You are on page 1of 1

STRUCTURAL NOTES

A. GENERAL 4. ALL THE CONCRETE SHOULD SATISFY THE DURABILITY CONDITION GIVEN BELOW FOR SUPER STRUCTURE CONCRETE ONLY.

A1. THE STRUCTURAL DRAWING SHALL BE READ IN CONJUNCTION WITH THE RELEVANT ARCHITECTURAL, REQUIREMENTS OF CONCRETE D. STRUCTURAL STEEL / SPACE FRAME
ELECTRICAL, MECHANICAL AND OTHER STRUCTURAL DRAWING IN PARTICULAR, CUT-OUTS IN SLAB NO TESTS TEST METHOD SPECIFICATION LIMIT GENERAL NOTE
D1. THE CONTRACTOR SHALL BE RESPONSIBLE FOR THE DESIGN OF THE PARAPETS & ARCHITECTURAL FEATURES.,
AND WALLS FOR BUILDING SERVICES SHALL BE READ IN CONJUNCTION WITH THE ELECTRICAL AND AND ANY STRUCTURAL STEEL WORK BY THE SPECIALIZED SUB CONTRACTOR. AND IN ACCORDANCE WITH THE DESIGN LOADS.
MECHANICAL DRAWINGS. 1. temperature ( at placement ) ASTM 1064 25° C max.
for all grades; ''' THE DESIGN CALCULATIONS SHALL BE SUBMITTED TO THE ENGINEER FOR APPROVAL.
A2. FOR MAIN SETTING LINES AND LEVELS, REFER TO THE ARCHITECTURAL DRAWINGS. 2. slump mm ( at placement ) BS 1881; pat 102 150 ± 25 mm
ALL DIMENSIONS MUST BE VERIFIED ON SITE AND ANY DISCREPANCIES SHALL BE BROUGHT D2. THE SHOP DRAWINGS SPECIFICATION AND METHOD OF STATEMENTS FOR THE STEEL WORKS SHALL BE SUBMITTED
3. water permeability DIN 1048 18mm max.
TO THE ENGINEER FOR APPROVAL PRIOR TO CONSTRUCTION.
TO THE ATTENTION OF THE ENGINEER BEFORE PROCEEDING WITH THE PORTION OF WORK INVOLVED.
4. rapid chloride penetration ( RCP ) ASTM C1202 1500 col.. max.
D3. ALL BOLTS SHALL BE GRADE 8.8 TO BS 3692.
A3. ABBREVIATIONS 1.8% col.. max.
5. water absorption BS 1881; part 122
D4. THE PROTECTIVE POINT SYSTEM FOR THE STEEL WORK SHALL BE IN ACCORDANCE WITH THE SPECIFICATION.
EF = EACH FACE
B (B1 & B2) = OUTER & INNER BOTTOM BARS 6. chlorides by weight of cementations material BS 1881; part 124 0.3% max.
D5 ALL STRUCTURAL STEEL WORK SHALL BE GRADE 5275 TO BS EN10025.
T (T1 & T2) = OUTER & INNER TOP BARS 7. sulphates (503) by weight of cementations material BS 1881; part 124 4.0% max.
BW (EW) = BOTH WAYS (EACH WAY) D6 UNLESS SHOWN OTHERWISE ON THE DRAWING, ALL CONNECTIONS SHALL BE IN ACCORDANCE WITH
''' :- TO BE CONFIRMED BY THE SUPPLIER. THE FOLLOWING MINIMUM REQUIREMENTS :
= COLUMN CONTINUED
= COLUMN UNDER NOTE:-2 NOS CONCRETE TEST PRISMS 3m X 3m X 3m TO BE TESTED ON SITE PRIOR TO ANY CONCRETING, ONE FOR SUB STRUCTURE AND
I) ALL WELDS SHALL BE AT LEAST 6mm CONTINUOUS FILLET WELDS ALL ROUND.
