Harga Satuan
No. Scope Works Unit QTY Total
(Rp.)
I. Baronawati Scope Works
1 Base C 40 cm m3 580.01 Rp -
2 Coneblock 21x10,5 bh 1,450.02 Rp -
3 m3 Rp -
4 m3
5 m2 Rp -
6 m2 Rp -
7 m2 Rp -
II. Trisari Scope Works
1 Base A 20 cm m3 1,047.20 Rp -
2 Base C 30 cm m3 1,570.80 Rp -
3 Coneblock 21x10,5 m2 5,236.00 Rp -
4 Peninggian saluran drainase m3 Rp -
5 m2 Rp -
6 m2 Rp -
7 m2 Rp -
III.
1 m3 Rp -
2 m3 Rp -
3 m3 Rp -
4 m3 Rp -
5 m2 Rp -
6 m2 Rp -
7 m2 Rp -
IV.
1 m3 Rp -
2 m3 Rp -
3 m3 Rp -
4
m3 Rp -
5 m2 Rp -
6 m2 Rp -
7 m2 Rp -
V.
1 m3 Rp -
2 m3 Rp -
3 m3 Rp -
4 m3 Rp -
5 m2 Rp -
6 m2 Rp -
7 m2 Rp -
VI.
1 m3 Rp -
2 m3 Rp -
3 m3 Rp -
4 m3 Rp -
5 m2 Rp -
6 m2 Rp -
7 m2 Rp -
REKAPITULASI PERHITUNGAN VOLUME
PROYEK PENATAAN LINGKUNGAN
Harga Satuan
No. Scope Works Unit QTY Total
(Rp.)
VII.
1 m3 Rp -
2 m3 Rp -
3 m3 Rp -
4 m3 Rp -
5 m2 Rp -
6 m2 Rp -
7 m2 Rp -
VIII.
1 m3 Rp -
2 m3 Rp -
3 m3 Rp -
4 m3 Rp -
5 m2 Rp -
6 m2 Rp -
7 m2 Rp -
BACK UP DATA
PEKERJAAN TANAH
1. Pekerjaan Base C 40 cm
Volume = 0.40 + 0.40 x 0.45 x 1.00 = 0.180 m3
2
H Panjang = 3.50 x 3.00 = 10.500 m3
Panjang = 1.25 x 1.00 = 1.250 m3
V Panjang = 4.50 x 2.00 = 9.000 m3
Panjang = 1.50 x 1.00 = 1.500 m3
Volume = 22.25 x 0.18 = 4.005 m3
Untuk 1 unit Volume = 4.01 x 1.00 unit = 4.005 m3
PEKERJAAN KONSTRUKSI
1 Pekerjaan Pondasi Menerus
Pondasi Menerus Volume = 0.20 + 0.40 x 0.40 x 1.00 = 0.120 m3
2
H Panjang = 3.50 x 3.00 = 10.500 m3
Panjang = 1.25 x 1.00 = 1.250 m3
V Panjang = 4.50 x 2.00 = 9.000 m3
Panjang = 1.50 x 1.00 = 1.500 m3
Volume = 22.25 x 0.12 = 2.670 m3
Untuk 1 unit Volume = 2.67 x 1.00 unit = 2.670 m3
b. Bekisting
Luas = 0.20 x 3.50 x 3.00 x 2.00 = 4.200 m2
Luas = 0.20 x 1.25 x 1.00 x 2.00 = 0.500 m2
Luas = 0.20 x 4.50 x 2.00 x 2.00 = 3.600 m2
Luas = 0.20 x 1.50 x 1.00 x 2.00 = 0.600 m2 = 8.900
Untuk 1 unit Volume = 8.90 x 1.00 unit = 8.900 m3
b. Bekisting
Luas = 0.15 x 3.40 x 3.00 x 2.00 = 3.060 m2
Luas = 0.15 x 3.40 x 2.00 x 2.00 = 2.040 m2
Luas = 0.15 x 3.40 x 2.00 x 2.00 = 2.040 m2
Luas = 0.15 x 3.40 x 2.00 x 2.00 = 2.040 m2 = 9.180
Untuk 1 unit Volume = 9.18 x 1.00 unit = 9.180 m2
d. Pembesian besi Ø6
Besi Ø7 m Berat/m = 7.00 x 7.00 x 0.01 = 0.302 kg/m
panjang =( 0.60 + 0.08 ) x 2.00 x 23.00 x 3.000 = 93.840 m'
panjang =( 0.60 + 0.08 ) x 2.00 x 23.00 x 2.000 = 62.560 m'
panjang =( 0.60 + 0.08 ) x 2.00 x 23.00 x 2.000 = 62.560 m'
panjang =( 0.60 + 0.08 ) x 2.00 x 23.00 x 2.000 = 62.560 m'
