huawei.com Fax:
Implementation Solution for Change

Contents

1 Description of Change....................................................................................................... 4

1.1 Description of Sites ............................................................................................... 4

1.2 Purpose and Requirements .................................................................................... 4

1.3 Description of Change and Change Influence....................................................... 4

1.3.1 Software Version ........................................................................................................ 4

1.3.2 Monitoring and Maintenance Switches ..................................................................... 5

1.3.3 Feature Related Parameters....................................................................................... 5

1.4 Change Period ....................................................................................................... 8

1.5 Composition of Change Team and Responsibility of Team Members ................. 8

1.5.1 Change Team of Optus ..................................................................................... 8

1.5.2 Huawei On-site Change Team ......................................................................... 9

1.5.3 Huawei Support & Guarantee Team .............................................................. 9

1.6 Check of Equipment Running ............................................................................... 9

1.7 Change Risks and Countermeasures ..................................................................... 9

1.8 Issue terminals ..................................................................................................... 10

1.9 Check Before Change ......................................................................................... 10

2 Operation Steps for Change ............................................................................................ 11

2.1 Change Steps ....................................................................................................... 11

2.1.1 Overall Description ............................................................................................. 11

2.1.2 Operation Steps for Change .......................................................................... 12

2.1.3 Script for Change ............................................................................................. 12

2.2 Test and Verification ........................................................................................... 12

2.3 Solution for Rollback In the Case of Failure ....................................................... 13

2.3.1 Definition of Change Failure.......................................................................... 13

2.3.2 Information Collection Before Rollback ..................................................... 13

2.3.3 Overall Description of Rollback .................................................................... 13

Technical support website: Technical support hotline: Page 2 of 14


http://support.huawei.com Fax:
Implementation Solution for Change

2.3.4 Rollback Steps .................................................................................................. 13

2.3.5 Script for Rollback ........................................................................................... 14

2.3.6 Equipment Status Check ................................................................................ 14

2.3.7 Rollback Risk Analysis ................................................................................... 14

2.4 Change of Spare Parts and Emergency Workstation........................................... 14

Technical support website: Technical support hotline: Page 3 of 14


http://support.huawei.com Fax:
Implementation Solution for Change

1 Description of Change

1.1 Description of Sites

The target sites of activating feature WRFD-010652 SRB over HSDPA are HSDPA

enabled site.

The current SRB is setup on DCH while HSDPA service is setup, the transmit power

control (TPC) command is transmitted to the UE on an A-DPCH. After feature

WRFD-010652 SRB over HSDPA is activated, downlink SRB of a support UE are

carried on HSDPA, and the A-DPCH is replaced with the F-DPCH.

1.2 Purpose and Requirements

F-DPCH binding with SRB over HSDPA can make full use of the downlink codes

and power due to replacing many DPCHs. As a result, it make more codes and

power available for HSDPA to improve the downlink capacity. (eg., if A-DPCH using

code SF=256, F-DPCH can be shared by 10 UEs, which means max 9 SF=256

codes and power resource can be saved). Moreover, the SRB over HSDPA is

prerequisite of another feature WRFD-010686 CPC-DTX/DRX which is planned to

be introduced to production network.

This feature requires both network and handsets to support.

1.3 Description of Change and Change Influence

To enable this feature, the network performance optimization parameters and

function switches are going to be tuned to ensure the user experiences.

1.3.1 Software Version

The WRFD-010652 SRB over HSDPA feature will be enabled on SRAN9.0

software RNC and NodeBs

Technical support website: Technical support hotline: Page 4 of 14


http://support.huawei.com Fax:
Implementation Solution for Change

Technology Testing Performed Against

UMTS-RNC MBSC V900R016C00SPC620

UMTS-NodeB MBTS V100R009C00SPC120

1.3.2 Monitoring and Maintenance Switches

After WRFD-010652 SRB over HSDPA being enabled on production network,

there are risks that PS call drop rate will increase. The following switches will be set

to recommended value to facilitate the investigation and troubleshooting process.

Recommend Current Setting


Parameter Name Parameter ID
Setting
Process Control Switch 2 PROCESSSWITCH2 RNC_PCHR_O PCHR_OUTPUT
UTPUT_CTRL_ _CTRL_SWITC
SWITCH-0 H-0
Flow Type FlowType DCCC-1 DCCC-0

Flow Type FlowType SRB2_STAT-1 SRB2_STAT-0

1.3.3 Feature Related Parameters

The following parameters and switches strongly related to feature performance, which will

be set to recommended value.