= COLUMN TRANSFERRED OR PLANTED AT THIS LEVEL. (NO COLUMN UNDER) ONE FOR SUPER STRUCTURE WITH FULL TEMPERATURE MONITORING ON SITE ALONG WITH DURABILITY TESTS.
II) ALL BOLTS SHALL BE AT LEAST M20. WITH A MINIMUM OF 2 BOLTS OER CONNECTION.
= OPENING IN SLAB OR WALL C5. USE OF CONCRETE ADDITIVES PURLIN BOLTS TO BE IN ACCORDANCE WITH THE SUPPLIERS RECOMMENDATIONS.
EJ = EXPANSION JOINT CONCRETE ADDITIVES APPROVED BY THE ENGINEER SHALL BE USED TO IMPROVE CONSISTENCY, WORKABILITY, QUALITY
III) ALL GUSSET PLATES SHALL BE AT LEAST 10mm THICK.
AND STRENGTH OF CONCRETE
C/C = CENTRE TO CENTRE.
CHEMICAL ADMIXTURES MANUFACTURER SHALL PROVIDE CERTIFIED TEST REPORTS FROM QUALIFIED, INDEPENDENT, ACCREDITED IV) ALL CAP PLATES SHALL BE AT LEAST 12 MM THICK
A4. DRAWINGS.
THE CONTRACTOR SHALL SUBMIT WORKSHOP DRAWINGS SHOWING ALL REQUIREMENTS FOR SERVICES, LABORATORIES SHOWING ACTUAL TEST RESULTS INDICATING MATERIALS COMPLY IN ALL RESPECTS WITH DURABILITY REQUIREMENTS
V) ALL BASE PLATES SHALL BE AT LEAST 12mm THICK.
PENETRATIONS ETC. FOR THE ENGINEER'S APPROVAL. MODIFICATION NECESSITATED BY DETAILED PLANT HIGH RANGE WATER REDUCING ADMIXTURE SHALL BE NAPHTHA LENE SULPHONATE POLYMER BASED MATERIAL LIKE
INFORMATION SHALL BE SUBJECT TO THE ENGINEER'S APPROVAL. CONPLAST SP 2000, OR CONPLAST SP 432 OR EQUAL APPROVED BY THE ENGINEER SHALL BE USED D7 THE STEEL FABRICATOR SHALL BE RESPONSIBLE FOR DESIGN OF CONNECTION IN ACCORDANCE
WATER REDUCING AND RETARDING ADMIXTURE SHALL CONFIRM TO BS EN-934-2 OR ASTM AT 494 TYPE FOR G WITH THE FACTORED DESIGN LOADS GIVE ON THE DRAWING. THE CONNECTION DESIGN CALCULATION
A5. STRUCTURE IS DESIGNED FOR RESIDENTIAL BUILDING (2B + G +3P.+ 23TYP.FLRS) SHALL BE SUBMITTED TO THE ENGINEER FOR APPROVAL PRIOR TO COMMENCEMENT OF FABRICATION.

B. EARTHWORKS AND FOUNDATIONS D8 THE PURLIN SUPPORTING THE CLAD AREAS OF THE ROOF STEEL STRUCTURE SHALL BE
COLD FORMED Z TYPE PURLINS SELECTED FROM APPROVED SUPPLIER, AND SHALL BE
B1. GRANULAR FILL UNDER FOUNDATIONS AND SLAB CAST-ON-GROUND SHALL BE SELECTED GRANULAR MATERIAL CAPABLE OF RESISTING THE FOLLOWING UNFACTORED WIND LOADS.
