ADDITIONAL WORKS
Removal of CCTV
Distmantling 1 lot 1,000.00 1,000.00
Excavation 90x90x90=.72m3 300.00 300.00
Rebars 1 lot 600.00
Formworks .84m3 x 200 168.00
Concreting .24m3 x 600 145.00
Erection 1 lot 1,000.00 1,000.00
Subtotal 13,131.00
Manual Excavation
6.50 x 0.70 x 2.10 9.55m3 275.00 2,627.00
5.10 x 0.70 x 2.10 7.49m3 275.00 2,061.00
Disposal 8.11m3 300.00 2,434.20
8.20 x 1.00 x 2.10 x 2 34.44m3 300.00 10,332.00
Disposal 8.61m3 300.00 2,583.00
Backfill 34.44 300.00 10,332.00
Pedestal Excavation
1.30 x 0.70 x 2.10 x 2 3.82m3 275.00 1,050.00
Formworks 49.40m2 200.00 9,880.00
Shoring 18.85x2=37.7m2 200.00 7,580.00
Shoring 5.60x4=29.12 200.00 5,824.00
Cutting of Pipe 225dia
Elbow 12ea 150.00 1,800.00
Pipe 12dia 12ea 100.00 1,200.00
Vertical 12pcs 50.00 600.00
Elbow Fabrication
3” 6pcs 200.00 1,200.00
Pipe Corrosive Tape 112rolls 97.00 10,864.00
Assist to MERALCO 1lot 8,000.00
Total 91,498.20
Mark up (10%) 9,149.82
Grand Total 100,648.02