Recommend Current Setting


Parameter Name Parameter ID
Setting
Type of Channel SrbChlType HSPA(UL_EDC HSUPA
Preferably Carrying H,DL_HSDSCH)
Signaling RB .
Effective Flag of SrbChlTypeRrcEffectFl FALSE. FALSE
Signaling RB Channel ag
Type
Cell Hspa Enhanced HspaEnhSwitch E_F_DPCH_ON. E_F_DPCH_OF
function switch F
Extra Power For Srb ExtraPowerForSrb 2 N/A

Dynamic Resource DraSwitch2 DRA_BASE_CO DRA_BASE_CO


Allocation Switch 2 VER_LOAD_SR VER_LOAD_SR
B_H2D_SWITC B_H2D_SWITC
Technical support website: Technical support hotline: Page 5 of 14
http://support.huawei.com Fax:
Implementation Solution for Change

Recommend Current Setting


Parameter Name Parameter ID
Setting
H-1 H-0

DL Non-HSPA Power SrbH2DNonHLoadState DL_OVERLOA DL_LOADED_S


Initial Load State for SRB DED_STATE TATE
H2D
RSCP Lower Thld for SrbOverHsdpaRscpDow -88 -90
SRB over HS-DSCH nThd
RSCP Upper Thld for SRB SrbOverHsdpaRscpUpT -80 -80
over HS-DSCH hd
Ec/N0 Lower Thld for SrbOverHsdpaEcn0Dow 25 (-12dB) 29(-10dB)
SRB over HS-DSCH nThd
Ec/N0 Upper Thld for SrbOverHsdpaEcn0UpT 31(-9dB) 35(-7dB)
SRB over HS-DSCH hd
HSPA Technologies RetryCapability SRB_OVER_HS SRB_OVER_HS
Retried by UEs DPA-1 DPA-1
Fake EcNo FakeEcNo 25 (-12dB) 50(0.5dB)

Process Control Switch 2 PROCESSSWITCH2 RNC_PS_QUER RNC_PS_QUER


Y_UE_IMEI_S Y_UE_IMEI_S
WITCH-1 WITCH-0
Special User Function SpecUserFunctionSwitc SPECUSER_SR N/A
Switch3 h3 B_OVER_HSDP
A_DISABLED_
SWITCH-1
DRA_PCPICH_ DRA_PCPICH_
Dynamic Resource ECN0_ON_RAC ECN0_ON_RAC
DraSwitch2
Allocation Switch 2 H_UPDATE_S H_UPDATE_S
WITCH-1 WITCH-0
FDPCH Maximum FDPCH Maximum -30(-3dB)
30(3dB)
Reference Power Reference Power
FDPCH Minimum -200 (-20dB)
FdpchMinRefPwr -150(-15dB)
Reference Power
FDPCH_SUPPO FDPCH_SUPPO
Cell Capability Container CellCapContainerFdd
RT-0 RT-0

CMP_UU_FDPC CMP_UU_FDPC
Compatibility Switch CmpSwitch H_COMPAT_S H_COMPAT_S
WITCH-0 WITCH-0

UALGORSVPARA RESERVED_S RESERVED_S


RsvSwitch11 WITCH_11_BIT WITCH_11_BIT
Reserved swtich 5-1 5-0

Technical support website: Technical support hotline: Page 6 of 14


http://support.huawei.com Fax:
Implementation Solution for Change

Recommend Current Setting


Parameter Name Parameter ID
Setting

UALGORSVPARA RESERVED_S RESERVED_S


RsvSwitch7 WITCH_7_BIT1 WITCH_7_BIT1
Reserved swtich 4-0 4-1

UALGORSVPARA RESERVED_S RESERVED_S


RsvSwitch11 WITCH_11_BIT WITCH_11_BIT
Reserved swtich 12-1 12-1

PS_RL_SETUP_ PS_RL_SETUP_
Optimization Switch Optimization Switch
SWITCH-1 SWITCH-1

IUR_RL_REEST IUR_RL_REEST
Process Control Switch 4 PROCESSSWITCH4
_SWITCH-1 _SWITCH-1

TRB_RESET_R TRB_RESET_R
Process Control Switch 4 PROCESSSWITCH4 L_REEST_SWI L_REEST_SWI
TCH-1 TCH-1

SRB_RESET_R SRB_RESET_R
Optimization Switch OptimizationSwitch L_SETUP_SWI L_SETUP_SWI
TCH-1 TCH-1

RLFAIL_RL_SE RLFAIL_RL_SE
Optimization Switch OptimizationSwitch
TUP_SWITCH-1 TUP_SWITCH-1