LAID IN 200 mm LAYERS AND MECHANICALLY COMPACTED TO AT LEAST 95% OF ITS MAXIMUM DRY DENSITY. C6. CONCRETE FORM WORK - DOWNWARD PRESSURE =2.0 KN/m²
B2. THE BACK FILLING MATERIAL SHALL BE SELECTED GRANULAR MATERIAL COMPACTED AT LEAST 95% OF ITS MINIMUM PERIODS IN DAYS FOR STRIKING OTHER FORM WORK SHOULD BE IN ACCORDANCE WITH THE FOLLOWING TABLE - UPWNWARD PRESSURE =2.0 KN/m²
MAXIMUM DRY DENSITY AND IN ACCORDANCE WITH THE SPECIFICATIONS.
B3. TESTS:- CPT TEST TO BE DONE ON BACK FILLING. AT LEAST 1/150m² SLAB ( PROPS LEFT UNDER ) 7 D9 THE FABRICATION AND ERECTION OF THE STRUCTURAL STEEL WORK SHALL BE
AREA. SUPERVISED BY QUALIFIED PERSONNEL TO ENSURE THAT ALL DESIGN REQUIREMENTS
BEAM SOFFITS ( PROPS LEFT UNDER ) 10
ARE MET. DETAILS OF ERECTION SEQUENCE SHALL BE SUBMITTED TO THE ENGINEER
C. REINFORCED CONCRETE PROPS TO SLABS 16 FOR APPROVAL PRIOR TO COMMENCEMENT OF ERECTION.

C1.CONCRETE SUB STRUCTURE PROPS TO BEAMS 21


(RAFT & BASEMENT WALLS) 1
VERTICAL SURFACES FOR WALLS & COLUMNS
CONCRETE FOR RAFT, R.C.C.BASEMENT WALL (ANY OTHER STRUCTURAL ELEMENT CONTACT WITH EARTH) SHALL HAVE A
CHARACTERISTIC STRENGTH, DETERMINED FROM CUBES AT 28 DAYS, OF 48 N/mm², E : BLOCKWORK.
MIX SHALL BE ( PORTLAND CEMENT WITH 36% TO 65% GGBS ( GROUND GRANULATED BLASTFURNACE SLAG )+ MICRO SILICA). C7. CURING
MAXIMUM WATER / CEMENT RATIO OF 0.35. a. HORIZONTAL SURFACES E1: BLOCKS SHALL HAVE A MINIMUM CHARACTERISTIC COMPRESSIVE STRENGTH OF 12.5 N/mm² AT
IT SHALL HAVE A CHARACTERISTIC STRENGTH, DETERMINED FROM TEST CUBES AT 28 DAYS, OF 48N/mm². 28 DAYS FOR LOAD BEARING WALLS AND 7.5 N/mm² FOR NON-LOAD BEARING PARTITIONS TO
1) POLYTHENE SHEET MUST BE PLACED IMMEDIATELY AFTER FINISHING
BS5628 : PARTS 1, 2 & 3 : 1992. ALL BLOCKS SHALL BE IN ACCORDANCE WITH LOCAL
C2. CONCRETE SUPER STRUCTURE (2ND BAS. TO 16TH TYPICAL FLOOR) (COLUMNS,WALLS,CORE WALLS & SPANDERL BEAMS.) 2) AFTER FINAL SET HAS TAKEN PLACE, POLYTHENE SHEET SHALL BE REPLACED BY WET HESSION MUNICIPALITY REGULATIONS.
3) AFTER 7 DAY HESSAIN & POLYETHENETO BE REMOVED AND ON APPROVED ALUMINIZED OR WHITE RESIGN -BASED
ALL CONCRETE WORK SHALL CONFIRM TO THE BRITISH STANDARD BS 8110 :1997. EXCEPT WHERE OTHERWISE NOTED, E2: ALL BLOCK WALLS SHALL BE CONSTRUCTED WITH LIGHT WEIGHT BLOCKS.
