Sewer Works Acceleration proposals.

Sewer works have started only on the main trunk (OWS 5.5: SEWER LINE A.11 - A.0 (5,465m) for DN
375mm pipe.
Available resources for this work section are:
1. Excavator-320c- 1No.
2. Concrete Mixer-1No.
3. Dewatering Pump-1No.
4. Surveyor-1No.
5. Foreman-1No.
6. Pipe fitter-1No.
7. Chainmen-2No.
8. Dumpy level-1No.
9. Total Station-1No.
10. Levelling Staff-1No.
11. Ranging Rods-3no.
12. Measuring Tape (100m)-1No.

We have encountered rock on this section. We recommend an excavator with hammer capabilities to be
availed to work on this area rather than having two excavators on this section.
We propose to start works on the laterals hence two additional work teams are needed.
Each work team will implement two of the lines listed below and later join the trunk sewer or
stabilization ponds implementation.
i. OWS 5.1: SEWER LINE A.8.2.1 - A.8.2 (1,168 M)
ii. OWS 5.2: SEWER LINE A.8.2 - A.8.1 (577 m)
iii. OWS 5.3: SEWER LINE A.8.1 - A.8 (630 m)
iv. OWS 5.4: SEWER LINE A.14.1 - A.14 (423m)
v. OWS 5.6: ADDTITIONAL SEWER LINES (6,000m)
The following resources to be availed:
1. Excavator- 2No. (At least one with hydraulic hammer capabilities)
2. Concrete Mixer-2No.
3. Poker Vibrator-2No.
4. Dewatering Pump-2No.
5. Foreman-1No.
6. Pipe fitter-2No.
7. Chainmen-4No.
8. Operator-2No.
9. Dumpy level-2No.
10. Levelling Staff-2No.
11. Ranging Rods-6no.
12. Measuring Tape (100m)-2No.
13. Vehicle for Surveying team
14. Canter for casuals and materials transportation
We are seriously facing transportation problems because we have only two vehicles (KAZ 120R and KBM
813V) to take workers to work sections. Provision of two additional vehicles for the surveying team and
Canter for the workers and materials transportation is highly recommended.