RL_RESTORE_ RL_RESTORE_
Optimization Switch OptimizationSwitch
SWITCH-1 SWITCH-1

Optimization Switch OptimizationSwitch ASU_RL_RESE ASU_RL_RESE


T_SWITCH-1 T_SWITCH-1

Optimization Switch OptimizationSwitch MC_RL_RESET MC_RL_RESET


_SWITCH-1 _SWITCH-1

PHY_RECFG_R PHY_RECFG_R
Process Control Switch 4 PROCESSSWITCH4 EEST_SWITCH- EEST_SWITCH-
1 1

PHYCHRECFG PHYCHRECFG
Process Control Switch 4 PROCESSSWITCH4 _ENH_RL_REE _ENH_RL_REE
ST_SWITCH-1 ST_SWITCH-0

RB_SETUP_EN RB_SETUP_EN
Process Control Switch 4 PROCESSSWITCH4 HANCE_RL_RE HANCE_RL_RE
EST_SWITCH-1 EST_SWITCH-1

RBRECFG_EN RBRECFG_EN
Process Control Switch 4 PROCESSSWITCH4 H_RL_REEST_ H_RL_REEST_
SWITCH-1 SWITCH-1

Optimization Switch OptimizationSwitch RB_RECFG_RL RB_RECFG_RL


_REEST_SWIT _REEST_SWIT
CH-1 CH-1

Improvement Switch Improvement Switch NON_DCCC_R NON_DCCC_R


BRECFG_RL_R BRECFG_RL_R
Technical support website: Technical support hotline: Page 7 of 14
http://support.huawei.com Fax:
Implementation Solution for Change

Recommend Current Setting


Parameter Name Parameter ID
Setting
EEST_SWITCH- EEST_SWITCH-
1 1

Improvement Switch Improvement Switch SMC_RL_REES SMC_RL_REES


T_SWITCH-1 T_SWITCH-1

IRATHO_HOC IRATHO_HOC
Process Control Switch 4 PROCESSSWITCH4 ANCEL_RL_RE ANCEL_RL_RE
EST_SWITCH-1 EST_SWITCH-0

Optimization Switch OptimizationSwitch UE_SRB_RESE UE_SRB_RESE


T_SWITCH-1 T_SWITCH-1
Process Control Switch 2 PROCESSSWITCH2 CELLUPT_RLF CELLUPT_RLF
AILURE_SRBR AILURE_SRBR
EESTAB_SWIT EESTAB_SWIT
CH-1 CH-1
Performance PerfEnhanceSwitch3 PERFENH_RLR PERFENH_RLR
Enhancement Switch 3 ESETUP_GUAR ESETUP_GUAR
ANTEE_SWITC ANTEE_SWITC
H-1 H-0
Optimization Switch6 OptimizationSwitch6 ASU_RSP_FAIL ASU_RSP_FAIL
_REL_UE-1 _REL_UE-0
Process Control Switch 2 PROCESSSWITCH2 ASU_RSP_TIM ASU_RSP_TIM
EOUT_HANDL EOUT_HANDL
E_SWITCH-1 E_SWITCH-1

1.4 Change Period

The change period is from 23:00, 16/02/2015 to 06:00 17/02/2015.

1.5 Composition of Change Team and Responsibility of Team


Members

Feature Activation: Fan Bai

Drive test: Huawei DT team

1.5.1 Change Team of Optus

Name Responsibility Telephone No.

Wance Shand Project Manager 0431 501 880

Technical support website: Technical support hotline: Page 8 of 14


http://support.huawei.com Fax:
Implementation Solution for Change

Ruth Foo RNC platform Owner 0402 974 738

Rainier Collantes Capacity Manager 0433 788 081

Marcin Wierzbicki RAE Prime 0434 739 988

Alan Loo Mobile Tier2 0434 763 295

Gabriel Prasad Mobile Tier2 0402 792 982

Shift Duty Tier I, GMS Pro Active 1800 505 777 * 3

1.5.2 Huawei On-site Change Team

Name Responsibility Telephone No.

Joyce Yu Project Manager 0432 329 858

Fan Bai RAN Engineer 0423 715 506

Mac Chin Technical Specialist 0434 679 157

Bill Li CSSD Manager 0425 510 050

1.5.3 Huawei Support & Guarantee Team

Name Responsibility Telephone No.

Supporting overall 0452 625 158

Cherry Li coordination as the

technical expert

Product support contact 0425 510 050


Bill Li
person

1.6 Check of Equipment Running

It is required to check the health of the trial RNC and NodeB before feature

activation.

1.7 Change Risks and Countermeasures


Risk existing in change duration: the PS call drop rate may increase after feature

Technical support website: Technical support hotline: Page 9 of 14


http://support.huawei.com Fax:
Implementation Solution for Change

activation.