CONCRETE SHALL BE OF GRADE C60., IT SHALL HAVE A CHARACTERISTIC STRENGTH, DETERMINED FROM TEST CUBES AT 28 TROPICAL CURING COMPOUND APPLIED. THE HESSAIN & POLYTHENE SHALL REMAIN FOR FURTHER 7 DAYS ( ALTERNATIVELY )
DAYS, OF 48N/mm². AND HAVE NOMINAL MAXIMUM AGGREGATE SIZE OF 20mm TO BS 882. CONCRETE MIX DESIGN SHALL E3: BLOCK WALLS BELOW GROUND FLOOR LEVEL SHALL BE CONSTRUCTED WITH SULPHATE RESISTING BLOCK.(CONTACT WITH SOIL)
b. VERTICAL SURFACES
COMPLY WITH BS 5328. THE MINIMUM CEMENT CONTENT SHALL BE 420 kg/m³
1) POLYTHENE OR WET HESSAIN SHALL BE SECURED TO THE SURFACES IMMEDIATELY AFTER REMOVAL OF THE FORM WORK
MIX SHALL BE (PORTLAND CEMENT WITH 36% TO 65% GGBS ( GROUND GRANULATED BLASTFURNACE SLAG )+ MICRO SILICA ). E4: THE STRUCTURAL FLOOR PLANS SHOW THE LAYOUT OF LOAD BEARING WALLS ONLY. ALL OTHER
MAXIMUM WATER / CEMENT RATIO OF 0.35. THE CEMENT SHALL BE ORDINARY PORTLAND CEMENT (OPC) TO BS 12. 2) AFTER 7 DAYS THE HESSAIN & POLYTHENE SHALL BE REMOVED AND ON APPROVED ALUMINIZED OR WHITE RESIN BASED BLOCKWORK WALLS ARE TO BE CONSIDERED AS NON-LOAD BEARING PARTITIONS AND SHALL BE
FOR TESTING, CERTIFICATION, PLACING, COMPACTING, CURING AND PROTECTION OF CONCRETE REFERENCE SHALL BE MADE TROPICAL CURING COMPOUND APPLIED CONSTRUCTED AFTER COMPLETION OF THE STRUCTURE. FOR SETTING OUT OF BLOCK WALL REFER
TO THE GENERAL PROJECT SPECIFICATION. CONTRACTOR SHALL SUBMIT ALL ADDITIVES & PLASTICIZERS REQUIRED FOR c. CURING COMPOUND APPROVED BY THE CONSULTANT COMPLYING ASTM TO BE USED FOR A MINIMUM OF 7 DAYS FOR PILE CAP. TO ARCHITECTURAL DRAWINGS.
IMPROVING THE WORKABILITY OF CONCRETE FOR THE APPROVAL OF THE ENGINEER.
C6. CONCRETE FORM WORK E5: LOAD BEARING BLOCK WALLS SHALL BE REINFORCED HORIZONTALLY WITH GALVANIZED EXPANDING
MINIMUM PERIODS IN DAYS FOR STRIKING OTHER FORM WORK SHOULD BE IN ACCORDANCE WITH THE FOLLOWING TABLE METAL LATHS PLACED AT EVERY 5th . COURSE VERTICALLY.
C3. CONCRETE SUPER STRUCTURE (16TH TYPICAL FLOOR LEVEL TO TERRACE FLOOR LEVEL)
E6: BRACING OF BLOCK WALLS TO BE PROVIDED FOR WALLS EXCEEDING 14m2 AREA
(COLUMNS,WALLS,CORE WALLS & SPANDERL BEAMS.) SLAB ( PROPS LEFT UNDER ) 7
BEAM SOFFITS ( PROPS LEFT UNDER ) 10 F: ALUMINIUM/SHEETING PH5
ALL CONCRETE WORK SHALL CONFIRM TO THE BRITISH STANDARD BS 8110 :1997. EXCEPT WHERE OTHERWISE REVISION :
NOTED, CONCRETE SHALL BE OF GRADE C60: IT SHALL HAVE A CHARACTERISTIC STRENGTH, DETERMINED FROM F1 SHEETING TO BE ALUMINUM STANDING SEAM ROOF PANELS 1.0 mm THK.OR AS/SPECIFICATION
PROPS TO SLABS 16 07
TEST CUBES AT 28 DAYS, OF 48N/mm². AND HAVE NOMINAL MAXIMUM AGGREGATE SIZE OF 20mm TO BS 882. F2 LINER SHEET, THICKNESS 0.7 mm ALUMINUM IN 25 MICRONS POLYESTER COLOR COATING. OR
CONCRETE MIX DESIGN SHALL COMPLY WITH BS 5328. THE MINIMUM CEMENT CONTENT SHALL BE 480 kg/m³. PROPS TO BEAMS 21 06
AS/SPECIFICATION.