= 281.52 x 0.302 = 85.008 kg
Untuk 1 unit Volume = 85.01 x 1.00 unit = 85.008 kg
b. Bekisting
Luas = 0.25 x 3.50 x 4.00 x 2.00 = 7.000 m2
Luas = 0.25 x 4.50 x 2.00 x 2.00 = 4.500 m2
Luas = 0.25 x 1.50 x 1.00 x 2.00 = 0.750 m2 = 11.500 m2
Untuk 1 unit Volume = 11.50 x 1.00 unit = 11.500 m2
d. Pembesian besi Ø6
Besi Ø6 m Berat/m = 6.00 x 6.00 x 0.01 = 0.222 kg/m
panjang =( 0.80 + 0.08 ) x 2.00 x 24.00 x 4.000 = 168.960 m'
panjang =( 0.80 + 0.08 ) x 2.00 x 30.00 x 2.000 = 105.600 m'
panjang =( 0.80 + 0.08 ) x 2.00 x 10.00 x 1.000 = 17.600 m'
= 292.16 x 0.22 = 64.816 kg
Untuk 1 unit Berat = 64.82 x 1.00 unit = 64.816 kg
- Bekisting
Luas = 0.25 x 3.50 x 1.00 x 2.00 = 1.750 m2
Luas = 0.25 x 1.00 x 2.00 x 2.00 = 1.000 m2 = 2.750 m2
Untuk 1 unit Volume = 2.75 x 1.00 unit = 2.750 m2
- Pembesian besi Ø6
Besi Ø6 m Berat/m = 6.00 x 6.00 x 0.01 = 0.222 kg/m
panjang =( 0.80 + 0.08 ) x 2.00 x 24.00 x 1.000
panjang =( 0.80 + 0.08 ) x 2.00 x 14.00 x 2.000 = 49.280 m'
= 49.28 x 0.22 = 10.933 kg
Untuk 1 unit Berat = 10.93 x 1.00 unit = 10.933 kg
- Bekisting
Luas = 0.25 x 2.10 x 1.00 x 2.00 = 1.050 m2 = 1.050 m2
Untuk 1 unit Volume = 1.05 x 1.00 unit = 1.050 m2
- Pembesian besi Ø6
Besi Ø6 m Berat/m = 6.00 x 6.00 x 0.01 = 0.222 kg/m
panjang =( 0.80 + 0.08 ) x 2.00 x 11.00 x 1.000 = 19.360 m'
= 19.36 x 0.22 = 4.295 kg
Untuk 1 unit Volume = 4.30 x 1.00 unit = 4.295 kg
PEKERJAAN KERAMIK
1 Pekerjaan Lantai Keramik 20 x 20
Luas = 1.25 x 1.50 = 1.875 m2
Untuk 1 unit Luas = 1.88 x 1.00 unit = 1.875 m2
PEKERJAAN SANITASI
Pekerjaan Pembuatan Septictank
a. Galian Tanah Volume = 1.50 x 2.00 x 1.75 = 5.250 m3
Untuk 1 unit Luas = 5.25 x 1.00 unit = 5.250 m3
b. Cor Beton K225 u/Lantai Volume = 1.50 x 2.00 x 0.10 = 0.300 m3
Untuk 1 unit Luas = 0.30 x 1.00 unit = 0.300 m3
c. Bekisting Volume = 1.50 x 2.00 x 1.00 = 3.000 m2
Untuk 1 unit Luas = 3.00 x 1.00 unit = 3.000 m2
d. Pembesian besi Ø10
Besi Ø10 m Berat/m = 10.00 x 10.00 x 0.01 = 0.616 kg/m
panjang =( 1.50 + 0.10 ) x 10.00 x 2.00 = 32.000 m'
panjang =( 2.00 + 0.10 ) x 8.00 x 2.00 = 33.600 m' = 65.600 m'
Berat = 0.62 x 65.60 = 40.426 kg
Untuk 1 unit Luas = 40.43 x 1.00 unit = 40.426 kg
e. Pasangan Bata 1 : 4 Luas =( 1.50 + 2.00 ) x 2.00 x 1.65 = 11.550 m2
Untuk 1 unit Luas = 11.55 x 1.00 unit = 11.550 m2
f. Cor Beton K225 u/penutup Volume = 1.50 x 2.00 x 0.10 = 0.300 m3
Untuk 1 unit Luas = 0.30 x 1.00 unit = 0.300 m3
g. Pipa Hawa