You are on page 1of 2

Reference :

07 April 2017

PROPOSED SHOPS AND SOHO DEVELOPMENT ON PLOT B OF LOT 17469, KOTA WARISAN, SEPANG
FOR CAHAYA SERIJAYA SDN BHD

MINUTES OF SITE MEETING


HELD ON FRIDAY, 07/04/2017 AT 3.00PM
AT THE SITE OFFICE

ITEM PARTICULARS ACTION


--------------------------------------------------------------------------------------------------------------------------------------
1.0 MINUTES OF SITE MEETING

1.1 The minutes were confirmed as correct SSB

2.0 PRELIMINARIES Info

Contract Particulars :
a. Main Contractor : SMCGC (M) Sdn Bhd
b. Contract Sum : RM83,714,082.90
c. The Completion period for the contract shall be twenty four (24) months
inclusive of mobilization period and public holidays
d. Date of Commencement: 5 Dec 2016
e. Completion Date : 4 Dec 2018 for main building works
: 4 Sep 2018 for TNB Substitution & M&E Rooms
f. Liquidated Damages : RM 26,000.00 per day for main building works
RM 5,0000.00 per day for TNB substation
& M&E rooms
g. Period of interim certificate : one (1) month
h. Percentage of Certified Value of work retain : Ten (10) percent
i. Limit of retention fund : Five (5) percent
j. Period of final measurement and valuation : 12 months
k. Defects liability period : 27 months

2.1 PRA reported to reply memo proper with sample use A.I attachment SSB

3.0 QUALITY, ENVIRONMENT, SAFETY & HEALTH (QESH) SHO

3.1 SSB reported that there are total 97 people on site. SSB is to ensure that all SSB/SHO
workers are have permit and have valid CIDB Green Card. PRA is reminded
to set appointment with CIDB if their can handle training at site office.

3.2 SSB reported prepare Cost of CIDB Green Card by or before 15 April 2017 SSB/SHO
…………………………………………………………………………………………………………………………………………………………….
ITEM PARTICULARS ACTION
…………………………………………………………………………………………………………………………………………………………….

4.0 SCHEDULE & PROGRESS OF WORKS


4.1 CSSB requested daily report of progress
4.2 SSB informed to put date taken photographs below the picture in progress report

5.0 CIVIL & STRUCTURE WORKS

6.0 MECHANICAL, ELECTRICAL & PLUMBING WORKS

6.1 PRA requested copy lift drawing

6.2 PRA informed letter to extend working hour for site workers until 10pm has be
submitted & waiting for approval

6.3 SSB reminded to follow up with SYABAS for water supply SSB

7.0 ARCHITECTURAL WORKS

8.0 OTHER CONTRACTS

9.0 CERTIFICATES & VARIATIONS

10.0 CONTRACT DOCUMENTS

11.0 OTHER MATTERS

12.0 NEXT MEETING ALL


12.1 The next meeting will be held on Friday, 14 April 2017 at 3.00pm at the site office.