MIX SHALL BE (PORTLAND CEMENT WITH 36% TO 65% GGBS ( GROUND GRANULATED BLASTFURNACE SLAG ). 1 05
VERTICAL SURFACES FOR WALLS & COLUMNS
MAXIMUM WATER / CEMENT RATIO OF 0.35. THE CEMENT SHALL BE ORDINARY PORTLAND CEMENT (OPC) TO BS 12.) G: SOIL REPORT 04
FOR TESTING, CERTIFICATION, PLACING, COMPACTING, CURING AND PROTECTION OF CONCRETE REFERENCE C7. CURING
03
SHALL BE MADE TO THE GENERAL PROJECT SPECIFICATION. CONTRACTOR SHALL SUBMIT ALL ADDITIVES & a. HORIZONTAL SURFACES NATIONAL LAB FOR SOIL INVESTIGATION REF NO. DXB/0053/15 DATE 6TH JUNE 2015
02
PLASTICIZERS REQUIRED FOR IMPROVING THE WORKABILITY OF CONCRETE FOR THE APPROVAL OF THE ENGINEER. 1) POLYTHENE SHEET MUST BE PLACED IMMEDIATELY AFTER FINISHING 01
CONCRETE (GRADES)
2) AFTER FINAL SET HAS TAKEN PLACE, POLYTHENE SHEET SHALL BE REPLACED BY WET HESSION NO. DATE REVISED APPROVED
(SUB STRUCTURE AND SUPER STRUCTURE).
SLAB AND BEAMS FOR ALL FLOORS C60. 3) AFTER 7 DAY HESSAIN & POLYETHENETO BE REMOVED AND ON APPROVED ALUMINIZED OR WHITE RESIGN -BASED PROJECT:
H: WATER TABLE
TROPICAL CURING COMPOUND APPLIED. THE HESSAIN & POLYTHENE SHALL REMAIN FOR FURTHER 7 DAYS ( ALTERNATIVELY )
C4. CONCRETE (GRADES) WATER TABLE IS AT 5.0 TO 5.3m BELOW EXISTING GROUND SURFACE LEVEL. PROPOSED: RESIDENTIAL BUILDING
THE CHARACTERISTIC CUBE STRENGTH ARE FOR CONCRETE WHICH HAVE BEEN CURED AT TEMPERATURE OF 20± 1°C. b. VERTICAL SURFACES
AND ARE THE VALUMES BELOW WHICH NO MORE THAN 5% OF THE TEST RESULTS MAY FALL. THE 7 DAY STRENGTHS 1) POLYTHENE OR WET HESSAIN SHALL BE SECURED TO THE SURFACES IMMEDIATELY AFTER REMOVAL OF THE FORM WORK
DEWATERING WILL BE CONTRACTOR'S RESPONSIBLITY. ( 2B + G + 3P + 23 TYPICAL FLRS. )
SHALL BE USE ONLY AS A GUIDE TABLE OF MIXES. 2) AFTER 7 DAYS THE HESSAIN & POLYTHENE SHALL BE REMOVED AND ON APPROVED ALUMINIZED OR WHITE RESIN BASED CLIENT:
CONCRETE GRADE FOR (COLUMNS/SPANDREL BEAMS/CORES %%UCOLUMNS,WALLS,CORE WALLS,BEAMS,SPANDERL TROPICAL CURING COMPOUND APPLIED DESIGN LOADS
BEAMS,SLABS,RAFT & BASIC WALLS) c. CURING COMPOUND APPROVED BY THE CONSULTANT COMPLYING ASTM TO BE USED FOR A MINIMUM OF 7 DAYS FOR PILE CAP.
LOADS :- AL KHALEEJ ARABI PROPERTIES
1) PARKING FLOOR SLAB (BASEMENT FLOOR)
FLOORS conc. class 28 days strength N/mm² C8. REINFORCEMENT
-DEAD LOAD-
SELF WEIGHT + 1.0 KN/m² FINISHING
TITLE:
REINFORCEMENT SHALL BE DEFORMED TYPE 2AND MARKED TO INDICATE HIGH YIELD STRENGTH OF 460 N/mm² TO BS 4449 .
16TH TYPICAL TO SERVICES 0.5 KN/m²
C60 48
TERRACE FLOOR THE CONTRACTOR SHALL PROVIDE DETAILED AND BAR BENDING SCHEDULES FOR THE ENGINEER'S APPROVAL.
-LIVE LOAD-
5.0 KN/m²
GENERAL DETAILS
2ND BASEMENT TO
16TH TYPICAL C60 48 CHAIRS, SPACERS ETC. SHALL PROVIDE AS NECESSARY, TO THE APPROVAL OF THE ENGINEER ON SITE.
FLOOR LEVEL
RAFT & COMPRESSION LAP LENGTH OF THE REINFORCEMENT TO BE 50 TIMES THE BAR DIAMETER 2) GROUND FLOOR
C60 48
BASEMENT WALL
+111.20 cm

-DEAD LOAD-
THE TENSION LAP LENGTH SHOULD BE AT LEAST EQUAL TO THE DESIGN ANCHORAGE SELF WEIGHT + 2.0 KN/m² FLOOR FINISHING + 2.5 KN/m² PARTITION WALLS.
NOTE:- 1. MIX DESIGN TO BE PROPOSED FOR ALL MIXES BY THE SUPPLIER TO THE CONSULTANT FOR APPROVAL . SERVICES 0.5 KN/m²
LENGTH OR EQUAL TO 50 TIMES THE BAR DIAMETER.
2. (*) SUPPLIER SHOULD CONFIRM THE MIX DESIGN FOR CONCRETE WITH NO SHRINKAGE CRACKS. AND THE QUANTITIES -LIVE LOAD-
GIVEN ABOVE ARE TENTATIVE. 5.0 KN/m² & 10.0KN/m.2 ENG. ADNAN SAFFARINI
ALL CONDUITS SHALL RUN ABOVE BOTTOM REINFORCEMENT AND BELOW TOP REINFORCEMENT OF SLAB,
NOTE:- 1. MIX DESIGN TO BE PROPOSED FOR ALL MIXES BY THE SUPPLIER TO THE CONSULTANT FOR APPROVAL INSIDE BEAM AND COLUMN LINK AND BETWEEN WALL EXTERNAL REINFORCEMENT LAYERS. 3) PODIUM FLOOR DESIGN, SUPERVISON & CONSULT
MECHANICAL COUPLERS TO BE USED FOR 40 mm,32 mm AND 25 mm DIA BARS. -DEAD LOAD-
2. MAXIMUM PEAK TEMPERATURE OF CONCRETE TO BE NOT MORE THAN 70° C & THE MAXIMUM DIFFERENTIAL TEMPERATURE SELF WEIGHT + 1.0 KN/m² FLOOR FINISHING. HEAD OFFICE , POST BOX - 4000 DUBAI : 04-2222002
SHOULD NOT BE MORE THAN 18° C. ( SPECIFICATION OF COUPLERS WRITTEN ON FOUNDATION PLAN ALSO. ) SERVICES 0.5 KN/m² ABUDHABI:02-626050,SHJ:06-5733100,ALAIN:03-668970
3. ALL THE CONCRETE SHOULD SATISFY THE DURABILITY CONDITION GIVEN BELOW FOR SUBSTRUCTURE CONCRETE PARALLEL THREADED COUPLERS WITH BAR BREAK GUARANTEE TO BE USED -LIVE LOAD-
ONLY. 5.0 KN/m².