No. Risk Description Possibility Impact Countermeasure

(High/Middle/ (High/Middle

Low) /Low)

1 Data backup Low Low N/A

2 Impact on NEs Low Low RSSR, DCR, HO SSR

Risk in change Middle Middle RSSR, DCR, HO SSR


3
duration

1.8 Issue terminals

To our best knowledge, the following terminals are not compatible with SRB over HSDPA.

It is required to block these terminals to use SRB over HSDPA. The following table lists

the blacklisted terminals know by HUAWEI.

Description TAC

1 Blackberry BB9900 35427905

2 HUAWEI U8860 86894300

3 HUAWEI E367 35361304

4 HUAWEI E372 35314704

5 SAMSUNG Galaxy S2 35884804

6 Blackberry BB9810 35812304

7 MotorolaXT890 35253105

1.9 Check Before Change

No. Preparations Before Change Owner Completion Da

te

Technical support website: Technical support hotline: Page 10 of 14


http://support.huawei.com Fax:
Implementation Solution for Change

1 Solution for rollback in the case of failure Fan Bai

2 Test solution Mac. Chin

3 Confirming change risks and emergency Fan Bai

measures

4 Readiness of mobile phone test card Mac. Chin

5 Readiness of change test personnel Mac. Chin

6 Readiness of relevant equipment N/A

maintenance personnel

7 Readiness of support & guarantee team Mac. Chin

8 Readiness of remote log-in environment Fan Bai

9 Readiness of emergency spare parts N/A

10 Readiness of boards, tools, and N/A

instruments

2 Operation Steps for Change

2.1 Change Steps

2.1.1 Overall Description

The whole procedure of change is composed of following sub-tasks

 Pre- Drive test

 Data Backup(Configuration, Alarm .etc)

 Check the path for transmitting SRBs has been configured.

 Run Script to activate SRB over HSDPA

 Turn on License Control item of SRB over HSDPA

 System Verification

 Post- Drive test

Technical support website: Technical support hotline: Page 11 of 14


http://support.huawei.com Fax:
Implementation Solution for Change

2.1.2 Operation Steps for Change

No. Change Step Operation Implementation Time

Person

1 Pre-Drive test Drive test for benchmark DT team 12:00

2 Backup Configuration file , Fan Bai 23:00


Data backup
Active Alarm, License file

3 Check the Check the path for transmitting Fan Bai 23:30

configuration SRBs has been configured

4 Feature Turn On Feature Switches and Fan Bai 0:00

Activation License Control

5 System Alarm check Fan Bai 1:30

verification KPI monitoring

6 KPI report Fan Bai 3:00

7 Post-Drive DT team 12:00


Drive test
test

2.1.3 Script for Change

2.2 Test and Verification

No. Operation Item Operation Method Owner Time


1 Alarm Check Clear new Alarm caused by Fan 0:00
feature activation if applicable Bai
2 KPI monitoring Confirm Major KPI Fan 2:00
performance is no degradation Bai
3 Drive test Post Drive Test DT 12:00
Technical support website: Technical support hotline: Page 12 of 14
http://support.huawei.com Fax:
Implementation Solution for Change

team

2.3 Solution for Rollback In the Case of Failure

2.3.1 Definition of Change Failure

A change failure shall be recognized if the major KPI degradation could


not be resolved before 4:00 am.
Upon the suiation of change failure, rollback operation shall be taken and
finished before 6:00 am.

2.3.2 Information Collection Before Rollback

 Configuration file

 Operation Log

 Performance Data

 CHR, PCHR

2.3.3 Overall Description of Rollback

 Data Backup(Configuration, Alarm .etc)

 Run Script to rollback the configuration

 System Verification

 Post- Drive test

2.3.4 Rollback Steps

No. Change Step Operation Implementation Time

Person

1 Backup Configuratio file , Active Fan Bai 4:00


Data backup
Alarm, License file
Technical support website: Technical support hotline: Page 13 of 14
http://support.huawei.com Fax:
Implementation Solution for Change

2 Feature Run roll back scripts to turn Off Fan Bai 4:30

deactivation Feature Swicthes

3 System Alarm check Fan Bai 5:30

verification KPI monitoring

5 KPI report Fan Bai 6:00

2.3.5 Script for Rollback

2.3.6 Equipment Status Check

N/A

2.3.7 Rollback Risk Analysis

N/A

2.4 Change of Spare Parts and Emergency Workstation

N/A

Technical support website: Technical support hotline: Page 14 of 14


http://support.huawei.com Fax: