Investigasi Awal Analisis Permasalahan Analisis Data yang Diperlukan

Start: Mon 15/01/18ID: 1 Start: Tue 16/01/18 ID: 2 Start: Thu 18/01/18ID: 3
Finish: Mon 15/01/18Dur: 1 day Finish: Wed 17/01/18Dur: 2 days Finish: Mon 22/01/18Dur: 3 days
Res: Res: Res:

Page 1
Analisis Proses yang Diperlukan
Start: Tue 23/01/18 ID: 4
Finish: Tue 30/01/18Dur: 6 days
Res:

Rancangan dan Data


Start: Tue 23/01/18 ID: 5
Finish: Wed 24/01/18Dur: 2 days
Res:

Rancangan Interface (antar-muka)


Start: Wed 31/01/18ID: 6
Finish: Fri 02/02/18 Dur: 3 days
Res:

Rancangan Proses dan Program


Start: Mon 05/02/18ID: 7
Finish: Thu 08/02/18Dur: 4 days
Res:

Page 2
Pemograman dan Pengujian Pengajuan Sistem Instalasi
Start: Fri 09/02/18 ID: 8 Start: Tue 20/02/18 ID: 9 Start: Thu 22/02/18ID: 10
Finish: Mon 19/02/18Dur: 7 days Finish: Wed 21/02/18Dur: 2 days Finish: Fri 23/02/18 Dur: 2 days
Res: Res: Res:

Page 3
Critical Critical Summary Critical Marked Project Summary

Noncritical Summary Marked Highlighted Critical


Project: UAS
Date: Fri 12/01/18 Critical Milestone Critical Inserted Critical External Highlighted Noncritical

Milestone Inserted External