C9. COVER TO REINFORCEMENT. 4) TYPICAL FLOOR SLAB
REQUIREMENTS OF CONCRETE ARCHITECT Ar. AHMED SAFFARINI SIGN
COVER TO REINFORCEMENT SHALL BE FOLLOWS UNLESS SHOWN OTHERWISE ON THE DRAWING :- -DEAD LOAD-
NO TESTS TEST METHOD SPECIFICATION LIMIT PILES =75mm SELF WEIGHT + FINISHES(2.0 KN/m²) & PARTITION WALLS = 2.5 KN/m² STRUCTURE ENG. SHAKEEB SIGN
PERIPHERAL WALL LINE LOAD = 7.5 KN/m
PILE CAP BOTTOM =AS/SKETCH SERVICES 0.5 KN/m²
1. 30° C max. " ELECTRICAL ENG. ----- SIGN
temperature ( at placement ) ASTM 1064 PILE CAP SIDES & TOP =75mm EXTERNAL -LIVE LOAD-
for all grades; ''' GROUND BEAMS =40mm INTERNAL / 75mm EARTH FACES 2 KN/m² MECH. ENG. ----- SIGN
2. slump mm ( at placement ) BS 1881; pat 102 150 ± 25 mm SUSPENDED SLAB =25mm INTERNAL 40mm EXTERNAL 5) TERRACE FLOOR SLAB
3. 10mm max. BEAMS, LINTELS & CAPPING BEAMS =30mm INTERNAL 40mm EXTERNAL -DEAD LOAD- CAD BY: SYED SHAMEEM SIGN
water permeability DIN 1048
COLUMNS =30mm INTERNAL 40mm EXTERNAL /60mm EARTH FACES SELF WEIGHT + 3.5 KN/m² FINISHING + PARAPETS + ARCHITECTURAL FEATURES
4. 1500 col.. max. R.C. WALLS =30mm INTERNAL 50mm EXTERNAL /60mm EARTH FACES SERVICES 0.5 KN/m²
rapid chloride penetration ( RCP ) ASTM C1202 CHECKED BY : DATE: MAY 2016
WATER TANK =50mm INTERNAL 50mm EXTERNAL -LIVE LOAD-
5. BS 1881; part 122 1.8% col.. max. 5 KN/m² +30KN/m² (WATER TANK )
water absorption EXTERNAL RELATES TO CONCRETE FACES EXPOSED TO THE EXTERNAL ENVIRONMENT. REVIEWED BY : DATE:
SEISMIC ZONE - 2B AS/ UBC 97
6. chlorides by weight of cementations material BS 1881; part 124 .15% max. C10. JOINT FILLER/SEALANT SOIL PROFILE TYPE - SC.
EMIRATES: CITY: LOCATION: PLOT NO.:
7. sulphates (503) by weight of cementations material BS 1881; part 124 4.0% max. JOINTS FILLER SHALL BE FLEXL BY FOSROC OR EQUIVALENT APPROVED. JOINT SEALANT SHALL BE
DUBAI DUBAI BUSINESS BAY 346-572
THIOFLEX 600 BY FOSROC OR EQUIVALENT APPROVED. ALL APPLICATIONS ARE TO BE CARRIED OUT BB.A05.032
" :- 10° C FOR RAFT
''' :- TO BE CONFIRMED BY THE SUPPLIER. STRICTLY IN ACCORDANCE WITH THE MANUFACTURER'S INSTRUCTION.
PROJECT No.: DATE: SCALE: SHEET NO:

P-46460 02-01-2016 1 : 200 S 100

You might also like